2009 International Conference on Information Management, Innovation Management and Industrial Engineering

Application Research on the Investment Control of Construction Project


with Value Engineering at Design Stage

XU Bing
School of Economics and Management
North China University of Technology
Beijing, China
xbhello@163.com

Abstract—How to determine project investment reasonable


and to improve the utilization of funds is an important content II. THE IMPACT OF PROJECT DESIGN STAGE TO CONTROL
of owners’ investment management. However, as a function- INVESTMENT
cost analysis method, value engineering provides an effective Project investment will be completed gradually in the
way to solve these problems. This paper analyzes the
decision-making stage, the design stage and the
investment control method of construction project with Value
implementation stage. Therefore, the control activities of
engineering at design stage, focused on the application
procedure of value engineering, the objects choice of value project investment should run through every stage of project
engineering, features analysis of project, cost calculation of construction. However, it shows that the effect of investment
project and determination of function weight and so on, and control is different in the different stages of project (as
applies the results in cost control of construction project. shown in Figure 1, 2).
Practice shows that Value engineering will help owners to Percentage
control project investment actively at the design stage and to
improve the utilization of funds effectively. Finally, this paper
discusses the advantages and obstacles that use value 8
engineering to control project investment at design stage. 7
Keywords- value engineering; investment control; design 6
stage 5
75
4
I. INTRODUCTION
3
Project control investment refer to the process that
owners monitor project funds effectively and realize 2
investment objectives. Generally, project investment control 20
1 5
involves two aspects. The first is how to allocate investment
reasonable and how to obtain returns were as high as 0
Design stage Construction stage Completion stage
possible. The second is how to strict the use of investment
and control actual investment within the approved limit. Figure 1. The impact to investment of the project different stages
However, in practice, the projects investment control of
owners focused on how to prevent out-of-control of the Percentage
investment scale, and lack attention on how to use the project
investment more. 40
In Wenchuan earthquake, a large number of buildings
collapsed, and cause a great loss to the whole society. In 30
these collapse cases, a considerable portion of structural 40
system lack adequate security and reliability. A very 20
important reason is that there were serious "function-value” 20 25
mismatch for the use of investment in these projects. Project 10 15
investment of being used for decoration engineering and
installation engineering are larger relatively, that of being 0
Preliminary Technical Construction Construction
used for structural engineering are less relatively. As a result,
design stage design design prepare design stage
greater losses have been brought in earthquake.
stage stage
Therefore, it is necessary that using value engineering
optimize design scheme in the design phase of the project so
that to achieve a more reasonable match between functions Figure 2. The impact to investment of the project different design stage
and values.

978-0-7695-3876-1/09 $26.00
$25.00 © 2009 IEEE 411
DOI 10.1109/ICIII.2009.408
Figure 1 shows the impact of project design stage to ratio between the function of products and the cost which
control investment up to 75%, much higher than the impact attain the function. Its expression is:
of project construction and completion stage to control
investment. Figure 2 shows there are different impact to V=F/C
investment at the different design stage of projects. The F - function
impact to the investment is about 20% at the preliminary C - cost
design stage, about 40% at the technical design stage, about From the expression, value is proportional to function
25% at the construction design prepare stage, about 15% at and inverse proportion to cost. Therefore, there are the
the construction design stage. Therefore, the project design following five areas to improve the product value:
phase is a critical stage of investment control. • To keep the same functions and reduce cost;
• To keep the same cost and improve functions;
III. THE METHODS OF USING VALUE ENGINEERING TO
• To reduce cost a little and improve functions
CONTROL INVESTMENT AT DESIGN PHASE
significantly;
A. The basic principle of value engineering • To reduce functions a few and reduce cost
significantly;
Value Engineering (VE) is also known as value analysis. • To improve functions and reduce cost.
The core of value engineering is function analysis. It seeks to
achieve necessary functions of products reliable at the lowest B. The work steps which apply value engineering at the
cost, and to pursuit the match of product features and costs. design stage
Function refers to the properties of products that meet the According to the general analysis process of value
some needs of people. Cost means the product life cycle cost engineering, and combined with the characteristics of the
which include the whole expense from product development, project, the work steps which apply value engineering at the
design, manufacturing to using stage. Value refers to the design stage of construction project can be constructed as
shown in Figure 4.

