You are on page 1of 17

MRP Thermal Fatigue

Program Update

Paul Crooker
Technical Leader, Principal

Materials R&D Tech Exchange Meeting


May 23, 2017

© 2017 Electric Power Research Institute, Inc. All rights reserved.


Presentation Content

 MRP thermal fatigue program evolution


 Operating experience history
 MRP response
 Recent trending of operating experience
 MRP current effort
 Recent OE inspection challenges and MRP response

2
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Thermal Fatigue Program Evolution

 Original plant designs and inspection programs did not


conceive of all potential thermal fatigue vulnerabilities
– Thermal stratification
– Thermal mixing
 PWR OE during the mid 1980s alerted Industry to the need
for management of thermal fatigue
 Industry responded - collaborative research led to a better
understanding of system behavior
 MRP strategy focuses on component identification,
inspection and mitigation

3
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Thermal Fatigue Program Evolution (2)

 MRP thermal fatigue management under NEI 03-08 is


implemented by:
– MRP-146 Cyclic stratification in non-isolable RCS branch lines
(“Needed” item)
– MRP-192 Thermal mixing tees in RHR systems
(“Good Practice” item)

4
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Thermal Fatigue Program Evolution (3)

5
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Operating Experience History

 5 Events leading into NRC Bulletin 88-08


– All through-wall (2 US plants)
 6 Events subsequent to Bulletin thru 2000 (12 years)
– All through-wall (2 US plants)
 3 Events after industry guidance thru 2012 (12 years)
– All part-wall (2 US plants, cracking discovered during planned MRP-
146/192 program examinations)
 10 Events in US between 2013 and 2015 (2 years)
– 3 through-wall
– 7 part-wall (cracking discovered during planned MRP-146/192
examinations or extent of condition examinations)

6
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Response
 Program successful in detecting flaws before leakage occurs
in many instances; however, opportunities for improvement
identified
 EPRI Thermal Fatigue Focus Group (TFFG) established to
assess impact of OE and recommend corrective actions
 TFFG objectives:
– Publish Interim Guidance to prevent thermal fatigue degradation from
exceeding Regulatory limits
– Identify actions for program improvement
 TFFG process:
– Review each event
– Identify specific program failures
– Identify potential causes and determine mitigation alternatives
– Develop Interim Guidance to detect cracks at an early stage
– Identify knowledge gaps and propose specific research to close gaps
& improve program
7
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Response (2)

 TFFG major findings:


– Certain screening criteria found suspect – population of susceptible
piping to increase
– Need for expansion of MRP-146/192 inspection zones
– Newer NDE techniques and procedures are better in detecting
cracking
 Interim Guidance issued in May 2015
– 2 “Good Practice” requirements
– 8 “Needed” requirements
 EDF and Japanese thermal fatigue program benchmarking
effort initiated and completed (MRP-408/409)
 Additional NDE mock-ups created to aid in examiner training

8
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Response (3)

 Maintain plant staff expertise


– EPRI Fatigue Management Handbook updated (MRP-235)
– Fatigue management training conducted and recorded
 MRP-146 Revision 2 published in September 2016
incorporating Interim Guidance
 MRP-192 Revision 3 under development and to be
published in 2017 incorporating Interim Guidance

9
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Recent Trending of Operating Experience

 7 Events in US between 2016 and 2017 (1 year)


– One through-wall
– 5 part-wall (cracking discovered during planned MRP-146
examinations or extent of condition examinations)
– 1 part-wall (detected via planned Section XI examinations)

10
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Recent Trending of Operating Experience (2)
Date Reactor Component Flaw Depth Method of
Supplier Detection
March W Drain Line 58% Part-wall Extent of
2016 Condition*
March W Charging Line 44% Part-wall MRP-146
2016 Inspection
May W RHR Suction 24% Part-wall Section XI
2016 Line Program
February W Safety Injection Through-wall N/A
2017 Line
March W Safety Injection 21% Part-wall MRP-146
2017 Line Inspection
April W RHR Suction 14% Part-wall Extent of
2017 Line Condition*
May W Safety Injection Part-wall in MRP-146
2017 Line socket weld Inspection
* Inspection methods consistent with MRP-146 inspection guidance.
11
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Current Effort

 All 7 events reveal a potential need for modified guidance


– Drain line was screened out based on MRP-146 generic guidance,
OE was not expected
– One crack location was not considered likely due to line size and
geometry, discovered during a one-time inspection
– RHR suction lines were screened out as to run fully hot, OE was not
expected
– Possible new source of in-leakage identified from SI system cross-
flow
– Flaws detected outside of MRP-146 inspection zone

12
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Current Effort (2)

 TFFG is carefully reviewing each event to fully understand


root causes and then make a determination if program
changes are necessary
 Instrumentation for temperature, vibration and/or strain
monitoring has been employed at 3 sites
– Data has been very valuable in understanding loading conditions
contributing to crack initiation and fatigue crack growth
– Data being reviewed by the TFFG to further understand the thermal
fatigue mechanisms and component susceptibility
 Publication of Interim Guidance, if necessary, expected later
this year

13
© 2017 Electric Power Research Institute, Inc. All rights reserved.
MRP Current Effort (3)

 Overall, the MRP Thermal Fatigue Program has proven


successful in detecting flaws before leakage occurs or when
cracking presents a challenge to existing structural margins
 Through the continued engagement of the MRP and the
TFFG, improvements in existing thermal fatigue
programmatic guidance will be evaluated and implemented
as necessary

14
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Recent OE Inspection Challenges

 Newly Identified Cracking Morphologies


– RCS High Pressure Injection Nozzle cracking (3-inch OD)
 Axial cracks on the nozzle side without craze cracking
 Examination from the nozzle side may be difficult due to geometry
– NDE Challenge: single-side examination for axial crack
detection
– RCS Drain cracking (2-inch OD)
 Weld cracks initiating in the heat-affected zone then propagating
into the weld
– NDE challenge: difficult to detect the crack tip inside the weld
– NDE challenge: weld complexity may trigger false calls
 Elbow skewed cracks
– NDE challenge: cracks with complex skewed paths difficult to
detect

15
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Inspection TAC Deliverables

 To respond to the OE, Inspection TAC plans include:


– Revise the thermal fatigue examination procedure
 Develop a cover sheet for use with PDI UT-2
 Revise the generic thermal fatigue examination procedure
– Revise MRP-23, MRP-36 (CBT)
– Fabricate 7 additional mockups
– Add thermal fatigue mockups to Virtual UT System
 Deliverables scheduled for December 2017

16
© 2017 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity

17
© 2017 Electric Power Research Institute, Inc. All rights reserved.

You might also like