Process Table E
Transfer Molding -
Process Table F
Extrusion -
Process Table G
Equipment - O
Process Table H
Part Inspection & Testing - O
Personnel Contacted:
Name: Sirichai Chaikumlop Title: QA MGR Phone: +66-63-386-8625 Email: sirichai@thai.fujiseiki.com
Auditors/Assessors:
Name: Goro Fukuda Company: TFS Phone: +66-63-663-7999 Email: g.fukuda@fujiseiki.com
Assessment
To ensure readily available expertise, there shall be a Yes, Mr. Khomsun (Mold Maintenance
dedicated and qualified molding person on the site. Chief Engineer) and Mr. Vimol (Injection
This individual shall be a full-time employee and the Condition Chief Engineer), They have
position shall be reflected in the organization chart. A experience more than 10 years in
Is there a dedicated and
job description shall exist identifying the qualifications molding operation.
1.1 qualified molding professional
for the position including chemical and molding O
on-site?
knowledge. The qualifications shall include a Evidence:
minimum of 5 years experience in molding operation - TFS Organization
or a combination of a minimum of 5 years of formal - Job Description of Mr. Khomsun &
technical education and molding experience. Mr. Vimol
Yes, we do.
The quality management system shall include a
Does the Quality Department
process for documenting, reviewing, and addressing
review, address, and Evidence:
1.12
document customer and
customer concerns and any other concerns internal to
- Control of Document and control of O
the molder. A disciplined problem solving approach
internal concerns? Record (10-P-001)
shall be used.
The molder shall maintain a responsibility matrix Yes, we do In-house Training and Public
Is there a responsibility matrix identifying all key management and supervisory Training for all key management and
to ensure that all key functions and the qualified personnel who may perform supervisory functions
1.17 management and supervisory such functions. It shall identify both primary and O
functions are performed by secondary (backup) personnel for the key functions Evidence:
qualified personnel? (as defined by the molder). This matrix shall be readily - In-house & Public Training record
available to management at all times. - Certificate (after pass training)
Is the handling, storage and The molder's in-process handling and shipping
2.9 packaging adequate to process shall be assessed for risk of part damage or Yes, we control and check on this matter O
preserve product quality? other quality concerns.
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
Job Identity:
Customer: Hitachi Astemo Chonburi Powertrain Ltd
Shop Order Number:
Part Number: FA1320000031L
Part Description: DEFAULT LEVER
Molding Requirements:
Related
Molding System Customer or Internal Job (Shop) Order or Reference Actual Condition Pass / Fail
Question # Job Audit Question
Assessment Requirement Documentation Requirement (Objective Evidence) / N/A
Question #
1.1
Is contract review and advanced quality
1.2
planning, FMEA, Control Plans, etc., in Have document FMEA ,
3.1 1.3 N/A Pass
place and performed by qualified Control Plan
1.4
individuals?
1.6
Process #1:
Process #2:
1.5 Each part may have one or more requirements determined by the molding specification.
What are the product inspection
3.6 2.13 Parts must meet each requirement. List each requirement below and validate.
requirements?
2.14 (Listed below are some examples)
1.4
1.6 Document standard is
Were appropriate process steps signed
3.7 2.2 signed by Leader Pass
off?
2.3 /Supervisor/manager
2.11
1.2
Were steps/operations performed that
3.9 1.4 Not have Pass
were not documented in the Control Plan?
1.6
1.2
1.4
If additional steps were performed, were
3.10 1.6 N/A N/A
they authorized?
1.10
1.16
Packaging Requirements
2.6
3.15 Are packaging requirements identified? 2.7 Packing Standard Pass
2.9
Shipping Requirements
2.3
3.17 Were the parts properly identified? Lot Card on box Pass
2.9
2.3
3.18 Were the containers properly labeled? Packing Standard Pass
2.9
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
The customer may have additional requirements, e.g., inspection testing, greater frequencies, etc. When performing the job audit, the auditor shall verify molder is conforming to customer requirements.
*If minimum requirements are not met, provide supporting records to justify actual conditions.
Related
Molding
Observation/
Item # System Category/Process Steps Type of Control Monitoring Frequency
Comments
Assessment
Question #
Minimum Requirement Actual Condition Minimum Requirement Actual Condition (Pass / Fail /
N/A)
1.4
Incoming components assessment procedure, covering onsite
A1.2 2.1 Manual Not concern part Hitachi Once per lot Not concern part Hitachi N/A
testing or acceptance of supplier testing, with criteria (if applicable).
