Professional Documents
Culture Documents
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : A.1.1 (8)
Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : Month
Output - As Submitted :1
Output - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. 1
Page 1
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : A.1.4 (1)
Provision of Progress Photographs
Unit of Measurement : Each
Output - As Submitted : 240
Output - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. 2
Page 2
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : B.5
Project Billboard / Signboard
Unit of Measurement : Each
Output - As Submitted : 2.00
Output - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. 3
Page 3
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : B.7 (1)
Occupational Safety and Health Program
Unit of Measurement : Month
Output per Month - As Submitted : 1.00
Output per Month - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 4
Page No. 4
Page 5
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : B.9
Mobilization / Demobilization
Unit of Measurement : Lump Sum
Output - As Submitted : 1.00
Output - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 6
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 101 (1)
Removal of Structures and Obstruction
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 7
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 803 (1) a
Structure Excavation, Common Soil
Unit of Measurement : cu.m.
Output per hour - As Submitted : 20.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 8
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 804 (1) a
Embankment, From roadway/structure excavation
Unit of Measurement : cu.m.
Output per hour - As Submitted : 9.84
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
#REF!
Page 9
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 804 (1) b
Embankment, From borrow
Unit of Measurement : cu.m.
Output per hour - As Submitted : 9.84
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
#REF!
Page 10
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 804 (4)
Gravel fill
Unit of Measurement : cu.m.
Output per hour - As Submitted : 1.20
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 11
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 900 (1) c2
Structural Concrete (Footings and Slab on Fill), A, 28 days
Unit of Measurement : cu.m.
Output per hour - As Submitted : 0.36
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. #REF!
Page 12
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 900 (1) c3
Structural Concrete (Footing Tie Beams), A, 28 days
Unit of Measurement : cu.m.
Output per hour - As Submitted : 0.27
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. #REF!
Page 13
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 900 (1) c4
Structural Concrete (Columns), A, 28 days
Unit of Measurement : cu.m.
Output per hour - As Submitted : 0.27
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. #REF!
Page 14
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 900 (1) c5
Structural Concrete (Suspended Slab), A, 28 days
Unit of Measurement : cu.m.
Output per hour - As Submitted : 0.27
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page No. #REF!
Page 15
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 900 (1) c6
Structural Concrete (Beams/Girders), A, 28 days
Unit of Measurement : cu.m.
Output per hour - As Submitted : 0.27
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 16
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 902 (1) a
Reinforcing Steel (Deformed), Grade 40
Unit of Measurement : kg.
Output per hour - As Submitted : 129.09
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 17
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 903 (2)
Formworks and Falseworks
Unit of Measurement : sq.m.
Output per hour - As Submitted : 4.50
Output per hour - As Evaluated :
Page 18
Materials
a. Phenolic board (.0019 x 1.2 x 2.4) - 5 uses pc 0.35 1,336.00 92.72
F.2 b. Good Lumber bd.ft 4.73 55.00 86.66
c. Consumables (5% of Material Cost) 20.88
Sub- Total for F.2- As Evaluated 200.26
G.1 Direct Unit Cost (E.1 + F.1) - As Evaluated 511.66
G.2 Direct Unit Cost (E.2+ F.2) - As Submitted 511.66
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 15% of G.1 76.75
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 15% of G.2 76.75
I.1 Contractor's Profit (CP) - As Submitted 10% of G.1 51.17
I.2 Contractor's Profit (CP) - As Evaluated 10% of G.2 51.17
J.1 Value Added Tax (VAT)- As Submitted 5% of (G.1 + H.1 + I.1) 31.98
J.2 Value Added Tax (VAT)- As Evaluated 5% of (G.2 + H.2 + I.2) 31.98
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 671.56
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 671.56
Prepared by: Checked/ Reviewed by:
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 19
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1000 (1)
Soil Poisoning
Unit of Measurement : Liter
Output per hour - As Submitted : 5.40
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 20
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1001 (8)
Sewer Line Works
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
Page 21
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 22
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1001 (9)
Storm Drainage and Downspout
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 23
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1002 (4)
Plumbing Fixtures
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 24
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1002 (24)
Cold Water Lines
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 25
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1003 (1) a1
Ceiling, 4.5 mm, Metal Frame, Fiber Cement Board
Unit of Measurement : sq.m.
Output per hour - As Submitted : 1.49
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 26
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1004 (2)
Finishing Hardware
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 27
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1007 (1) a
Aluminum Framed Glass Door, Sliding Type
Unit of Measurement : sq.m.
Output per hour - As Submitted : 0.26
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 28
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1007 (1) b
Aluminum Framed Glass Door, Swing Type
Unit of Measurement : sq.m.
Output per hour - As Submitted : 0.26
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 29
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1008 (1) a
Aluminum Glass Windows, Sliding Type
Unit of Measurement : sq.m.
Output per hour - As Submitted : 0.26
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 30
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1008 (1) c
Aluminum Glass Windows, Awning Type
Unit of Measurement : sq.m.
Output per hour - As Submitted : 0.36
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 31
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1010 (1)
Frames, Jambs, Sills, Head, Transoms and Mullion
Unit of Measurement : Set
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 32
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1010 (2) a
Doors, Flush
Unit of Measurement : sq.m.
Output per hour - As Submitted : 0.36
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 33
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1013 (2) b1
Fabricated Metal Roofing Accessory, gauge 24, Gutters
Unit of Measurement : l.m.
Output per hour - As Submitted : 11.80
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 34
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1014 (1) b2
Prepainted Metal Sheets, above 0.427 mm, Rib Type, Long Span
Unit of Measurement : sq.m.
