Professional Documents
Culture Documents
1,584
1,947
page 44 155,762
4,895
162,604
page 45 4,411
2,481
3,463
172,959
page 46 9,438
10,103
192,500
page 47 6,075
198,575
page 48 6,483
22,971
3,312
231,341
page 49 35,149
111,349
377,839
page 50 97,154
6,224
481,217
page 51 7,358
35,867
524,442
page 52 20,565
6,505
551,512
page 53 76,956
23,076
651,544
page 54 724
31,514
683,782
page 55 17,377
1,233
702,392
page 56 2,942
705,334
page 57 23,965
26,595
755,894
page 58 3,330
3,948
763,172
page 59 6,336
172
769,680
page 60 1,440
600
164
771,884
page 61 552
62
462
303
773,263
page 62 445
773,708
SEIGNIORAGE CHARGES
SAND 40
AGG 50 0.05
38666
19375
19291
40 MM- 0.65 X 0.90 X 50= 29.25 0.65 0.65 29.25
SAND- 0.65 X 0.45 X 40= 11.70 11.7
OTG- 1.37 X 1.1 X 50= 75.35 1.37 1.37 75.35
SAND- 1.37 X 0.33 X 40= 18.08 18.08
20mm HBG- 34.6 X 0.90 X 50= 1,557.00 0.97 0.77 0.62 1.74 3.79 6.03 19.68 1 34.6 1557
SAND- 34.6 X 0.45 X 40= 622.80 622.8
20mm HBG- 25.46 X 0.0625 X 0.6 X 0.90 X 50= 42.96 25.46 25.46 42.96
SAND- 25.46 X 0.0625 X 0.6 X 0.45 X 40= 17.19 17.19
20mm HBG- X 0.0254 X 0.90 X 50= 0.00 0 0
SAND- X 0.0254 X 0.45 X 40= 0.00 0
SAND- 37.52 X 0.20 X 40= 300.16 3.55 33.97 37.52 300.16
3,457.47 3457.47
3,457.00
SCHEDULE -A
NAME OF THE WORK: CONSTRUCTION OF DRAWING HALL OVER FUELS LAB GOVT POLYTECHNIC, SRIKAKULAM
CONTRACTOR PRINCIPAL
36,738
S.no Quantity Description per rate Amount
9 Plastering 12 mm thick in Single coat in CM (1:4) with Sponge finishing
including cost and conveyance of all materials and water to work site
and all operational incidental labour charges such as scaffolding, mixing
85.32 mortar, curing etc., complete for finished item of work. (Staircase)- GF 10 sqm 712.00 6,075
Sqm
10 Painting to new outer walls with 2 coats of Snowcem paint of
approved brand and shade over a primary coat, after throughly brushing
the surface to remove dust and removing of loose powdered materials
and all operational incidental labour charges etc., completed for finished
67.32 item of work. (Staircase)- GF 10 sqm 963.00 6,483
Sqm
11 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
3.79 Machine mixing, vibrating, curing etc., -columns - FF 1 cum 6061.00 22,971
Cum
12 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
1.00 Machine mixing, vibrating, curing etc., -Lintels & Shades - FF 1 cum 6224.00 6,224
Cum
28.90 1 rm 289.00 8,352
RM
13 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
6.03 Machine mixing, vibrating, curing etc., -Beam & Slab - FF 1 cum 5829.00 35,149
Cum
19.68 1 cum 5658.00 111,349
Cum
14 Supplying, fitting and placing HYSD bar reinforcement, complete as per
drawings and technical specifications for Bars below 36 mm dia including
3.402 over laps and wastage, where they are not welded -FF 1 MT 45799.00 155,808
MT
15 Brick Masonry in C.M (1:6) using II class bricks having crushing strength
conforming with standard specifications including cost and conveyance
of all material and water to work site and all operational incidental labour
charges such as scaffolding, mixing of mortar, construction of masonry
33.97 lift charges etc., computed for finished work for superstructure. -FF 1 cum 2860.00 97,154
Cum
16 Plastering outside 20 mm thick in Single coat in CM (1:4) with finishing
including cost and conveyance of all materials and water to work site
and all operational incidental labour charges such as scaffolding, mixing
327.25 mortar, curing etc., complete for finished item of work. -FF 10 sqm 1096.00 35,867
Sqm
522,170
CONTRACTOR PRINCIPAL
522,170
S.no Quantity Description per rate Amount
17 Plastering inside 12 mm thick in Single coat in CM (1:4) with finishing
including cost and conveyance of all materials and water to work site
and all operational incidental labour charges such as scaffolding, mixing
287.22 mortar, curing etc., complete for finished item of work. - FF 10 sqm 716.00 20,565
Sqm
18 S&F best Sal wood frame of size 3" X 4" for all doors including cost
