Professional Documents
Culture Documents
Task Planning
Permit/Work Order No: Name of Company: Department: Date:
Mohtarefo Al Maden Electrical 16th Oct 2019
Contracting Est.
Task Description: FMP 1990 Full Shutdown of Panel 4304A-PP-01A Retail from main source to change
the main breaker
1
Project Management Department
Supervisor Details:
Name Company BADGE /ID Qualifications Yrs. Of
No. Experience in
Role
Mohtarefo Al Maden Foreman Electrician
Nasar Ali Contracting Est. 149043 8 Yrs.
Operatives Details
Name Company Badge/ID Trade/skills Yrs. of Experience
No. in Role
Mohtarefo Al Maden Foreman Electrician
Nasar Ali 149043 8 Yrs.
Contracting Est.
Mohtarefo Al Maden Electrician
Muhammad Zahid 147286 5 Yrs.
Contracting Est.
Mohtarefo Al Maden Electrician 5 Yrs.
Mohd. Attiq 147124
Contracting Est.
Mohtarefo Al Maden Electrician
Farzand Ali 149780 3 Yrs.
Contracting Est.
Mohtarefo Al Maden Electrician
Haider Jan 149779 3 Yrs.
Contracting Est.
2
Project Management Department
Damage Injury
4 4
Total Fatality 4 8 12 16
Failure
3 3
Major Major 3 6 9 12
OUTCOME
2 2
Minor Minor 2 4 6 8
1 1
Nil No Injury 1 2 3 4
1 2 3 4
Unlikely Possible Probable Definite
PROBABILITY
METHOD STATEMENT
A Method Statement is an agreement between the workforces, Service Provider and the Person or Organization
requesting the work and that the work being undertaken is being managed and any risk is mitigated to an acceptable
level.
The method of work must be clearly communicated and understood by all parties involved. Operatives undertaking the
works the works supervisor and line managers must sign the document as agreement with the method of works.
It must be noted that more than one method statement may be required for any sequence of works.
Method statements and risk assessments go hand in hand, as the method of work is dictated by the risks identified, and
the risk is identified by the proposed method of work.
3
Project Management Department
ENSURE YOU COLOR CODE THE RISK SCORES (refer to above matrix)
Ensure the requirement of Work Permit Process (HSE-OHSMS-SOP-09) shall be applied for in advance of the
activity. (Confined space entry PTW)
Ensure that signatures are obtained from all relevant KAUST personnel, including MACC, O&M, building
management, HSE and EMS.
Notify KAUST fire service & obtain approval prior of start work.
PPE, tools and equipment will be checked by supervisor.
Barricade to working area and providing warning signs.
Task 1: Full Shutdown of Panel 4304A-PP-01A Retail to change the main breaker
Method of statement:
Shutdown
Inform the KAUST maintenance team for shutdown job after complete the work permit process
Isolate the required panel from main source by KAUST maintenance team and Test the residual energy through
MultiMate
Place sign over breaker, Lock distribution board, Place sign on the panel notifying LOTO in place
Remove the front cover from panel 4304A-PP-01A Retail
Remove the main cable the main breaker
Replace the main breaker
Re-Connect the main cable and tie it properly
Make sure the bolts are tied well and check the other wire terminals as well for its tightness
Fix the front cover back on the panels
Re-Energization
Inform the KAUST maintenance team for Re-Energization after complete all the activities
Before energization, make sure the power panel is in safe condition
Ensure all the cables & wires are properly terminated
Check all the terminal one by one for its tightness
After making sure everything is OK then Switch on the require breaker from the main source (By KAUST
Maintenance team)
RISK RISK
SCORES SCORES
Hazard RISK PROPOSED CONTROLS WITHOUT WITH
CONTROLS CONTORLS
4
Project Management Department
RISK RISK
SCORES SCORES
Hazard RISK PROPOSED CONTROLS WITHOUT WITH
CONTROLS CONTORLS
Good housekeeping routine
orderly prior to respective
Dust Allergy
Poor area of work.
Slip, Trip & Fall
housekeeping. Proper segregation of
Dust inhalation. materials, chemicals and 4 2
tools
Provide waste trash or
garbage plastic.
5
Project Management Department
TEST
SERIAL DATE OF LAST
ITEM NAME CERTIFICATE REMARKS
NUMBER MAINTENANCE
ATTACHED
Insulated Hand
N/A
Tools
Clamp Meter 0694357
Insulation
CP 05943
Tester
6
Project Management Department
TEST
SERIAL DATE OF LAST
ITEM NAME CERTIFICATE REMARKS
NUMBER MAINTENANCE
ATTACHED
Hard Hat - - -
Safety Shoes - - -
Protective
Leather - - -
Gloves
Face Mask - - -
Safety - - -
Goggles
Safety - - -
Barricade
- - -
Warning Sign
Face shield
Rubber MAT
7
Project Management Department
8
Project Management Department
All Personnel Should Read, Agree & Sign on this sheet before starting the Activity
Acknowledgement
OPERATIVES SIGN OFF SHEET
I acknowledge receiving and understanding these instructions, I will fully comply with the assigned task
requirements
NAME COMPANY BADGE/ID NO. Position / SIGNATURE
Trade / Skills
Mohtarefo Al Maden
Mohd. Khalid Contracting Est. 136544 Supervisor
Electrical
Mohtarefo Al Maden Electrician
Fazal Rahman Contracting Est. 147120
(Supervisor will ensure completed combined Method Statement and Risk Assessment forms are forwarded to the Area /Bldg. Manager and
PTW Office)