You are on page 1of 17

2-07-631-Xuan.

qxd 12/06/08 8:25 am Page 253

A Performance-Based Design Approach for Coupled


Core Wall Systems with Diagonally Reinforced
Concrete Coupling Beams

Gang Xuan1, Bahram M. Shahrooz2,*, Kent A. Harries3 and Gian A. Rassati2


1ChristieEngineering LLC, Bedminster, New Jersey, USA
2University of Cincinnati, Ohio, USA
3University of Pittsburgh, Pennsylvania, USA

(Received: 16 October 2007; Received revised form: 18 March 2008; Accepted: 20 March 2008)

Abstract: Coupled core wall systems (CCWs) are lateral force resisting systems that
can provide remarkable lateral stiffness for mid- to high-rise buildings, exceeding the
lateral stiffness of isolated walls while providing the redundancy and force
redistribution capabilities of framed systems. The lateral stiffness provided by CCWs
largely depends on the type of coupling beams used to transfer forces between wall
piers. Diagonally-reinforced concrete coupling beams are one of the more common
details although composite alternatives (e.g., those using structural steel W-shapes,
hollow structural steel sections, or embedded steel plates) or beams with rhombic
reinforcement are increasingly being selected as viable alternatives. Despite the
favorable behavior exhibited by diagonally-reinforced coupling beams in experimental
studies, designing and constructing diagonally-reinforced coupling beams having
practical span-to-depth ratios presents significant difficulties, impacting the use of
CCWs as a viable lateral force resisting system. This paper presents a performance-
based design (PBD) approach that allows the designer to successfully proportion a
code-compliant CCW system that addresses the shortcomings related to the traditional
strength-based design approach. A prototype building is designed following both
approaches, and is analyzed both statically and dynamically. Results show that the
PBD approach produces a code-compliant structure that satisfies the most pressing
constructability constraints.

Key words: coupled walls, reinforced concrete, performance-based design, seismic design, design criteria.

1. INTRODUCTION form of core walls, containing elevator shafts, stairwells,


Coupled core wall systems (CCWs) are lateral force and service space. The most efficient system for resisting
resisting systems that have the potential to provide very lateral loads, particularly those caused by earthquakes, is
large lateral stiffness without compromising commercially obtained when individual wall piers are connected by
valuable horizontal and vertical space, while at the same means of coupling beams distributed over their height.
time providing structural redundancy and resistance to The resulting lateral force resisting system is stiffer and
catastrophic loading and fire (FEMA 2003). The stronger than the sum of the individual isolated walls.
combination of concrete flat slab floor systems with CCWs resist lateral forces through a combination of
reinforced concrete walls is ideal in minimizing floor-to- flexural behavior of the wall piers (isolated cantilever
floor heights in mid- to high-rise residential, office, and wall pier flexure) and frame action imparted by the
hospitality structures. Often, structural walls take the coupling beams (accumulation of shear forces in

*Corresponding author. Email address: Bahram.Shahrooz@uc.edu; Fax: +1-513-556-2599; Tel: +1-513-556-3667.

Advances in Structural Engineering Vol. 11 No. 3 2008 253


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 254

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

coupling beams resulting in an axial couple across 1997) have been proposed. Such methods are commonly
multiple wall piers). A measure of this behavior is given referred to as Performance-Based Design (PBD)
by the so-called degree of coupling. The degree of approaches, and entail a preliminary choice of performance
coupling (DOC) of a CCW system is defined as the ratio objectives followed by the design of the structural
of the total overturning moment resisted by the axial members to meet these objectives. By employing a PBD
couple resulting from frame action to the total method for the design of a CCW system, it is possible to
overturning moment resisted by the system: directly recognize the preferred yielding mechanisms of
such systems, and to take full advantage of their
NLw ductility and redundancy characteristics. By doing so,
DOC = (1)
∑ M w + NLw the coupling beams may be permitted to yield at a base
shear sensibly lower than the code-prescribed design
in which, Lw = Lever arm between centroids of the base shear, while the wall piers are still detailed to yield
individual wall piers, Mw = Overturning moments at the prescribed level of base shear provided the
resisted by the individual wall piers, N = Wall axial performance objectives (typically drift-related) are met.
load due to the accumulation of the coupling beam shear Hence, distinct behaviors of the system can be attained
forces. A DOC equal to zero implies that the wall piers at different performance levels. A structure, for
behave as isolated walls (i.e., the walls are connected by instance, can be designed to behave as a CCW system
pinned links). A DOC value of unity implies that the for a “life safety” (LS) performance level (as defined in
structure behaves as a single cantilever wall pier FEMA 356 2000b), and as a collection of isolated wall
spanning the footprint of the coupled system. A number piers at a “collapse prevention” (CP) level (Harries and
of studies have indicated that there is little structural McNeice 2006). This design approach allows for a more
advantage in providing DOC values less than 0.3 and rational use of the favorable characteristics of all
that structurally efficient CCWs are realized for DOC structural elements, and has the potential of resulting in
values ranging from 0.6 to 0.8. In this context, earlier more economical and easily constructed structures. In
Canadian practice (NBCC 1995) designated those walls the following, the coupling beams and the wall piers of
having a DOC less than 0.66 as being “partially a prototype structure are designed based on both the
coupled” while those having a DOC greater than 0.66 code-prescribed SBD method and the proposed PBD
are “fully coupled”. Seismic force reduction factors methods. Static and dynamic analyses of the resulting
were increased for fully coupled systems reflecting their designs are presented and discussed to demonstrate how
superior structural performance. the PBD method is capable of resulting in a structure
The foundation of current building codes and provisions that meets the performance objectives and current code-
is the strength-based design (SBD) method. This prescribed constraints.
method requires that all individual members in a
structural system be provided sufficient capacity to 2. COUPLING BEAM SHEAR AND
resist forces induced by some prescribed set of loads. ROTATION CAPACITY
The application of the SBD method to the design of The response of CCWs is greatly affected by load and
CCW systems presents some difficulties. In particular, deformation characteristics of coupling beams, and an
design shear stresses in coupling beams will invariably accurate assessment of yield and ultimate strengths and
exceed the ACI 318-prescribed limits (Harries et al. rotational capacities of the beams is important from a
2004; Harries and McNeice 2006). The large shear design as well as modeling point of view. In an effort to
demands in coupling beams result from the assumption estimate the expected strength and rotational capacities of
implicit to SBD that wall piers and beams will yield diagonally reinforced concrete coupling beams, a database
practically simultaneously at the code-specified base containing experimental data from 16 reported tests,
shear. However, field observations in the aftermath of which were deemed to represent the most reliable set of
the 1964 Alaska earthquake (Berg and Stratta 1964) data, was compiled. A number of available theoretical
indicate that all or most coupling beams in CCW models of behavior were evaluated against the
structures yielded well before the strength of the experimental results contained in the database. The
coupled walls was attained. In support of this analytical models examined were Paulay’s model (Paulay
observation, theoretical studies (Park and Paulay 1975) 2002), Hindi’s model (Hindi 2001), and the FEMA
also verify that most coupling beams will yield before 356 acceptance criteria (FEMA 2000b). As evident from
the wall capacity is reached. As an alternative to SBD Table 1, these models, by various degrees, either
methods, approaches for the “design and engineering of underestimate or overestimate yield and ultimate strengths
buildings for targeted performance objectives” (Bertero and chord rotations. In order to more reasonably predict