Output per hour - As Submitted : 2.08
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 35
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1016 (1) a
Waterproofing, Cement-base
Unit of Measurement : sq.m
Output per hour - As Submitted : 1.88
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 36
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1018 (1)
Glazed Tiles and Trims
Unit of Measurement : sq.m
Output per hour - As Submitted : 1.37
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 37
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1018 (2)
Unglazed Tiles
Unit of Measurement : sq.m
Output per hour - As Submitted : 1.95
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 38
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1027 (1)
Cement Plaster Finish
Unit of Measurement : sq.m
Output per hour - As Submitted : 7.13
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 39
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1032 (1) a
Painting Works, Masonry/Concrete
Unit of Measurement : sq.m
Output per hour - As Submitted : 2.10
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 40
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1046 (2) a1
CHB Non Load Bearing (including Reinforcing Steel), 100 mm
Unit of Measurement : sq.m
Output per hour - As Submitted : 3.83
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 41
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1046 (2) a2
CHB Non Load Bearing (including Reinforcing Steel), 150 mm
Unit of Measurement : sq.m
Output per hour - As Submitted : 3.18
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 42
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1047 (2) a
Structural Steel, Trusses
Unit of Measurement : kg
Output per hour - As Submitted : 85.00
Output per hour - As Evaluated :
Page 43
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1047 (6)
Metal Structure Accessories (Steel Plates)
Unit of Measurement : kgs.
Output per hour - As Submitted : 12.995
Output per hour - As Evaluated : .
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 44
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1051 (6)
Railing
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 45
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1100 (10)
Conduits, Boxes and Fittings (Conduit Works/Conduit Rough-in)
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
Page 46
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 47
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1101 (33)
Wires and Wiring Devices
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
Page 48
#REF! Construction Section
Page 49
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1102 (1)
Panelboard with Main & Branch Breakers
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 50
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1103 (1)
Lighting Fixtures and Lamps
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 51
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1105 (20)
Network Cabling
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 52
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1109 (1)
Grounding System
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 53
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1111 (8)
2 Spool Insulator Wire Rack
Unit of Measurement : Set
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 54
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1202 (6) a1
Fire Extinguisher, 10 lbs, ABC with bracket
Unit of Measurement : Set
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 55
Err:509
Err:509
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM POW-2015-01D-00
Item No./ Description : 1208(1)
Fire Alarm System
Unit of Measurement : Lump Sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
PRINCESS M. MURIA
Engineer II
#REF! Construction Section
Page 56
BACK-UP COMPUTATION
0 cu.m.
Length Width Height Quantity
TB 4.50 x 0.25 x 0.45 x 0 = 0
TB 5.50 x 0.25 x 0.45 x 0 = 0
TB 3.50 x 0.25 x 0.45 x 0 = 0
TB 2.50 x 0.25 x 0.45 x 0 = 0
8.9010 cu.m.
Length Width Height Quantity
C1 0.3 x 0.30 x 4.30 x 23 = 8.901
C2 0 x 0.00 x 0.00 x 0 = 0
18.00 cu.m
Area Thickness Qty
SLAB 180 x 0.1 x 1.000 = 18.00 cu.m.
8.04 cu.m
Height Width Length Quantity
0.00 x 0.00 x 0.00 x 0 = 0.0000
0.00 x 0.00 x 0.00 x 0 = 0.0000
fb
0.00 x 0.00 x 0.00 x 0 = 0.0000
0.00 x 0.00 x 0.00 x 0 = 0.0000
0.30 x 0.20 x 4.00 x 12 = 2.8800
0.30 x 0.20 x 3.00 x 18 = 3.2400
rb
0.30 x 0.20 x 2.50 x 4 = 0.6000
0.30 x 0.20 x 5.50 x 4 = 1.3200
FLOOR BEAM Beam Length No. of Bars Dev Length (0.3) Quantity
0.00 x 0.00 x 0.30 x 0 = 0.0000
0.00 x 0.00 x 0.30 x 0 = 0.0000
fb
0.00 x 0.00 x 0.30 x 0 = 0.0000
0.00 x 0.00 x 0.30 x 0 = 0.0000
4.00 x 4.00 x 0.30 x 12 = 57.6000 l.m. 16.mmØ
3.00 x 4.00 x 0.30 x 18 = 64.8000
rb
2.50 x 4.00 x 0.30 x 4 = 12.0000
5.50 x 4.00 x 0.30 x 4 = 26.4000
(L/4 + 0.3)*2 L-(2*L/5)+0.3+ No. of Bars Quantity
0.60 x 0.30 x 5 x 0 = 0.0000
0.60 x 0.30 x 5 x 0 = 0.0000
fb
0.60 x 0.30 x 5 x 0 = 0.0000
0.60 x 0.30 x 5 x 0 = 0.0000
10mmØ Rebars
end bend span net length set
base hor. bars 0.30 3 3.30 10.00 = 66 m
base long. bars 0.30 1.5 1.8 5.00 = 9 m
east vert. bars 0.30 1.5 1.8 5.00 = 9 m
east hor. bars 0.30 1.5 1.8 5.00 = 9 m
part 1 vert. bars 0.30 1.5 1.8 5.00 = 9 m
part 1 hor. bars 0.30 1.5 1.8 5.00 = 9 m
part 2 vert. bars 0.30 0 0.3 0.00 = 0 m
part 2 hor. bars 0.30 0 0.3 0.00 = 0 m
west t vert. bars 0.30 1.5 1.8 5.00 = 9 m
west hor. bars 0.30 1.5 1.8 5.00 = 9 m
north vert. bars 0.30 3 3.3 10.00 = 33 m
west hor. bars 0.30 1.5 1.8 5.00 = 9 m
lift bar 0 0.4 0.00 = 0 m
171 m
Area Quantity
Two-Way slab 180.00 x 0 = 0.00 l.m. 10mm Ø
(Using Slab Area)
wt factor: Weight
25 mm Ø 0.00 l.m. 3.853 0.00 kgs
20 mm Ø 0.00 l.m. 2.469 0.00 kgs
16 mm Ø 630.30 l.m. 1.580 995.87 kgs
12 mm Ø 929.00 l.m. 0.888 824.95 kgs
10 mm Ø 1414.35 l.m. 0.617 872.65 kgs
Ceiling, 4.5 mm, Metal Frame, Fiber Cement Board 180.00 sq.m.
Prepainted Metal Sheets, above 0.427 mm, Rib Type, Long Span 242 sq.m.
CHB Non Load Bearing (including Reinforcing Steel), 100 mm 0.00 sq.m.
