REPORT

PREPARATION WORK AND ENERGIZING PLAN FOR


22KV SUPPLY FROM SWITCHYARD TO POWER HOUSE AND 0.4KV
AUXILIARY EQUIPMENT AT POWER HOUSE - THUONG KON TUM HPP

I. Conditions for energizing 22kV and 0.4kV equipment


1. Installation, testing, calibration and acceptance of equipment.
Completing installation, testing, testing of general control and protection circuit
and acceptance for completion of installation of equipment assembly including:
- Two 22kV dynamic cable circuits from 22kV SWITCHGEAR PANEL to
22kV ISOLATOR PANEL;
- 22kV ISOLATOR PANEL;
- Two 22kV dynamic cable circuits from 22kV ISOLATOR PANEL to AxT-3
and AxT-5 transformers;
- AxT-3 and AxT-5 transformers;
- All 0.4kV dynamic cables from AxT-3, AxT-5 transformers to MDB-3 panel
and to MDB-1,2,3; GDB-1,2,3
- 0.4kV supply distribution panel: MDB-1,2,3; GDB-1,2,3; ACDB1,2;
illumination busbar 1,2
- Supply for control, protection and operation of equipment assemblies:
oSupply distribution panel: 22kV ISOLATOR PANEL; MDB-1,2,3; GDB-
1,2,3
oTransformer: AxT-3, AxT-5
2. Working and agreement with related units
2.1. Temporary numbering diagrams of 22kV and 0.4kV equipment which are
agreed between the parties to serve equipment operation, is available
2.2. Fire prevention and fighting equipment in equipment positions which are
energized according to approved design, are installed and equipped

3. Human resources, documents, equipment for energizing and operating


equipment
3.1. Equipment operators have been trained for equipment operation
knowledge from the manufacturer and are capable of operating 22kV and
0.4kV equipment
3.2. As-built documents to serve energizing and operation management of
22kV and 0.4kV equipment at the Central Control House and Power House
are completed
3.3. Documents, means, tools and instruments for the operation management,
operating and troubleshooting of equipment are completed.

1/15
3.4. Safety tools for people and equipment are fully equipped; Operation sheet
and Working sheet must be available for operation management.
3.5. Energizing plan for 22kV and 0.4kV equipment - Thuong Kon Tum Plant
has been agreed among related parties
3.6. Operation sheet for energizing 22kV and 0.4kV equipment - as per agreed
scope of energizing plan - is available (enclosed with Protection relay
regulation sheet for surge energizing of transformer).

II. Working modes of protection relays during energizing


1. At 22kV SWITCHGEAR PANEL, there is protection for 2 22kV cable
outgoing segments to the Power House.
Equipment name Protection relay Function
P111L 50/51; 50/51N
VCB-3 CB Mastertrip 86
VCB-4 CB Monitoring trip
95
circuit

2. Overheat protection system for AxT-3,5 transformers


Transformer coil temperature protection relays Type TR-7570 issue alarm and
control signals including:
+ Alarm (high temperature): 130ºC
+ Trip (extremely high temperature): 140ºC
3. Protection relay system for MDB-1,2,3 and GDB-1,2,3 auxiliary distribution
panels
Equipment name Protection relay Function
PNA 442 50/51; 50/51N
MDB-1,2,3 Mastertrip 86
GDB-1,2,3 Monitoring trip 95
circuit

III. Preparation work before energizing


1. Establishing 22kV and 0.4kV equipment status and conditions:
Before energizing 22kV cable, 22kV and 0.4kV equipment at the Power House,
it is necessary to establish equipment status and conditions according to the
following table:

