PROPOSAL PROP-BPK-CIV-001 00
SHEET 1 OF 8
Issue Record
REVISION HISTORY
TABLE OF CONTENTS
Land clearing work is a site job to be estimated or in other words an "exact" job,
because the amount of production is erratic and the work is one to the other. The
equipment used and the way chosen for this land clearing job determines the amount
of production.
Various equipment that can be used in land clearing work can be seen in the table
below
Chainsaw, Axe,
1-4 Ha Blade Bulldozer Chainsaw Machine.. Blade Bulldozer
The right and correct method of work will greatly affect the productivity of the tool,
to determine which method is appropriate depending on many factors such as the
volume/specification of the project and the time available..
a. Underbrushing
b. Felling / Cutting
c. StockPilling of Log
The activity of collecting the timbers which are then collected into piles of
wood at a certain distance, it is necessary to note the existence of a pile path
that corresponds to the direction of the wind.
Suitable applied to the area average, after the plot area to be opened has been
determined , then the bulldozer began to cut down or uproot the tree , from the
outside heading into , around the plot area with motion bulldozer bedrlawanan
with needle clock.
c. Contour Method
PROF-BPK-PRO-CIV-001 Page 7 of 12 Rev. 00
EPC of Pumping System for transporting biodiesel at benete area
Civil Work Procedure
The method is applied to the area is hilly , bulldoer cut down , cut down on ats
hill to the bottom in the area with an altitude that is equal (contour that is the
same).
d. Zigzag Method
Just like the perimeter and out crop methods , the ig zag method can be applied
to flat areas.
One of the methods that have the efficiency of work the highest , the method is
having the efficiency of work 98,8 %.
a. Kelebatan pepohonan
Number of trees
Size of the trees
The violence
Root state
Clump-clump that exist.
Should we consider whether the purpose of the land clearing is later , for
example, to the benefit of making dams, roads highway or for the purposes
of another. Because of the things referred to will be a material consideration
in choosing a method and apparatus are used to work land clearing.
Factors state of the ground and the power capacity of the soil also must we
consider , including the factors of this are:
Field slope .
Channels that exist .
Swamp - marsh are there .
Big rock .
Hill..
f. Job Specifics
Factors specifically is among others can depend on the terms / conditions
of the following :