Length height qty
0 x 0 x 0.00 = 0
2nd flr 0 x 0 x 0.00 = 0
0 x 0 x 0.00 = 0
0 x 0 x 0.00 = 0
0 x 0 x 0.00 = 0
grnd flr
0 x 0 x 0.00 = 0
0 x 0 x 0.00 = 0
0
Length height qty
D1 0.8 x 2.1 x 0.00 = 0
W1 0 x 0 x 0.00 = 0
0
CHB Non Load Bearing (including Reinforcing Steel), 150 mm 204.67 sq.m.
Length height qty
0 x 0 x 0.00 = 0
2nd flr 0 x 0 x 0.00 = 0
0 x 0 x 0.00 = 0
9 x 4.3 x 1.00 = 38.7
9 x 4.3 x 1.00 = 38.7
grnd flr
20 x 4.3 x 1.00 = 86
20 x 4.3 x 1.00 = 86
249.4
area to be deducted
Length height qty
D-1 2.50 x 2.15 x 1.00 = 5.375
D-2 0.90 x 2.10 x 6.00 = 11.34
D-3 0.80 x 2.10 x 1.00 = 1.68
D-4 0.70 x 1.80 x 5.00 = 6.3
D-5 0.00 x 0.00 x 0.00 = 0
D-6 0.00 x 0.00 x 0.00 = 0
D-7 0.00 x 0.00 x 0.00 = 0
24.695
Length height qty
W1 0.60 x 0.60 x 5.00 = 1.8
W2 1.80 x 0.60 x 2.00 = 2.16
W3 2.10 x 1.20 x 2.00 = 5.04
W4 1.20 x 1.20 x 1.00 = 1.44
W5 2.00 x 1.20 x 4.00 = 9.6
W6 0.00 x 0.00 x 0.00 = 0
W7 0.00 x 0.00 x 0.00 = 0
W8 0.00 x 0.00 x 0.00 = 0
W9 0.00 x 0.00 x 0.00 = 0
20.04
1100 (10) Conduits, Boxes and Fittings (Conduit Works/Conduit Rough-in) 1 Lump Sum
1101 (33) Wires and Wiring Devices 1 Lump Sum
1102 (1) Panelboard with Main & Branch Breakers 1 Lump Sum
1103 (1) Lighting Fixtures and Lamps 1 Lump Sum
PROJECT TITLE
: Soil Poisoning
Unit of Measurement : Liter
Output per hour : 5.40
Item No./ Description : Ceiling, 4.5 mm, Metal Frame, Fiber Cement Board
Unit of Measurement : sq.m.
Output per hour : 1.49
Item No./ Description : Fabricated Metal Roofing Accessory, gauge 24, Gutters
Unit of Measurement : l.m.
Output per hour : 11.80
###
Item No./ Description : Prepainted Metal Sheets, above 0.427 mm, Rib Type, Long Span
Unit of Measurement : sq.m.
Output per hour : 2.08
###
PROJECT TITLE
Item No./ Description : CHB Non Load Bearing (including Reinforcing Steel), 100 mm
Unit of Measurement : sq.m
Output per hour : 3.83
###
Item No./ Description : CHB Non Load Bearing (including Reinforcing Steel), 150 mm
Unit of Measurement : sq.m
Output per hour : 3.18
###
PROJECT TITLE
Item No./ Description : Conduits, Boxes and Fittings (Conduit Works/Conduit Rough-in)
Unit of Measurement : Lump Sum
Output per hour : 1.00 ###
Item No./ Description : Panelboard with Main & Branch Breakers ###
Unit of Measurement : Lump Sum
Output per hour : 1.00
Designation
No. of Person/s No. of day/s Daily Rate Amount (PhP)
Labor
A.1 Registered Electrical Engineer 0 7.00 1,200.00 -
Registered Master Electrician / NCII Electrician 3 7.00 550.00 11,550.00
Unskilled Laborer 6 7.00 420.00 17,640.00
Sub- Total for A.1. 29,190.00
Name and Capacity No. of Unit/s
No. of day/s Daily Rate Amount (PhP)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 2,335.20
Sub- Total for B.1. 2,335.20
C.1 Total (A.1 + B.1) . 31,525.20
D.1 Output per hour . 1.00
E.1 Direct Unit Cost (C.1 / D.1) . 31,525.20
Name and Specification Unit
Quantity Unit Cost Amount (PhP)
Materials
DP Main: 100AT/125AF, 2P, Bolt-on type, NEMA 1, set 12.00 7,410.00 88,920.00
Branches: 40AT, 2P, BOLT-ON TYPE ls 48.00 1,500.00 72,000.00
F.1 -
-
-
-
Consumables (3% of material cost) 4,827.60
Sub- Total for F.1. 165,747.60
G.1 Direct Unit Cost (E.1+ F.1) - As Evaluated 197,272.80
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 9% of G.1 17,754.55
I.1 Contractor's Profit (CP) . 8% of G.1 15,781.82
J.1 Value Added Tax (VAT). 12% of (G.1 + H.1 + I.1) 27,697.10
K.1 Total Unit Cost . (G.1 + H.1 + I.1 + J.1) 258,506.28
###
PROJECT TITLE ###
Name and Capacity No. of Unit/s No. of day/s Daily Rate Amount (PhP)
B.1 Equipment
Minor Tools (8% of Labor Cost) 1,629.60
Sub- Total for B.1. 1,629.60
C.1 Total (A.1 + B.1) . 21,999.60
D.1 Output per hour . 1.00
E.1 Direct Unit Cost (C.1 / D.1) . 21,999.60
Materials
Led Fluorescent Tube 18W pc 0 700.00 -
2-40W Flourescent Lamp pc 60 280.00 16,800.00
F.1 40W Compact Flourescent Lamp pc 0 149.00
25W PinLight pc 48 65.00 3,120.00
Consumables (3% of material cost) 597.60
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
Sub-total P -
DAYS NUMBER RATE/DAY
B. LABOR :
Skilled Laborer 4.00 1 550.00 2,200.00
Unskilled Labor 4.00 2 420.00 3,360.00
Sub-total P 5,560.00
DAY NUMBER RENTAL RATE/DAY
C. EQUIPMENT :
Cargo Truck 2 1 5,000.00 5,000.00
Miscellaneous Handtools 5,000.00
Sub-total P 10,000.00
D. ESTIMATED DIRECT COST (TOTAL) P 15,560.00
E. MARK-UPS P -
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 0% of EDC -
2. Contractor's Profit, 0% of EDC -
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
Sub-total P -
DAYS NUMBER RATE/DAY
B. LABOR :
Skilled Laborer 2.00 2 550.00 2,200.00
Unskilled Labor 2.00 2 420.00 1,680.00
Sub-total P 3,880.00
DAY NUMBER RENTAL RATE/DAY
C. EQUIPMENT :
Backhoe 1.00 1 12,000.00 12,000.00
Dump Truck 1.00 1 5,000.00 5,000.00
