You are on page 1of 8

Standard 

Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  1 
00257650‐0000‐45EG‐0004 

CLIENT:     LITHIUM NEVADA CORPORATION 

PROJECT: THACKER PASS 
 
 
    SIGNATURE    DATE 
   
 
PREPARED BY:  D. Lyon 
   
 
REVIEWED BY:  Y. Zhou 
   
 
APPROVED BY:  T. Van Daele 
 

ISSUE/REVISION HISTORY 

Issue  Revision 
Revision Details 
Code  No.  By  Rev’d.  App.  Date 
RD  PA  DL  YZ  TVD  2020.01.06  Released for Review 
RI  PB  DL  YZ  TVD  2020.01.06  Released for Information 
             
             
             
             
             
             

Issue Codes:  RC = Released for Construction, RD = Released for Design, RF = Released for Fabrication, RI = Released for Information, RP = Released for 
Purchase, RQ = Released for Quotation, RR = Released for Review and Comments. 

This  Specification  is  the  property  of  EXP  U.S.  Services  Inc.  (EXP).    Information  and  know‐how  herein  are 
confidential and may not be used, reproduced, or revealed to others except in accordance with contract or 
other written permission of EXP. 
   

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 1 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  2 
00257650‐0000‐45EG‐0004 

TABLE OF CONTENTS 
 
1  DESCRIPTION .................................................................................................................................. 3 

2  GENERAL ........................................................................................................................................ 3 

3  ASSEMBLY OF MANUALS ................................................................................................................ 3 

4  MANUAL CONTENT ......................................................................................................................... 4 
4.1  Installation Manuals ................................................................................................................... 4 
4.2  Operating and Maintenance Manuals ........................................................................................ 5 
5  SAMPLE BINDER COVER INSERTS .................................................................................................... 8 

 
 
 
 
 
 
 

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 2 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  3 
00257650‐0000‐45EG‐0004 

1 Description 
This specification describes the requirements for the uniform preparation of Installation, Operating 
and Maintenance Manuals supplied with equipment specified in the technical specifications. 

2 General 
Provide a manual for installation instructions and a separate manual for operating and maintenance 
instructions. 
Ensure manuals are inclusive of all components of the equipment including components supplied by 
Sub‐Vendors / Contractors. 
Comply with specification 002576520‐0000‐40EG‐0001 Vendor Documentation for document sizing 
and format. 
Submit completed manuals in accordance with quantities indicated in the Vendor Data Requirements. 
Provide all manuals in English. 

3 Assembly of Manuals 
Assemble manuals in white, plastic covered, D‐Ring type binders with a clear plastic front and spine 
pocket for insertion of the manual title sheet.  No other type of binder is acceptable, including the 
Vendor’s standard binders. 
Provide  rigid  plastic  inserts  in  the  binder  before  the  first  page  and  after  the  last  page  to  assist  in 
pushing the pages into their proper orientation when closing the binder. 
Provide coloured plastic dividers to separate each section of the manual. Mark dividers numerically 
to correspond with the index. 
Sub‐divide and index each section of the manual to facilitate referencing. 
Fold and enclose in an 8.5” x 11” size plastic pocket, of adequate strength, all drawings and charts 
larger than 8.5” x 11”. 
Enclose originals of all brochures. Photocopies are not acceptable. 
Where a general brochure is applicable to a range of equipment, identify the specific item, catalogue 
number or model number. The same applies to lists of spare parts. 
Wherever possible provide exploded views and pictorial descriptions. 
Refer to Section 5.0 of this specification for details of the inserts for the front cover and spine pockets. 
The font shall be Calibri and all characteristics shall be the same as that shown. Number each volume, 
e.g. 1 of 1, 1 of 2, 2 of 2, etc. 
Comply  with  Section  4.0  for  the  minimum  content  and  order  of  assembly  in  the  manuals.  Include 
detailed operating, maintenance and repairs, parts lists, test certificates, data sheets, specifications, 
calculations, etc. for the plant/equipment including all parts and components. 

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 3 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  4 
00257650‐0000‐45EG‐0004 

4 Manual Content 
4.1 Installation Manuals 
4.1.1 Table of Contents 
Provide  each  volume  of  a  manual  with  a  table  of  contents  listing  the  contents  of  all  volumes  that 
comprise the complete manual. 

4.1.2 Section 1 ‐ Contact Personnel 
Reserve this section specifically for addresses, phone numbers, fax numbers, e‐mail addresses and 
contact names of technical personnel who have knowledge and expertise on the installation of the 
equipment. 

