TOWER -2 External Finishing Works Status As of 25-3-2012

Rasping, Grooving & Corner 
Preparation & plumb check 

Ceresit 1st coat & fixing ct 
Block works for enclosing 

Electrical LED light fittings

External Painting works
Balcony waterproofing 

Tile works for balcony

Balcony hand railing
Balcony false ceiling

Aluminium profile
Ceresit Final coat
Insulation fixing
drainage risers.
ELEVATION FLOOR

Drop beams

325 mesh
for EIFS

strips
North North-1 Planned 100% 100% 100% 100% 100% 100% 100% 100%

North North-1 Actual

North North-2 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-2 Actual 70% 100% 100% 95% 100% 90%

North North-3 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-3 Actual 70% 100% 100% 95% 100% 90%

North North-4 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-4 Actual 70% 100% 100% 95% 100% 90%

North North-5 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-5 Actual 70% 100% 100% 95% 100% 90%

North North-6 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-6 Actual 70% 100% 100% 95% 100% 90%

North North-7 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-7 Actual 70% 100% 100% 95% 100% 90%

North North-8 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-8 Actual 70% 100% 100% 95% 100% 90%

North North-9 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-9 Actual 70% 100% 100% 95% 100% 80%

North North-10 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-10 Actual 70% 100% 100% 95% 100% 70%

North North-11 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-11 Actual 70% 100% 100% 95% 100% 70%

North North-12 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 33% 100%

North North-12 Actual 70% 100% 100% 90% 100% 70%

North North-13 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-13 Actual 70% 100% 50% 100% 20%

North North-14 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-14 Actual 70% 100% 100%

North North-15 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 92%

North North-15 Actual 70% 100% 100%

North North-16 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-16 Actual 70% 100% 100%

North North-17 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-17 Actual 70% 100%

North North-18 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100%

North North-18 Actual 70% 80%

North North-19 Planned 100% 100% 100% 100% 100% 100% 100% 100% 42%

North North-19 Actual 50% 80%

Page 1 of 4
TOWER -2 External Finishing Works Status As of 25-3-2012

Rasping, Grooving & Corner 
Preparation & plumb check 

Ceresit 1st coat & fixing ct 
Block works for enclosing 

Electrical LED light fittings

External Painting works
Balcony waterproofing 

Tile works for balcony

Balcony hand railing
Balcony false ceiling

Aluminium profile
Ceresit Final coat
Insulation fixing
drainage risers.
ELEVATION FLOOR

Drop beams

325 mesh
for EIFS

strips
East East-1 Planned 100% 100% 100% 100% 100% 100% 100% 100%

East East-1 Actual

East East-2 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-2 Actual 80% 100% 100% 95% 98% 90% 70% 50% 40%

East East-3 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-3 Actual 80% 100% 100% 95% 98% 90% 70% 50% 40%

East East-4 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-4 Actual 80% 100% 100% 95% 98% 90% 70% 50% 40%

East East-5 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-5 Actual 80% 100% 100% 95% 98% 90% 70% 50% 40%

East East-6 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-6 Actual 80% 100% 100% 95% 98% 90% 70% 50% 40%

East East-7 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-7 Actual 80% 100% 100% 95% 98% 90% 70% 50% 40%

East East-8 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-8 Actual 80% 100% 100% 95% 98% 90% 70% 50%

East East-9 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-9 Actual 80% 100% 100% 80% 98% 90% 70% 50%

East East-10 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-10 Actual 80% 100% 100% 95% 90% 90% 70% 50%

East East-11 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-11 Actual 80% 100% 100% 95% 90% 90% 70% 40%

East East-12 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 33% 100%

East East-12 Actual 80% 100% 100% 95% 90% 90% 70% 40%

East East-13 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-13 Actual 80% 100% 90% 90% 70% 40%

East East-14 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-14 Actual 80% 100% 90% 90% 40%

East East-15 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 92%

East East-15 Actual 80% 100% 90% 90% 40%

East East-16 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-16 Actual 80% 100% 90% 90%

East East-17 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-17 Actual 80% 100% 90% 90%

East East-18 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100%

East East-18 Actual 70% 100%

East East-19 Planned 100% 100% 100% 100% 100% 100% 100% 100% 42%

East East-19 Actual 50%

Page 2 of 4
TOWER -2 External Finishing Works Status As of 25-3-2012

Rasping, Grooving & Corner 
Preparation & plumb check 

Ceresit 1st coat & fixing ct 
Block works for enclosing 

Electrical LED light fittings

External Painting works
Balcony waterproofing 

Tile works for balcony

Balcony hand railing
Balcony false ceiling

Aluminium profile
Ceresit Final coat
Insulation fixing
drainage risers.
ELEVATION FLOOR

