1. Scope of Work:
The Scope of Work includes
i) Mobilization and demobilization of required man power machinery and all other required
equipment as per work requirement etc.
ii) Taking trial bore of 150mm dia in ground & water level up to required depth in all types of
soils including hire charges and machinery and labour etc. as directed by the engineer in
charge.
iii) Collection of undisturbed & disturbed soil samples 100mm dia X 450mm long tubes with
one side threaded and both side wax ceilings as directed by engineer in charge.
iv) Conducting standard penetration test as per IS 2131 -1981 using split spoon sampler and
drive weight assembly of required depth in all types of soil including hire charges for
machinery and Labour etc., work shall be execute as per directed by engineer in charge.
v) To submit all the required soil bore log data with all details as directed by the engineer in
charge.
3. Duration of Work:
Commencement of Work: Immediately on Receipt of Work Order and to be completed with 5
days from the start date of sample collection.
Submission of Geotechnical Investigation Reports: With 10 Days from sample collection
Date.
Total duration of Work: To be completed within 15 days from the start date of work.
4. Submission of Reports:
Submission of Geotechnical Reports consisting of Field Bore Log Details, Laboratory test
results consisting of Atterberg's Limit, SPT, UDS test, Tri-axial test, Vane shear test, core
sample test, plate load test, Grain Size distribution, Bulk density, Natural moisture content,
Specific gravity , Consolidation, Unconfined - compression test etc. and Calculations for Safe
Bearing Capacity of soils.