33.50 m. 7.50 m. 22.50 m. 22.50 m. 7.50 m. 33.50 m.


3.00 m. 3.00 m.
PROVISION FOR FUTURE IMPROVEMENT SHOULDER RUNWAY RUNWAY SHOULDER PROVISION FOR FUTURE IMPROVEMENT

S. E. s=2.0% s=1.5% s=1.5% s=2.0% S. E. FENCE


FENCE s=2.5% s=2.5%

HEIGHT OF NATURE OF CUT SLOPE FILL SLOPE


TABLE FOR SHOULDER SLOPE (M.) MATERIAL RATIO RATIO
SLOPE "S"
(HIGH SHOULDER) 0.0 to 1.0 EARTH 4:1 4:1

1.1 to 2.0 EARTH 2:1 2:1


e S SOFT ROCK,
VARIES FROM
1.1 to 2.0 CORAL SHALE,
1/2:1 TO 1:1
2:1
3 -3 CEMENTED GR.

4 -3 NATURE BREAK
1.1 to 2.0 HARD ROCK, (DESIGN SLOPE) 2:1
5 -2 1/4:1

6 -1 Over 2.0 EARTH 1 12:1 1 12:1


7 0 SOFT ROCK,
VARIES FROM
Over 2.0 CORAL SHALE,
1/2:1 TO 1:1
1/2:1 to 1:1
8 1
CEMENTED GR.

NOTE: NATURE BREAK


1. ALGEBRAIC DIFFERENCE OF CROSS - OVER Over 2.0 HARD ROCK (DESIGN SLOPE) 1 1 4: 1 to 1 12:1
SHOULD BE LESS THAN OR EQUAL TO 7 % 1/2:1
2 . FOR E GREATER THAN 7 % SHOULDER BE
PAVED WITH CONCRETE, THICKNESS = 150 MM. 1. CUT/FILL SLOPE STAKE VARIES ON THE STABILITY OF MATERIAL

CONCURRED :

CAPTAIN JIM C. SYDIONGCO


DIRECTOR GENERAL
DATE :

PREPARED : PROJECT NAME AND LOCATION : SHEET CONTENTS : CHECKED : SUBMITTED : REVIEWED : RECOMMENDED : APPROVED : SET NO. SHEET NO.

ALPHA & OMEGA GEN. AS-STAKED PLAN REPUBLIC OF THE PHILIPPINES


CONTRACTOR & DEV'T CORP./ S 14
RUNWAY STRIP GRADE CORRECTION OF DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SABENIANO D. CALIAO, JR. ZENAIDA T. TAN
ABIB BUILDERS ENTERPRISES CEZARAH ROWENA C. DISCAYA OZAMIZ CITY AIRPORT ROAD, MISAMIS TYPICAL RUNWAY SECTION REGION - X
ADELINO T. TANGAPA, DM VIRGIE G. NAYVE REY PETER B. GILLE
AUTHORIZED MANAGING PROJECT ENGINEER III CHIEF, CONSTRUCTION DIVISION CHIEF, PLANNING AND DESIGN DIVISION ASSISTANT REGIONAL DIRECTOR REGIONAL DIRECTOR 3 3
(JV) OFFICER