Construction of Langham Place by Raymond Wong Wai Man

Project Background
and Coverage
Mong Kok is one of the most
densely populated and aged
districts in the metro area of Hong
Kong. Some streets within the area
have a development history which
can date back up to the end of the
19th Century. Being a city under
fast development, majority of the
old streets and historic buildings
were demolished to give way for
development under usual free-
market environment. Except for
some modern commercial
buildings using as office,
entertainment or retail purposes,
majority of the remaining buildings
in the district were constructed
after the World War II with
averaged age ranging from 30 to
50 years. Due to the insufficiency
of space and urban facilities which
inherited from outdated city
planning, the district is deteriorated
in a very fast manner and created
a lot of associated social problems.
In view of this, through the Land
Development Corporation (reformed that formed part of the ground Foundation in general cranes and dumping trucks were
as the Urban Renewal Authority in transportation relief strategies for the The foundation works were carried stationed during the excavation
2000), the government started to existing congested neighborhood in out at the same time for the both process. The formation level of the
resume altogether about 150 blocks downtown Mongkok. The total sites at the end of 1999. The cofferdam was about -28m.p.d. The
of old buildings within an area development involved a gross floor contract involved the forming of main structures located inside the
bounded by 7 streets. After the area (GFA) of about 167,400 sq m. various cut-off systems in the form cofferdam included the core wall,
vocation of the land, the project was Connection provisions in the of sheet pile wall, diaphragm wall four composite columns and 6 other
developed by a private developer development have been provided in and small diameter pipe-pile wall; as minor columns in RC for the support
under carefully negotiated contract. the design in order to enhance the well as the usual bored piles as of the upper structure. The
The development was known as the flow between the two sites. A 2-way support for the upper structures. basement structure, constructed of
Langham Place afterward. traffic vehicular tunnel is constructed Majority of the bored piles were in-situ RC and traditional timber
The Langham Place project covers to link up the two basements which 2.5m in diameter formed by formwork, was done in a usual
a total land area of about 12,000 both served for car parking purpose. reversed circulation drilling process bottom-up manner with the walls
sq m, which is further sub-divided into This tunnel is required due to the site and seated on bedrock averaged and floors cast in convenient
two lots of land, separated by the layout constraints that only a 45m below ground. To facilitate the sections.
Shanghai Street in the middle. The vehicular entrance point at Site A is construction of the basement at The core wall and the composite
larger lot (Site A) is an island site, approved by the government for the convenient stages at a later time, a columns continued upwards from
bounded by the Argyle Street, reason not to further congest the section of sheet pile wall were also the basement until they reached
Portland Street, Shanghai Street and relatively narrow roadway in the provided. This arrangement could Level 5 where a 5m-thick transfer
Shan Tung Street on the four sides, area in particular in view of the allow the construction of the plate located. A falsework system
with an area of about 7950 sq m. Site provision of a new public light bus foundation raft and the basement erected in tubular scaffold and
A accommodates a 59-storey office terminus situated at Site B after the portion of the main tower in an universal steel beams was provided
tower block, a 16-storey retail mall with completion of the project. advanced phase before the full to facilitate the casting of the transfer
shopping and entertainment facilities, The other linkage provision commencement of the basement plate. Upon the completion of the
and a 5-level basement uses as retail between the two sites is the structure under the retail podium. transfer plate, a set of jump form was
and carpark that stretches the entire construction of two covered assembled for the forming of the
area of Site A. pedestrian footbridges on Level 3 The main tower core wall for the upper structure.