254 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd
12/06/08
8:25 am

Table 1. Ratios of computed to measured values

Specimen Vy/Vy,e θy/θy,e Vu/Vu,e θu/θu,e


Page 255

Source I.D. L/h Paulay Hindi FEMA Proposed Paulay Hindi FEMA Proposed Paulay Hindi FEMA Proposed Paulay Hindi FEMA Proposed
Paulay & 316 1.29 0.91 1.28 0.91 0.91 0.65 0.77 0.13 0.88 0.75 1.08 0.75 0.94 0.90 0.07 0.53 0.36
Binney, 317 1.29 1.04 1.64 1.04 1.04 0.75 0.88 0.12 1.01 0.88 1.48 0.88 1.10 2.05 0.20 1.19 0.83
1974 395 1.03 1.15 1.65 1.15 1.15 0.65 0.78 0.08 0.87 0.88 1.34 0.88 1.10 1.01 0.11 0.67 0.40
Tassios CB-2A 1.00 0.90 1.67 0.90 0.90 0.29 0.35 0.02 0.38 0.68 1.44 0.68 0.85 2.57 0.33 1.06 1.17
et al., CB-2B 1.66 0.93 1.68 0.93 0.93 0.39 0.47 0.04 0.53 0.63 1.30 0.63 0.79 3.67 0.47 0.98 1.73
1996

Advances in Structural Engineering Vol. 11 No. 3 2008


Galano & P05, b1 1.50 0.64 1.27 0.64 0.64 0.70 0.87 0.05 0.90 0.66 1.20 0.66 0.82 2.68 0.17 1.01 1.52
Vignoli, P06, b1 1.50 0.69 1.44 0.69 0.69 0.69 0.85 0.04 0.89 0.64 1.27 0.64 0.80 — — — —
2000 P07, b1 1.50 0.72 1.55 0.72 0.72 0.81 1.01 0.05 1.05 0.66 1.46 0.66 0.82 3.02 0.19 1.14 1.71
P08, b1 1.50 0.72 1.56 0.72 0.72 0.86 1.06 0.05 1.11 0.67 1.48 0.67 0.84 — — — —
P10, b2 1.50 0.64 1.33 0.64 0.64 0.76 0.94 0.05 0.98 0.66 1.96 0.66 0.82 2.90 0.67 1.10 1.65
P11, b2 1.50 0.79 1.57 0.79 0.79 0.75 0.93 0.05 0.97 0.65 1.81 0.65 0.82 — — — —
P12, b2 1.50 0.77 1.55 0.77 0.77 0.60 0.75 0.04 0.78 0.64 1.82 0.64 0.80 3.21 0.79 1.22 1.82
PCA, C6 2.50 1.15 1.15 1.15 1.15 1.00 1.10 0.22 1.42 0.67 0.67 0.67 0.84 2.21 0.14 0.59 1.05
1978 C8 5.00 1.22 1.22 1.22 1.22 1.86 2.37 0.46 2.33 0.70 0.70 0.70 0.88 2.38 0.17 0.38 1.01
Hindi et al. 1 2.74 0.85 1.08 0.85 0.85 1.21 1.35 0.27 1.72 0.62 0.81 0.62 0.77 3.11 0.35 0.66 1.72
Santha B 1.25 0.31 0.36 0.31 0.31 1.18 1.43 0.17 1.56 — — — — 1.28 0.30 0.87 0.64
kumar,
1974
Average 0.84 1.38 0.84 0.84 0.82 0.99 0.11 1.09 0.69 1.32 0.69 0.86 2.38 0.31 0.88 1.20
Standard Deviation 0.23 0.33 0.23 0.23 0.37 0.46 0.12 0.48 0.08 0.39 0.08 0.10 0.87 0.22 0.28 0.53
Coefficient of Variation 27.8% 24.3% 27.8% 27.8% 44.6% 46.0% 104.6% 43.9% 11.9% 29.6% 11.9% 11.9% 36.5% 71.7% 32.0% 43.9%

Vy = Yield strength; θy = Yield rotation


Vu = Ultimate strength; θu = Ultimate rotation
Subscripts “e” refers to the measured values.
L = Span; h = Depth

255
2-07-631-Xuan.qxd 12/06/08 8:25 am Page 256

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

∆y
As = Area of diagonal reinforcement

Asfy

∆y
Asfy

Horizontal deformation (elongation) of coupling beam is ignored.

Figure 1. Coupling beam deformation

the expected yield and ultimate strengths and rotations, a this deformation is restrained by the floor diaphragm,
modified version of Paulay’s model is proposed. Similar and also because its contribution will be small for coupling
to ACI 318 (2005) provisions, the contribution of concrete beams with the most commonly used span-to-depth
confined in the diagonal cores is ignored and the diagonal ratios of around 2.5 to 4.
steel reinforcement is assumed to govern the strength. The yield chord rotation (θby) is:
Hence, the yield shear capacity (Vy) and yield moment
capacity (My) are: θ by = ∆ y / s = 0.65ε y ( s /cos α + 40 d b ) / s (sin α ) (6)