and conveyance of all materials and S&F best sal wood flush doors of
single leave of size1.05 x 2.1m of 11/2" thick of flush type including cost and
conveyance of all materials, cutting,making, polishing, tower bolts of
200mm length, 6 nos of butt hinges of 150mm,Door handles of 125mm and
aldrops of 300mm and flat latches and labour charges etc, completing as
1 directed by departmental officers.. - FF 1 NO. 6505.00 6,505
No
19 S&F best Sal wood frame of size 3" X 4" for all windows including cost
and conveyance of all materials and S&F best sal wood flush doors of
2 leaves of size 0.6 x 2.1m of 11/2" thick of flush type including cost and
conveyance of all materials, cutting,making, polishing
to frame, 4 tower bolts of 100mm length, 4 nos of butt hinges of 75mm
handles of 125mm and labour charges etc, completing as directed
12 by departmental officers. - FF 1 No. 6413.00 76,956
No.s
20 Supplying and fixing of WINDOW Grills with frame made up of flat section
20x5mm with 10mm square rods as safety bars at 75 mm c/c
36 including favricating and welding charges of size 0.40 x 1.07 m. - FF 1 No. 641.00 23,076
No.s
21 S & F Pre-cast cenment concrete jallies for ventilator including cost and
2.16 conveyance of all materials completes as per drawing. - FF 1 sqm 335 724
Sqm
22 Painting to new outer walls and Roof with 2 coats of Snowcem paint of
approved brand and shade over a primary coat, after throughly brushing
the surface to remove dust and removing of loose powdered materials
and all operational incidental labour charges etc., completed for finished
327.25 item of work. - FF 10 sqm 963.00 31,514
Sqm ~walls outside plastering quantity
23 Painting to new walls with 2 coats of ready mixed oil bound wahsable
distemper of approved brand and shade over a base coat of appropriate
primer of approved brand, making 3 coats in all to give an even shade
after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, and all operational incidental labour charges
etc.,complete for finished work as per SS 911 for internal walls. -FF
287.22 walls inside plastering quantity 10 sqm 605.00 17,377
Sqm
698,887
CONTRACTOR PRINCIPAL
698,887
S.no Quantity Description per rate Amount
24 Painting to new steel work with 2 coats of first quality synthetic Enamel
Paint of approved brand and shade over a base of red oxide primer
including cost and conveyance of all materials to work site, completes
22.25 for finished item of work. - FF 10 sqm 554.00 1,233
Sqm
25 Painting to New wood work with 2 coats of ready mixed first quality
Enamel paint of approved brand and shade over a coat of wood primer
of approved brand making 3 coats in all including cost and conveyance
of all materials to work site and all operational incidental labour charges
48.71 completes for finished item of work. - FF 10 sqm 604.00 2,942
Sqm
26 Gronolithic Concrete Flooring 20 mm thick with (1:1:2), using 6mm to 12 mm
size hard granite machine crushed metal laid over CC bed already laid ,
in alternate panels of size not exceeding 1.50 m x 1.50 m and finishing
the top surface to required smoothness and slopes and thread lining
including cost of all materials like cement, metal, sand and water etc.,
complete, including seigniorage charges, etc., complete for finished item
126.00 of work, but excluding the cost of conveyance of all materials. -FF 10 sqm 1902.00 23,965
Sqm
27 Supply and Fixing of 25mm dia 2mm thick PVC pipe (ISI MARK)
CONTRACTOR PRINCIPAL
764,212
S.no Quantity Description per rate Amount
31 Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) P.V.C. insulated F.R flexible
copper cable (ISI MARK) in existing pipe with 6A switch, Ceiling rose and
3mm thick hylam sheet covering to switch control box including all labour
charges etc., complete for light, bell, fan and exhaust fan points in
24.00 Residential Buildings. I RM 264.00 6,336
RM
32 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control