Miscellaneous Handtools 5,000.00
Sub-total P 22,000.00
D. ESTIMATED DIRECT COST (TOTAL) P 25,880.00
E. MARK-UPS P -
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 0% of EDC -
2. Contractor's Profit, 0% of EDC -
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
Sub-total P -
DAYS NUMBER RATE/DAY
B. LABOR :
Skilled Laborer 2.00 2 550.00 2,200.00
Unskilled Labor 2.00 2 420.00 1,680.00
Sub-total P 3,880.00
DAY NUMBER RENTAL RATE/DAY
C. EQUIPMENT :
Mini Backhoe 2.00 1 10,000.00 20,000.00
Dump Truck 2.00 1 5,000.00 10,000.00
Minor Tools (8% of Labor Cost) 310.40
Sub-total P 30,310.40
D. ESTIMATED DIRECT COST (TOTAL) P 34,190.40
E. MARK-UPS P 5,812.37
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 3,077.14
2. Contractor's Profit, 8% of EDC 2,735.23
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
Sub-total P -
DAYS NUMBER RATE/DAY
B. LABOR :
Skilled Laborer 3.00 2 550.00 3,300.00
Unskilled Labor 4.00 2 420.00 3,360.00
Sub-total P 6,660.00
DAY NUMBER RENTAL RATE/DAY
C. EQUIPMENT :
Plate Compactor (5 hp) 3.00 1 984.00 2,952.00
Mini Backhoe 4.00 1 10,000.00 40,000.00
Minor Tools (8% of Labor Cost) 532.80
Sub-total P 43,484.80
D. ESTIMATED DIRECT COST (TOTAL) P 50,144.80
E. MARK-UPS P 8,524.62
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 4,513.03
2. Contractor's Profit, 8% of EDC 4,011.58
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 9,752.93
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 5,163.31
2. Contractor's Profit, 8% of EDC 4,589.61
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 247,712.87
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 131,142.11
2. Contractor's Profit, 8% of EDC 116,570.76
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 315,876.06
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 167,228.50
2. Contractor's Profit, 8% of EDC 148,647.56
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 95,172.56
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 50,385.47
2. Contractor's Profit, 8% of EDC 44,787.09
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 29,094.51
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 15,402.98
2. Contractor's Profit, 8% of EDC 13,691.54
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 12,467.04
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 6,600.20
2. Contractor's Profit, 8% of EDC 5,866.84
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 47,950.10
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 25,385.35
2. Contractor's Profit, 8% of EDC 22,564.75
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 7,502.36
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 3,971.84
2. Contractor's Profit, 8% of EDC 3,530.52
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
BILL NO. : Ceiling, 4.5 mm, Metal Frame, Fiber Cement Board
ITEM NO. 13 :
E. MARK-UPS P 69,403.79
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 36,743.18
2. Contractor's Profit, 8% of EDC 32,660.61
Assumed Qty. :
LOCATION : Brgy. Imelada, San Juan, Batangas
E. MARK-UPS P 36,531.30
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 19,340.10
2. Contractor's Profit, 8% of EDC 17,191.20
ITEM NO. 15 :
E. MARK-UPS P 11,278.63
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 5,971.04
2. Contractor's Profit, 8% of EDC 5,307.59
BILL NO. : Prepainted Metal Sheets, above 0.427 mm, Rib Type, Long Span
ITEM NO. 16 :
E. MARK-UPS P 61,136.89
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 32,366.59
2. Contractor's Profit, 8% of EDC 28,770.30
ITEM NO. 17 :
E. MARK-UPS P 81,942.79
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 43,381.48
2. Contractor's Profit, 8% of EDC 38,561.31
ITEM NO. 18 :
E. MARK-UPS P 46,799.05
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 24,775.97
2. Contractor's Profit, 8% of EDC 22,023.08
ITEM NO. 19 :
E. MARK-UPS P 48,138.77
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 25,485.23
2. Contractor's Profit, 8% of EDC 22,653.54
BILL NO. : CHB Non Load Bearing (including Reinforcing Steel), 100 mm
ITEM NO. 20 :
E. MARK-UPS P 61,621.24
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 32,623.01
2. Contractor's Profit, 8% of EDC 28,998.23
BILL NO. : CHB Non Load Bearing (including Reinforcing Steel), 150 mm
ITEM NO. 21 :
E. MARK-UPS P 136,435.85
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 72,230.74
2. Contractor's Profit, 8% of EDC 64,205.10
ITEM NO. 22 :
E. MARK-UPS P 98,570.93
1. Overhead, Contingence, Miscellaneous (OCM) & Expenses, 9% of EDC 52,184.61
2. Contractor's Profit, 8% of EDC 46,386.32
ITEM NO. 23 :
1 2 3 4
30
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
60
37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68