The smaller site (Site B) is and 4, which provide a convenient The tower founded on a 5m RC raft Column configuration was in 4
opened two sides to Shanghai throughway for users between the constructed in a bottom-up manner. composite mega-columns plus 6 in-
Street and Reclamation Street, and hotel block and the retail mall. To facilitate the construction of the situ RC side columns for floors
with the shorter ends abutted to raft, a 42m x 42m cofferdam was below the transfer plate, which was
existing buildings, with an area Construction Highlights formed with diaphragm wall lined on re-configured to 12 in-situ RC
about 4,300 sq m. This site consists The major construction works for the 3 sides and sheet pile wall on the columns layout with shorter span
a 2-level basement while the upper project can be sub-divided into five other as cut-off provision, and arrangement above the transfer
structure is a 42-storey hotel building core elements, that is, the laterally supported by a complicated plate. The floor system is of usual
with 750 rooms. Except for an foundations, the construction of the strut and bracing system with 7 main/secondary beams design,
entrance foyer for the hotel, majority main tower, the basement structure layers of lateral supporting frame. which was constructed in RC using
of the area on the ground level is on site A, the retail mall structure, The support system also provided traditional timber form and
used as a public light bus terminus and the hotel block on site B. a work platform on which mobile connected to the core wall with build-
in couplers. Headroom of the typical majority of the sub-soil is of made- highly impressive entrance to the inside the main structure of the mall
floors is 3.9m and the average ground with small amount of marine retail mall. in which two fast-track escalator
coverage of typical floor is about deposits. The basement structure The basic layout of the mall systems were located. There is also
1,000 sq m in size. A 4-day cycle consists of 5 levels, with the upper structure roughly follows a 8.5m-grid a provision for a skating rink on
was adopted for the construction of 2 levels use mainly as retail, while system but with the out-setting and Level 12 with averaged 15m
typical floor with the core wall the remaining as car parking multi-level design on each floor. The headroom, and cladded on the sides
constructed using a hydraulic lifting purposes. The basement was joined actual layout exhibits a very with glass wall to provide
slip form in an advanced phase and to the portion under the main tower interesting irregularity that makes transparency and natural lighting for
floor slab in traditional timber which was constructed in a bottom- the spatial arrangement inside the the area.
formwork. up manner in an advanced stage mall interior having an extremely
The core wall measured about during the progress of basement novelty look in the design. Hotel Block on Site B
15m x 32m on plan with 2m-splayed construction. The grand atrium is of no doubt The hotel block started its basement
corners. The maximum thickness of One very spectacular structure in an eye-catching structure which work in August 2001. The basement
wall is 1.2m for the lower floors the basement is a 36m diameter provides a covered void inside the adopted a rather tradition method to
(along the edge wall at the long vehicular ramp which serves as an mall with 77,000 cu m of space. The construct, that is, it was done in a
axles), and reduced to 600mm when access for vehicles into the grand atrium is a space truss bottom up arrangement, with the
reaching the upper levels. basement carpark from an entrance supported y 10 columns on two excavation carried out in layers
There are 2 outrigger systems at Shan Tung Street. The ramp sides of the atrium and connected starting from the ground level, until
incorporated in the superstructure of served as an important provision for by the metal roof to form a portal it reached the formation level where
the building as a stiffening design. spoil disposal and material delivery frame. The columns are made of the pile caps were constructed. The
They are located on Level 16 and during the peak period of basement tubular steel trusses in rectangular averaged depth of excavation was
L e v e l 3 8 r e s p e c t i v e l y. T h e excavation and construction. shape. The height of columns about -14m from street level with the
outriggers are in simple bracing Besides, the escalator voids located ranges from 51m to 63m from level maximum depth at -19m to
frame design, with inclined inside the basement was also made 4 to the roof truss. Space between accommodate the lowest lift pit. Side
composite tie members stretched use of for similar purposes during the columns is tied by truss cables support was by the use of
from the 2 shorter axles at the corner the construction process. and tubular girders for the mounting diaphragm wall with a section of
of the core wall and ties rigidly with of the glass wall at a later stage. pipe-pile wall at the north end where
the external frame. Instead of a fully- The Retail Mall The steel roof curves slightly it abutted to existing buildings. Six
braced belt truss system, a simple The retail mall is a very complicated upward to provide cover for the layers of strut frame were provided
truss in the form of an inverted “A” structure with the lower portion (from remaining portion of the retail mall as the lateral support system, with
configuration is adopted as the ground to Level 4, the main deck) structure. The steel roof is a 50m x 12m temporary platform
external truss of the outrigger. constructed of in-situ RC, and the constructed of 14 sets of main erected on top as work station to
upper portion in a structural steel trusses, with an average depth of facilitate the excavation process.