2.13
1.4
2.3 Stock rotation system in place for First in/First out (FIFO) and shelf- FIFO - per Lot
A2.1 Automatic/Manual Manual FIFO , Shelf life Pass
2.11 life Shelf life - pull for use
2.12
1.4 Continuous monitoring by
A2.2 2.11 Environment temperature controlled Automatic Automatic controller or manual Manual verification daily Pass
2.12 verification daily
1.4
1.6
Handling of partial containers to ensure no contamination (closed
A2.3 2.7 Automatic/Manual Manual Continuous Continuous Pass
container, clean environment)
2.11
2.12
1.4
1.6
A2.4 2.7 Partial container quantity Automatic/Manual Manual Per Container Per Container Pass
2.11
2.12
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
1.4
Continuous monitoring by Continuous monitoring
A3.1 2.11 Dryer temperature per resin manufacturer guidelines (per material) Automatic Automatic Pass
controller by controller
2.12
1.4
Per Resin Manufacturer Per Material Maker
A3.2 2.11 Dryer time per resin manufacturer guidelines (per material) Manual Manual Pass
Guidelines Guidelines
2.12
1.4
Material change ,
A3.3 2.11 Drying equipment (dryer dedicated or clean procedure in place) Manual Manual Material change Pass
Material filling
2.12
1.4
Continuous monitoring by Continuous monitoring
A3.4 2.11 Dew point Automatic Automatic Pass
controller by controller
2.12
1.4
Control Drying Material
A3.5 2.11 Moisture analysis, if applicable, per Resin Manufacturer Guidelines Manual Manual At start-up and once per shift* Pass
at 140oC (+5oC) , >6 hrs.
2.12
1.4
1.11 Recycle ratio (per print, inspection standard or manufacturer Once every 8 hours and at
A4.1 Automatic Not concern part Hitachi Not concern part Hitachi N/A
2.11 guidelines). Verified by feed pressure, weight or volume every part change over
2.13
1.4
1.11
A4.2 Dedicated regrind equipment or cleaning procedure in place Manual Not concern part Hitachi Material change Not concern part Hitachi N/A
2.11
2.12
1.4
1.11
A4.3 Fines management (de-dusting) Automatic/Manual Not concern part Hitachi Material change Not concern part Hitachi N/A
2.11
2.12
1.4
1.11
A4.4 Move regrind to IMM (contamination) Automatic/Manual Not concern part Hitachi Start-up and continuous Not concern part Hitachi N/A
2.11
2.12
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
1.4
A5.1 2.11 Pigment blending - percent loading, if applicable Automatic/Manual Not concern part Hitachi Start-up and continuous Not concern part Hitachi N/A
2.12
1.4
A5.2 2.11 Color change procedure Manual Not concern part Hitachi Continuous Not concern part Hitachi N/A
2.12
1.4
1.15 There shall be a standardized startup procedure/checklist that Start-up and restart after long Start-up and restart after
A6.1 Manual Manual Pass
2.11 defines things to do at start-up down time event stop more than 3 hours
2.12
1.4
1.15 Start-up and restart and after Start-up and restart after
A6.2 Production plan (machine, mold, materials, part style) Manual Manual Pass
2.11 long down time event stop more than 3 hours
2.12
1.4
1.15 At start-up, and after long Start-up and restart after
A6.3 Startup check (verify process settings against setup sheet) Manual Manual Pass
2.11 down time event stop more than 3 hours
2.12
1.4
1.15 Startup check - Secondary Equipment (De-gate, assembly At start-up, and after long Start-up and restart after
A6.4 Manual Manual Pass
2.11 equipment, welders, etc.) down time event stop more than 3 hours
2.12
1.4
Continuous if automatic, or at
1.15 Do each start-up and do
A6.5 Mold surface temperature Automatic/Manual Manual start-up and after down time Pass
2.11 once a day
event
2.12
1.4
1.15 Plastication - Temperature (barrel, nozzle, hot manifold if applicable),
A6.6 Automatic Automatic Continuous Continuous Pass
2.11 screw RPM, and back pressure
2.12
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
1.4
1.15 Manual (as condition
A6.7 Plastication - Melt temperature N/A Start-up Start-up Pass
2.11 Std.)
2.12
1.4
1.15 Manual (as condition
A6.8 Plastication - Screw recovery time N/A Continuous Continuous Pass
2.11 Std.)
2.12
1.4
1.15
A6.9 Fill - Screw velocity or velocity profile Automatic Automatic Continuous Continuous Pass
2.11
2.12
1.4
1.15 Manual (as condition
A6.10 Fill - Fill time and peak pressure N/A Continuous Continuous Pass
2.11 Std.)
2.12
1.4
1.15
A6.11 Hold - Hold pressure and hold time Automatic Automatic Continuous Continuous Pass