No. Content Conditions/Status


A General conditions
1 Construction, testing, calibration and Finished
acceptance of equipment.
2/15
2 Announcing the scope and time for Informed
energizing the entire Site from the 220kV
Switchyard - 22kV cable line - 0.4kV
MDB-1,2,3 and GDB-1,2,3 distribution
panels.
3 People and means of construction All withdrawn (with
Minutes of
confirmation of
related parties)
4 Compartment of 22kV Switchgear Panel at Successfully
Central Control Room energized from 22kV
local grid
5 DC supply for operation, control and Provided
monitoring of all MV & LT auxiliary
equipment in the Power House.
6 Fire extinguisher in the area of equipment Sufficient, right type
which are energized. and good quality
control
7 Fire protection system along 22kV cable Installed and accepted
line according to the
approved fire
prevention and
fighting plan
8 All mobile earthing within the scope of All removed
energized equipment
9 Operating mode of 22kV and 0.4kV panels Only operate in Local
mode
B Energizing 2 22kV dynamic cable circuits from 22kV
Switchgear Panel bus bar to 22kV Isolator Panel at Power
House.
1 Two CBs: VCB-3 and VCB-4 at 22kV At Test position
Switchgear Panel
2 MCBs of TU secondary circuit at Outgoing Close
line segment 1,2 at 22kV Switchgear Panel
3 Protection relay for Outgoing line segment Put into work
1,2 at 22kV Switchgear Panel
4 Measurement instruments for Outgoing Put into work
line segment 1,2 at 22kV Switchgear Panel
5 Earth switch: ES-3 and ES-4 at 22kV Open
Switchgear Panel
6 Two Disconnectors: DS1 and DS-2 at Open
22kV Switchgear Panel
3/15
7 ES-9 and ES-10 at 22kV Switchgear Panel Open
C Surge energizing for AxT-3 and AxT-5 transformers
1 AxT-3 and AxT-5 transformers Ready for charging
2 Temperature monitoring relays for AxT-3 Put into work
and AxT-5 transformers
3 Two CBs: Q05 and Q06 at MDB-3 panel At Test position
D Energizing 0.4kV MDB-3 bus bar panel
1 At MDB-3 panel: ACB-4; ACB-5 and all Open
MCCBs used for load.
2 MCB of TU secondary circuit at MDB-3 Close
3 Protection relays, measurement instruments Put into work
in MDB-3 panel
E Energizing 0.4kV MDB-1 bus bar panel
1 MC Q01 At Test position
2 MC Q02 At Test position
3 MC Q07 At Test position
4 All MCCBs used for load of MDB-1 bus Open
bar:
5 MCB of TU secondary circuit at CB Q02 Close
compartment
6 Measurement and protection circuit of CB Put into work
Q02 compartment and MDB-1 bus bar
7 Protection circuit of CB Q02 compartment Put into work
and MDB-1 bus bar
F Energizing 0.4kV MDB-2 bus bar panel
1 MC Q03 At Test position
2 MC Q04 At Test position
3 MC Q07 At Test position
4 All MCCBs used for load of MDB-2 bus Open
bar:
5 MCB of TU secondary circuit at CB Q04 Close
compartment
6 Measurement and protection circuit of CB Put into work
Q04 compartment and MDB-2 bus bar
7 Protection circuit of CB Q04 compartment Put into work
and MDB-2 bus bar
G Energizing 0.4kV GDB-1 bus bar panel
1 MC ACB-7 At Test position
2 MC ACB-8 At Test position
3 All MCCBs used for load of GDB-1 bus Open
bar:
4 MCBs of TU secondary circuit Close
5 Measurement and protection circuit of Put into work
4/15
GDB-1 bus bar
6 Protection relays of GDB-1 bus bar Put into work
H Energizing 0.4kV GDB-2 bus bar panel
1 MC ACB-9 At Test position
2 MC ACB-10 At Test position
3 All MCCBs used for load of GDB-2 bus Open
bar:
4 MCBs of TU secondary circuit Close
5 Measurement and protection circuit of Put into work
GDB-2 bus bar
6 Protection relays of GDB-2 bus bar Put into work
I Energizing 0.4kV GDB-3 bus bar panel
1 MC ACB-11 At Test position
2 MC ACB-12 At Test position
3 All MCCBs used for load of GDB-3 bus Open
bar:
4 MCBs of TU secondary circuit Close
5 Measurement and protection circuit of Put into work
GDB-3 bus bar
6 Protection relays of GDB-3 bus bar Put into work
J Energizing ACDB-1 bus bar
1 General MCB supplying for ACDB-1 Open
2 All MCCBs used for load of ACDB-1 bus Open
bar:
3 Measurement circuit at ACDB-1 Put into work
K Energizing ACDB-2 bus bar
1 General MCB supplying for ACDB-2 Open
2 All MCCBs used for load of ACDB-2 bus Open
bar:
3 Measurement circuit at ACDB-2 Put into work
L Energizing ILLUMINATION-1 transformer and illumination
busbar -1CM
1 General MCB supplying for illumination Open
busbar -1CM
2 All MCCBs used for load of illumination Open
busbar - 1CM:
3 Measurement circuit at illumination bus bar Put into work
- 1CM
L Energizing ILLUMINATION-1 transformer and illumination
busbar -2CM
1 General MCB supplying for illumination Open
busbar -2CM
2 All MCCBs used for load of illumination Open
busbar - 2CM:
5/15
3 Measurement circuit at illumination bus bar Put into work
- 2CM
M Separating control signals, remote signals
1 AH shall provide Appendix A for the list of The list of terminals to
Remote Control cable terminals, PPU shall be isolated then shall
separate cable terminals based on the above expire. Until the
list under the supervision of AH. After that, isolating of cable
AH and PPU shall check and record in the terminals becomes
Operation sheet and the two Parties shall unnecessary.
sign to confirm the correctness of cable
isolating result to ensure safety for
equipment and people.
2 Authorized people for isolating, energizing AH: Mr. Sathish.T
and issuing work permits PPU: According to
shift schedule of
equipment watchshift