Choose the sub- project of Identify problems, analyze the


value analysis design scheme
The purpose of this
feature The current cost of
each functions
Sub-project Sub-project cost
function analysis analysis
Means to achieve the
function The reasonable cost
of each function
Sub-project value analysis

The cost of each function Advance the new design


scheme
Possible alternatives
Whether to achieve the
design scheme
necessary functions reliably
Evaluate the new
design scheme
The effectiveness of the new Solve problems, optimized
design scheme design scheme
Determine design
scheme

Figure 3. The work steps which apply value engineering at the design stage

when using value engineering at the design phase of the


C. The discussion on the application of value engineering project:
at the design stage 1) The choice objects of value engineering
The content and methods of value engineering which In general, the project has been accustomed to divide
involved in construction project design stage are basically into a number of components by some specified standards.
the same as that in other areas. However, by the impact of Such as a construction project is divided into a number of
project characteristics, the following are different aspects single projects, a single project is divided into a number of

412
professional projects, and a professional project is divided direct costs, indirect costs, taxes and profits. Profits can be
into a number of part projects. So, the choice object of value assumed by the average profit level.
engineering at project design stage should be combined with
the division methods of construction project, and correspond
with the design, pricing and construction process of Decorative modeling
construction project so that to function and cost analysis
expediently. Figure 5 is an object decomposition system Lighting and ventilation
which applies to general civil construction projects.
Seepage, moisture proof, waterproof
Building construction
engineering Thermal insulation

Building decoration engineering


Building decoration Sound insulation
engineering
General civil construction projects

Structure safety
Building water supply,
drainage and heating Pipeline installation and maintenance
engineering
Materials fire protection
Building electrical
engineering Indoor pollution control

Intelligent building Workability


engineering
Materials ' durability
Ventilation and air-
condition engineering Energy and material saving

Elevator engineering Daily maintenance

Figure 4. The object decomposition system of general civil construction


projects. Figure 5. Building decoration engineering feature analysis system

2) The determination of function project 4) The determination of function weight


The functions of the project vary with the project type. The determination of function weight will impact
When functional analysis, it is necessary that to define directly on the outcome of the function evaluation. Due to
project’s functions combine the characteristics of projects, the complexity of the project, there are big difference views
purposes and the role of the future. At the same time, the to weights among different evaluator. Therefore, the level of
function analysis need consider the sub-project which analysis and expert scoring method should be combined to
contained in the project. In some literature, the functional of determine weight. This method combine qualitative and
residential projects are broken down into the application quantitative so that to ensure the objectivity of the weights
performance, security performance, durable performance, relatively.
environmental performance, economic performance and so
IV. THE ADVANTAGES AND OBSTACLES OF USING VALUE
on. Although the function system which determine by this
ENGINEERING TO CONTROL PROJECT INVESTMENT AT DESIGN
method is comprehensive, it lack the corresponding
relationship with the sub-project that the projects included in. STAGE
The results will bring more difficult to the cost analysis. A
feasible approach is to analysis respectively the function of A. Comparison with other control methods
various objects by various sub-projects which obtained from The major methods of control project investment at
project object decomposition. Figure 6 is a functional design stage include:
analysis for building decoration engineering • Using bidding to choose design units
3) The determination of project cost • Implementing quota design
When determining the object of value engineering, the • Adopting standardized design
project has been divided in accordance with the • Utilizing value engineering to optimize design
construction’s customary methods. Therefore, the cost of scheme
sub-project can be directly determined by the project budget In the above-mentioned methods, owns can choose an
when cost analysis. The sub-project budgets will include the appropriate design unit by bidding. However, this method