Vy = 2 As f y sin α (2) Assuming a 25% increase in capacity due to strain


hardening, the ultimate yield shear capacity (Vu) and
moment capacity (Mu) are Vu = 1.25Vy and Mu =
M y = Vy s 2 (3) 1.25My. The ultimate chord rotation (θbu) is calculated
assuming a bi-linear force-rotation relationship with
The parameters are defined in Figure 1. The yield chord post-elastic stiffness Er equal to 5% of the elastic
rotation is calculated as a function of the axial stiffness E, in accordance with FEMA 365 (2000b), as
deformations of the diagonal tension and compression follows:
chords at yielding (∆T and ∆C, respectively). The
elongation of the compression chord is taken as 30% of
that of the tension chord, based on experimental results
( )
θ bu = θ by + Vu − Vy / Er (7)

(Paulay 2002): Table 1 summarizes the resulting averages and standard


deviations of the calculated versus experimental ratios
 s 
∆T = ε y  + 40 d b  ; ∆ C = 0.3∆ T (4) for all the models considered in this study. It is evident
 cos α  that the proposed model reproduces the experimental
data with appreciably better accuracy than the existing
The coefficient 40 in Eqn 4 is based on the assumption
models examined.
of having 20db (db = bar diameter) of development
length, as recommended by ACI-ASCE (2002), into
each wall pier. Hence, the vertical component of the 3. THE PROTOTYPE STRUCTURE
average diagonal deformation (∆y) is: A typical 15-story reinforced concrete CCW office
building was chosen as the prototype structure for this
study. The initial layout of the structure was based on a
∆ y = ( ∆ T + ∆ C ) / ( 2 sin α ) = (1.3∆ T ) / ( 2 sin α ) (5) similar research project focusing on a 10-story CCW
= 0.65ε y ( s / cos α + 40 d b ) / sin α structure (Harries et al. 2004). The two governing
requirements driving the design are: (1) the maximum
Note that in the aforementioned derivation, the contribution interstory drift should be less than 2% at the design load
of horizontal deformation has been neglected because level as required by NEHRP (FEMA 2000a); and (2)

256 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 257

Gang Xuan, Bahram M. Shahrooz, Kent A. Harries and Gian A. Rassati

displacement at the corner of the building to that at the


centroid. An average value of the torsion amplification
N factor at all stories was used in the design (Brienen
2002). The dimensions of the core walls and beams
Dw = 3.05 m, s = 1.83 m
b = 7.6 m, t = 508 mm were chosen after a preliminary equivalent lateral force
t
(ELF) analysis performed using the analysis program

5@6.1m = 30.5m
ETABS (CSI 1997). The columns were modeled using
b ETABS column elements and pinned at each end to
ensure no contribution to lateral resistance. The post-
tensioned slabs were modeled as rigid diaphragms. The
Dw s Dw
flanges and webs of the C-shaped core walls were
modeled by means of ETABS panel elements and fixed
at the base of the building. Coupling beams were
modeled with ETABS beam elements and rigidly
connected to the wall panels. The effective flexural
5@6.1m = 30.5m stiffness (“cracked” stiffness) of the core wall in the
ground story was taken as 0.35EcIg, and 0.70EcIg for the
Figure 2. Plan view of prototype structure other stories (Ec = concrete modulus of elasticity and Ig
= gross moment of inertia). As per ACI 318 (2005)
the DOC of the CCW should be at least 0.66. The
recommendations, the stiffness of the coupling beams
prototype structure shown in Figure 2 is assumed to be
was taken as 0.35EcIg. The design concrete compressive
located in San Francisco, CA and is situated on a Class
strength (fc’) was 41.4MPa and Grade 60 reinforcement
C site, and thus falls into seismic design category D. For
(yield strength, fy = 414MPa) was assumed for all the
the chosen site, the parameters defining the design
members. The dimensions for the CCW of the prototype
spectrum are: Ss = 1.5g and S1 = 0.65g (FEMA 2000a).
structure resulting from this preliminary analysis are
The ground story is 3.71m high and stories 2 through 15
shown in Figure 2. With these dimensions, the ELF
are 2.80m high, for a total height of 42.9m. The floors
analysis predicts the greatest story drifts to be 1.97%
are 30.5m square having 20cm thick post-tensioned
and 1.73% in the coupled (EW) and uncoupled (NS)
reinforced concrete slabs. Two load resisting systems
directions, respectively. The DOC was determined from
are identified: (a) columns uniformly spaced in the floor
ELF analysis to be equal to 0.80.
plan and (b) a CCW at the center of the floor plan,
consisting of two C-shaped wall piers, connected by 4. TRADITIONAL STRENGTH-BASED
coupling beams at the ends of both flanges at every floor DESIGN
level. Considering that the lateral stiffness of the CCW Once a prototype structure was identified through ELF
is significantly larger than that provided by the columns, analysis, modal response spectrum analysis (MRSA)
it is assumed that the CCW carries 100% of the lateral was used to evaluate the structural response and the
forces and its tributary share of gravity loads (self earthquake-induced forces in the CCW system. Using
weights of structural components, 480N/m2 for partition the first two flexural modes of the structure in the
load, 240N/m2 mechanical load and 720N/m2 cladding coupled EW direction, 91% of the mass was excited,
load on external surfaces), while the columns carry only complying with NEHRP (FEMA 2000a) requirements
their tributary share of gravity loads. For the sake of that at least 90% of the structural mass be represented in
simplicity, since the columns do not affect the lateral a MRSA.
force response of the system, it is assumed that all In order to obtain the shear demands in the coupling
columns in a floor have the same size as a generic beams, in accordance to NEHRP (FEMA 2000a), the
interio column. The response modification factor, R, is results of the elastic modal analyses were multiplied by
selected as 6 in accordance with Table 5.2.2 of NEHRP three magnification factors: (1) redundancy factor ρ,
(FEMA 2000a). The occupancy importance factor, I, dependent on the ratio of shear demand in one element
was chosen as unity considering the anticipated use of and total story shear demand, and applied to the
the building. Accidental torsional effects were included horizontal component of earthquake forces; (2) strength
in the analysis, corresponding to the lateral force level reduction factor φ, taken as 0.75 for coupling beams;
multiplied by 5% of the transverse lateral dimension of and (3) base shear amplification factor Cb, dependent on
the building considered. Furthermore, for seismic category the ratio of the base shear obtained using an ELF
D, the accidental torsion at each story is amplified by a analysis and the square root of the sum of the squares
torsion amplification factor depending on the ratio of the (SRSS) of the base shear forces for all modes