on a common switch board with earth continuity including wire leads,
2.00 earth connections along with all labour charges etc., complete. 1 Pt 86.00 172
Pts
33 Supply and run of 2 of 14/0.3mm (1.0 Sq.mm) F.R P.V.C. insulated
60.00 flexible copper cable in existing pipe for mains I RM 24.00 1,440
RM
34 Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for earth continuity including all labour
50.00 charges etc., complete. I RM 12.00 600
RM
35 Fixing of 40W tube light luminaire on wall / Ceiling with / TW round blocks
with all accessories including giving connections and all labour charges
2.00 etc., complete. 1 Pt 82.00 164
Pts
36 Supply and Transportation of 1x40W patty type tube light luminaire with
2.00 copper choke, starter etc., including 1No 40W .. Complete 1 Pt 276.00 552
Pts
37 Supply of ISI, 20mm dia, 16 guage thickness MS conduit pipe of makes
1.00 NAI / Bharath / GB I RM 62.00 62
RM
38 3.00 10 kA - 6-32A range SP MCBs 1 No 154.00 462
No.s
39 1.00 Supply of 32A DP Isolator of make Standard / Havells / HPL / Toyoma. 1 No 303.00 303
No.s
40 1.00 Supply of 4 Way SPN DB with IP 20 Protection of makes Standard / 1 No 445.00 445
No.s Havells / HPL / Toyoma.
774,748
Deduct Tender Percentage (0.05 % less) Rs. 387
Value of Work done under this Agreement 774,361
(Rupees Seven Lakhs Seventy Four Thousand Three Hundred and Sixty one only)
CONTRACTOR PRINCIPAL
CONSTRUCTION OF DRAWING HALL OVER FUELS LAB GOVT POLYTECHNIC, SRIKAKULAM
22 S&F best Sal wood frame of size 3" X 4" for all windows including cost
and conveyance of all materials and S&F best sal wood flush doors of
2 leaves of size 0.6 x 2.1m of 11/2" thick of flush type including cost and
conveyance of all materials, cutting,making, polishing
to frame, 4 tower bolts of 100mm length, 4 nos of butt hinges of 75mm
handles of 125mm and labour charges etc, completing as directed
12.00 by departmental officers 1 No. 6413.00 76,956
23 Supplying and fixing of WINDOW Grills with frame made up of flat section
20x5mm with 10mm square rods as safety bars at 75 mm c/c
36.00 including favricating and welding charges of size 0.40 x 1.07 m 1 No. 641.00 23,076
24 S & F Pre-cast cement concrete jallies for ventilator including cost and
2.16 conveyance of all materials completes as per drawing 1 Sqm 335.00 724
25 Painting to new outer walls and Roof with 2 coats of Snowcem paint of
approved brand and shade over a primary coat, after throughly brushing
the surface to remove dust and removing of loose powdered materials
and all operational incidental labour charges etc., completed for finished
327.25 item of work. 10 Sqm 963.00 31,514
26 Painting to new walls with 2 coats of ready mixed oil bound wahsable
distemper of approved brand and shade over a base coat of appropriate
primer of approved brand, making 3 coats in all to give an even shade
after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, and all operational incidental labour charges
287.22 etc.,complete for finished item of work as per SS 911 for internal walls 10 Sqm 605.00 17,377
27 Painting to new steel work with 2 coats of first quality synthetic Enamel
Paint of approved brand and shade over a base of red oxide primer
including cost and conveyance of all materials to work site, completes
22.25 for finished item of work 10 Sqm 554.00 1,233
28 Painting to New wood work with 2 coats of ready mixed first quality
Enamel paint of approved brand and shade over a coat of wood primer
of approved brand making 3 coats in all including cost and conveyance
of all materials to work site and all operational incidental labour charges
48.71 completes for finished item of work 10 Sqm 604.00 2,942
29 Gronolithic Concrete Flooring 20 mm thick with (1:1:2), using 6mm to 12 mm
size hard granite machine crushed metal laid over CC bed already laid ,
in alternate panels of size not exceeding 1.50 m x 1.50 m and finishing