53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68
90
69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84
69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84
85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
120
101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116
101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116
117 118
117 118
150
Activity Symbol
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
W
X
Y
Z
A'
B'
C'
D'
E'
TOTAL
Activity
Mobilization
Site Clearing
Excavation
Embankment From Excavated Material
Soil Poisoning
Gravel Fill
Reinforcing Steel (Fabrication)
Reinforcing Steel (Installation)
Structural Concrete-Foundation Footing & GF slab, beam, column (formworks and concrete pouring)
Reinforcing Steel (Fabrication)
Reinforcing Steel (Installation)
Structural Concrete-2nd Floor slab, beam, colum (formworks and concrete pouring)
Trusses and Purlins Fabrication and Installation with water leak test
Roofing Installation
Concrete Curring
Rebars fabrication and installation, Formworks and Concrete Pouring for Stairs
Laying of CHB and other wall partitions
Electrical wirings (Rough-ins)
Ceiling Finish Installation
Electrical Fixtures, Panel Board and Circuit breakers Installation
Concrete Plastering
Windows Installation
Doors Installation
Cold Water Lines Installation
Sewer Lines installation
Laying of CHB and cover slab for septic tank
Tiles Installation
Building Accessories Installation
Plumbing Fixtures installations
Concrete Painting
Demobilization
TOTAL
Predecessor Duration Start Finish Amount wt. (%) cum. wt. (%)
- 2 3 1 3 ₱11,618.13 0.10% 0.10%
A 1 2 4 5 ₱28,985.60 0.25% 0.35%
B 1 2 6 7 ₱44,803.10 0.38% 0.73%
C 3 3 8 11 ₱65,709.75 0.56% 1.29%
C 3 3 8 11 ₱224,267.36 1.91% 3.19%
E 6 6 12 18 ₱75,177.85 0.64% 3.83%
F 4 4 12 16 ₱486,969.40 4.14% 7.97%
G,F 8 8 19 27 ₱486,969.40 4.14% 12.11%
H 14 12 28 42 ₱881,013.85 7.49% 19.61%
G 4 4 17 21 ₱486,969.40 4.14% 23.75%
J, I 8 8 43 51 ₱486,969.40 4.14% 27.89%
K 14 12 52 66 ₱881,013.85 7.49% 35.38%
L 7 15 67 74 ₱759,807.92 6.46% 41.84%
M 6 7 75 81 ₱558,195.88 4.75% 46.59%
I 13 14 43 56 ₱0.00 0.00% 46.59%
L 7 3 67 74 ₱1,367,983.25 11.63% 58.23%
P 19 13 75 94 ₱1,450,337.11 12.33% 70.56%
N 6 6 82 88 ₱53,648.20 0.46% 71.02%
R 10 13 89 99 ₱534,980.76 4.55% 75.57%
S 6 6 100 106 ₱450,300.88 3.83% 79.40%
Q 13 17 95 108 ₱360,738.05 3.07% 82.46%
U 5 5 109 114 ₱140,795.93 1.20% 83.66%
U 5 5 109 114 ₱140,795.93 1.20% 84.86%
H 6 7 28 34 ₱57,829.92 0.49% 85.35%
H 6 7 28 34 ₱96,098.84 0.82% 86.17%
Y 3 4 35 38 ₱76,333.53 0.65% 86.82%
U 19 20 109 128 ₱631,634.29 5.37% 92.19%
D' 13 7 129 142 ₱172,005.46 1.46% 93.65%
A' 6 6 129 135 ₱369,610.64 3.14% 96.79%
U 13 14 109 122 ₱371,064.99 3.16% 99.95%
B', C' 1 2 136 137 ₱5,809.07 0.05% 100.00%
232 1 142 ₱11,758,437.73 100.00%
2872
SCURVE DATA
ADJUST NIYO MANPOWER (MAGIC METHOD) NO. OF WORKERS
TOTAL WORKERS
30
1 1 1
1 1
1 1
1 1 1
1 1 1
1 1 1 1 1
1 1 1 1
1
1
1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.03 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
15 15 15 15 15 15 15 15 15 15 9 9 9 9 9
15 15 0 0 0 0 0 0 0 0 0 0 0 0 0
8 8 8 8 8 8 8 8 8 8 8 16 16 16 16
8 8 0 0 0 0 0 0 0 0 0 0 0 0 0
3 3 3 4 4 4 4 16 16 16 16 31 31 31 31
₱1,546,242.94
₱1,546,242.94
13.15%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1.2
0.8
Axis Title
0.6
0.4
0.2
0
0 5 10 Axis 15
Title 20 25 30
30
1 1 1 1 1 1 1 1
1 1 1 1 1 1
1 1 1
1 1 1 1 1 1
1 1 1 1 1 1
0
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
9 9 18 18 18 18 18 18 18 9 9 9 9 10 10
0 18 0 0 0 0 0 0 0 0 0 0 0 0 0
16 16 16 16 16 10 10 10 10 10 10 10 10 7 7
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
31 31 31 31 31 31 31 31 31 31 31 31 31 31 31
₱1,476,503.19
₱3,022,746.13
25.71%
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
0 0
18 13.15%
36 25.71%
54 36.09%
72 68.45%
90 79.12%
108 95.08%
115 100.00%
60
1 1 1 1 1 1
1 1 1 1 1 1 1 1
1 1
1 1 1 1 1 1 1 1 1 1
1
1
1 1 1 1
0
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
10 10 5 5 5 7 7 7 7 7 6 6 8 8 8 8
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 10 10 10 10 10 8 8 11 11 11 11 16 16 16 16
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
31 31 31 31 35 35 35 35 35 35 35 35 30 30 30 30
₱1,221,147.61
₱4,243,893.74
36.09%
31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
60
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1
1 1 1 1
1 1 1
1 1 1
0
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
12 12 12 12 12 12 12 12 12 24 12 12 12 12 12 12
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 16 16 16 16 32 14 14 14 14 14 14 14 14 14 14
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
30 30 30 30 30 30 30 30 30 30 30 28 28 28 28 28
