Professional Documents
Culture Documents
Barred supplier
more than 14 from 1
0
0
Controlled supplier
max. 14 none 36
Approved supplier
max. 7 none >>n.e. rated
P2 Project Management
P3.1 Are the specific product and process requirements available? n.e.
Is the feasibility comprehensively evaluated according to the product and
P3.2 n.e.
process requirements?
P4 Implementation of the product and process development
Are the actions which were defined in the product and process
P4.1 n.e.
development phases implemented?
Are the material resources available and suitable to ensure the start of
P4.3 n.e.
serial production?
Are the required approvals and releases for the product and process
P4.4 n.e.
development available?*
P5 Supplier Management
P5.1 Are only approved/released and quality capable suppliers used? n.e.
P5.2 Are the customer's requirements taken into account in the supply chain? n.e.
Are the necessary releases available for purchased products and
P5.4 n.e.
services?
P5.5 Is the agreed upon quality of purchased products and services ensured? n.e.