Advances in Structural Engineering Vol. 11 No. 3 2008 257


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 258

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

15
0.27 f′c 0.59 f′c ACI Limit(0.83 f′c)
14

13

12

11
0.91 f′c
10 0.42 f′c

9
Story

8
1.09 f′c
7 0.50 f′c

6 From SBD Method


5 Average Values from SBD Method

4 Proportionally Scaled Values

3 Proportionally Scaled Design Values

2
1
0.0 0.2 0.4 0.42 f′c 0.6 0.8 0.91 f′c 1.0 1.2
Coupling Beam Shear Stress ( f′c)

Figure 3. Selection of coupling beam design shear stress

considered. Shears resulting from accidental torsion, C1 Lines through C2


magnified by the torsion magnification factor Ax the N.A.
(FEMA 2000a), were then added to the results of the
two-dimensional modal analysis. Wall pier B Wall pier
The resulting shear demands and in particular the
θw θb θw
maximum shear stresses for all the coupling beams were
calculated. It is worth mentioning that section 21.7.7.4 A
of ACI 318 (2005) specifies a maximum value for shear Coupling
Beam
stress in a diagonally reinforced coupling beam equal to
0.83 fc′ (in MPa). Figure 3 indicates that the largest Dw s Dw
calculated value of coupling beam shear stress occurs at
the 4th story, with a shear stress equal to 1.15 fc′ . In Figure 4. Deformation relationship between coupling beam
addition, the coupling beam shear stresses for the first and wall piers
10 stories exceed the maximum value allowed by ACI
318. Previous studies (Harries et al. 2005; Fortney deformation relationship between the wall piers and the
2005) suggest an even lower limit on the shear stresses coupling beams, however, is incompatible with this
of a coupling beam in order that they are practically assumption, as discussed in Paulay (2002). With
constructible. A maximum value of shear stress equal to reference to Figure 4, it is possible to calculate the
0.5 fc′ is recommended as a practical upper limit in vertical distance between points A and B due to wall
order to avoid reinforcement congestion problems in rotation (assuming that the floor diaphragm is rigid in
reasonably proportioned beams. As show in Figure 3, plane, and thus both walls rotate by the same amount):
none of the coupling beams of the prototype structure
can be practically constructed, based on this criteria ∆ AB = θ w × c1 + θ w × ( Dw − c2 )
(8)
even if their stresses were within the acceptable code- = θ w × ( Dw + c1 − c2 )
prescribed limit.
The large shear stresses obtained are the result of the In the simple case of rectangular wall piers in which c1
implausible assumption used in the SBD method, is equal to c2, Eqn 8 becomes:
according to which the wall piers and the beams will
yield approximately at the same level of base shear. The ∆ AB = θ w × Dw (9)

258 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 259

Gang Xuan, Bahram M. Shahrooz, Kent A. Harries and Gian A. Rassati

Alternatively, the same vertical distance between points


A and B can be expressed in terms of the beam chord
Vu Vu
rotation as follows:
Vwy
Vwy
∆ AB = θ b × s (10) VB VB
Vby
Vby
For compatibility, Eqns 9 and 10 must be equal:
T T
θb Dw (a) SBD (b) PBD
θw = s (11)
Figure 5. Comparison of design demands on CCW elements

Eqn 11 indicates that the ratio of beam chord rotation to et al. 2004). This proposed PBD method identifies three
wall pier rotation is equal to the ratio of the wall length stages for the seismic response of a CCW system, in
to the span of the beam. For the selected prototype, this terms of the yielding sequence of the structural
ratio is equal to 1.67. Considering the toe-to-toe channel- members. The first stage is the elastic stage, in which all
shaped wall pier arrangement of the prototype structure, structural members are elastic. The second stage is the
in Eqn 8 c1 > c2 (see Figure 4); thus, Eqn 11 will transition stage, in which the coupling beams yield
underestimate the beam rotation based on the wall progressively and the wall piers remain elastic. The final
rotation. The yield rotation of one wall pier (θwy) can be stage is the global yielding stage, in which wall piers
approximated as φwyhe/2 (Paulay 2002) where he is the yield and the coupling beams continue to rotate in a
distance from the base of the wall to the point of plastic manner and may reach their ultimate
inflection taken as 3/4 of the building height based on deformation capacities. Note that this final stage does
ETABS elastic model of the prototype structure. The not correspond to the formation of a mechanism,
yield curvature, φwy, may be taken as 1.55εy/Dw where εy considering that the wall piers, albeit yielded, have not
= the yield strain (Paulay 2002). The value of θwy is yet reached their ultimate capacity and can still provide
calculated to be 0.0167 rad. for the prototype. Based on lateral resistance. In order to meet this three-stage
the approximation made by Eqn 11, when the wall pier behavior objective, the following CCW performance
yields, the chord rotation of the coupling beam is θb requirements are proposed: (a) at the life-safety (LS)
= 0.0280rad. Using the proposed model (Eqn 6), the performance level, the beams are allowed to yield, but
yield chord rotation capacity of a coupling beam of the the wall piers are required to remain elastic. The
prototype structure is estimated to be θby = 0.0065rad. maximum drift of the structure should remain below 2%
A comparison of this rotation with the rotational demand (FEMA 2000a); and (b) at the collapse prevention (CP)
on coupling beams at wall yielding suggests that performance level the wall piers are allowed to yield,
simultaneous yielding of coupling beams and wall piers and the beams may reach their ultimate deformation
is an unrealistic expectation for practical structures. capacities. These criteria are consistent with the
Practitioners invariably find themselves in the difficult definitions of structural performance at LS and CP
position of having to forego the use of CCW systems on levels found in FEMA 356 (FEMA 2000b) and are
account of the unrealistically high shear stress demands on consistent with the intent of SBD provisions. With these
the coupling beams, due to the SBD method promulgated performance objectives in mind, the design demands for
in current codes. Alternatively, practitioners report coupling beams and wall piers differ from those
arbitrarily reducing the assumed coupling beam cracked obtained through a SBD approach. Figure 5 qualitatively
stiffness to lower the shear forces in the beam and/or illustrates the spectral response of the SBD and
unrealistically increasing the concrete shear strength – proposed PBD approaches for a CCW system. Using the
clearly neither approach has a sound basis. A more former approach, the yielding shear forces Vby and Vwy
rational approach is, therefore, needed in order to take full for beams and walls, respectively, are very close to the
advantage of the favorable behavior of CCW systems. design base shear value VB (corresponding to LS
performance level). It is worth pointing out that a design
5. PROPOSED PERFORMANCE-BASED check at the ultimate base shear Vu (corresponding to CP
DESIGN APPROACH performance level) is not required, because it is assumed
Since the traditional SBD does not appear to be capable that the detailing provisions provided in the codes are
of addressing the expected seismic performance of CCW adequate to ensure development of sufficient deformation
systems, a PBD approach has been proposed (Harries capacity to reach Vu. A review of analytical studies of

