Periodic Maintenance
Estimated Duration
Frequency Assumed Equipment
Maintenance Task (man.day) or basis for
(months) implementation Location
estimate
In-Service Inspection of ESPN: 4 VST 60 DTR
Scope – VSTs, all HMS tanks 4 process vessels
(x5), all HMS pipes up to EXC, PAR
RP lines between NRV and VST. Approx. 200m pipework
Calibration of Non-SIC 91 instruments LTM NBC /
instrumentation DTR / L3
Testing / Calibration of SIC 100 instruments LTM NBC / DTR
instrumentation (depends on
integrity level)
Sampling and dosing of water in 7 vessels LTM DTR
VSTs and HMS process vessels
Replacement of gas analysers 6 analysers DTR
Purging/evacuation of gas NBC / DTR
spaces
Leak testing of primary vacuum 2 x bleed valves NBC
barrier 2 x rupture discs
Exercise of WRC pumps 0.5 (2 pumps) LTM DTR
Exercise/testing of ST-VS fans 1 (2 fans) B14
Exercise of valves 120 process valves LTM NBC /
+solenoid valves for DTR / L3
instruments
Demonstration of Hard-Core 8 valves LTM DTR
isolation post valve exercise
Testing of PAR 1 18-24 DTR
Reactivation of PAR 10 120 DTR
Testing of WRC 1 18-24 DTR
Reactivation of WRC 10 120 DTR
DOP testing filters 1 24 (LTM) L3
Flow testing of PST dilution air 1 LTM DTR
filters
Radiological monitors calibrated DTR
Flame arrestors inspection 1 (4 arrestors) DTR
VST ejector testing 1 (4 ejectors) DTR