Customer Contract

Location #
Project
Contractor
AREVA T&D Site test record RELAY TEST Doc. Ref.

MBCH12- DIFFERENTIAL RELAY


1. GENERAL DATA AND INFORMATION:
Circuit Ref. Designation
Panel No. Serial No.
Make Model No.
Dwg & Sh No. Aux. Voltage
Flag Type No. of Contacts

2. MECHANICAL CHECKS AND VISUAL INSPECTION:


ITEM DESCRIPTION CHECKED
1 Inspect for any physical damage or defects.
2 Verify connections as per approved drawings.
3 Check that serial no. of relay matching with serial no. of case.
4 Relay CT shorting function checked.
5 Test switch checked for correct function.

3. ELECTRICAL TESTS:
3.1 PICKUP / DORP OFF TEST:

Current Current Red phase Yellow phase Blue phase


injection setting
terminal (Is) Drop out Drop out
Pickup (A) Pickup (A) Pickup (A) Drop out (A)
(A) (A)
0.1 x In
0.2 x In
Bias coil –
1 Terminal 0.3 x In
23 - 27
0.4 x In
0.5 x In
0.1 x In
0.2 x In
Bias coil –
2 Terminal 0.3 x In
25 - 27
0.4 x In
0.5 x In

Test performed by Test witnessed by Date of test


AREVA T&D
Name MUSTAFA HAJI

Signature
Customer Contract
Location #
Project
Contractor
AREVA T&D Site test record RELAY TEST Doc. Ref.

MBCH12- DIFFERENTIAL RELAY


3.2 OPERATING TIME TEST:
Measured operating time in msec
Current Limits
Injected Red phase Yellow phase Blue phase
injection
current
terminal
Pickup Pickup Pickup 3.5 x In 4.5 x In

Bias coil–1 3.5 x In


Terminal
23 – 27 4.5 x In

Bias coil–1 3.5 x In


Terminal
25 - 27 4.5 x In

3.3 BIAS CURRENT CHECK TEST:


Calculated
Measured current values As per curve
I1 – test current mean bias
Phase Results
setting
I1 I2 I1+I2/2 Id

I1=0.6xIn=
R
Is=
I1=1.7xIn=

I1=0.6xIn=
Y
Is=
I1=1.7xIn=

I1=0.6xIn=
B
Is=
I1=1.7xIn=

Test performed by Test witnessed by Date of test


AREVA T&D
Name MUSTAFA HAJI

Signature
Customer Contract
Location #
Project
Contractor
AREVA T&D Site test record RELAY TEST Doc. Ref.

MBCH12- DIFFERENTIAL RELAY


3.4 INRUSH CURRENT CHECK TEST:

Operation of relay when switch s2 is closed: --------------------------


No operation of relay when switch s2 is opened: ----------------------
3.5 RELAY BURDEN AT UPPER VOLTAGE RATING:

Burden (W) Burden Limits


Voltage Current
Terminal
(V) (mA) Quiescent O/P optd. Quiescent O/P optd.

3W for 48/54V 4W for 48/54V


4W for 110/125V 7W for 110/125V

Test performed by Test witnessed by Date of test


AREVA T&D
Name MUSTAFA HAJI

Signature
Customer Contract
Location #
Project
Contractor
AREVA T&D Site test record RELAY TEST Doc. Ref.

MBCH12- DIFFERENTIAL RELAY


3.6. RELAY FINAL SETTING TEST:
3.6.1 PICKUP / DORP OFF TEST:

Current Current Red phase Yellow phase Blue phase


injection setting
terminal (Is) Drop out Drop out
Pickup (A) Pickup (A) Pickup (A) Drop out (A)
(A) (A)
Bias coil –
1 Terminal
23 - 27
Bias coil –
2
Terminal
25 - 27

3.6.2 OPERATING TIME TEST:


Is= In=
Current Measured operating time in msec
Injected Limits
injection
current Red phase Yellow phase Blue phase
terminal 3.5 x In 4.5 x In
Bias coil–1 3.5 x In
Terminal
23 – 27 4.5 x In

Bias coil–1 3.5 x In


Terminal
25 - 27 4.5 x In

4. FUNCTIONAL TESTS:
Item Description Checked
1 All output contacts resistance measured.
2 LED operation checked.
3 Check BIAS Interconnection
4 If required check 3 phase tripping

Test performed by Test witnessed by Date of test


AREVA T&D
Name MUSTAFA HAJI

Signature