Professional Documents
Culture Documents
ENGINEERING SURVEYING
QUESTION 1
b. In what ways can the branches mentioned above compliment engineering surveying and be
of use to a civil/agricultural engineer. [3 Marks]
c. The polygon traverse PQRSTP is to be sub-divided into two equal farming areas by a straight
line that must pass through point R and meets the line TP at Z. The coordinates of the points
are given in the table below.
P 613.26 418.11
Q 806.71 523.16
R 942.17 366.84
S 901.89 203.18
T 652.08 259.26
1
i. calculate the area of the polygon PQRSTP [6 Marks]
QUESTION 2
b. The tangent length of a simple circular curve was 202.120m and the deflection angle of a
30m chord was found to be 02°18’00’’. Calculate
i) the radius of the curve [3 Marks]
c. A circular curve of radius 800m has been set out connecting two straights with a deflection
angle of 42.00.00. It is then decided for construction reasons that the mid-point of the curve
must be moved 4m towards the centre, i.e. away from the intersection point. If the
alignment of the straights is to remain the same, calculate
ii) the distance from the intersection point to the new tangent points [3 Marks]
iii) the deflection angle for setting out the 30m chords on the new curve [3 Marks]
2
QUESTION 3
a. What do you understand by the term control in surveying? Explain any two different ways
that can be employed to establish control. [2 Marks]
b. Apart from taping, what two other methods can be used for horizontal distance
measurement. What are the advantages and disadvantages of using either of the method
you have mentioned? [4 Marks]
d. In order to mark the boundary of a civil/agricultural engineering project, a link traverse was
run between stations A and E. The coordinates of these points in metres are:
Point Y X
A -40 076.90 +26 992.30
E -39 794.17 +27 116.82
The lengths of the legs and the directions adjusted for angular misclosure are:
3
QUESTION 4
a. Levelling forms an important component for most engineering works. Explain why and
how levels are useful to an agricultural/civil engineer? [5 Marks]
c. The following figures were obtained from a surveyor’s link leveling process
The reduced levels of BM1 and BM2 are 99.980m and 100.445m respectively. Construct and
reduce an HPC booking sheet with all necessary checks using the results above. [10 Marks]
4
QUESTION 5
b. You have been tasked to produce a large scale map (with contours) of a section of the
university. Outline in detail the steps you will undertake to accomplish your task. Highlight
in your answer different sets of equipment you may use. Which of the sets would you
prefer? Justify your answer. [10 Marks]
d. A distance of 220,450m was measured with a steel band of nominal length of 30m. On
standardisation the tape was found to be 30,003m. Calculate the correct measured distance
assuming the error is evenly distributed throughout the tape.
[4 Marks]