Advances in Structural Engineering Vol. 11 No. 3 2008 259


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 260

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

CCWs suggest that this implicit assumption of the SBD (ACI 2005) provisions. In order to ensure the desired
method may not be appropriate for CCW structures due structural behavior, it is important that regardless of
to the significant disparity between frame and wall shear demand, diagonally reinforced coupling beams be
action component stiffnesses (Harries 2001). The PBD used at each level if they are required at any level.
approach, on the other hand, allows the coupling beams (Unless beams having span-to-depth ratios greater than
to yield well before VB is reached. This allowance implies 4 are used, the largest design shear of 0.50 fc ' will
that design forces in coupling beams may be reduced require the use of diagonal reinforcement.) This
and that at the same time the demand on the wall piers requirement will generally lead to providing beams having
be increased. In this case, the ultimate base shear Vu is the same dimensions at each level but with different
related to the onset of the collapse mechanism for the reinforcing details. Coupling beam details for the
structure, corresponding either to the formation of plastic prototype structure are illustrated in Figure 6.
hinges at the base of the wall piers, or to the maximum The design of wall piers follows the same
interstory drift exceeding some assigned value, taken as performance requirements outlined above. It is assumed
2.5% (the maximum code specified value) in this work. that a) the internal forces in the wall piers are calculated
Finally, as a result of the desired three-stage behavior, considering all of the coupling beams have yielded,
the structural period will elongate (shifting the period to thereby transferring a higher demand onto the walls; and
the right in Figure 5), effectively reducing seismic b) the tension and compression walls exhibit different
demands on the wall piers, as the beams progressively stiffness characteristics because of the presence of axial
yield. If this effect is considered, the theoretical increase forces produced by coupling action. The stiffness ratio
in wall pier demand noted above may be mitigated. between the tension and compression walls is taken as
Such an analysis, however, is not presented here. 0.3/0.7 (Paulay 2002). Hence, the flexure and shear
In order to design the coupling beams based on the forces are not distributed equally between the wall piers.
above-mentioned performance requirements, two design For the first assumption, the shear force at each level can
criteria are selected. First, to ensure constructability of be considered equal to the yield capacity Vy of the beams.
beams having practical dimensions, the maximum shear Based on the free-body diagram in Figure 7, the moment
stress in a coupling beam should not exceed 0.50 fc ' . in the tension wall is taken as 30% of the effective
Second, the vertical distribution of shear stresses in moment ME, which is equal to the overturning moment
coupling beams (Figure 3), as obtained in SBD less the moment due to coupling action (ΣVbyL); that is:
approach, is retained. The second criterion is intended to for the two wall system considered, ME is the ΣMw term
enforce simultaneous yielding of most beams. from Eqn 1. Correspondingly, the moment in the
Additionally, to simplify design, coupling beams with
compression wall at each story is taken as 70% of ME.
similar shear demands are grouped as follows: beams
Horizontal shear forces for the tension (Vtx) and
from levels 2 to 7 are classified as group I; beams in
compression (Vcx) walls are also assumed to be 30% and
level 1 and from levels 8 to 10 are classified as group II;
70% of the total story shear Vstr, respectively. In the
and beams from levels 11 to 15 are classified as group
coupled direction, the story shears in the C-shaped
III. This grouping is based on the following guidelines:
compression and tension walls are distributed equally to
a) beam shear stress redistribution required for grouping
the two parallel flange walls. The web of the C-shaped
should not exceed 20% of the calculated stresses prior to
wall pier is not assumed to carry any story shear in the
grouping; and b) the sum of the resulting shear
coupled direction as shown in Section A-A in Figure 7.
capacities of the grouped beams should be not be less
A modal response spectrum analysis is performed in the
than the sum of the calculated stresses prior to grouping.
two orthogonal directions (coupled (EW) and uncoupled
Based on the SBD analysis, beams in group I, II, and III
(NS) directions), and the demand is assessed
have average shear stresses of 1.09 fc′ , 0.91 fc′ , and
considering the effects of 100% of lateral forces in one
0.59 fc′ , respectively as shown in Figure 3. In order to direction plus 30% of those in the orthogonal direction
meet the first design criterion, for group I, the design (FEMA 2000a). The wall shears resulting from the
shear stress is reduced to 0.50 fc ' . To maintain the effects of accidental torsion are distributed in a manner
second design criterion, the shear stresses in the other consistent with the expected torsional behavior of the
groups are proportionally reduced by the ratio 0.50/1.09. core wall sections, neglecting warping. Like story shear
Hen ce, the design shear stresses for groups I, II, and III forces, torsion-induced shear forces are distributed in
are, respectively, 0.50 fc ' , 0.42 fc′ , and 0.27 fc′ . proportion, 30%-70% to the tension and compression
The resulting shear stress distribution and beam grouping wall piers, respectively. Axial and bending effects in
is shown in Figure 3. The coupling beams for each both directions are combined to verify biaxial axial-
group are designed and detailed according to ACI 318-05 flexural demands. Shear forces are considered separately

260 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 261

Gang Xuan, Bahram M. Shahrooz, Kent A. Harries and Gian A. Rassati

# 11 Wall #4 distributed bars


Longitudinal bars @ 132mm o.c.
Group III Beams U #4 ties @ 152mm o.c.
#4 ties @ 100mm o.c.