The entire contents of establishing initial condition of equipment status for


energizing must be checked and signed by the operating unit and AH for proper
status.

2. Other preparations
- Arranging, preparing human resources, technical documents, tools and
equipment to be ready to manipulate and handle incidents during energizing.
- A Minutes must be available, affirming that “people and construction tools
have withdrawn from site and all mobile earthing at equipment has been
removed: compartments VCB-3 and VCB-4 at 22kV Switchgear panel; two
22kV dynamic cables from 22kV Switchgear busbar panel to 22kV Isolator
Panel at the Power House; 22kV Isolator Panel; 22kV two dynamic cable
circuits from 22kV Isolator Panel to AxT-3 and Ax-T5 transformers; 0.4kV
cable from AxT-3 and Ax-T5 transformers to MDB-3 panel; MDB-3 panel;
0.4kV cable from MDB-3 panel to MDB-1 and MDB-2; MDB-1 panel;
MDB-2 panel; all 0.4kV cables from GDB-1,2,3, ACDB-1,2 panels;
illumination panel 1&2; illumination bus bar 1CM&2CM are qualified for
operating and ready to be energized” by related parties: AH, Lilama10, Ialy,
Thac Mo Consultant, PMU

IV. Energizing plan for 22kV cable from Switchyard to Power House and
22k, 0.4kV auxiliary equipment at the Power House.
1. Items and sequence of energizing:
1.1 Energizing 22kV cable from CCR to Power House
6/15
- Energizing first 22kV dynamic cable circuit from 22kV Switchgear bus bar
panel of CCR to 22kV Isolator Panel at Power House using VCB-3;
- Break VCB-3 CB
1.2 Energizing 22kV cable from CCR to Power House
- Energizing second 22kV dynamic cable circuit from 22kV Switchgear bus bar
panel of CCR to 22kV Isolator Panel at Power House using VCB-4;
- Break VCB-4 CB
1.3 Surge energizing for AxT-3 Transformer
- Surge energizing for Transformer AxT-3 by VCB-3 CB;
1.4 Surge energizing for AxT-5 Transformer
- Surge energizing for Transformer AxT-5 by VCB-4 CB
1.5 Energizing MDB-3 bus bar panel from AxT-3
- Energize bus bar assembly at MDB-3 panel from AxT-3 by Q05 CB;
- Break Q05 CB
1.6 Energizing MDB-3 bus bar panel from AxT-5
- Energize bus bar assembly at MDB-3 panel from AxT-5 by Q06 CB
1.7 Energizing MDB-1 bus bar panel
- Energizing 0.4kV cable from MDB-3 to MDB-1 panels by ACB-4 CB;
- Energize bus bar assembly at MDB-1 panel from MDB-3 by Q02 CB
1.8 Energizing MDB-2 bus bar panel
- Close Q07 coupling CB to supply 0.4kV from MDB-1 to MDB-2;
- Break Q07 CB;
