You are on page 1of 1

7' 6' 5' 4' 3' 2' 1' 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

K K

MOLDING ROOM
CLEAN ROOM 1 CH=5600
J (AUTOMATIC ASSEMBLY LINE)
CLASS 10,000
J
CH=3500

I I

H H
ANTE ROOM 1
CH=3500
CLEAN ROOM 2
(MANUAL ASSEMBLY LINE)
G CLASS 10,000
CH=3500 G
ANTE ROOM 2
CH=3500

F F

E PACKING ROOM
E
CH=5500

INVENTORY WAREHOUSE
D CH=5500 D

C C
B B
MATERIAL WAREHOUSE
LOADING & UNLOADING ROOM CH=5500
CH=5500 FEMALE
TOILET 3

A A
LOADING AREA

A' A'

1 GROUND FLOOR PLAN


A-01 SCALE (A1) 1:200 M

DESIGNER / IN-CHARGE OF CONSTRUCTION: PROJECT TITLE: OWNER : SHEET CONTENT/S: SHEET NO.
AS-BUILT BY: CJS

CCT CONSTRUCTORS GIANFRANCO N. LEH NEW FACTORY BUILDING PROJECT


DATE: -

CORPORATION ARCHITECT YAMAICHI SEIKO PHILIPPINES, INC. CHECKED BY: VVA GROUND FLOOR PLAN A-02
3RD FLR. PRINCESS BUILDING,
PHASE - 2 FIT-OUT WORKS DATE: -
PRC NO: 0024849 PTR NO: 2535382
104 ESTEBAN ST. LEGASPI VILLAGE, MAKATI CITY
TEL. NOS.: 810-2001 TO 03; FAX: 811-3090 TIN NO: 224-984-148 ISSUED AT: PASIG CITY APPROVED BY: J.KUDO REV. DATE:
MR. MITSUHIRO KIDO
IAPOA NO: 21876 ISSUED ON: JAN. 17, 2017 LOT 13-A, FIRST PHILIPPINE INDUSTRIAL PARK II (SEZ), STO. TOMAS, BATANGAS PRESIDENT DATE: - AS-BUILT DRAWING MAY 06, 2017

CCT-QP-10.0-ENG D2 Rev. No.: 0