Professional Documents
Culture Documents
Equipment
Filling pup trial with Ultrasonic Flow Meter (UFM) (calibration certificate expired
1 on Jul 21)
5 KSB pump repair to be expedite to reduce filling water duration and existing
manifold to be modify
Compressor with flow rate > 1000 CFM; with 15 Barg SPJ (only for 1 week
6
duration) to be revisit for pigging at ORF
Compressor at least 100 CFM flow to be provided at GOP for driving chemical
7 injection pump
8 Air Dryer flow rate > 1000 CFM during drying SPJ to be revise
Hydraulic Torque wrench M 65 to be provided during SDV installation WO has
9
been issued to CMP
10 Dew point meter will be provided by Teknik Nusantara (max 2 days duration)
11 Air Compressor 920 CFM for Chemical injection pump
Consumable
1 Additional Chemical (corrosion inhibitor) arrival to be expedite
2 Pig available :
Pig medium Density 8 EA
Pig low density 9 EA
New Bidi pig 1, Spare seal 2 Set Used 2 Pcs
Poly Pig 1 New and 3 Used (1 still in good condition recommend to use for
flooding)
3 Gauging Plate 3 Pcs
Nitrogen for Purging Gas Line awaiting instruction for mobilization WO has been
4 issued to Aneka gas, Additional WO with pigging scheme during drying to
accelerate reaching O2 content target will be required.
5 Seal pig door (QOC) 2 pcs remaining; to be considered to have additional 2 spare
more
Spare Gasket 12 Pcs 20” for SDV, and interchange blind spade and spacer has
6
been received at site and consider to relocate at TSF from warehouse
7 Insulation gasket to be relocate to TSF
N2 bottle to be provided for leak test SDV and Pig launcher portion at GOP SPB to
8 be issued.
Remaining pipeline portion at ORF that not leak tested yet, Considering using N2
9 bottle or ISO tank with booster pump.
Status Action
Done Anggi
EHS
Khafidz
Khafidz
Khafidz
Khafidz
Khafidz