Group II Beams See Note 1


#4 distributed bars
below.
U @ 127mm o.c.
Note 1 : Diagonal core
Group I Beams out-to-out dimensions:
124 mm 280 mm (wide) ×
98 mm 152 mm (high)
Group II Beams
A-A B-B 118 mm

A B

Note 1:
Group I: 6 # 11
Group II: 6 # 10
Group III: 6 # 8

A B
Coupling Beam Dimensions:
508 mm wide × 762 mm deep

Figure 6. Coupling beam details

Lines through beam


X Modal inflection points
lateral load F.B.D.
Beam shear capacity

Beam shear capacity

Y
0.15Vstr 0.35Vstr
Compression wall
Tension wall

Vstr

Beam X
axial
force
0.15Vstr 0.35Vstr
A-A

A A

Vtx = 0.3Vstr Vcx = 0.7Vstr

0.3ME 0.7ME
T P

Figure 7. Analysis in the coupled direction

Advances in Structural Engineering Vol. 11 No. 3 2008 261


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 262

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

Distributed web steel:


Two curtains of vertical steel: #7 @ 254 mm
Two curtains of horizontal steel: #7 @ 254 mm

Distributed flange steel:


Two curtains of vertical steel: #7 @ 203 mm
Two curtains of horizontal steel: #7 @ 203 mm

Wall thickness = 508 mm

Boundary elements:
longitudinal steel : #11
Transverse steel: #7 @ 127 mm

8@137

2@173 2@173

7@137
2@173 2@137

Figure 8. Typical wall details (floors 1 through 3)

to assess the shear demand. Boundary reinforcing frame model of the structure was used with beam-column
elements are provided at the ends of the wall flanges, per elements for the wall piers, and cubic-interpolated beam
ACI 318 requirements. A typical design of a C-shaped elements with rigid offsets for the coupling beams (see
wall pier is shown in Figure 8. Additional details Figure 9). The mass of the CCW system is equally
regarding design of the walls are provided by Xuan distributed among the nodes at each level.
(2005).
6.1. Modeling of Coupling Beams
6. NONLINEAR STATIC AND DYNAMIC Accurate modeling of coupling beams is necessary to
ANALYSES assess beam behavior ensuring that at LS level the
The response of the 15-story prototype structure designed beams have yielded, but still maintain enough ductility
following the proposed PBD methodology was evaluated to reach the CP level, at which point the loss of some or
by means of static pushover and dynamic nonlinear all beams is acceptable. A bilinear moment-curvature
analyses conducted in the coupled (EW) direction. The NS relationship was used to represent the behavior of the
direction was found to have adequate behavior and is not coupling beams. The yield curvature of the beams (φy)
of interest in the present context. The nonlinear finite 6∆ y
element program Ruaumoko (Carr 2000) was used for this is φ y = 2 in which ∆y is computed based on Eqn 5.
s
purpose. For the sake of simplicity, a two-dimensional The yield moment (M y ) corresponds to the nominal

262 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 263

Gang Xuan, Bahram M. Shahrooz, Kent A. Harries and Gian A. Rassati

Rigid links

dp
βdp
rK

K K(dy/dm)α
dy dm

Parameter Walls Beams


α 0 0.1
β 0.60 0.5
0.015 (Floors 1 − 3)
P r 0.007 (Floors 4 − 7) 0.02
Parabolic 0.003 (Floors 8 − 15)
surfaces

Hysteresis model for coupling beam and wall elements


Balanced conditions
M
Multiplier on yield moment

Beams: δ1 = 4.5, δ2 = 8, Residual = 0.6


Walls: δ1 = 8, δ2 = 14, Residual = 0.6
1.0

P-M Interaction surface


for wall elements
Residual

δ1 δ2

Displacement ductility

Strength reduction factors for


coupling beam and wall elements

Figure 9. Analytical model and elements for pushover and dynamic analyses

capacity of the coupling beam, and the effective moment A cross-sectional nonlinear fiber-analysis program,
My XTRACT (Imbsen 2002), was used to produce the
of inertia (Ie) is I e = which is calculated based on
E cφ y nonsymmetric (i.e., tension and compression behavior)
elastic analysis hypothesizing a linear distribution of axial-flexure interaction curves needed for generating
curvature along the beam. The value of the ratio of post- the necessary input parameters for the RUAMOKO
yield residual stiffness to initial stiffness is taken as 0.02, model. The effective moment of inertia was taken as the
which is an empirical value generally accepted for effective stiffness as calculated by XTRACT, divided
reinforced concrete structures. Considering that the model by the ACI (2005) specified Young’s Modulus for
is two-dimensional, each beam in the model represents the concrete. The residual stiffness ratio was taken as the
two beams at each level in the three-dimensional value calculated by XTRACT. Two pushover analyses
prototype structure. were conducted: a) appropriately incorporating tension
and compression pier properties (as obtained from
6.2. Modeling of Wall Piers separate XTRACT analyses), and b) using average
The wall piers were modeled with quadratic beam-column values of tension and compression pier properties for
elements, taking into account axial-flexure interaction. both walls. While it is easy to establish which wall pier

Advances in Structural Engineering Vol. 11 No. 3 2008 263


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 264

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

1.6 Range of yielding 1.48 1.6 Range of yielding 1.42


1.36 of wall piers 1.34 of wall piers
Normalized base shear (V/Vt)

Normalized base shear (V/Vt)


1.4 1.4
1.19 1.33
1.18 1.16
1.2 1.2
1.15 1.15
1.0 1.0
0.8 0.8
0.8 0.8
0.6 LS CP 0.6 LS CP
Range of yielding Range of yielding
of coupling beams of coupling beams
0.4 0.4

0.2 0.2

0.0 0.0
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 0.0% 0.5% 1.0% 1.5% 2.0% 2.5%
Roof drift ratio Roof drift ratio
(a) Different tension and compression wall pier properties (b) Average properties for tension and compression wall piers