,221,147.61 ₱3,804,706.1
,243,893.74 ₱8,048,599.9
36.09% 68.45%
47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62
90
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1
0
2 2 2 2 2 2 2 2 2 4 6 8 10 12 14 16
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.14 0.21 0.28 0.35 0.42 0.49 0.56
12 12 12 12 12 12 12 12 12 8 8 8 8 8 8 8
0 0 0 0 0 0 0 0 0 16 16 16 16 16 16 16
14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
0 0 0 0 0 0 0 0 0 28 28 28 28 28 28 28
28 28 28 28 28 28 28 28 28 28 28 28 25 25 25 25
₱3,804,706.19
₱8,048,599.93
68.45%
63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78
1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
2
18 20 22 24 26 28 30 32 34 36 40 44 48 52 55 58
0.63 0.70 0.77 0.84 0.91 0.97 1.04 1.11 1.18 1.25 1.39 1.53 1.67 1.81 1.92 2.02
8 8 8 7 7 7 7 7 7 7 7 7 7 7 7 7
16 16 16 14 14 14 14 14 14 14 28 28 28 28 21 21
14 14 14 12 12 12 12 12 12 12 6 6 6 6 7 7
28 28 28 24 24 24 24 24 24 24 24 24 24 24 21 21
25 25 25 25 25 25 25 25 25 25 24 24 24 24 24 24
₱1,254,158.79
₱9,302,758.72
79.12%
79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94
120
1 1 1
1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1
1
1 1 1 1 1 1 1 1 1
3
61 64 67 67 67 70 73 75 77 79 81 83 85 87 89 91
2.12 2.23 2.33 2.33 2.33 2.44 2.54 2.61 2.68 2.75 2.82 2.89 2.96 3.03 3.10 3.17
7 7 7 4.2 7 6.68 5 5 5 5 5 5 5 5 5 5
21 21 21 0 0 20.04 15 10 10 10 10 10 10 10 10 10
7 7 7 7 7 7 7 9 9 9 9 7 7 7 7 7
21 21 21 0 0 21 21 18 18 18 18 14 14 14 14 14
24 24 24 24 24 24 24 24 24 24 24 24 24 24 30 30
₱1,876,672.13
₱11,179,430.85
95.08%
95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110
1 1 1 1 1 1
1 1 1 1 1
1 1
2
93 95 97 98 99 99 99 99 99 99 99 99 99 99 99
3.24 1.71 3.38 3.41 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
6.68 6.68 6.68 5 5 10 9 9 9 8 8 8 8 8 8
13.36 13.36 13.36 5 5 0 0 0 0 0 0 0 0 0 0
7 7 7 10 11 12 13 14 15 16 17 18 19 20 21
14 14 14 10 11 0 0 0 0 0 0 0 0 0 0
30 30 30 30 26 26 26 26 26 26 26 26 20 20 20
₱579,006.88
₱11,758,437.73
100.00%
150
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
9 9 9 18 5 5 5 5 5 5 9 9 9 9 9 9
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
22 23 24 25 26 27 28
0 0 0 0 0 0 0
20 20 20 16 16 16 16 16 16 16 10 10 10 10 10 10
₱0.00
₱11,758,437.73
100.00%
3 ₱11,618.13 ₱0.00
2 ₱28,985.60 ₱0.00
2 ₱44,803.10 ₱0.00
3 ₱65,709.75 ₱0.00
3 ₱224,267.36 ₱0.00
6 ₱75,177.85 ₱0.00
4 ₱486,969.40 ₱0.00
8 ₱121,742.35 ₱365,227.05
12 ₱0.00 ₱881,013.85
4 ₱486,969.40 ₱0.00
8 ₱0.00 ₱0.00
12 ₱0.00 ₱0.00
15 ₱0.00 ₱0.00
7 ₱0.00 ₱0.00
14 ₱0.00 ₱0.00
3 ₱0.00 ₱0.00
13 ₱0.00 ₱0.00
6 ₱0.00 ₱0.00
13 ₱0.00 ₱0.00
6 ₱0.00 ₱0.00
17 ₱0.00 ₱0.00
5 ₱0.00 ₱0.00
5 ₱0.00 ₱0.00
7 ₱0.00 ₱57,829.92
7 ₱0.00 ₱96,098.84
4 ₱0.00 ₱76,333.53
20 ₱0.00 ₱0.00
7 ₱0.00 ₱0.00
6 ₱0.00 ₱0.00
14 ₱0.00 ₱0.00
2 ₱0.00 ₱0.00
₱1,546,242.94 ₱1,476,503.19
0
99 99 99
3.45 3.45 3.45
9 9 8
0 0 0
10 3 3
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱486,969.40 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱734,178.21 ₱146,835.64 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱759,807.92 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱79,742.27 ₱478,453.61 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱1,367,983.25 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱1,450,337.11 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱53,648.20 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱246,914.20 ₱288,066.56 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱450,300.88 ₱0.00
₱0.00 ₱0.00 ₱360,738.05 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱28,159.19 ₱112,636.74 ₱0.00
₱0.00 ₱0.00 ₱28,159.19 ₱112,636.74 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱0.00
₱0.00 ₱0.00 ₱31,581.71 ₱568,470.86 ₱31,581.71
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱172,005.46
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱369,610.64
₱0.00 ₱0.00 ₱26,504.64 ₱344,560.34 ₱0.00
₱0.00 ₱0.00 ₱0.00 ₱0.00 ₱5,809.07
₱1,221,147.61 ₱3,804,706.19 ₱1,254,158.79 ₱1,876,672.13 ₱579,006.88
₱11,758,437.73
180
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
₱0.00
180
240
270
300 330 360
0 390 420 450
480 1 2
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
3 4 5 6 7
8
Activity Symbol
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
W
X
Y
Z
A'
B'
C'
D'
E'
TOTAL
Activity
Mobilization
Site Clearing
Excavation
Embankment From Excavated Material
Soil Poisoning
Gravel Fill
Reinforcing Steel (Fabrication)
Reinforcing Steel (Installation)
Structural Concrete-Foundation Footing & GF slab, beam, column (formworks and concrete pouring)
Reinforcing Steel (Fabrication)
Reinforcing Steel (Installation)
Structural Concrete-2nd Floor slab, beam, colum (formworks and concrete pouring)
