Professional Documents
Culture Documents
4
Guiding Codes for Engineering Works:
5
To take up any work following are required:
1. Administrative Sanction
2. Technical Sanction
6
Procedure involved in taking up of any work is:
7
Procedure involved in taking up of any work is:
Safe Bearing Capacity (SBC) / California Bearing Ratio (CBR) Values are
required for Buildings / Roads respectively.
Specification Report.
Current Year Schedule of Rates (SoR) effect from 1st June of year.
Rates based on Revised Standard Data 2009 and its amendments invouge.
Technical Sanction.
8
Execution of Works on:
Handing over Site (As per APDSS Para 58, if the site to be handed over
within 2months from the date of issue of work order the Contractor can
withdraw the contract and EMD to be refunded if this is not done).
10
d) Price Adjustment clause as per G.O.Ms.No.94 TR & B (R.I) Dept. dt.16-04-
2008, G.O.Ms.No.252 TR & B (R.I) Dept. dt.28-08-2008, & G.O. Ms. No. 35 TR &
B (R.I) Dept. dt.30-01-2009 . Generally Price Adjustment will be allowed when
the variation in rates are more than 5% decrease or increase.
11
Programmes Existing from Central Govt. & State Govt. are as
follows:
IAY etc.
12
State Works:
Plan Schemes
Maintenance Grants
Irrigation works
Hospitals
13
Technical Sanction Powers:
14
General pattern of Engineering Department:
15
Major Rural Programme:
iv. Crematoria
viii. Houses Sanctioned under IAY (Min. built up area 20sqm / 215sft).
areas over and above the funds approved under IAY programme
17
Designs:
A) Foundations: Based on type of soil and its Safe Bearing Capacity
the following may be adapted:
18
E) Columns: RCC / Masonry: For RCC Designs we have to
consider i) Dead Loads / Wind Loads / Earthquake loads
ii) Eccentricity iii) Long column effect (height more than 12
D))
F) Flooring: Brick Bat Flooring / Ellise pattern (1:2:4) /
Kadapa / Macherla / Bethamcherla / Shahabad / Mable /
Granite Flooring ( Prefer locally available material)
G) Finishings: Plastering, painting, doors, windows,
ventilators, electrifications, water supply & sanitation
Type of structures we used to have prior to RCC/ Concrete
technology, Mid 18th Century : Stone structures with lime
or mud mortars, Mud houses with thatched roofing,
Timber houses.
19
Appropriate Technologies:
1. What is an appropriate technology?
2. Why it is required?
20
3. Various appropriate technologies available & its safe adoption.
Construction of Building is broadly divided into the following:
1) Sub – Structure - Foundations & Basement
2) Super Structure
3) Roofing
4) Finishings
1) Sub-structure:
a) Foundations: Type of foundation is based on soils and its safe
bearing capacities
i) In hard soils: Preferably Stub or Arch or concrete &
masonry with stone or brick
ii) Loose & filled up soils: Individual footings or strip
foundation
iii) BC soils: Under reamed piles with single or double
bulbs
21
Stub Foundation: Maximum C/C distance between Two
stubs is 2.50m
22
Arch Foundation
Arch Foundation
24
25
b) Basement:
i) In Hard soils: RR Masonry/ Solid CC Blocks with Damp Proof
Course on top
ii) In Medium & Loose soils: RR Masonry/ Solid CC Blocks with
plinth beam
iii) Basement height to be decided depending up on site conditions,
water logging areas etc.
iv) Basement filling: Sand or gravel or crusher dust in BC soil areas.