413
only create a necessary precondition to obtain a good design, stage by value engineering, and use the results of the
it does not guarantee access to good design scheme. Quota analysis to improve project design. From the theoretical
design can achieve effectively the aim of control the total analysis and project practice, the following conclusions
project investment, but it can not guarantee the rationality of obtained in this paper:
the design scheme. Adopting standardized design can save • Value engineering can help the project design
design costs significantly, speed up the pace of design scheme reach the best combination, and make the
drawings, and shorten the design cycle, but it contributes project investment structure more reasonable, and
little to optimize the design scheme. achieve the aim of control project investment.
Value Engineering study how to obtain the necessary • The key which use value engineering at the project
functions with the minimum cost. It emphasizes through design phase s to identify the object. The object
functional analysis and functional improvements to make the determination of value engineering should
project design scheme reach the best combination at the consistent with the custom division of construction
technical and economic. This is the advantage that the other project so that to convenience the functionality and
control methods do not possess. Therefore, there is great cost analysis
significance to analyze and adjust the matching degree of • It is necessity that to set up a special link for value
functions and cost among the various sub-project through engineering at the review of design scheme, and to
the use of value engineering at the design stage. Value establish service fee rules and reward system for the
engineering will help to form a good design scheme, make use of value engineering.
the project investment structure more reasonable, increase
the utilization of funds, and control project investment ACKNOWLEDGMENT
effectively. The paper supported by Funding Project for Academic
B. The obstacles of the using value engineering at the Human Resources Development in Institutions of Higher
design phase Learning Under the Jurisdiction of Beijing
Municipality(PHR-IHLB).
As an important means of scheme optimization, value
engineering did not receive a valid application in the field of
projects investment control in China. The reason lies mainly REFERENCES
in the following areas: [1] Charles Y.J. Cheah and Seng Kiong Ting, “Appraisal of value
1) Lack professionals which master the knowledge of engineering in construction in Southeast Asia,” International Journal
value engineering of Project Management, Volume 23, Issue 2, Feb. 2005, pp 151-158.
When using value engineering, professionals should not [2] Ugo Ibusuki and Paulo Carlos Kaminski, “Product development
only master the method of value engineering, but also process with focus on value engineering and target-costing: A case
understand construction technology and investment study in an automotive company,” International Journal of
Production Economics, Volume 105, Issue 2, Feb. 2007, pp 459-474.
management however, the phenomenon which is widespread
is that engineers do not understand the contents of [3] Jin Wang, Yujie Xu and Zhun Li, “Research on project selection
system of pre-evaluation of engineering design project bidding,”
investment management, and investment managers know International Journal of Project Management, Volume 27, Issue 6,
little about the technical knowledge of construction. Aug. 2009, pp 584-599.
2) Lack a special link which optimize the design scheme [4] Zhang Hongwei, “Conformity Utilization of Construction
by value engineering Programming and Value Engineering,” Value Engineering, vol. 26,
Value Engineering is a process which combines with Nov. 2007, pp. 71-73.
technical scheme and economic evaluation. Under the [5] WANC Jun, JIN Hao, SHI Qiyin, “Application of value engineering
current management of project design, technical scheme and in design options of bidding,” Sichuan Buildiun Science, vol. 32, Feb.
2006, pp. 171-173.
economic evaluation are completed by different departments.
[6] MIAO Zhiping, “Application of Value Engineering in Optimizing
Technical and economic professionals work relatively Design Schemes,” Optimization of Capital Construction, vol. 27, Dec.
independent, lack a mechanism which completes the design 2006, pp. 61-63.
work jointly. [7] GU Guanwei and SUN Lingli, “On Application of Value
3) Lack a system which insure the use of value Engineering in Project Optimization Design,” Journal of Jianghan
engineering at the design stage Petroleum University of Staff and Workers, vol. 22, Jan. 2009, pp.
At present, there lack the special content which use value 38-40.
engineering to review design scheme at design phase. There [8] Liangjun, “Value engineering applicable to construction project
isn’t a corresponding service fee rules and reward system for schemes Choice”, Railway Operation Technology, vol. 8, Oct. 2002,
pp. 30-35.
the use of value engineering to optimize design scheme. As
[9] Xueqing Zhang, Xiaoming Mao and Simaan M. AbouRizk,
a result, design units have no interest to optimize design “Developing a knowledge management system for improved value
scheme and improve investment benefit by using value engineering practices in the construction industry,” Automation in
engineering. Construction, Volume 18, Issue 6, Oct. 2009, pp 777-789.
[10] SHAO Ling, “Brief Discussion on Cost Control of Construction
V. CONCLUSION Project in Design Phase,” Jiangsu Construction, vol. 115, Oct. 2006,
pp. 62-64.
Base on the above methods, the paper analyzes projects
investment to a construction project in Beijing at design