Trusses and Purlins Fabrication and Installation with water leak test
Roofing Installation
Concrete Curring
Rebars fabrication and installation, Formworks and Concrete Pouring for Stairs
Laying of CHB and other wall partitions
Electrical wirings (Rough-ins)
Ceiling Finish Installation
Electrical Fixtures, Panel Board and Circuit breakers Installation
Concrete Plastering
Windows Installation
Doors Installation
Cold Water Lines Installation
Sewer Lines installation
Laying of CHB and cover slab for septic tank
Tiles Installation
Building Accessories Installation
Plumbing Fixtures installations
Concrete Painting
Demobilization
TOTAL
Predecessor Duration Start Finish Amount wt. (%) cum. wt. (%)
- 2 3 1 3 ₱11,618.13 0.10% 0.10%
A 1 2 4 5 ₱28,985.60 0.26% 0.36%
B 1 2 6 7 ₱44,803.10 0.40% 0.76%
C 3 4 8 11 ₱65,709.75 0.58% 1.34%
C 3 4 8 11 ₱224,267.36 1.99% 3.33%
E 6 7 12 18 ₱75,177.85 0.67% 3.99%
F 4 5 12 16 ₱486,969.40 4.32% 8.31%
G,F 8 9 19 27 ₱486,969.40 4.32% 12.62%
H 14 15 28 42 ₱881,013.85 7.81% 20.43%
G 4 5 17 21 ₱486,969.40 4.32% 24.75%
J, I 8 9 43 51 ₱486,969.40 4.32% 29.06%
K 14 15 52 66 ₱881,013.85 7.81% 36.87%
L 7 8 67 74 ₱759,807.92 6.73% 43.61%
M 6 7 75 81 ₱558,195.88 4.95% 48.55%
I 13 14 43 56 ₱0.00 0.00% 48.55%
L 7 8 67 74 ₱1,367,983.25 12.12% 60.68%
P 19 20 75 94 ₱999,095.62 8.85% 69.53%
N 6 7 82 88 ₱53,648.20 0.48% 70.01%
R 10 11 89 99 ₱534,980.76 4.74% 74.75%
S 6 7 100 106 ₱450,300.88 3.99% 78.74%
Q 13 14 95 108 ₱360,738.05 3.20% 81.94%
U 5 6 109 114 ₱140,795.93 1.25% 83.18%
U 5 6 109 114 ₱140,795.93 1.25% 84.43%
H 6 7 28 34 ₱57,829.92 0.51% 84.94%
H 6 7 28 34 ₱96,098.84 0.85% 85.80%
Y 3 4 35 38 ₱52,583.98 0.47% 86.26%
U 19 20 109 128 ₱631,634.29 5.60% 91.86%
D' 13 14 129 142 ₱172,005.46 1.52% 93.38%
A' 6 7 129 135 ₱369,610.64 3.28% 96.66%
U 13 14 109 122 ₱371,064.99 3.29% 99.95%
B', C' 1 2 136 137 ₱5,809.07 0.05% 100.00%
232 1 142 ₱11,283,446.69 100.00%
2872
SCURVE DATA
ADJUST NIYO MANPOWER (MAGIC METHOD) NO. OF WORKERS
TOTAL WORKERS
30
1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.03 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
15 15 15 15 15 15 15 15 15 15 9 9 9 9 9
15 15 0 0 0 0 0 0 0 0 0 0 0 0 0
8 8 8 8 8 8 8 8 8 8 8 16 16 16 16
8 8 0 0 0 0 0 0 0 0 0 0 0 0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
3 3 3 4 4 4 4 16 16 16 25 25 25 25 25
3 3 3 4 4 4 4 16 16 16 25 25 25 25 25
35
30
25
No. of Workers
20
15
10
0
1 4 7 10 13 16 19 22 25 28 31 34
30
0
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
9 9 18 18 18 18 18 18 18 9 9 9 9 10 10 10
0 18 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 16 16 16 16 10 10 10 10 10 10 10 10 7 7 7
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
25 25 25 25 25 25 25 25 25 31 31 31 31 31 31 31
25 25 25 25 25 25 25 25 25 31 31 31 31 31 31 31
28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76
No. of Days
60
0
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
10 5 5 5 7 7 7 7 7 6 6 8 8 8 8 12
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 10 10 10 10 8 8 11 11 11 11 16 16 16 16 16
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
31 31 31 31 31 25 25 25 25 25 25 25 25 30 30 30
31 31 31 31 31 25 25 25 25 25 25 25 25 30 30 30
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
12 12 12 12 12 12 12 12 24 12 12 12 12 12 12 12
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 16 16 16 32 14 14 14 14 14 14 14 14 14 14 14
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
30 30 30 30 30 30 30 30 28 28 28 28 25 25 25 25
30 30 30 30 30 30 30 30 28 28 28 28 25 25 25 25
90
0
2 2 2 2 2 2 2 2 4 6 8 10 12 14 16 18
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.14 0.21 0.28 0.35 0.42 0.49 0.56 0.63
12 12 12 12 12 12 12 12 8 8 8 8 8 8 8 8
0 0 0 0 0 0 0 0 16 16 16 16 16 16 16 16
14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
0 0 0 0 0 0 0 0 28 28 28 28 28 28 28 28
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79
25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
2
20 22 24 26 28 30 32 34 36 40 44 48 52 55 58 61
0.70 0.77 0.84 0.91 0.97 1.04 1.11 1.18 1.25 1.39 1.53 1.67 1.81 1.92 2.02 2.12
8 8 7 7 7 7 7 7 7 7 7 7 7 7 7 7
16 16 14 14 14 14 14 14 14 28 28 28 28 21 21 21
14 14 12 12 12 12 12 12 12 6 6 6 6 7 7 7
28 28 24 24 24 24 24 24 24 24 24 24 24 21 21 21
80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95
25 25 25 25 25 25 25 25 25 25 30 30 30 30 30 28
25 25 25 25 25 25 25 25 25 25 30 30 30 30 30 28
120
3
64 67 67 67 70 73 75 77 79 81 83 85 87 89 91 93
2.23 2.33 2.33 2.33 2.44 2.54 2.61 2.68 2.75 2.82 2.89 2.96 3.03 3.10 3.17 3.24
7 7 4.2 7 6.68 5 5 5 5 5 5 5 5 5 5 6.68
21 21 0 0 20.04 15 10 10 10 10 10 10 10 10 10 13.36