Figure 10. Normalized base shear – roof drift response from pushover analysis

is in tension and which is in compression for a pushover better represents the actual structural behavior, although
analysis, during a dynamic analysis these conditions the average properties analysis results in a model that
alternate. Similar to the second procedure for pushover may also be used for dynamic analyses.
analyses, the average properties were used for the The LS and CP drifts corresponded to base shears of
dynamic analyses. 1.19Vt or 1.18Vt and 1.36Vt or 1.34Vt, respectively,
depending on whether appropriate tension and
7. RESULTS OF PUSHOVER ANALYSIS compression pier properties or average values are used
The applied load pattern corresponding to the shape of for the wall piers. The observed behavior is generally
the fundamental mode obtained from a modal analysis consistent with the performance objectives discussed
was used for the pushover analysis (FEMA 2000a), above and presented in Figure 5(b). In both analyses, the
which was terminated once any interstory drift exceeded first yielding of the walls occurs prior to the CP level; for
2.5%. Figure 10 shows the roof drift ratio as a function the analysis having appropriate tension and compression
of the non-dimensional lateral loads, normalized by the properties (Figure 10(a)), the compression wall pier
modal base shear Vt. Both analyses, with appropriate yields at its base, whereas the analysis with average wall
tension and compression pier properties and with properties (Figure 10(b)) indicates the tension wall yields
average pier properties are shown. The roof drift at its base. In either case, the coupling beams underwent
response is essentially a tri-linear curve representing the significant additional nonlinear deformations between
elastic, transition, and inelastic states described the LS and the CP levels.
previously. In both analyses, the first coupling beam
was observed to yield at a base shear of 0.80Vt and all 8. RESULTS OF DYNAMIC ANALYSES
beams had yielded at a base shear of 1.15Vt. Since the The finite element model having average wall pier
wall piers are assigned different properties in each properties was used for a series of nonlinear dynamic
analysis, the observed wall behaviors are different. For analyses. In this case, the required hysteretic behavior of
the analysis with appropriate tension and compression the beam and wall elements was modeled using the
pier properties, the compression wall yields at its base at modified Takeda hysteretic model (Carr 2000). Stiffness
1.33Vt and the tension wall exhibits first yield at 1.34Vt. and strength degradation coefficients were chosen
When average wall properties are used, the resulting according to those used previously by Harries et al.
increased distribution of forces to the tension wall (1998). Refer to Figure 9 for various parameters
causes this wall to yield sooner in the analysis (at defining the hysteretic models and strength reduction
1.16Vt), with yielding of the compression wall factors. Five ground motions were selected; three
(occurring at its base) delayed until reaching a base records were recorded acceleration records (El Centro
shear of 1.36 Vt. Regardless of the analysis, however, 1940 NS, Northridge 1994 at Pacoima Dam NS, and
the trilinear pushover behavior is exactly the same prior Northridge 1994 at Sylmar Hospital NS), and two were
to wall yielding and essentially the same thereafter since artificial accelerograms generated to be consistent with
the total stiffness of the structure in each analysis the code-prescribed (FEMA 2000a) response spectra for
remains the same. It is assumed that the first analysis LS and CP performance criteria, respectively. The
with appropriate wall pier properties (Figure 10(a)) spectra for these ground motions are shown in Figure 11;

264 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 265

Gang Xuan, Bahram M. Shahrooz, Kent A. Harries and Gian A. Rassati

4.0

LS Design
3.5
CP Design

Artificial LS Level
3.0
Artificial CP Level

2.5 El Centro N-S


Acceleration (g)

Northridge pacoima N-S


2.0 Northridge Sylmar N-S

1.5

1.0

0.5

0.0
0 0.25 0.5 0.75 1 1.25 1.5 1.75 2
Period (sec.)

Figure 11. Response spectra of selected ground motions

15
14
13
12
11
10
9
LS Limit
8
Floor

7
6
5 El Centro N-S

4 Northridge pacoima N-S

3 Northridge Sylmar N-S

2 Artificial CP Level

1 Artificial LS Level

0
0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0%
Inter-story Drift

Figure 12. Interstory drift envelopes

based on these, the El Centro and artificial LS records match the expected input energy for the corresponding
can be considered service level earthquakes, while the earthquakes. It is important to notice that the response of
others are CP level. The fundamental period of the the system to both LS and CP level earthquakes are
structure in the coupled direction is 1.44 seconds. compatible with the performance requirements and the
Figure 12 shows a summary of the interstory drift design criteria adopted, and meet the NEHRP (FEMA
envelopes for all levels for each of the seismic records 2000a) provisions. The full set of results of these
used in the analyses. The magnitudes of these drifts analyses is provided in Xuan (2005). Table 2 shows the

Advances in Structural Engineering Vol. 11 No. 3 2008 265


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 266

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

Table 2. Maximum chord rotation

Chord rotation Rotation capacity* (rad)


Ground motion (rad) Location θy θu
El Centro 0.030 Floor 12 0.0081 0.0484
Artificial LS 0.036 Floor 13 0.0081 0.0484
Artificial CP 0.055+ Floor 14 0.0081 0.0484
Northridge @ Pacoima N-S 0.060+ Floor 14 0.0081 0.0484
Northridge @ Slymar N-S 0.077+ Floor 14 0.0081 0.0484

*Rotation capacity corresponding to the floor where the maximum chord rotation is obtained. The yield rotation (θy) and ultimate rotation (θu) capacities were
computed from Eqns 6 and 7, respectively.
+Although the coupling beams have exceeded their ultimate rotation capacities, the wall piers can still provide resistance because they have not reached their

ultimate capacities.

0.06
θu=0.048
0.05

0.04

0.03

0.02 θy=0.0081
Chord rotation (rad.)

0.01

0.00
0 2 4 6 8 10 12 14 16 18 20
−0.01

−0.02

−0.03

−0.04

−0.05

−0.06
Time (sec.)

Figure 13. Representative coupling beam chord rotation history

maximum chord rotations for coupling beams in the earthquakes, the wall piers continue to provide resistance
CCW system for all selected ground motions. For the because they do not reach their ultimate capacities.
service level ground motions (El Centro 1940 and An examination of the response of the CCW prototype
artificial LS), the coupling beam chord rotations exceed shows that the service level records did not cause yielding
the predicted yield chord rotation capacities, but remain of the wall piers, whereas the collapse prevention level
below the expected ultimate rotation capacity. This excitations cause transient excursions into post-elastic
behavior is compatible with the previously discussed LS behavior of wall pier elements (Xuan 2005). Both of
level requirements. For the collapse prevention level these behaviors are in accordance with the predetermined
excitations (artificial CP record and the two Northridge requirements for LS and CP levels. A close examination
records), all the beams exceed their ultimate chord of the response of all wall pier elements (Xuan 2005)
rotation capacities, although this is acceptable within shows that, although inelastic deformations are more
the CP criteria discussed previously. Nevertheless, the likely to take place at the base level of the structure,
excursions beyond the ultimate rotational capacity are other floors may also experience yielding, albeit less
instantaneous; for example, Figure 13 shows the chord frequently. This can be attributed to the gradual stiffness
rotation history of the 14th floor coupling beam, which degradation of the coupling beams in the post-yielding
experienced the largest rotational demand, under the phase, which imparts a larger demand on the wall
artificial CP record. Although some of the coupling beams elements. This observation is also supported by existing
exceed their ultimate rotation capacities under CP level literature (McNeice 2004).