4.1.3 Section 2 ‐ Health and Safety Precautions 
Specify the Health and Safety hazards which may be encountered and precautions to be taken during 
the installation of the equipment, including the following: 
 Special  safety  precautions  or  health  related  equipment  required  for  the  installation  of  the 
equipment. 

4.1.4 Section 3 ‐ Installation Instructions 

Provide complete installation instructions, including the following: 
 Storage requirements for components prior to installation. 
 Lifting  points  and  weights  of  components,  including  crane  requirements.  Note  critical  lifting 
points. 
 Complete details of the erection and installation sequence including the extent of shop and site 
assembly. 
 Detailed installation drawings. 
 Details of specialized labour required for installation. 
 Details of specialized equipment required for installation (i.e.: special tools, jigs, spreader beams 
etc.) 
 Details of corrosion protection systems used and method of repair or re‐coating. 
 Warnings regarding procedures or practices likely to cause damage to equipment during erection, 
installation and maintenance. 
 Lubrication details.  
 

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 4 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  5 
00257650‐0000‐45EG‐0004 

4.2 Operating and Maintenance Manuals 

4.2.1 Table of Contents 
Provide each volume of a manual with a table of contents listing the content of all volumes which 
comprise the complete manual. 

4.2.2 Section 1 ‐ Contact Personnel 
Reserve this section specifically for addresses, phone numbers, fax numbers, e‐mail addresses and 
contact names of technical personnel closest to site, including Sub‐Vendors / Contractors, who have 
knowledge and expertise on the operation and maintenance of the plant/equipment. 

4.2.3 Section 2 ‐ General Description 
Provide the operator a brief overview of what the equipment does, how it operates, what its main 
performance characteristics are, etc.  This section serves to assist with training of operators. 

4.2.4 Section 3 ‐ Health and Safety Precautions 
Specify in this section the health and safety hazards which may be encountered and precautions to 
be taken during the operation and maintenance of the equipment, including the following: 
 Special  safety  or  health  related  equipment  required  for  the  operation,  e.g.  safety  goggles,  ear 
protection, special gloves, face shields, etc. 
 MSDS sheets for all materials. 

4.2.5 Section 4 ‐ Operating Instructions 
Provide  the  operator  with  detailed,  step‐by‐step  instructions  of  how  to  start  up  and  operate  the 
equipment under all conditions including the following: 
 Pre‐commissioning and commissioning check list. 
  A detailed step‐by‐step, safe working procedure for the Operator. 
 The  performance  specification  of  the  equipment,  giving  details  of  the  operating  parameters, 
limits, capacity, settings, etc. 
 Pre‐operation checklist including lubrication/grease. 
 Fault diagnosis and instructions (at Operator level). 
 Emergency shut‐down procedures. 
 Special  operating  procedures  for  abnormal  conditions  e.g.  after  emergency  shut‐down,  during 
stand‐by mode or manual mode. 
 Relevant disposal instructions for consumable items. 
 

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 5 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  6 
00257650‐0000‐45EG‐0004 

4.2.6 Section 5 ‐ Maintenance Instructions 
Provide detailed step‐by‐step instructions to maintain the equipment under all conditions, including 
the following: 
 Details of the operating parameters, tolerances, limits, capacity, etc. 
 Fault diagnosis instructions (at all levels). 
 Lubrication Schedule.  
Also  include  a  list  of  daily,  weekly,  monthly  and  yearly  tasks  for  scheduled  maintenance.  Indicate 
standard durations for each task.  
Prepare the maintenance schedule as shown in Table 1. 
TABLE 1 – MAINTENANCE SCHEDULE 
Drawing/  Part No.  Description  Maintenance  Duration  Maintenance Interval 
Reference  Actions  / Cycle 
           
           
Where  applicable,  include  Condition  Monitoring  Programs  and  Reliability  Centered  Maintenance 
principles. 
Provide list of special tools and equipment required for the maintenance of the equipment, which is 
not commonly used or available, as shown in Table 2. 
TABLE 2 – SPECIAL TOOLS AND EQUIPMENT 
 
Part No. /  Description  Quantity  Size / Rating  Supplier/ 
Reference  Specification  Manufacturer 

Provide a hazard analysis with respect to the use of special tools or uncommon maintenance practices. 
Include a lubrication schedule to give full details of lubrication points, lubrication types, filters and 
intervals for lubrication of the plant or equipment. Include with the lubrication schedule a lubrication 
chart or diagram showing the location of all lubrication points and filters referred to in the schedule. 
Provide the lubricant schedule as shown in Table 3. 

