Professional Documents
Culture Documents
1. PURPOSE AND SCOPE: - The purpose of this method statement is to provide general
guidelines for painting works, and to define the inspection activities. It covers the activities
of painting works at all project sites.
3. REFERENCE DOCUMENTS:-
➢ IFC drawings
➢ PTS
➢ Painting system approval
➢ Applicable company standards
4. RESPONSIBILITY:
Project Manager
Site Manager
5.
Site Manager will be responsible for:-
➢ Over-all direction.
➢ Monitoring.
➢ Coordination.
➢ Control of all the constructions activities related to the paintings.
1
Document Title:
SMART TAMEER PVT LTD MOS Paintings
Site Engineer/Supervisor
QA/QC Manager/Engineer
HSE engineer/Supervisor
2
Document Title:
SMART TAMEER PVT LTD
MOS Paintings
➢ Scrappers
➢ Abrasive papers
➢ Bucket
Materials:
➢ Floor Finishes : Chemical Surface Hardener (For Cable Basement Floors)
➢ Interior and Exterior walls : Epoxy Enamel Paint & Polyurethane Paint
➢ Sealant
6 PROCEDURE:
Painting Procedure:
➢ Mockup sample would be made for selection and approval of the COMPANY
representative prior to the commencement of the work.
➢ Check material and painting system is approved from the COMPANY.
➢ Delivered paint shall be checked with the following points:
3
Document Title:
SMART TAMEER PVT LTD
MOS Paintings
➢ Expiry date, original labeled container, Manufacturers name, type of paint brand name,
color designation and instruction of mixing.
➢ Material shall be stored in cool, well ventilated dry place, away from direct sun light.
➢ Storage of paint material shall be strictly followed as per manufacturer recommendations.
Surface Preparation:
➢ Make sure block masonry works, plastering, Slab/wall/foundation pours and grout Etc.
are properly cured as per manufacturer requirements prior to commencement of work.
➢ Confirm the surfaces cleaned of all contaminants.
➢ Confirm the surface imperfections, nail head protrusions are repaired.
➢ Confirm unsound and friable concrete removed and repaired with a suitable concrete
repair mortar as per Concrete Procedure - P-ALF-C-001.
➢ Confirm surface irregularities and blow holes repaired with suitable repair mortar.
➢ Confirm the surface is dry.
➢ Confirm holes/voids are filled up prior to first coating.
➢ Hardware material which are already fixed and not to be painted shall be removed, if
removal not possible shall be covered/Protected.
➢ Clean and concrete or cement plaster surfaces to be painted. Efflorescence, chalk, dust
dirt, grease and oil shall be removed.
➢ The surface of the area to be painted would be prepared by removing loose partials, flaws
and any foreign material shall be removed by way of sanding.
Sealant Application:
➢ The joints shall be thoroughly cleaned to remove all traces of dust, oil, grease or any
unsound or contaminated material that might affect subsequent adhesion bond between the
sealant and substrate.
➢ Then backing rod will be inserted into the joints up to the nominated sealant depth.
➢ Sealant will then be inserted/pushed by hand tools or sealant gun.
➢ Tooling of sealant will be carried out immediately after application.
Application of Paintings:
4
SMART TAMEER PVT LTD Document Title:
MOS Paintings
➢ Make sure block masonry works, plastering, Slab/wall/foundation pours and grout Etc. are
properly cured as per manufacturer requirements prior to installation of finish.
➢ All painting shall be thoroughly mechanically stirred to a uniform consistency.
➢ Thinning and mixing ratio shall be in accordance with manufacturer recommendations.
➢ The primer shall be applied as per manufacturer recommendations with correct thickness
required.
➢ All priming and filling shall be rubbed down to a smooth surface with fine abrasive paper
and cleaned off all dust before application of first coat.
➢ Material shall be evenly spread and applied smoothly without runs and sags, by skilled
workers.
➢ Care shall be taken to avoid brush marks, sags and other defects.
➢ The coat interval, curing period and DFT of each coat shall be checked as per manufacturer
requirements. (Manufacturer painting system attached for reference)
➢ All coats of paint shall be allowed to dry before the subsequent coats.
➢ Apply number of coats as per specification and manufacturer recommendation.
➢ Painting shall be done as per approved RAL number.
➢ Each coat shall be checked and released by QAQC personnel.
➢ Related drawings
➢ Material approval
➢ Mock up sample approval
➢ Request for inspection
➢ Checklist
7 ATTACHMENT: