Project Name: Rawdat Al Khail Building (3B+G+8F+PH)

Client : Assets Real Estate Development Co


Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date
Taken
Status
Date Days Open Signature

Main Door 1. Provide protection of all finished


1 04/18/21 Entry Living works to avoid any damages.
Area

Main Door 1. Provide protection of all finished


2 04/18/21 Entry Living works to avoid any damages.
Area

Page 1
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

Main Door 1. Visible paint marks, scratches and


3 04/18/21 Entry Living smudges on the door frame
Area

Main Door 1. Visible paint marks on the edge of


4 04/18/21 Entry Living the fire alarm cover box
Area

Page 2
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

Main Door 1. Untagged Breaker Board without


5 04/18/21 Entry Living the designated room location f each
breaker
Area

Main Door 1. No Breaker Room Location


6 04/18/21 Entry Living Diagram to indicated the
Area location of each breaker

Page 3
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible paint marks on the top


end corner of the wall near the
7 04/18/21 Guest Toilet
ceiling and uneven edges of the
ceiling edges

8 04/18/21 Guest Toilet 1. Visible marks on the inside


corner of the door frame

Page 4
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible adhesive marks on the


9 04/18/21 Guest Toilet side end of the wood
shelveunder the countertop

10 04/18/21 Kitchen 1. Visible marks on the inside


corner of the door frame

Page 5
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible unpainted corner of


11 04/18/21 Kitchen the ceiling on the both opoosite
of the kitchen hod shaft

1. Visible paint marks of the top


12 04/18/21 Kitchen end corner of the wall

13 04/18/21 Kitchen 1. Visible vertical streak on the


end corner of the wall

Page 6
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Incomplete installation of Data


14 04/18/21 Living outlet and accessories

1. dark spot s and smudges on the


15 04/18/21 Living wall surface

1. Visible scratches on the end


16 04/18/21 Living corner cutrain wall frame

Page 7
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible chipped edges of the


architrave and door frame and
17 04/18/21 Bedroom white marks

1. Visible excess dried paint drops


and grouting on the corner end of
18 04/18/21 Bedroom the sliding door track

Page 8
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible scratches on the end


19 04/18/21 Bedroom corner cutrain wall frame

1. Visible uneven edges of excess


paint and marks on all sides of the
20 04/18/21 Bedroom balcony door

Page 9
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible uneven edges of excess


paint and marks on all sides of the
21 04/18/21 Balcony balcony door

1. Visible uneven edges of excess


paint and marks on all sides of the
22 04/18/21 Balcony balcony door

Page 10
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible pen marks on the glass


23 04/18/21 Balcony panel surface of ballustrade

Master 1. Incomplete installation of Data


24 04/18/21 Bedroom
outlet and accessories

1. Visible excess dried paint drops


Master and grouting on the corner end of
25 04/18/21 the sliding door track
Bedroom

Page 11
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

1. Visible excess dried paint drops


Master and grouting on the corner end of
26 04/18/21 the sliding door track
Bedroom

1. Visible excess dried paint marks


Master on the side of the door frame and
27 04/18/21 Bedroom
incomplete grouting on top
between skiritng

Master 1. Missing cover plate for wrdrobe


28 04/18/21 door hinge
Bedroom

Page 12
Project Name: Rawdat Al Khail Building (3B+G+8F+PH)
Client : Assets Real Estate Development Co
Consultant: Universal Design Center
Main Contractor: Urbacon Trading & Contracting Co.
Main Sub Contractor: Golden Bay Contracting & Trading

Snag Observation Report Apartment No : 51


Action Completion Number of
Sr.No Report Date Location Description of Defect/Snag Photos Before Photos After Action Date Taken Status Date Days Open Signature

Master 1. Misaligned ceiling mounting of


29 04/18/21 Bedroom diffuser
Toilet

Contractor- GBCT Consultant-UDC Operator -Retaj Client -Assets

Signature/ Date

Name Wafieq Altouki -PM Michael Domagas-PM Malek Nabhan-HM Ragheb Jalabi-PD

Page 13
Apartment No : 511

Remarks

Page 14
Apartment No : 511

Remarks

Page 15
Apartment No : 511

Remarks

Page 16
Apartment No : 511

Remarks

Page 17
Apartment No : 511

Remarks

Page 18
Apartment No : 511

Remarks

Page 19
Apartment No : 511

Remarks

Page 20
Apartment No : 511

Remarks

Page 21
Apartment No : 511

Remarks

Page 22
Apartment No : 511

Remarks

Page 23
Apartment No : 511

Remarks

Page 24
Apartment No : 511

Remarks

Page 25
Apartment No : 511

Remarks