2.11
2.12
1.4
1.15 Manual (as condition
A6.12 Hold - Cushion N/A Continuous Continuous Pass
2.11 Std.)
2.12
1.4
1.15
A6.13 Hold - Cavity pressure (if applicable) N/A N/A Continuous Not applicable N/A
2.11
2.12
1.4
1.15 Temperature Control Cooling - Coolant inlet temperature and cooling
A6.14 Automatic Automatic Continuous Continuous Pass
2.11 time
2.12
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
1.4
Start-up and restart after
1.15
A6.15 Part weight (if applicable) Manual Manual Once every 8 hours* stop more than 3 hours Pass
2.11
and once a shift
2.12
1.4
1.15 Start-up, and restart after Start-up and restart after
A6.16 First piece approval Manual Manual Pass
2.11 down time event stop more than 3 hours
2.12
1.4
1.15 Material purge/evacuation of barrel - included in unplanned and Start-up and End of run
A6.17 Manual Manual End of run or long downtime Pass
2.11 downtime procedures or long downtime
2.12
1.4
1.15
A6.18 Shut down procedures Manual Manual End of production or run End of production or run Pass
2.11
2.12
1.4
Per cavity, start-up and once Per cavity, start-up and
A7.2 2.11 Dimensions Manual Manual Pass
every 8 hours once a shift and last shot
2.12
1.4
Per cavity, start-up and once Per cavity, start-up and
A7.3 2.11 Appearance (vs. boundary sample or per instruction) Manual Manual Pass
every 8 hours once a shift and last shot
2.12
1.4
Per cavity, start-up and once Per cavity, start-up and
A7.4 2.11 Physical properties (if applicable) Manual Manual Pass
every 8 hours once a shift and last shot
2.12
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
The customer may have additional requirements, e.g., inspection testing, greater frequencies, etc. When performing the job audit, the auditor shall verify molder is conforming to specifications or other
requirements.
Note that not all tests are applicable to all molding processes.
Related
Molding
Item # System Category/Process Steps Monitoring Frequency Observation/Comments
Assessment
Question #
Dimension, Weight, Appearance, Minimum Requirement Actual Condition (Pass / Fail / N/A)
1.0 General
Dimensions
Appearance
Performance
1.4 Procedures are in place to prevent damage to the finish or part during the QA OUT GOING
H1.1 100% Pass
2.9 inspection and packaging processes (30-WI-004)
Appearance (flash, color and gloss, short shots, splay/burns, blister, sink
First off by quality and 100%
H1.2 1.4 marks, gate vestige, and other molding defects) of the molding shall be Operator check 100% Pass
by operator
verified per specification and applications manual
H1.3 1.4 Cracks, Weld line/Knit lines, and Whitening/ stress mark First off and last off Operator check 100% Pass
H1.4 1.4 Part identification First off Operator check 100% Pass
H1.6 1.4 Dimensional check (e.g., Go-no go, Plug and Ring gage) First off and once per shift QC check 1 shift / time Pass
H1.8 1.4 General - Weight, Resin, Components, Porosity/Voids (if applicable) First off N/A N/A
CQI-23
Special Processes: Molding System Assessment
Version 1, 3/2014
The customer may have additional requirements, e.g., inspection testing, greater frequencies, etc. When performing the job audit, the auditor shall verify molder is conforming to specifications or other
requirements.
Note that not all tests are applicable to all molding processes.
Related
Molding
Item # System Category/Process Steps Monitoring Frequency Observation/Comments
Assessment
Question #
Dimension, Weight, Appearance, Minimum Requirement Actual Condition (Pass / Fail / N/A)
The customer may have additional requirements, e.g., inspection testing, greater frequencies, etc. When performing the job audit, the auditor shall verify molder is conforming to customer requirements.
Related
Calibration /
Molding System Injection Blow Vacuum Compression Transfer Included in Preventative
Item # Equipment Type Extrusion Verification Frequency Certification Comment
Assessment Molding Molding Forming Molding Molding Maintenance Plan
Frequency *
Question #
G1.4 2.14 Injection Mold Machine X Per Preventive Maintenance Every 5 years TFS PM once per month
G1.6 2.14 Blow mold machine X Per Preventive Maintenance Every 5 years TFS N/A
G1.7 2.14 Vacuum molding machine X Per Preventive Maintenance N/A TFS N/A
G1.8 2.14 Compression molding machine X X Per Preventive Maintenance N/A TFS N/A
G1.9 2.14 Extrusion machine X Per Preventive Maintenance Every 5 years TFS N/A
G1.10 2.14 Dryer X X X X Per Preventive Maintenance N/A TFS PM once per month
G1.11 2.14 Regrinder X X X Per Preventive Maintenance N/A TFS PM once per month
G2.2 2.14 Conveyers X X X X X X Per Preventive Maintenance N/A TFS PM once per month
G2.3 2.14 Degater/Trim Operation X X X X X X Per Preventive Maintenance N/A TFS N/A
G2.5 2.14 Robot X X X X X Per Preventive Maintenance At Installation TFS PM once per month
G2.6 2.14 Oven, if applicable X X X X Per Preventive Maintenance Annual TFS PM once per month
G2.7 2.14 Cooling Fan, if applicable X X Per Preventive Maintenance Annual TFS PM once per month
G2.8 2.14 End of arm tooling X X X X X Per Preventive Maintenance N/A TFS PM once per month
G3.1 2.14 Cure Testing, if applicable X X Per lot Annual TFS N/A
G3.2 2.14 Leak Testing, if applicable X X X At start up and per shift Every 6 months TFS N/A
G3.3 2.14 Color X X Before each use Annual TFS one per shift
G3.4 2.14 Gloss X X Before each use Annual TFS one per shift
G3.6 2.14 Dimensions X X X X X X At start up Every 6 months TFS one per shift
G3.7 2.14 Moisture X X X X X X Per Manufacturer Guidelines Every 6 months TFS one per shift
G3.8 2.14 Performance, if applicable X X X X X X Per Manufacturer Guidelines Annual TFS one per shift