BMS SCHEDULE
SWIMMING POOL HEATING
SEQUENCE OF OPERATIONS
THE SWIMMING POOL WATER HEATING IS INITIATED BY AN OPERATOR COMMAND OR
SCHEMATIC SYSTEM DESCRIPTION WHEN THE POOL WATER TEMPERATURE FALLS BELOW A PRESET LOW LIMIT
DESCRIPTION NOTES TEMPERATURE (TWO DEGREES BELOW THE POOL TEMPERATURE SETPOINT).
REFERENCE THE WATER HEATING CYCLE SHALL OPERATE IN THE FOLLOWING SEQUENCE:
THE SYSTEM CONSISTS OF THE FOLLOWING EQUIPMENT (FOR THE ACTUAL QUANTITIES
OF MECHANICAL EQUIPMENT REFER TO THE MECHANICAL SCHEDULES AND RISER 1. HOT WATER VALVES SHALL OPEN.
DIAGRAMS): 2. THE HOT WATER VALVES SHALL CLOSE WHEN THE WATER TEMPERATURE
ENTERING THE HEAT EXCHANGER REACHES THE PRESET POOL WATER
PWT POOL WATER TEMPERATURE X X 1. TWO CIRCULATION PUMPS TEMPERATURE SETPOINT.
CHWVC CHILLED WATER VALVE COMMAND X 7. ALL NECESSARY COMPONENTS AND ACCESSORIES REQUIRED FOR THE
CHWVS CHILLED WATER VALVE STATUS X
PROPER OPERATION OF THE SYSTEM ALARMS & EQUIPMENT STATUS LEVEL +9.40 M (QNHD) = +0.00 M (ARCHITECTURAL)
THE SWIMMING POOL WATER COOLING IS INITIATED BY AN OPERATOR COMMAND OR INTEGRATION WITH BUILDING BMS
PUMPS WHEN THE POOL WATER TEMPERATURE EXCEEDS A PRESET HIGH LIMIT TEMPERATURE
(TWO DEGREES ABOVE THE POOL TEMPERATURE SETPOINT).
PSS PUMP START/STOP X X A COMPLETE INTERFACE SOLUTION TO THE BMS SHALL BE PROVIDED.
THE WATER COOLING CYCLE SHALL OPERATE IN THE FOLLOWING SEQUENCE:
PS PUMP STATUS (ON/OFF) X
1. CHILLED WATER VALVES SHALL OPEN.
THE INTERFACE BETWEEN THE WATER TREATMENT CONTROLLERS AND BMS SHALL
PNF PUMP NORMAL/FAULT (TRIP) X X THROUGH DIFFERENTIAL PRESSURE SWITCH 2. THE CHILLED WATER VALVES SHALL CLOSE WHEN THE WATER TEMPERATURE
INCLUDE ALL NECESSARY CABLES AND REQUIRED CONTACTS FOR THE PROPER
P-HOA-MAN PUMP IN "MANUAL" POSITION AT MCC X X ENTERING THE HEAT EXCHANGER REACHES THE PRESET POOL WATER
HARDWIRED AND / OR SOFTWARE TRANSFER OF THE INFORMATION TO THE BMS.
PUMP SWITCH POSITION TO BE SHOWN ON SCREEN TEMPERATURE SETPOINT.
P-HOA-OFF PUMP IN "OFF" POSITION AT MCC X X
WATER FEATURE
HAMMAM MOTORIZED DAMPERS
SEQUENCE OF OPERATIONS
SYSTEM DESCRIPTION
FADS: DI EADS: DI
THE SYSTEM CONSISTS OF THE FOLLOWING EQUIPMENT:
FADC: DO EADC: DO
1. FILTRATION PUMPS SETS
2. FILTERS
3. CHEMICAL DOSING UNITS (WHERE APPLICABLE)
4. ALL NECESSARY COMPONENTS AND ACCESSORIES REQUIRED FOR THE PROPER OPERATION OF
THE SYSTEM FRESH AIR EXHAUST AIR PROJECT
THE SYSTEM SHALL BE DIRECTLY CONTROLLED AND MONITORED BY MEANS OF A DEDICATED CONTROL
PANEL.
THE CONTROL PANEL SHALL BE CONNECTED TO THE BUILDING MANAGEMENT SYSTEM (BMS). KATARA TOWERS AT LUSAIL
Lusail District, Doha
NORMAL OPERATION SEQUENCE
CLIENT
SYSTEM OFF
SGS: DI
WHEN THE SYSTEM IS DISABLED, ALL PUMPS ARE OFF. Katara Hospitality
SYSTEM START-UP & OPERATING SEQUENCE
Katara Hospitality Building, Marina District,
SYSTEM SHALL BE STARTED MANUALLY FROM THE PUMP ROOM, AUTOMATICALLY ACCORDING TO A Lusail City, PO Box 2977 Doha, Qatar
PREDEFINED SCHEDULE OR REMOTELY FROM THE BMS.
HAMMAM
IF THE DUTY PUMP FAILS TO START, THE STANDBY PUMP SHALL CUT IN AND AN ALARM SHALL BE SENT TO LEAD
THE BMS. CONSULTANT
ALTERNATION
IN ORDER TO PROVIDE EQUAL OPERATING TIMES, ALL PUMPS IN EACH SET SHALL BE AUTOMATICALLY
ALTERNATED AS DUTY/STANDBY.
THE INTERLOCK SHALL PREVENT THE START-UP OF THE PUMPS IN CASE OF LOW WATER LEVEL IN THE
SURGE TANK (OR LOW FLOW AS APPLICABLE).
BMS SCHEDULE
Q17017-0100D TD GN MI 801 1 OF 1 00