Evaluation for topographic survey report

ID ITEMS TO BE CHECKED C CC NC COMMENT/ REMARK/ Condition Report page #/ Drawing reverance no.s

Method of survey for traversing, leveling and


1
detail survey was provided briefly
Method adopted for minimizing/ correcting errors
2
for traverse and level indicated
Structure survey considers sufficient
3 upstream/downstream extension as well as
demarcation of stream characteristics
List of established control points with coordinates,
4 offset from centre, monument/ pillar type was
given
5 Are list of abbreviations used attached
6 Are soft copies of “csv” file obtained
Evaluation on pavement design report

Show, detailed description of all the works undertaken with


1 respect to pavement
investigation,
Base line Traffic estimation and forecasting for pavement
2 structure is made and is
satisfactory
3 Assumed traffic growth, and design life are satisfactory.
Weather condition in relation to subgrade CBR investigation
4 method and identification of design CBR for homogenous
sections is safely estimated.
Weather condition in relation to surface drainage has been
5
considered
Construction material utilization program in relation to identified
6
quantity of proposed quarries has been revisited.

7 Recommendation for problem soils has been made (if applicable)

8 show existing pavement evaluation


Description of proposed pavement structures stretches consistent
9
with the final alignment chainage has been tabulated
n on pavement design report
Evaluation on
hydrological |
hydraulic

Proper
a metrological data
has been used

Catchment
b delineation is
made annexed

Land cover and


land use data are
c
properly utilized
for design

Discharge
estimation for
appropriate design
d period of each
selected structure
is
made and annexed

Optimum and
economic Cross
drainage structure
e
is selected where
alternatives
exist

Summary of
hydraulic
calculation has
f been tabulated for
both minor and
major
drainage structures

List, location, type


and dimension of
g each cross
drainage structure
is tabulated

Catchment
h delineated map
has been attached

Side drains and


turnouts are
i identified and
clearly designed
for

Erosion protection
structures are
j identified and
proposed where
appropriate
Evaluation on
Structural Design
of Bridges

BRIDGE
a
GEOMETRY

Confirm hydraulic
requirement
i
including
freeboard

Check of
consistency of
ii alignment and
details with
roadway plans

Confirm Depth of
iii
foundation

Confirm Potential
iv
scour requirements

APPLICABLE
b BRIDGE DESIGN
STANDARDS

ADOPTED
c DESIGN
METHODS
MATERIAL
d
PROPERTIES

BRIDGE
LOADING (Dead,
Additional Dead,
d Design Vehicle
Load, Associated
Live Loads, Earth
pressure …)

CHECKING
e DESIGN
CRITERIA FOR:

Bridge width &


i Sidewalks, Bridge
Section

Railings, Drains,
ii
Cross fall

Abutment, wing
iii walls &
Foundations

Annexed
f Structural statical
Calculation

Check Analysis of
g the most important
structural elements
Evaluation for
Drawings

Sequence of
a
drawings

b Cover sheet

Drawing index
c
sheet

d Typical section

Crown, foreslopes,
ditch slopesk,
e
typical cut and fill
slopes are shown

Proposed
pavement structure
f clearly shown and
variability with
station tabulated

List of
g
Bm’s/pillars

h Plan profiles

Pavement
i
thickness

j List of structures

Drainage standard
k
drawings

Plan profile should


be presented in
scale of

1= 200 horizontal
L
& 1= 2000 vertical

(400) (4000)

On each plan
horizontal
alignment data,
curve data,
M stationing and
bearings are
clearly indicate
and provided in
tabular form

On each profile
vertical curve
data, VPI
information, K
values, length of
N verticle
curves, grades, has
been clearly
detailed on the
drawing and
tabulated

Sheet ( naming
O /numbering) is
consistant.
Control point are
P indicted on each
plan.

Cut/fill operation
Q
is balanced
MINOR
DRAINAGE

Cross drainage
i structures are
indicated on plan

Hydraulic
recommendations
followed
(hydraulic
ii information, slope,
length, and
invert elevations
shown on
plan/profile)

List, location, type


and dimension of
iii each cross
drainage structure
is tabulated

Standard bridge
iv loading and bridge
width provided

Bridge sites shown


and cross-
v
referenced to
bridge plans

Standard drawings
vi
are attached

You might also like