7 7 7 7 7 7 9 9 9 9 7 7 7 7 7 7
21 21 0 0 21 21 18 18 18 18 14 14 14 14 14 14
96 97 98 99 100 101 102 103 104 105 106 107 108 109 110
28 28 25 25 25 25 25 25 18 18 18 18 15 3 3 18
28 28 25 25 25 25 25 25 21 21 21 21 21 21 18 18
2
95 97 98 99 99 99 99 99 99 99 99 99 99 99 99
1.71 3.38 3.41 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
6.68 6.68 5 5 10 9 9 9 8 8 8 8 8 8 9
13.36 13.36 5 5 0 0 0 0 0 0 0 0 0 0 0
7 7 10 11 12 13 14 15 16 17 18 19 20 21 22
14 14 10 11 0 0 0 0 0 0 0 0 0 0 0
18 18 18 18 15 3 3
18 18 18 18 15 3 3
150
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
9 9 18 5 5 5 5 5 5 9 9 9 9 9 9 9
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
23 24 25 26 27 28
0 0 0 0 0 0
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
9 8 8 8 5 5 5 5 5 7 7 7 7 7 4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
180
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
180
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
240
0
99 99 99 99 99 99 99 99 99 99 99 99 99 99 99 99
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
270 300
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
0
99 99 99 99 99 99 99 99###
######
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
3.45 3.45 3.45 3.45 3.45 3.45 3.45 3.45
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
4 4 4 4 4 4 4 ###
4###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
0 0 0 0 0 0 0 ###
0###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
300 330 360 390
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
90 420 450 480
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
1 2 3 4 5 6 7 8
3
2
2
4
4
7
5
9
15
5
9
15
8
7
14
8
20
7
11
7
14
6
6
7
7
4
20
14
7
14
2
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
0 1 1 1 1 2 2 1 3
A B C
0 0 1 1 0 2 2 0 3
3 1 4
D
3 0 4
3 2 5 4 2 6 6 5 11 8 32
E SS1 F H SS2 I
3 0 5 4 0 6 6 0 11 8 0
SS1
5 3 8
G
5 0 8
11
R
59
11
S
58
40 3 43 43 2 45 45 3 48
SS2
J K M
49 9 52 52 9 54 54 9 57
40
I
40
40 7 47 47 5 52 52 3 55
L P Q
40 0 47 47 0 52 52 0 55
52 5 57
U
60 8 65
3 14
R
48 62 15 3 18
T
4 15 62 47 65
S
47 62
47 8 55
N
57 10 65
48 8 56
O
57 9 65
55 5 60 60 2 62 62 3 65
V W X
55 0 60 60 0 62 62 0 65
65 1 66
Q
65 0 66
Activity Symbol
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
W
X
Y
Activity
Mobilization
Site Clearing
Excavation
Embankment From Excavated Material
Soil Poisoning
Gravel Fill
Reinforcing Steel (Fabrication)
Reinforcing Steel (Installation)
Structural Concrete-Foundation Footing & slab, beam, column for Ground Floor (formworks and concrete pouring)
Purlins Fabrication and Installation
Roofing Installation
Laying of CHB and other wall partitions
Electrical wirings (Rough-ins)
Ceiling Finish Installation
Electrical Fixtures, Panel Board and Circuit breakers Installation
Concrete Plastering
Doors & Windows Installation
Cold Water Lines Installation
Sewer Lines installation
Laying of CHB and cover slab for septic tank
Tiles Installation
Concrete Painting
Building Accessories Installation
Plumbing Fixtures installations
Demobilization
Predecessor Duration (days) Start Finish 4 8 12
- 1 0 1 1
A 1 1 2 1
B 1 2 3 1
C 1 3 4 1
C 2 3 5 1 1
E(SS)1 2 4 6 1 1
E 3 5 8 1 1 1
F,G(SS)1 5 6 11 1 1 1 1 1
H(SS)2 32 8 40 1 1 1
I 3 40 43
J 2 43 45
I 7 40 47
K 3 45 48
M 8 47 55
M 8 48 56
L 5 47 52
P 3 52 55
H 3 11 14
H 4 11 15
R,S 3 15 18
P 5 52 57
Q 5 55 60
V 2 60 62
W 3 62 65
X 1 65 66
12 16 20 24 28 32
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1
1 1 1 1
1 1 1
36 40 44 48 52 56
1 1 1 1 1 1 1 1
1 1 1
1 1
1 1 1 1 1 1 1
1 1 1
1 1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1
1
56 60 64 68
1 1
1 1 1
1 1
1 1 1 1
1 1 1 1 1
1 1
1 1 1
1
0 3 3 3 2 5 5 2
A B C
0 0 3 3 3 5 5 0
23 7 30
X
99 76 106
7 3 10 10 6 16 16 7 23 23 11
D F H I
7 0 10 10 0 16 16 0 23 23 0
7
C
7
7 3 10 10 4 14
E G
9 2 12 12 2 16
14 4 18
J
30 16 34
A 3
B 2
C 2
D 3
E 3
F 6
G 4
H 7
I 11
J 4
K 7
L 11
M 14
N 7
O 14
P 3
Q 13
R 6
S 12
T 6
U 16
V 5
W 5
X 7
Y 7
Z 4
A' 18
B' 4
C' 6
D' 14
E' 2
23 7 30 30 4 34
Y Z
99 76 106 106 76 110
34 34 14 48
I O
34 96 62 110
34 7 41 41 11 52 52 3 55 55 13 68
K L P Q
34 0 41 41 0 52 52 0 55 55 0 68
52 14 66 66 7 73
M N
65 13 79 79 13 86
84 5 89
V
105 21 110
84 5 89
W
105 21 110
84 14 98 102 4 106
73 6 79 79 12 91 D' B'
R S 90 6 104 104 -2 108
86 13 92 92 13 104
91 6 97
T
104 13 110
108 2 110
E' END
108 0 110
6 6 6 9 9 10 7 12 29 29 29 29 29 29 29 29 29 29 29 29 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74
3 3 3 4 4 4 4 16 16 16 25 25 25 25 25 25 25 25 25 25 25 25 25 25 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 30 30 30 30 30 30 30 30 30 30 28 28 28 28 25 25 25 25 25 25 25 25 25 25 25 25 25
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
No. of Days