Block Work Method Statement


A Block Work Method Statement is a document commonly used in construction projects, especially
in the building and masonry sector. It outlines the procedures, sequence of activities, safety
measures, and other relevant details necessary for carrying out block work or masonry work in a
systematic and organized manner.

The primary purpose of a Block Work Method Statement is to ensure that the construction process
is conducted efficiently, safely, and in compliance with the project's specifications and requirements.

A. SCOPE
This procedure provides a method of control for the construction of block masonry work to achieve
compliance with the contract specifications and drawings.

B. PROCEDURE
• All precast concrete masonry blockwork will be carried out by the specification and Project
Quality Plan.
• In any circumstances where specifications are not provided or they are in any way
incomplete, the matter shall be referred to Consultant’s representative for additional
information.

1. Checks Before Start of Blockwork:


• Ensure that the area to receive the blockwork is as per the contract drawings and the
approved finishing schedule.
• Check if the preceding activities have been inspected and approved.
• Ensure that blocks are procured from the approved manufacturer (s). Except where
otherwise approved in writing, each material shall be obtained from a single source.
• Source certificates shall be obtained for all raw materials e.g., sand, cement, and blocks to
show compliance with the contract specification.

2. Handling and Storage of Materials:


• Blocks shall be delivered to the site palletized and offloaded as near to the point of use as
practicable on a clean hard surface free from contamination by mud or surface water.
• Cement shall be stored off the ground, kept dry, and used in order of delivery.
• Store metal ties and straps undercover and protect them from damage and distortion.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 1 of 5
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

3. Preparation of Work, Materials, and Components:


• When the materials and components are distributed to the work area, ensure that the
structure is not overloaded.
• Plan for scaffolding materials required for block work at heights. Plan for additional
manpower for lifting blocks at heights.
• Set out the anticipated positions of openings etc. in the work above to avoid unnecessary
cutting and adjustment of masonry units leading to incorrect or uneven bonding.

4. Preparation of Mortar Mixes:


• Mortar shall be mixed by machine except for small quantities only (not containing
plasticizer). Hand mixing (if permitted) may be done on a watertight platform.
• When mixed at the site, batch boxes shall be used to ensure correct and consistent mix
proportions.
• Use mortars (other than retarded mortars) within 2 hours of mixing or as specified.

5. Building Blocks Walls:


• Build block work within permissible deviations as specified.
• Unless otherwise specified/permitted, lay blocks on a full bed of mortar, and fill all joints.
Keep the courses level and the perpend vertically aligned. Plumb quoins and all faces as the
work proceeds. It is preferable to Align vertically every fifth or sixth perpend and `even out’
the size of Intermediate joints. Try to keep horizontal joints of uniform thickness.
• Do not carry one course more than the height specified in the contract specifications.
• Rake out joints as work proceeds, on all faces to be plastered or rendered. This will provide a
good key for the coating.
• If pointing is specified, the mortar used for the pointing should not be stronger than that
used when constructing the wall unless specified otherwise.
• All blockwork shall be bonded to adjacent reinforced concrete structures using galvanized
mild steel cramps at specified spacing unless specified otherwise.
• Partitions shall be bonded to the main walls by toothing as specified in the contract.

6. Chases and Holes:


Cut chases and holes neatly and without damaging the walls as per the following unless specified
otherwise:

• Chases in blockwork must be less than 75mm.


• For hollow units, maintain a minimum of 15mm thickness between the bottom of the chase
and the void.
• Do not cut horizontal chases to a depth exceeding one-third of the thickness of the single
leaf in walls or leaves contracted of solid units.
• Holes shall not exceed 300mm x 300mm unless specified otherwise.
• Do not cut chases back-to-back exceeding the dimensional restrictions. Offset such chases in
line by a distance at least equal to the wall thickness.
• It is preferable to use mechanical rotary cutters, particularly when it is necessary to avoid
heavy impact and vibration. The number and positions of chases shall be precisely set by the

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 2 of 5
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

specification since unauthorized chasing might adversely affect one or more of the functional
requirements of the walls e.g., its loadbearing capacity.

7. Appendix

• FINI/01/B shall be used to record deliveries of blocks if required by the specification.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 3 of 5
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

This is Site Register for the Block used to check the Quality, Quantity, and Dimensions are right.

Article Link: https://planningengineer.net/block-work-method-statement/

Useful links:

Join our email Newsletter, we send useful free content regularly:


https://planningengineer.net/newsletter/

Our Services: https://planningengineer.net/our-services/

Our Courses: https://planningengineer.net/lp-courses/

Free Arabic Basic Course Playlist:


https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J

---------------

Keep in Touch:

WhatsApp: +201277767728

Email: Info@PlanningEngineer.Net
Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 4 of 5
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos

Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906

Linked in: https://www.linkedin.com/company/planning-engineer-est/

Facebook Page: https://www.facebook.com/PlanningEngineerDotNet

Facebook Group: https://www.facebook.com/groups/1138400132963230

Twitter: https://twitter.com/PlanningEEst

Instagram: https://www.instagram.com/planningengineerest/

TikTok: https://www.tiktok.com/@planningengineerest

---------------

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 5 of 5