Other areas available excavated earth or gravel
2.Super structure: Brick masonry, doors & windows:
I) Brick Masonry:
a) Materials : Bricks / Blocks:
i) 2nd class
ii) mud with 5% of cement sun dried
iii) flyash
iv) stone blocks
v) Compressed Stabilised Earthen Blocks
b) Masonry:
i) English ‘or’ Flemish bonds in framed/ conventional
type of construction using 2nd class kiln burnt bricks
or flyash bricks or stone blocks or Mud Blocks or
Compressed Stabilised Earthen Blocks with cement or
lime mortar.
ii) Rat trap bond for framed / conventional method
construction using 2nd class, flyash and Compressed
Stabilised Earthen Blocks (CSEB)
II) Lintels:
i) Brick Arch
ii) Brick
iii) Stone
iv) Wooden (seasoned wood)
v) RCC: either cast in situ or precast
III) Sunshades:
i) RCC
ii) Precast CC
iii)Stone
IV) Doors & Windows:
i) Wooden frame & shutters
ii) RCC frame Wooden Shutters
iii) MS frame & shutters
V) Ventilators:
i) Precast CC
ii) Brick Lintels
TECHNOLOGIES DEMONSTRATED DURING
THE WORKSHOP
31
Jack Arch Ferro Cement Roof Slab
32
Waffle Slab
33
Brick Slab (Circular Room with Sloped Roofing)
34
Filler Slab With I Section for Sloped Roofing
35
Filler Slab With Tiles
36
Reinforced Cement Concrete Ribbed Brick Slab
Reinforced Ribbed Brick Slab
38
4) Finishings:
I) Plastering with
i)Cement Mortar
i) Lime
ii) Distemper
RAT-TRAP
The rat trap bond is a masonry
technique, where the bricks are used
in a way that creates a cavity within the
wall, while maintaining the same wall
thickness as of a conventional brick
masonry wall.
b) First layer, sill level layer, 1st layer above lintel level, layer below slab to
be of solid layer
41
Rat-trap brick masonry
42
CONSTRUCTION AND DESIGN
The principal requirement for rat-trap brickwork is the
availability of good quality bricks. The following may be
considered as a guiding principle for ensuring strength of bricks
Type
for of building
Rat-trap construction – Recommended compressive strength
brickwork:
Span not exceeding 4.2 0meters, of brick
Roof/ floor loads as per IS 875
Best Practice Minimum
allowable
45
QUANTITY REQUIRED
Data for 1.00 Cubic meter of rat-trap bonded brick masonry with wire
cut bricks in cement mortar (1:6).
Description Unit Quantity
Cement kg 36
Scaffolding cum 1
Skilled Labour Days 1.56
47
Filler slab
In simply supported RCC slab, Concrete
above the neutral axis takes care of
compressive forces and Steel below the
neutral axis takes care of tensile forces.
48
DESIGN AND CONSTRUCTION
Materials:
Cement – 6.6bags
Coarse sand – 0.46cum
Aggregate 20mm size – 0.61cum
Aggregate 10mm size – 0.31cum
Total Aggregates -0.92cum
Labour:
Mason 1st class – 1.67Nos.
Unskilled labour -3.72nos.
Curing labour - 1.22Nos.
Bar bender – 0.82Nos
• Depending up on tile size, the no. of tiles will vary and also reinforcement
spacing will vary.
• The data is for 1cum of regular concrete. For filler slabs the concrete quantity
will get reduced and consequently materials
52
Advantages
• It enhances the thermal .
53
The Basic Concept for adoption of Appropriate
Technologies is to:
54
Exposed wire cut brick and Random Rubble
Courtyard – Natural stones
Mangalore tiled roofing
Fillers Slab
Brick detailing
Brick detailing
Brick detailing
corbelling
Wood – Honne and Sal for frames
and shutters
Natural Lighting with ventilation to
allow hot air to escape
Natural Lighting in the
bathroom
Sensor based lighting externally and
internally with Led to conserve electricity
Solar Panel for hot water
Solar lights for the pathway
Solar Panel lighting for the
street
Mangalore tiles roof
Flooring – Jaisalmer and kota
Others
• Rain Water harvesting- Water is collected from all roof
tops and diverted to another sump which is used for
gardening, cleaning vessels and washing clothes.
• Organic garden- No fertilizers used . Coco pit with
neem cake, bone meal and cow dung are mixed to a
proportion to act as fertilizer. Kitchen waste is used to
create compost.