266 Advances in Structural Engineering Vol. 11 No. 3 2008


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 267

Gang Xuan, Bahram M. Shahrooz, Kent A. Harries and Gian A. Rassati

9. CONCLUSIONS Carr, J. (2000). Manual of Ruaumoko-Computer Program Library,


This paper discusses the drawbacks of the traditional Department of Civil Engineering, University of Canterbury.
strength-based design (SBD) methodology for the Computers and Structures Inc (CSI) (1997). ETABS V6.2, Three
design of coupled core wall (CCW) systems with Dimensional Analysis of Building Systems User Manual,
diagonally reinforced coupling beams. It is shown that Computers and Structures, Inc., Berkeley, California.
the underlying hypothesis in current code-based Federal Emergency Management Agency (2003). FEMA 403 World
provisions that the coupling beams and wall piers yield Trade Center Building Performance Study, Federal Emergency
simultaneously at the design base shear is unrealistic. Management Agency, Washington DC.
Furthermore, design based on this hypothesis results in Federal Emergency Management Agency (2000a). FEMA 368
unreasonable shear stress demands on the coupling NEHRP Recommended Provisions for Seismic Regulations for
beams, exceeding both constructability and code-based New Buildings and Other Structures, Federal Emergency
limits. As an alternative, the paper presents a Management Agency, Washington DC
performance-based design (PBD) approach that allows Federal Emergency Management Agency (2000b). FEMA 356
the designer to respect the actual seismic response of a Prestandard and Commentary for the Seismic Rehabilitation of
CCW system while permitting a rational design of the Buildings (FEMA 356), Federal Emergency Management
coupling beams, accounting for constructability issues. Agency, Washington DC.
The design of a prototype building based on SBD Fortney, P. (2005). Next Generation Coupling Beams, PhD
and PBD methodologies is outlined. In particular, the Dissertation, Department of Civil and Environmental Engineering,
choice of performance objectives and design criteria University of Cincinnati.
are discussed. Static and dynamic nonlinear analyses of Hindi, A. and Sexsmith, R. (2001.) “A proposed damage model for
the performance-based designed CCW system are R/C bridge columns under cyclic loading”, Earthquake Spectra,
presented and discussed. The structure designed using EERI, Vol. 17, No. 2, pp. 261–281.
the PBD approach meets the intended performance Harries, K.A., Mitchell, D., Redwood, R.G. and Cook, W.D. (1998).
objectives and design criteria for code-required seismic “Nonlinear seismic response predictions of walls coupled with
loads. The performance-based design approach presented steel and concrete beams”, Canadian Journal of Civil
is a rational and straightforward design methodology Engineering, Vol. 25, pp. 803–818.
that allows designers to produce code-compliant Harries, K.A. and McNeice, D.S. (2006). “Performance-based
structures that are constructible and that take full advantage design of high-rise coupled wall systems”, The Structural
of the considerable economical and structural Design of Tall and Special Structures, Vol. 15, No. 3, pp.
advantages of coupled core wall systems. 289–306.
Harries, K.A., Fortney, P., Shahrooz, B.M. and Brienen, P. (2005).
ACKNOWLEDGEMENTS “Design of practical diagonally reinforced concrete coupling
Financial support for the first author was provided by beams – a critical review of ACI 318 requirements”, ACI
the University of Cincinnati. Structures Journal, Vol. 102, No. 6, pp. 876–882.
Harries, K.A., Shahrooz, B.M., Brienen, P. and Fortney, P.J.
REFERENCES (2004). “Performance-based design of coupled wall systems”,
American Concrete Institute Committee 318 (2005). ACI 318-05 Composite Construction V, July 18-23, 2004, Kruger National
Building Code Requirements for Reinforced Concrete and Park, South Africa.
Commentary (ACI 318-05/ACI 318R-05), American Concrete Harries, K.A. (2001). “Ductility and deformability of coupling
Institute, Farmington Hills, MI. beams in reinforced concrete coupled walls”, Earthquake
ACI-ASCE Joint Committee 352. (2002). Recommendations for Spectra, EERI, Vol. 17, No. 3, pp. 457–478.
Design of Beam-Column Connections in Monolithic Reinforced Imbsen Software Systems (2002). Release Notes of XTRACT v
Concrete Structures (ACI 352R-02), American Concrete Institute, 2.6.2—Cross Sectional Xs Structural Analysis of Components,
Farmington Hills, MI. Imbsen Software Systems, Sacramento, CA,
Berg, V.B. and Stratta, J.L. (1964). “Anchorage and the Alaska McNeice, D. (2004). Performance Based Design of a 30 Story
Earthquake of March 27, 1964”, American Iron and Steel Coupled Core Wall Structure, M.S. Thesis, Department of Civil
Institute, New York, pp.63. Engineering, University of South Carolina.
Bertero, V. (1997). “Performance-based seismic engineering: a National Research Council of Canada (1995). National
critical review of proposed guidelines”, Seismic Design Building Code of Canada, (NBCC), Canadian Commission on
Methodologies for the Next Generation of Codes, A.A. Balkema Building and Fire Codes, National Research Council of
Publisher, pp. 1–32 Canada, Ottawa.
Brienen, P. (2002). “Spreadsheets (electronic version) of a 10-Story Park, R. and Paulay, T. (1975). Reinforced Concrete Structures,
CCW Building Design” John Wiley & Sons Inc., pp. 645–655.

Advances in Structural Engineering Vol. 11 No. 3 2008 267


2-07-631-Xuan.qxd 12/06/08 8:25 am Page 268

A Performance-Based Design Approach for Coupled Core Wall Systems with Diagonally Reinforced Concrete Coupling Beams

Paulay, T. (2002). “A displacement-focused seismic design of mixed Subedi, N.K., Marsono, A.K. and Aguda, G. (1999). “Analysis of
building systems”, Earthquake Spectra, EERI, Vol. 18, No. 4, pp. reinforced concrete coupled shear wall structures”, The Structural
689–718. Design of Tall Buildings, Vol. 8, pp. 117–143.
Subedi, N.K. (1990). “Ultimate strength analysis of reinforced Xuan, G. (2005). Performance Based Design of a 15 Story Reinforced
concrete coupling beams”, The Structural Engineer, Vol. 68, Concrete Coupled Wall Structures, M.S. Thesis, Department of
No. 3, pp. 45–49. Civil and Environmental Engineering, University of Cincinnati.

268 Advances in Structural Engineering Vol. 11 No. 3 2008


Copyright of Advances in Structural Engineering is the property of Multi-Science Publishing Co Ltd and its
content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's
express written permission. However, users may print, download, or email articles for individual use.

You might also like