Professional Documents
Culture Documents
SUPPORTING
S.NO SHUT DOWN JOB DESCRIPTION DEPARTMENT DAY TEAM
Crusher Section
Trolley: limit switch checking, JB connection tightening/dressing, Cable dressing. DAY 3 TAWSEEF
1
All belt conveyers: JB connection tightening/dressing, ZSS, Pull Cord rope and Belt sway DAY 3 TAWSEEF
checking/replacement,Cable dressing.
2
3 Apron feeder: VFD pannel dressing/cleaning/contactor checking. Parameter list update DAY 3 TAWSEEF
4 Protection guards for installed Vibro sensors and all R.T.D’s. Mechanical DAY 2 MUZAFFAR
8 Bin weighing system maintenence and calibration. Parameter List Update DAY2 TAWSEEF
Pull Chord Electrical connection scheme - revamping / standradisation Mechnical DAY 1 MUZAFFAR
9
Purge Feed Back/ Healthy Feed back for Bag filter to CCR DAY 1 TAWSEEF
10
Bag filtersMaintenance - pannel connection tightening/dressing/cleaning - Purging cycle testing, diaphram DAY1 TAWSEEF
replacement if required
11
Raw Mill Section
All belt conveyers: JB connection tightening/dressing, ZSS, Pull Cord rope and Belt sway
checking/replacement,Cable dressing.
1
Damper actuators operation and cross checking of end limit indication/travel time/interlock along with Process
Process Engineer.
2
Folaphone maintenance and cross check along with Process Engineer Process
3
Maintenance / Calibration of all Weigh feeders. Parameter List Update DAY 2 SAFEER/TAJAMUL
4
AC Drives Panel for all weighfeedersdressing/cleaning/contactor checking. Parameter List Update DAY 1 SAFEER/TAJAMUL
5
Vibro sensors / Vibro Controller maintenance / replacemnet if required - Cros check with Mechanical Mechanical DAY 1 SAFEER/TAJAMUL
6
Lubrication Systems cycle operation to be checked and tested along with mechnical Mechanical
7
Bag filtersMaintenance - pannel connection tightening/dressing/cleaning - Purging cycle testing, diaphram
replacement if required
8
Installation of DP switch in Bag Filters / cable laying. Purge Feed Back/ Healthy Feed back for Bag filter to Mechanical/DYNAMIC SHOWKET
CCR
9
Maintenance for all Bucket elevators boot level and BDS.
10
RTDs and Thermocouples connection tightening/dressing/cleaning -calibration
11
JBs connection tightening/cleaning and proper covering with polyethylene stretch cling
12
Maintenance and Calibration of SFM Reject. Parameter List Update
13
Dressing and Ferruling of I/O panels.
14
Change of auxiliary contactors in O-Sepa and RA fan panels, replacement if required
15
Pull Chord Electrical connection scheme - revamping / standradisation DAY 4 SHOWKET
16
Change of geared motor of 351WF2
17
Iron ore / Silca weighfeeder panel interchange as per drawings and data sheet. Parameter List Update DAY1 & DAY3 SHOWKET
18
RABH
Checking of Solenoid valves, limit switches,proxies for puppet valves Mechanical DAY 4 MUZAFFAR
1
Cable revamping/relocation and proper dressing DAY 4 MUZAFFAR
2
Screw conveyers ZSS checking, cable dressing,conduit replacement and proper covering with polyethylene
stretch cling
3
Damper actuators operation and cross checking of end limit indication/travel time/interlock along with Process
Process Engineer.
4
JBs connection tightening/cleaning and proper covering with polyethylene stretch cling DAY 5 MUZAFFAR
5
Change of fresh air damper actuator / wiring on demand of Process and mechanical Process,Mechanical DAY 5 MUZAFFAR
6
HNL Polution equipment upgradiation as per HNL recommendation and CPCB norms
7
8 Cleaning of stack analszer panel and probes, Relocate probe in chimney as per CPCB norms
Blending Silo
1 Checking and Calibration of all motorized gates, pneumatic gates and butterfly valves. Mechanical DAY 5 TAWSEEF
1 Checking , maintenance, cleaning and calibration of all spouts of packing machine.Parameter List Update DAY 10 SAFEER/TAJAMUL
2 Check / Change of solenoids and filters of packing machine DAY 10 SAFEER/TAJAMUL
3 JB dressing, conduit, ZSS, Pull Cord and Belt Sway of all belt conveyers.
4 Cleaning and checking of all the PLC Panels.
5 Checking of all boot levels and BDS of elevators
6 Checking , maintenance, cleaning of truck loader
7 Proper UPS Power distribution DAY 11 SAFEER/TAJAMUL
8 Installation of new packer controllers
PLC
1 Cleaning and maintenance of Servers,Engineering station and CCR Opstations. DAY 13 SAFEER/TAJAMUL
Replacement of PLC battries.
2 Checking and cleaning of PLC panels.
3 Cleaning and checking of UPS Panel.
4 Checking and Cleaning of all I/O panels in MCC
5 Proper UPS Power distribution (Installation of New Panel) DAY 12 SHOWKET
SERVICES ENGINEERS
HNL for recommissioning of stack analyser Upgradiation
L&T Engineer for new Pannel installation Kiln Dc drive Upgradiation
ABB Gas Analyser O2 / PLC installation Upgradiation
FLSA - Packer Controllers Upgradiation
Hind Rectifier for checking of ESP Fields Upgradiation
Material Requisition
DESCRIPTION Req No. PO.No. Status as on 17-11-
2020
Vibro Sensors Req No 4843 N.A
Diaphragm Or Solenoid For Bag Filters Req No 5166, N.A
5167
Geared Motor Of 351WF2 And 511WF3 Req No 4851 N.A
Panel Cooling Fan In RABH AC Drive PO No. 4560 N.A
Position Transmitters Of Actuators 411DV1-DV6 PO No. 5626 N.A
Kiln Floating Limit Switches Req No 5164 N.A
Flow Meters In Cooler Fans PO No.4167 N.A
Panel Cooling Fan In existing Kiln DC Drive Req No. 1782 N.A
UPS Power Distribution (Installation Of New Panel) Dynamic N.A
Electricals
Change Of Panel Fan In Ac Drives PO No 5625 N.A
Magnetic Separator 521MS1 Panel Checking, Control Transformer Change PO No 3979 N.A
Change Of Drive In Weigh-Feeders 511WF3, 531WF3. PO No 5476 N.A
RTD To Analog Module Converter - Reckers Req No.5163 N.A
Metal Detector PO No 1980 N.A
VFD Cement Mill Osepa 250 KW Against VSK 250 N.A
KW VFD
D.C Drive Kiln 200 KW N.A
Department Tools Multimeter,Clamp N.A
meter, vibro
controller,screw
driver
7- Core cable 1.5sqmm for bag filter upgradiation set,blower,drill,DP
Req:5206 N.A
calibrator,telephon
Pyrometer communication cable M16-12 DIL Cable eReq:4865
tool box N.A
Raw mill
RABH
Blending Silo
Roll Press
Cement Mill
Grinding Unit
Packing
PLC
CHEDULE ( DECEMBER 2020 )
6 7 8 9 10 11 12 13 14 15