Project Background
and Coverage
Mong Kok is one of the most
densely populated and aged
districts in the metro area of Hong
Kong. Some streets within the area
have a development history which
can date back up to the end of the
19th Century. Being a city under
fast development, majority of the
old streets and historic buildings
were demolished to give way for
development under usual free-
market environment. Except for
some modern commercial
buildings using as office,
entertainment or retail purposes,
majority of the remaining buildings
in the district were constructed
after the World War II with
averaged age ranging from 30 to
50 years. Due to the insufficiency
of space and urban facilities which
inherited from outdated city
planning, the district is deteriorated
in a very fast manner and created
a lot of associated social problems.
In view of this, through the Land
Development Corporation (reformed that formed part of the ground Foundation in general cranes and dumping trucks were
as the Urban Renewal Authority in transportation relief strategies for the The foundation works were carried stationed during the excavation
2000), the government started to existing congested neighborhood in out at the same time for the both process. The formation level of the
resume altogether about 150 blocks downtown Mongkok. The total sites at the end of 1999. The cofferdam was about -28m.p.d. The
of old buildings within an area development involved a gross floor contract involved the forming of main structures located inside the
bounded by 7 streets. After the area (GFA) of about 167,400 sq m. various cut-off systems in the form cofferdam included the core wall,
vocation of the land, the project was Connection provisions in the of sheet pile wall, diaphragm wall four composite columns and 6 other
developed by a private developer development have been provided in and small diameter pipe-pile wall; as minor columns in RC for the support
under carefully negotiated contract. the design in order to enhance the well as the usual bored piles as of the upper structure. The
The development was known as the flow between the two sites. A 2-way support for the upper structures. basement structure, constructed of
Langham Place afterward. traffic vehicular tunnel is constructed Majority of the bored piles were in-situ RC and traditional timber
The Langham Place project covers to link up the two basements which 2.5m in diameter formed by formwork, was done in a usual
a total land area of about 12,000 both served for car parking purpose. reversed circulation drilling process bottom-up manner with the walls
sq m, which is further sub-divided into This tunnel is required due to the site and seated on bedrock averaged and floors cast in convenient
two lots of land, separated by the layout constraints that only a 45m below ground. To facilitate the sections.
Shanghai Street in the middle. The vehicular entrance point at Site A is construction of the basement at The core wall and the composite
larger lot (Site A) is an island site, approved by the government for the convenient stages at a later time, a columns continued upwards from
bounded by the Argyle Street, reason not to further congest the section of sheet pile wall were also the basement until they reached
Portland Street, Shanghai Street and relatively narrow roadway in the provided. This arrangement could Level 5 where a 5m-thick transfer
Shan Tung Street on the four sides, area in particular in view of the allow the construction of the plate located. A falsework system
with an area of about 7950 sq m. Site provision of a new public light bus foundation raft and the basement erected in tubular scaffold and
A accommodates a 59-storey office terminus situated at Site B after the portion of the main tower in an universal steel beams was provided
tower block, a 16-storey retail mall with completion of the project. advanced phase before the full to facilitate the casting of the transfer
shopping and entertainment facilities, The other linkage provision commencement of the basement plate. Upon the completion of the
and a 5-level basement uses as retail between the two sites is the structure under the retail podium. transfer plate, a set of jump form was
and carpark that stretches the entire construction of two covered assembled for the forming of the
area of Site A. pedestrian footbridges on Level 3 The main tower core wall for the upper structure.
The smaller site (Site B) is and 4, which provide a convenient The tower founded on a 5m RC raft Column configuration was in 4
opened two sides to Shanghai throughway for users between the constructed in a bottom-up manner. composite mega-columns plus 6 in-
Street and Reclamation Street, and hotel block and the retail mall. To facilitate the construction of the situ RC side columns for floors
with the shorter ends abutted to raft, a 42m x 42m cofferdam was below the transfer plate, which was
existing buildings, with an area Construction Highlights formed with diaphragm wall lined on re-configured to 12 in-situ RC
about 4,300 sq m. This site consists The major construction works for the 3 sides and sheet pile wall on the columns layout with shorter span
a 2-level basement while the upper project can be sub-divided into five other as cut-off provision, and arrangement above the transfer
structure is a 42-storey hotel building core elements, that is, the laterally supported by a complicated plate. The floor system is of usual
with 750 rooms. Except for an foundations, the construction of the strut and bracing system with 7 main/secondary beams design,
entrance foyer for the hotel, majority main tower, the basement structure layers of lateral supporting frame. which was constructed in RC using
of the area on the ground level is on site A, the retail mall structure, The support system also provided traditional timber form and
used as a public light bus terminus and the hotel block on site B. a work platform on which mobile connected to the core wall with build-
in couplers. Headroom of the typical majority of the sub-soil is of made- highly impressive entrance to the inside the main structure of the mall
floors is 3.9m and the average ground with small amount of marine retail mall. in which two fast-track escalator
coverage of typical floor is about deposits. The basement structure The basic layout of the mall systems were located. There is also
1,000 sq m in size. A 4-day cycle consists of 5 levels, with the upper structure roughly follows a 8.5m-grid a provision for a skating rink on
was adopted for the construction of 2 levels use mainly as retail, while system but with the out-setting and Level 12 with averaged 15m
typical floor with the core wall the remaining as car parking multi-level design on each floor. The headroom, and cladded on the sides
constructed using a hydraulic lifting purposes. The basement was joined actual layout exhibits a very with glass wall to provide
slip form in an advanced phase and to the portion under the main tower interesting irregularity that makes transparency and natural lighting for
floor slab in traditional timber which was constructed in a bottom- the spatial arrangement inside the the area.
formwork. up manner in an advanced stage mall interior having an extremely
The core wall measured about during the progress of basement novelty look in the design. Hotel Block on Site B
15m x 32m on plan with 2m-splayed construction. The grand atrium is of no doubt The hotel block started its basement
corners. The maximum thickness of One very spectacular structure in an eye-catching structure which work in August 2001. The basement
wall is 1.2m for the lower floors the basement is a 36m diameter provides a covered void inside the adopted a rather tradition method to
(along the edge wall at the long vehicular ramp which serves as an mall with 77,000 cu m of space. The construct, that is, it was done in a
axles), and reduced to 600mm when access for vehicles into the grand atrium is a space truss bottom up arrangement, with the
reaching the upper levels. basement carpark from an entrance supported y 10 columns on two excavation carried out in layers
There are 2 outrigger systems at Shan Tung Street. The ramp sides of the atrium and connected starting from the ground level, until
incorporated in the superstructure of served as an important provision for by the metal roof to form a portal it reached the formation level where
the building as a stiffening design. spoil disposal and material delivery frame. The columns are made of the pile caps were constructed. The
They are located on Level 16 and during the peak period of basement tubular steel trusses in rectangular averaged depth of excavation was
L e v e l 3 8 r e s p e c t i v e l y. T h e excavation and construction. shape. The height of columns about -14m from street level with the
outriggers are in simple bracing Besides, the escalator voids located ranges from 51m to 63m from level maximum depth at -19m to
frame design, with inclined inside the basement was also made 4 to the roof truss. Space between accommodate the lowest lift pit. Side
composite tie members stretched use of for similar purposes during the columns is tied by truss cables support was by the use of
from the 2 shorter axles at the corner the construction process. and tubular girders for the mounting diaphragm wall with a section of
of the core wall and ties rigidly with of the glass wall at a later stage. pipe-pile wall at the north end where
the external frame. Instead of a fully- The Retail Mall The steel roof curves slightly it abutted to existing buildings. Six
braced belt truss system, a simple The retail mall is a very complicated upward to provide cover for the layers of strut frame were provided
truss in the form of an inverted “A” structure with the lower portion (from remaining portion of the retail mall as the lateral support system, with
configuration is adopted as the ground to Level 4, the main deck) structure. The steel roof is a 50m x 12m temporary platform
external truss of the outrigger. constructed of in-situ RC, and the constructed of 14 sets of main erected on top as work station to
upper portion in a structural steel trusses, with an average depth of facilitate the excavation process.
Basement Structure on Site A composite. In addition, there is a 3.5m each. The roof cover employed In order to provide a 4-lane public
The basement under the retail mall grand atrium located in between the a 6-layered aluminum decking light bus terminus at the ground level
at Site A was constructed using a office block and the mall structure, system with basic insulation and of the site, the floor span on the
top-down approach. Total volume of which provides an averaged 52m waterproofing membrane within. lower levels of the hotel block is
excavation involved in the basement high unobstructed space above the Besides the grand atrium, there maximized by the use of thin
is about 170,000 cu m, in which main deck at Level 4 that forms the are 2 other atrium provisions placed composite columns in an
approximate 9m and 15m span excavated spoil and the delivery August 2001. During this period, major works. At a result, there
layout. The arrangement continues of materials during the basement the excavation work for the were more than 600 workers
upward until it reached Level 11 and superstructure construction, substructure was basically working in the site and with a
where the 3.2m-thick transfer plate in particular created numerous completed, while the cash flow of US$16 million per
locates. disturbances that very careful construction of the main tower month during the climax period.
The structure above Level 11 is planning and coordination for the began to reach its typical cycle. 3. Beside the general engineering
used as hotel guestrooms. The traffic arrangement was required. At the same time on the retail and technical concerns in the
structure is comprised of two 2. Large work frontage and mall portion, the podium installation of the steel frame
sections, one is the major core wall coverage structure in RC was completed building, there was also the
system which housed the lift shafts The entire project excluding the that followed by the erection of problem of working at high
and staircases; the other is the shear foundation works took 36 months the upper structure in structural altitude especially for the retail
wall block for the typical guestrooms. to complete. The peak period steel. The basement constructed mall structure. This was further
The averaged 500mm-thick core arrived about 15 months after the in top-down arrangement was worsened by the existence of a
wall system was constructed in an contract commencement in carried out in parallel to the other number of long-span and high-
advanced phase using a crane-lifted
gang form, while the averaged
300mm-thick shear walls were
constructed using large-panel type
steel form. The 3.15m-clearance
floor system in this case employed
a traditional timber formwork
propped with standard tubular
scaffold.