- Energizing 0.4kV cable from MDB-3 to MDB-2 panels by ACB-5 CB;
- Energize bus bar assembly at MDB-2 panel from MDB-3 by Q04 CB;
1.9 Energizing GDB-1 bus bar from MDB-2
- Energizing 0.4kV cable from MDB-2 to GDB-1 panels by F01 MCCB at
MDB-2 panel;
- Energizing GDB-1 bus bar from MDB-2 by ACB -8 CB
- Break ACB -8 CB.
1.10 Energizing GDB-1 bus bar from MDB-1
- Energizing 0.4kV cable from MDB-1 to GDB-1 panels by F01 MCCB at
MDB-1 panel;
- Energizing GDB-1 bus bar from MDB-1 by ACB -7 CB
1.11 Energizing GDB-2 bus bar from MDB-1
- Energizing 0.4kV cable from MDB-1 to GDB-1 panels by F02 MCCB at
MDB-1 panel;
- Energizing GDB-2 bus bar from MDB-1 by ACB -9 CB
- Break ACB -9 CB.
1.12 Energizing GDB-2 bus bar from MDB-2
- Energizing 0.4kV cable from MDB-2 to GDB-2 panels by F02 MCCB at
MDB-2 panel;
7/15
- Energizing GDB-2 bus bar from MDB-2 by ACB -10 CB
1.13 Energizing GDB-3 bus bar from MDB-2
- Energizing 0.4kV cable from MDB-2 to GDB-3 panels by F03 MCCB at
MDB-2 panel;
- Energizing GDB-3 bus bar from MDB-2 by ACB -12 CB
- Break ACB -12 CB.
1.14 Energizing GDB-3 bus bar from MDB-1
- Energizing 0.4kV cable from MDB-1 to GDB-3 panels by F03 MCCB at
MDB-1 panel;
- Energizing GDB-3 bus bar from MDB-1 by ACB -11 CB
1.15 Energizing ACDB-1 bus bar from GDB-1
- Energizing 0.4kV cable from GDB-1 to ACDB-1 panels by F08 MCCB at
GDB-1 panel;
- Energizing ACDB-1 bus bar from GDB-1 by MCCB at ACDB-1 panel.
1.16 Surge energizing ILLUMINATION transformer-1 from GDB-1
- Surge energizing ILLUMINATION transformer-1 by F16 MCCB at GDB-1
panel;
- Energizing illumination bus bar panel - MAIN LIGHTING PANEL
ILLUMINATION-1CM.
1.17 Energizing ACDB-2 bus bar from GDB-2
- Energizing 0.4kV cable from GDB-2 to ACDB-2 panels by F08 MCCB at
GDB-2 panel;
- Energizing ACDB-2 bus bar from GDB-2 by MCCB at ACDB-2 panel.
1.18 Surge energizing ILLUMINATION transformer-2 from GDB-2
- Surge energizing ILLUMINATION transformer-2 by F16 MCCB at GDB-2
panel;
- Energizing illumination bus bar panel - MAIN LIGHTING PANEL
ILLUMINATION-2CM.

2. Wiring diagram and supply for surge energizing:


- The electrical connection and wiring diagram has been temporarily numbered
and agreed between PPU and AH and sent to the parties: PMU, Ialy, Thac Mo
Consultant, Lilama10
- Supply for surge energizing: from 22kV SWITCHGEAR PANEL at CCR.

3. Energizing operations
Energizing operations are implemented according to Operation sheet issued by
PPU.

Operation sequences include:


No. Content
8/15
1. Energizing first 22kV dynamic cable circuit from 22kV Switchgear
bus bar panel of CCR to 22kV Isolator Panel at Power House using
VCB-3;
Step Determine parameters of protection relays at VCB-3 CB compartment
1 according to surge energizing value of the 22kV cable.
Step Put VCB-3 CB into “SERVICE” position.
2
Step Close VCB-3 CB
3
Check charging condition of 22kV cable, 3-phase voltage value on
Step
the meters and the indicators at measuring compartment 4F1 of VCB-
4
3 CB
Step Break VCB-3 CB
5
2. Energizing second 22kV dynamic cable circuit from 22kV Switchgear
bus bar panel of CCR to 22kV Isolator Panel at Power House using
VCB-4;
Step Determine parameters of protection relays at VCB-3 CB compartment
1 according to surge energizing value of the 22kV cable.
Step Put VCB-4 CB into “SERVICE” position.
2
Step Close VCB-4 CB
3
Check charging condition of 22kV cable, 3-phase voltage value on the
Step
meters and the indicators at measuring compartment 5F1 of VCB-4
4
CB
Step Break VCB-4 CB
5
3. Surge energizing for AxT-3 Transformer
Step Determine parameters of protection relays at VCB-3 CB compartment
1 according to surge energizing value of the AxT-3 Transformer.
Step Close DS-1 isolator
2
Step Step 3 VCB-3 CB for 3 times (with 5 minutes interval), check
3 energizing status, if it is good then maintain for 5 minutes.
Step Check 3-phase voltage value on the meters and the indicators at
4 measuring compartment of Q05 CB of MDB-3 panel.
4. Surge energizing for AxT-5 Transformer
Step Determine parameters of protection relays at VCB-4 CB compartment
1 according to surge energizing value of the AxT-5 Transformer.
Step Close DS-2 isolator
2
9/15
Step Step 3 VCB-4 CB for 3 times (with 5 minutes interval), check
3 energizing status, if it is good then maintain for 5 minutes.
Step Check 3-phase voltage value on the meters and the indicators at
4 measuring compartment of Q06 CB of MDB-3 panel.
5. Energizing MDB-3 bus bar panel
5.1 Energizing MDB-3 bus bar panel from AxT-3
Step Put Q05 CB into “SERVICE” position.
1
Step Close Q05 CB
2
Step Check MDB-3 bus bar voltage
3
Step Check phase sequence of MDB-3 bus bar
4
Step Break Q05 CB
5
5.2. Energizing MDB-3 bus bar panel from AxT-5
Step Put Q06 CB into “SERVICE” position.
1
Step Close Q06 CB
2
Step Check MDB-3 bus bar voltage
3
Step Check phase sequence of MDB-3 bus bar
4
6. Energizing 0.4kV cable from MDB-3 to MDB-1 panels
Step Put ACB-4 CB into “SERVICE” position.
1
Step Close ACB-4 CB
2
Step Check voltage of compartment 2F1 of MDB-1 bus bar
3
7. Energizing MDB-1 bus bar panel
Step Put Q02 CB into “SERVICE” position.
1
Step Close Q02 CB
2
Step Check MDB-1 bus bar voltage
3
Step Check phase sequence of MDB-1 bus bar panel.
4
8. Energizing MDB-2 bus bar panel
10/15
8.1 Energizing MDB-2 bus bar panel from MDB-1
Step Put Q07 CB into “SERVICE” position.
1
Step Close Q07 CB
2
Step Check MDB-2 bus bar voltage
3
Step Check phase sequence of MDB-2 bus bar panel.
4
Step Break Q07 CB
5
8.2 Energizing 0.4kV cable from MDB-3 to MDB-2 panels
Step Put ACB-5 CB into “SERVICE” position.
1
Step Close ACB-5 CB
2
Step Check voltage of compartment 2F1 of MDB-2 bus bar
3
8.3 Energizing MDB-2 bus bar panel from MDB-3
Step Put Q04 CB into “SERVICE” position.
1
Step Close Q04 CB
2
Step Check MDB-2 bus bar voltage
3
Step Check phase sequence of MDB-2 bus bar
4
9. Energizing GDB-1 panel
9.1. Energizing 0.4kV cable from MDB-2 to GDB-1 panels
Step Close MCCB F01 at MDB-2 panel
1
Step Check voltage of GDB-1 bus bar compartment
2
9.2. Energizing GDB-1 bus bar panel from MDB-2
Step Put ACB-8 CB into “SERVICE” position.
1
Step Close ACB-8 CB
2
Step Check GDB-1 bus bar voltage
3
Step Check phase sequence of GDB-1 bus bar
4
Step Break ACB-8 CB
5
11/15
9.3. Energizing 0.4kV cable from MDB-1 to GDB-1 panels
Step Close MCCB F01 at MDB-1 panel
1