Basement Structure on Site A composite. In addition, there is a 3.5m each. The roof cover employed In order to provide a 4-lane public
The basement under the retail mall grand atrium located in between the a 6-layered aluminum decking light bus terminus at the ground level
at Site A was constructed using a office block and the mall structure, system with basic insulation and of the site, the floor span on the
top-down approach. Total volume of which provides an averaged 52m waterproofing membrane within. lower levels of the hotel block is
excavation involved in the basement high unobstructed space above the Besides the grand atrium, there maximized by the use of thin
is about 170,000 cu m, in which main deck at Level 4 that forms the are 2 other atrium provisions placed composite columns in an
approximate 9m and 15m span excavated spoil and the delivery August 2001. During this period, major works. At a result, there
layout. The arrangement continues of materials during the basement the excavation work for the were more than 600 workers
upward until it reached Level 11 and superstructure construction, substructure was basically working in the site and with a
where the 3.2m-thick transfer plate in particular created numerous completed, while the cash flow of US$16 million per
locates. disturbances that very careful construction of the main tower month during the climax period.
The structure above Level 11 is planning and coordination for the began to reach its typical cycle. 3. Beside the general engineering
used as hotel guestrooms. The traffic arrangement was required. At the same time on the retail and technical concerns in the
structure is comprised of two 2. Large work frontage and mall portion, the podium installation of the steel frame
sections, one is the major core wall coverage structure in RC was completed building, there was also the
system which housed the lift shafts The entire project excluding the that followed by the erection of problem of working at high
and staircases; the other is the shear foundation works took 36 months the upper structure in structural altitude especially for the retail
wall block for the typical guestrooms. to complete. The peak period steel. The basement constructed mall structure. This was further
The averaged 500mm-thick core arrived about 15 months after the in top-down arrangement was worsened by the existence of a
wall system was constructed in an contract commencement in carried out in parallel to the other number of long-span and high-
advanced phase using a crane-lifted
gang form, while the averaged
300mm-thick shear walls were
constructed using large-panel type
steel form. The 3.15m-clearance
floor system in this case employed
a traditional timber formwork
propped with standard tubular
scaffold.

Special problems encountered


during the construction process
The Langham Place project
encountered a lot of work difficulties
during the construction due to
practical reasons. Below show some
of these examples.
1. E x t r e m e l y c o n g e s t e d
environment surrounding the site
The site (Site A and B) was
bounded by one main road with
3-lane dual way traffic and 4 busy
inner roadways with averaged
width below 12m. The site
activities such as the removal of
headroom atrium spaces which touching-up requirements were system comprised of steel panel the power for the jump lift. As the
involved very heavy pre- demanded especially in the hotel formwork, a supporting steel frame upper section of the lift shaft being
assembled components and block. Some were exterior works and a synchronized hydraulic completed, the lift machine room
other temporary supporting including inclined or overhanging jacking system. The formwork also and the cathead will be elevated and
falsework. installation such as the deck and reduced the lifting work load of the the jump lift can serve more floors.
4. Difficult site layout planning to cladding panel for the curvy roof tower crane and expedited the However, the installation required
meet the construction operation of the retail mall. These works formwork releasing process after the inspection by the government
The large work frontage and were often very expensive and concreting. In addition, the formwork (E&M Services Department) and
dynamicity of the construction fragile, having safety concern can cater for curved structure by the some advanced works may be
operations within a congested when installed, sometime also use of the rigid steel frame. The involved.
