Operation To start
Capacity 6 ton
Make Thermax
1. Boiler feed water can be filled 75% gauge glass level with fill mode operation yes
3. Ensure should not be any leakage in valve / joints / gasket area yes
4. Ensure and check furnace / grate properly cleaned from ash / deposition if any yes
6. Ensure to check air availability for feed water control , feed water inlet valve in on condition yes
8. Now the fuel can be fed inside the furnace / retort as per feeding philosophy yes
9. Initial firing can be slow with recommended sequence ( 15minute to 20mintue ) yes
10. yes
ID fan should be in on condition
11. After 15minute on the FD Fan yes
13. If furnace temperature reach 300℃ then adjust the FD-30% to 50% then open the damper yes
14. Observe main furnace shut off when boiler reaches operating Pressure yes
15. After water boiling vapour coming with 1kg/cm2 pressure then close the air vent valve yes
16. Safety valve and Pressure switch operation need to be checked to ensure safely is in line and man yes
goal and met goal also need to check
17. Then main steam valve open yes
Cooling water need to fill in the sell in then feed water working pressure come down on zero yes