TABLE 3 – LUBRICATION SCHEDULE 
Drawing /  Part  Description  No. of  Lubricating  Qty  Type of  Lubrication  
Reference  No.  Points  Method  Lubricant  Interval 
               
               
 
 

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 6 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  7 
00257650‐0000‐45EG‐0004 

4.2.7 Section 6 ‐ Commissioning Spares 
Complete  Spare  Parts  Form‐B  A,  Commissioning  Spares,  (refer  to  Standard  Specification  No. 
00257650‐0000‐45EG‐0002 Spare Parts) and include in the manual. 

4.2.8 Section 7 ‐ Spare Parts for Two (2) Years Operation 
Complete  Spare  Parts  Form‐A  B,  Two  Years  Operating  Spares,  (refer  to  Standard  Specification  No. 
00257650‐0000‐45EG‐0002 Spare Parts) and include in the manual.  

4.2.9 Section 8 ‐ Control Documents  
In this section include the following documents:  
 Conformity certificate issued by the appropriate authority 
 Performance Test curves and certificates 
 Warranty 

4.2.10 Section 9 ‐ Index of Drawings and Data Sheets 
Incorporate a master reference list of all relevant drawings and data sheets, including those which are 
not bound in the manual, which will be required for maintenance and operation of the equipment. 
List documents included in the manual in the index. 
Provide Index of Drawings and Data Sheets, as shown in Table 4. 

TABLE 4 – INDEX OF DRAWINGS AND DATA SHEETS 
Document No.  Rev.  Title  Cross Reference  Size 
         
         
Documents will typically include: 
 Current  general  arrangement  drawings  with  principal  dimensions,  interface  dimensions  and 
recommended clearances for removal of equipment and/or assemblies. 
 Wiring/terminal diagrams. 
 Electrical schematic diagrams. 
 Hydraulic schematic diagrams. 
 Pneumatic schematic diagrams. 
 PLC  program  listing/codes  (include  source  code  of  all  documentation,  especially  PLC/DCS 
programming). 
 Data sheets. 
 Instrumentation & controls diagrams 
 Pump curves, where applicable. 
 Motor performance curves, where applicable. 
00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 7 of 8 
Standard Specification  Revision   
Installation, Operation & Maintenance  No  Date  Page 
Manuals 
Specification No.  
PB  2020.01.16  8 
00257650‐0000‐45EG‐0004 

4.2.11 Section 10 – Supplier’s Catalogues 
Include  in  this  section  catalogue  information,  pamphlets,  data  or  specification  sheets  which  are 
relevant to the plant/equipment. Within the documentation, clearly indicate or highlight (underline 
or asterisk) specific items which are relevant to the plant/equipment. 

5 Sample Binder Cover Inserts 
The following notes apply to both the spine and front cover inserts: 
 Adjust the size of the inserts to suit the width and height of the binder; 
 Replace the words “EXP PROJECT NUMBER” with the relevant EXP project number. 
 Replace the words “OWNER” and “PROJECT NAME” with the names relevant to the project; 
 Replace  the  words  “EQUIPMENT  DESCRIPTION”  with  a  suitable  description  of  the  plant 
equipment; 
 Replace the word “VENDOR” with the Vendor’s registered name; and 
 A single volume manual shall be numbered Volume 1 of 1. 

PICTURE 1 – SPINE INSERT 
 
“EXP PROJECT NUMBER”  “EXP PROJECT NUMBER” 
 
“OWNER”  “OWNER” 
 
“PROJECT NAME”  “PROJECT NAME” 
 
 
INSTALLATION   OPERATING & MAINTENANCE 
 
INSTRUCTIONS  INSTRUCTIONS 
 
“EQUIPMENT DESCRIPTION”  “EQUIPMENT DESCRIPTION” 
 
     

P.O./CONTRACT NUMBER    P.O./CONTRACT NUMBER 
  “xxxxxxxxxxxxxxx” 
“xxxxxxxxxxxxxxx” 
 
“VENDOR”  “VENDOR” 
 
VOLUME 1 OF X  VOLUME 1 OF X 
 
 
DOCUMENT END 

00257650‐0000‐45EG‐0004_rev PB  ‐ Installation Operation and Maintenance Manuals.docx  Page 8 of 8 