Step Check voltage of GDB-1 bus bar compartment
2
9.4 Energizing GDB-1 bus bar panel from MDB-1
Step Put ACB-7 CB into “SERVICE” position.
1
Step Close ACB-7 CB
2
Step Check GDB-1 bus bar voltage
3
Step Check phase sequence of GDB-1 bus bar
4
10. Energizing GDB-2 bus bar
10.1. Energizing 0.4kV cable from MDB-1 to GDB-2 panels
Step Close MCCB F02 at MDB-1 panel
1
Step Check voltage of GDB-2 bus bar compartment
2
10.2. Energizing GDB-2 bus bar panel from MDB-1
Step Put ACB-9 CB into “SERVICE” position.
1
Step Close ACB-9 CB
2
Step Check GDB-2 bus bar voltage
3
Step Check phase sequence of GDB-2 bus bar
4
Step Break ACB-9 CB
5
10.3. Energizing 0.4kV cable from MDB-2 to GDB-2 panels
Step Close MCCB F02 at MDB-2 panel
1
Step Check voltage of GDB-2 bus bar compartment
2
10.4. Energizing GDB-2 bus bar panel from MDB-2
Step Put ACB-10 CB into “SERVICE” position.
1
Step Close ACB-10 CB
2
Step Check GDB-2 bus bar voltage
3
Step Check phase sequence of GDB-2 bus bar
12/15
4
11. Energizing GDB-3 bus bar
11.1 Energizing 0.4kV cable from MDB-1 to GDB-3 panels
Step Close MCCB F03 at MDB-1 panel
1
Step Check voltage of GDB-3 bus bar compartment
2
11.2 Energizing GDB-3 bus bar panel from MDB-1
Step Put ACB-11 CB into “SERVICE” position.
1
Step Close ACB-11 CB
2
Step Check GDB-3 bus bar voltage
3
Step Check phase sequence of GDB-3 bus bar
4
Step Break ACB-11 CB
5
11.3. Energizing 0.4kV cable from MDB-2 to GDB-3 panels
Step Close MCCB F03 at MDB-2 panel
1
Step Check voltage of GDB-3 bus bar compartment
2
11.4 Energizing GDB-3 bus bar panel from MDB-2
Step Put ACB-12 CB into “SERVICE” position.
1
Step Close ACB-12 CB
2
Step Check GDB-3 bus bar voltage
3
Step Check phase sequence of GDB-3 bus bar
4
12. Energizing ACDB-1 bus bar
12.1. Energizing 0.4kV cable from GDB-1 to ACDB-1 panels
Step Close MCCB F08 at GDB-1 panel
1
Step Check ACDB-1 panel voltage
2
12.2 Energizing ACDB-1 bus bar from GDB-1
Step Close MCCB supplying for ACDB-1 panel
1
Step Check ACDB-1 bus bar voltage
2
Step Check phase sequence of ACDB-1 bus bar
13/15
3
13. Energizing ACDB-2 bus bar
13.1 Energizing 0.4kV cable from GDB-2 to ACDB-2 panels
Step Close MCCB F08 at GDB-2 panel
1
Step Check ACDB-2 panel voltage
2
13.2 Energizing ACDB-2 bus bar from GDB-2
Step Close MCCB supplying for ACDB-2 panel
1
Step Check ACDB-2 bus bar voltage
2
Step Check phase sequence of ACDB-2 bus bar
3
14. Energizing illumination bus bar panel - LIGHTING PANEL-1CM
14.1 Energizing 0.4kV cable from GDB-1 to ILLUMINATION
Transformer-1 panels
Step Surge energizing ILLUMINATION transformer-1 by F16 MCCB at
1 GDB-1 panel;
Step Check voltage of the ILLUMINATION transformer-1 output
2
14.2. Energizing illumination bus bar panel - LIGHTING PANEL-
1CM
Step Energizing general MCCB supplying for illumination bus bar panel -
1 MAIN LIGHTING PANEL ILLUMINATION-1CM.
Step Check illumination bus bar voltage
2
Step Check phase sequence of illumination bus bar
3
15. Energizing illumination bus bar panel - LIGHTING PANEL-2CM
15.1 Energizing 0.4kV cable from GDB-2 to ILLUMINATION
Transformer-2 panels
Step Surge energizing ILLUMINATION transformer-2 by F16 MCCB at
1 GDB-2 panel;
Step Check voltage of the ILLUMINATION transformer-2 output
2
15.2 Energizing illumination bus bar panel - LIGHTING PANEL-2CM
Step Energizing general MCCB supplying for illumination bus bar panel -
1 MAIN LIGHTING PANEL ILLUMINATION-2CM.
Step Check illumination bus bar voltage
2
Step Check phase sequence of illumination bus bar
3

14/15
V. Organization for implementation
1. PPU shall hold a meeting to agree on the energizing plan with related parties
and submit to the Investor for approval to serve as a basis for deploying
preparation and organizing energizing.
2. Related parties, based on the Plan and Contract, shall organize the
implementation of preparations for energizing
3. PPU is in charge of energizing

PPU ANDRITZ