Professional Documents
Culture Documents
by
Dr. S.K. Navaratnarajah
Department of Civil Engineering
University of Peradeniya
Visiting Lecturer ‐ Open University of Sri Lanka 2
CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah
1 2
□ Several types of sheet piles are used in construction: □ Interlocks of sheet-pile sections
are shaped like following for
(a) wooden sheet piles;
watertight connections.
(b) precast concrete sheet piles;
(c) steel sheet piles, etc.
3 4
13‐Feb‐21
5 6
Cofferdams
Waterfront
structures
(e.g. wharfs).
7 8
13‐Feb‐21
Sheet Pile Walls Construction Methods Sheet Pile Walls Construction Methods
• Sheet-pile walls may be divided into two basic categories: 1. Backfilled structure
1. cantilever and The sequence of construction for a
2. anchored. backfilled structure is as follows:
• In the construction of sheet-pile walls, the sheet pile may be driven
into the ground and then the backfill placed on the land side, or the Step 1. Dredge the in situ soil in front
sheet pile may first be driven into the ground and the soil in front of and back of the proposed structure.
the sheet pile dredged.
Step 2. Drive the sheet piles.
• In either case, the soil used for backfill behind the sheet-pile wall is
usually granular. Step 3. Backfill up to the level of the
• The soil below the dredge line may be sandy or clayey. The surface of anchor and place the anchor system.
soil on the water side is referred to as the mud line or dredge line.
• Thus, construction methods generally can be divided into two Step 4. Backfill up to the top of the
categories (Tsinker, 1983): wall.
1. Backfilled structure For a cantilever type of wall, only Steps 1, 2,
2. Dredged structure 9 and 4 apply. 10
CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah
9 10
11 12
13‐Feb‐21
Cantilever wall
□ Cantilever walls are flexible & sufficient yield will occur to give
totally active earth pressure conditions.
d – Depth of embedment
13 14
Lateral yielding of a cantilever wall penetrating in sand □ For equilibrium, active pressure on the back of the wall
must be balanced by the passive pressure both in front of
and behind the wall.
15 16
13‐Feb‐21
17 18
□ Active thrust – permanent, unfavourable action Values of G;fav, G;unfav and Re for each design
□ Passive thrust – also should be treated as permanent,
approach.
unfavourable action.
19 20
13‐Feb‐21
Recap of EC7
□ Recommended values of Δa with normal site
□ For ULS design of gravity walls - design geometry shall account
for anticipated excavation or possible scour . control in place;
□ With ‘normal site control’, level of the resisting soil should be
lowered by an amount Δa. For a cantilever wall:
21 22
Figure 1
CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah 23 CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah 24
23 24
13‐Feb‐21
□ Due to anchorage - lateral yield in the upper part of the wall is similar to
□ Hence, pressure distribution on the back of an anchored sheet pile
yield in a timbered trench, whereas yield in lower part is similar to that of
is a combination of totally active and the arching-active cases.
a retaining wall yielding by rotation.
Anchor force 𝑻 𝑷𝒂 𝑷𝒑
25 26
27 28
13‐Feb‐21
29 30
31 32
13‐Feb‐21
□ Two water pressure diagrams are equal and therefore balance out.
□ Apart from taking the soil below the water as submerged, no special
treatment is necessary.
CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah 33 CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah 34
33 34
(b) Seepage □ An approximate method to allow for this is to assume that excess
□ With different water levels, seepage can occur. head causing flow is distributed linearly around the length of pile
that is within water zone.
35 36
13‐Feb‐21
Example 5:
A cantilever sheet pile wall retains an excavated depth of 5 m as shown in
Figure. An anchor is placed 1 m below the ground level behind the sheet pile
wall. Using free earth method of analysis, calculate the minimum depth of
embedment to provide stability using Eurocode 7 GEO limit state, Design
Approach 1. Assume Rankin’s condition is applicable. The soil properties are
φpeak = 30°, c′ = 0, ɤ = 20 kN/m3.
37 38
END OF
□ Once we determine d, next step is to determine size of the | SHEET PILE WALLS |
wall.
𝑴𝒎𝒂𝒙
𝑺
𝝈𝒂𝒍𝒍
Thank you!
CVX9416 ‐ Geotechnical Design and Soil Structure Interaction Dr. SK Navaratnarajah 39
39 40