Drop beams

325 mesh
for EIFS

strips
South South-1 Planned 100% 100% 100% 100%

South South-1 Actual

South South-2 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

South South-2 Actual 80% 100% 100% 95% 90% 90% 90% 40%

South South-3 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

South South-3 Actual 80% 100% 100% 95% 90% 90% 90% 40%

South South-4 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

South South-4 Actual 80% 100% 100% 95% 90% 90% 90% 40%

South South-5 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

South South-5 Actual 80% 100% 100% 95% 90% 90% 90% 40%

South South-6 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

South South-6 Actual 80% 100% 100% 95% 90% 90% 70% 40%

South South-7 Planned 100% 100% 100% 100% 100% 100% 100% 100% 22% 92%

South South-7 Actual 80% 100% 100% 95% 90% 90% 70% 40%

South South-8 Planned 100% 100% 100% 100% 100% 100% 100% 100%

South South-8 Actual 80% 100% 100% 95% 90% 90% 70%

South South-9 Planned 100% 100% 100% 100% 100% 22% 83%

South South-9 Actual 80% 100% 100% 95% 90% 90% 50%

South South-10 Planned 100% 100% 100% 100% 22%

South South-10 Actual 80% 100% 100% 95% 90% 90% 50%

South South-11 Planned 100% 100% 100% 100%

South South-11 Actual 80% 100% 100% 95% 90% 70% 50%

South South-12 Planned 100% 100% 100% 100%

South South-12 Actual 80% 100% 100% 50% 90% 70% 50%

South South-13 Planned 100% 100% 100% 100%

South South-13 Actual 80% 100% 90% 70% 50%

South South-14 Planned 100% 100% 100% 100%

South South-14 Actual 80% 100% 90% 70% 50%

South South-15 Planned 100% 100% 100% 100%

South South-15 Actual 80% 100% 90% 70% 20%

South South-16 Planned 100% 100% 100% 100%

South South-16 Actual 80% 100% 75% 10%

South South-17 Planned 100% 100% 100% 100%

South South-17 Actual 80% 100% 75%

South South-18 Planned 100% 100% 100% 100%

South South-18 Actual 80% 80%

South South-19 Planned 100% 100% 100% 100%

South South-19 Actual 50% 50%

Page 3 of 4
TOWER -2 External Finishing Works Status As of 25-3-2012

Rasping, Grooving & Corner 
Preparation & plumb check 

Ceresit 1st coat & fixing ct 
Block works for enclosing 

Electrical LED light fittings

External Painting works
Balcony waterproofing 

Tile works for balcony

Balcony hand railing
Balcony false ceiling

Aluminium profile
Ceresit Final coat
Insulation fixing
drainage risers.
ELEVATION FLOOR

Drop beams

325 mesh
for EIFS

strips
West West-1 Planned 100% 100% 100% 100%

West West-1 Actual

West West-2 Planned 100% 100% 100% 100% 100% 100% 10% 100% 100% 100%

West West-2 Actual 80% 100% 100% 95% 100% 100% 100% 100% 100%

West West-3 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

West West-3 Actual 80% 100% 100% 95% 100% 100% 100% 100% 100%

West West-4 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

West West-4 Actual 80% 100% 100% 95% 100% 100% 100% 100% 100%

West West-5 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

West West-5 Actual 80% 100% 100% 95% 100% 100% 100% 100% 100%

West West-6 Planned 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%

West West-6 Actual 80% 100% 100% 95% 100% 100% 100% 100% 100%

West West-7 Planned 100% 100% 100% 100% 100% 100% 100% 100% 22% 92%

West West-7 Actual 80% 100% 100% 95% 100% 100% 100% 100% 100%

West West-8 Planned 100% 100% 100% 100% 100% 100% 100% 100%

West West-8 Actual 80% 100% 100% 95% 100% 100% 100% 100%

West West-9 Planned 100% 100% 100% 100% 100% 22% 83%

West West-9 Actual 80% 100% 100% 95% 100% 100% 95% 80%

West West-10 Planned 100% 100% 100% 100% 22%

West West-10 Actual 80% 100% 100% 95% 100% 100% 95% 80%

West West-11 Planned 100% 100% 100% 100%

West West-11 Actual 80% 100% 100% 95% 100% 100% 95% 80%

West West-12 Planned 100% 100% 100% 100%

West West-12 Actual 80% 100% 100% 95% 100% 100% 95% 80%

West West-13 Planned 100% 100% 100% 100%

West West-13 Actual 80% 100% 100% 100% 95% 70%

West West-14 Planned 100% 100% 100% 100%

West West-14 Actual 80% 100% 100% 100% 90% 70%

West West-15 Planned 100% 100% 100% 100%

West West-15 Actual 80% 100% 100% 100% 90% 70%

West West-16 Planned 100% 100% 100% 100%

West West-16 Actual 80% 100% 100% 100% 90% 70%

West West-17 Planned 100% 100% 100% 100%

West West-17 Actual 50% 50% 100% 100% 90% 70%

West West-18 Planned 100% 100% 100% 100%

West West-18 Actual 50% 30%

West West-19 Planned 100% 100% 100% 100%

West West-19 Actual 50%