You are on page 1of 11

PACKAGE-2 Date:22.07.

2021
Supply & Installation of Energy Meter
OPTCL-TPWODL (WESCO)

Description TPWODL
Original LOA quantity 660,000

Amendment quantity 25,000


Total LOA quantity 685,000
Supply completed 685,000
Pending supply 0
Agencies supply(PGCIL,NTPC,GUPTA,LnT etc.) 52,350
Installation scope under WESCO 100,000
Additional meter delivered -2nd phase 9,480
Balance meters to be delivered 11,988
Total Meters under WESCO scope 121,468
Installation scope under Linkwell 511,182
Installation completed 510,484
Damaged meters to be replaced 698
Certification completed 430,603
RED 500

Baragarah 2090
BWED 1200
Amendment Order received
on 27 April 2020 Balangir 1700
Titlagarah 1986
Kalahandi 1834
Sambalpur 678
RED 500
RSED 350

RGP 600
SNG 50
JSG 150
BNED 350
Total 11988

Direct from
store 9480

Total 21468
-20,770 Damaged to be replaced
PACKAGE-2
Supply & Installation of Energy Meter
OPTCL-NESCO 12.6.21

Description NESCO

Original LOA quantity 540,000

Amendment quantity 87,095


Total LOA quantity 627,095
Supply completed 627,095
Agencies
supply(PGCIL,NTPC,GUPTA,LnT etc.) 60,700

Installation scope under NESCO 50,000


Installation scope under Linkwell 516,395

Installation completed 514,547


Installation to be done 1,848
Certification completion 470,329
PACKAGE-2 Date:25.06.2021
Supply & Installation of Energy Meter
OPTCL-TPCODCL

Description TPCODCL
Original LOA quantity 215,000

Amendment quantity 18,413


Total LOA quantity 233,413
Supply completed 233,413
Pending supply 0
Installation completed 233,202

Installation to be done 211


Certification completed 221,005
Certification to be done 12,197
amended LoA received
on 29.04.2020.Supply
completed

damaged meters
rectified to be handed
over to the store
PACKAGE-3
Supply & Installation of Energy Meter
OPTCL-SOUTHCO
22.07.2021
Description TPSODL

Original LOA quantity 931,874


Amendment quantity 82,641

Total LOA quantity 1,014,515


Supply completed 1,014,515
Pending supply 0

Installation scope under SOUTHCO 100,000

Installation scope under Linkwell 914,515


Installation completed 780,710
certification completed 630,357
Installation to be done 133,805
around
36000nos.replaced by
TPSODL

197,805 Including 64K

166,972 747543 63500

230,472
NESCO
WESCO
CESU
SOUTHCO

You might also like