Trigger:

PIRs are the quantities allocated to TFs by TF Corporate planning cell to initiate the
Production/Procurement process. These numbers are used in MRP to calculate procurement and/or
production quantities for a material.

Business Process Description Overview


This document describes the procedure for creating, changing PIR.

Input – Required Fields Field Value/Comments


Plant Enter the number of the plant for which this w/c will
be valid.
Material no. Enter material no. for which PV needs to be created.

Output - Results Comments


PIR will be created. Enter all data precisely.

____________________________________________________________________________________________
Page 1 of 7
BUSINESS PROCESS PROCEDURE

Title: PIR_Create_change_display
Organization
/Area

Release: ECC 6.00 File Name: PP_ PIR _ Create_Change_display doc


Last Edited on: 09/06/2010 Version: 1.0

Procedural Steps for creating PIR

1.1. Access transaction by:


Via Menus Logistics>Production>Production planning> Demand
management> Planned independent requirement>Create-MD61

Via Transaction Code MD61

1.2. On screen “Create Planned Independent Requirement: initial screen”, first enter the
required data and then click enter icon .

____________________________________________________________________________________________
Page 2 of 7
BUSINESS PROCESS PROCEDURE

Title: PIR_Create_change_display
Organization
/Area

Release: ECC 6.00 File Name: PP_ PIR _ Create_Change_display doc


Last Edited on: 09/06/2010 Version: 1.0

1.3. On screen “Plnd Ind. Reqmt Create: Planning Table”, enter the requirement as shown in
below pasted screen shot.

Click on save icon as a result following message will appear on status bar.

____________________________________________________________________________________________
Page 3 of 7
BUSINESS PROCESS PROCEDURE

Title: PIR_Create_change_display
Organization
/Area

Release: ECC 6.00 File Name: PP_ PIR _ Create_Change_display doc


Last Edited on: 09/06/2010 Version: 1.0

Procedural Steps for changing PIR

1.1. Access transaction by:


Via Menus Logistics>Production>Production planning> Demand
management> Planned independent requirement>Change-MD62

Via Transaction Code MD62

1.2. On screen “Change Planned Independent Requirement: initial screen”, first enter the
required data and then click enter icon .

____________________________________________________________________________________________
Page 4 of 7
BUSINESS PROCESS PROCEDURE

Title: PIR_Create_change_display
Organization
/Area

Release: ECC 6.00 File Name: PP_ PIR _ Create_Change_display doc


Last Edited on: 09/06/2010 Version: 1.0

1.3. On screen “Plnd Ind. Reqmt Change: Planning Table”, change the requirement as shown in
below pasted screen shot.

Change
quantity here.
Earlier it was
2000 now
changed to
1900

Click on save icon as a result following message will appear on status bar.

Procedural Steps for Displaying PIR

____________________________________________________________________________________________
Page 5 of 7
BUSINESS PROCESS PROCEDURE

Title: PIR_Create_change_display
Organization
/Area

Release: ECC 6.00 File Name: PP_ PIR _ Create_Change_display doc


Last Edited on: 09/06/2010 Version: 1.0

1.1. Access transaction by:


Via Menus Logistics>Production>Production planning> Demand
management> Planned independent requirement>Display-MD63

Via Transaction Code MD63

1.2. On screen “Display Planned Independent Requirement: initial screen”, first enter the
required data and then click enter icon .

____________________________________________________________________________________________
Page 6 of 7
BUSINESS PROCESS PROCEDURE

Title: PIR_Create_change_display
Organization
/Area

Release: ECC 6.00 File Name: PP_ PIR _ Create_Change_display doc


Last Edited on: 09/06/2010 Version: 1.0

1.3. On screen “Plnd Ind. Reqmt Display: Planning Table”, requirement will get displayed as
shown in below pasted screen shot.

____________________________________________________________________________________________
Page 7 of 7
Click on the
view which
you want to
see

You might also like