UNIT RATE ANALYSIS (UPA) FORMAT

Work Item : 1.4 Door Finish


Unit : pc
Estimated Quantity (Q) : 1000.00 Unit Rate: 8.98

Local Currency (BDT)


Ref. No. Equipment Costs Q'ty Unit
Unit Rate Amount
1 Equipment Costs 5.00 pc 150.00 750.00
2 transport 1.00 1500.00 1500.00
3 0.00
4 0.00
5 0.00
Sub-total (1) 2250.00

Local Currency (BDT)


Ref. No. Labor Costs Q'ty Unit
Unit Rate Amount
1 Skilled 1.00 person 750.00 750.00
2 Unskilled 1.00 person 550.00 550.00
3 0.00
4 0.00
5 0.00
Sub-total (2) 1300.00

Local Currency (BDT)


Ref. No. Material Costs Q'ty Unit
Unit Rate Amount
1 wood 65.00 sqft 75.00 4875.00
2 Glass 1.00 sqft 35.00 35.00
3 Steel handle 1.00 pc 250.00 250.00
4 Color 1.00 pc 200.00 200.00
5 Oil vernish 1.00 pc 65.00 65.00
Sub-total (3) 5425.00

Local Currency (BDT)


Ref. No. Other Direct Costs Q'ty Unit
Unit Rate Amount
1 0.00
2 0.00
3 0.00
4 0.00
Sub-total (4) 0.00

(5) Sub-Total Amount of Specification Item: (1)+(2)+(3)+(4) = 8975.00