site demands very accurate requiring necessary site layout formwork also produced a good
support in the site layout planning support to facilitate vertical alignment by monitoring the Milestone project to trigger the
provision and planning. Site work. steel formwork position on the reform of an aged district
facilities and equipment were not In order to obtain the best result, supporting frame. Erection of the As a congested and aged district
a major concern in the project. the contractor of the project has to formwork was done relatively easy located in the busiest downtown
How to locate the required maintain a very strong team on site to by moving the large panels sideward area of the Kowloon Peninsula of
services was often a problem in take care of the work under a short on hanging rollers and rails. Hong Kong, besides a significant
particular where the work front term and intermediate term basis. The Other provisions such as the use amount of scattered commercial
was difficult to access, located at role of the team was responsible to of a climbing work screen on development, Mong Kok also
a high altitude, or situated at take care of matters such as, works temporary guide rail to protect accommodated large amount of
enclosed work area such as coordination, planning and exterior work activities at high low-income inhabitants living in the
within the top-down basement or scheduling, temporary work level, the use of floor-to-floor averaged 30 years of age and
inside an atrium space within the provisions, construction safety and material hoist with a 4m x 6m poorly maintained residential
enclosed structure on the upper other logistic support, as well as to platform and a hoisting capacity of buildings. Many of these buildings
level. maintain a comprehensive temporary 2 tons driven by hydraulic action. In are of mixed used, with shops,
5. Delicate finishing works traffic management network with order to provide a convenient and snack bars, restaurants, cyber
The project involved the relevant parties and authorities to fast vertical transportation for game centres, or even low-class
construction of a Grade A office ensure the thorough running of the workers and materials to reach the dancing clubs at the lower floor,
tower and a high-quality nearby public traffic during the peak upper working floors, a series of and usual residential flats on the
shopping complex in which very period of construction. jump-lifts were installed. The lifts upper. Due to the existing statutory
expensive and delicate finishing At the same time, some made use of the permanent lift shaft constraint and the complicated
works were involved. The innovative provisions or special while it is still under construction. ownership situation, the
finishing works were of a wide equipment were also introduced to The constructed portion of the lift government can do nothing
variety of nature including improve the efficacy of work. These shaft would then be capped and the effectively to improve the urban
general finishes glass work, included the use of an advanced railing and lift car would be installed environment in the district.
stone work, woodwork and Climb Form for the construction of as if they were for permanent Having the clearance of 1.2
pavior works. Some were of the core wall of the office tower, installation. A temporary lift machine hectare of land full of aged and
interior design nature where which is a self-climbing pre- room and the cathead would be shabby buildings, and replacing it
extremely high workmanship and fabricated system formwork. The installed under the cap and served with a newly designed modern
functional centre of commercial enhance the situation serving as
nature, the social system of Mong a visitor focus centre that even
Kok has undergone an interesting provide very good motivation for
transform. The new facility, as the nearby buildings in weaker
observed after 8 months after its condition to reinstate or
completion, shows the following redevelop themselves.
significance. 5. The positive prospect of this
1. With the adding in of a huge outlet development set a sample case
point with large number of new for similar urban renewal projects
attractions in the already very which are scattered in other aged
busy district Mong Kok, Langham district around the metro area of
Place becomes a new focus and Hong Kong.
gathering place for the
neighbourhood, visitors or people Conclusive Remark
who are looking for food and Beside the input of large amount
entertainment. of investment and the significant
2. With the relocation of the previous use of effective means to manage
public light bus terminuses which and carry out the construction of
stationed on the road sides into the Langham Place, the project
the public transportation centre in also processes strong urban and
Site B (hotel block), the social meaning that set a good
surrounding streets are much precedence for similar projects of
more in order both for pedestrian which they are quite universal
and traffic. worldwide in big cities with huge
3. With the reform and upgrading of population and the coexistence of
the overall urban environment in new and old city environment. In
the area, the property value of the Hong Kong, some other district like
nearby buildings has increased the Kwun Tong town centre on
drastically. This will naturally East Kowloon, Causeway Bay and
erase the existence of low-value Wanchai district on the Hong Kong
commercial activities and attract Island side, situations are very
investors and business operators s i m i l a r. A n d o f c o u r s e , t h e
who are able to afford the high development process including the
property price or rent. arrival of an agreed procurement
4. Inside the office tower and retail scheme and the land requisition
mall of Langham Place it housed negotiation, will be very lengthy
large number of high-class retail and generate countless conflicts
shops, restaurant, snack bars between different interests. We are
and the alike. This further waiting to see what come next.