the top surface to required smoothness and slopes and thread lining
including cost of all materials like cement, metal, sand and water etc.,
complete, including seigniorage charges, etc., complete for finished item
126.00 of work, but excluding the cost of conveyance of all materials 10 Sqm 1902.00 23,965
30 Providing impervious coat to exposed RCC roof slab surface with
CM(1:3), 20mm thick with 1kg of water proof compound per
bag of cement laid over roof when it is green including cost
of all materials, seigniorage charges, excluding conveyance
charges of materials and including all operational, incidental
and labour charges for mixing mortar, laying, rendering smooth
124.39 slab etc,, complete for finished item of work 10 Sqm 2138.00 26,595
31 supplying and fixing 150mm dia PVC water pipe apped brand including
bends, shoes, collar fixed in position as directed fixed with M.S.clamps
including cost and conveyance of all materials to work site and all
18.00 operational incidental charges etc., completed for finished item of work 1 Rm 185.00 3,330
32 Supply and Fixing of 20mm dia 1.5mm thick P.V.C. pipe (ISI MARK)
concealed in wall with all required accessories including masonary work
for light, fan and separate plug point with well seasoned wooden deep
84.00 box including all labour charges etc., complete. 1 Rm 47.00 3,948
33 Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) P.V.C. insulated F.R flexible
copper cable (ISI MARK) in existing pipe with 6A switch, Ceiling rose and
3mm thick hylam sheet covering to switch control box including all labour
charges etc., complete for light, bell, fan and exhaust fan points in
24.00 Residential Buildings. 1 Pt 264.00 6,336
34 Supply and fixing of 6A 3 pin wall plug socket with 6A switch control
on a common switch board with earth continuity including wire leads,
2.00 earth connections along with all labour charges etc., complete. 1 Pt 86.00 172
35 Supply and run of 2 of 14/0.3mm (1.0 Sq.mm) F.R P.V.C. insulated
60.00 flexible copper cable in existing pipe for mains 1 Rm 24.00 1,440
36 Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for earth continuity including all labour
50.00 charges etc., complete. 1 Rm 12.00 600
37 Fixing of 40W tube light luminaire on wall / Ceiling with / TW round blocks
with all accessories including giving connections and all labour charges
2.00 etc., complete. 1 Pt 82.00 164
38 Supply and Transportation of 1x40W patty type tube light luminaire with
2.00 copper choke, starter etc., including 1No 40W .. Complete 1 Pt 276.00 552
39 Supply of ISI, 20mm dia, 16 guage thickness MS conduit pipe of makes
1.00 NAI / Bharath / GB 1 Rm 62.00 62
40 3.00 10 kA - 6-32A range SP MCBs 1 N0 154.00 462
41 1.00 Supply of 32A DP Isolator of make Standard / Havells / HPL / Toyoma. 1 N0 303.00 303
42 Supply of 4 Way SPN DB with IP 20 Protection of makes Standard /
1.00 Havells / HPL / Toyoma. 1 N0 445.00 445
773,708
Deduct Tender percentage 0.05% less 387
Value of work to be done under this Agreement 773,321
L/CE H.C.E.S PRINCIPAL
.
774,748 155,808
773,708 155,762
1,040 46
CONSTRUCTION OF DRAWING HALL OVER FUELS LAB GOVT POLYTECHNIC, SRIKAKULAM
8.000 16.0
columns main reinforcement 14 6 3.9 327.6
stirupps 14 16 1.06 237.440
237.440 327.60
8mm 237.44 0.394 93.55
16mm 327.60 1.578 516.95
610.50 0.611 MT
2 3/2/2011 V.R.C.C (1:1 1/2:3), 20mm size HBG machine crushed chips including cost,
Seigniorage and conveyance of all materilas and labour charges, such
as machine mixing, Vibrating and curing etc, (FF)
~Columns 14 0.38 0.23 1.60 1.958
3 4/2/2011 V.R.C.C (1:1 1/2:3), 20mm size HBG machine crushed chips including cost,
Seigniorage and conveyance of all materilas and labour charges, such
as machine mixing, Vibrating and curing etc, (FF)
~Columns 14 0.38 0.23 1.50 1.835
4 6/2/2011 Supplying, fitting and placing HYSD bar reinforcement, complete as per
drawings and technical specifications for Bars below 36 mm dia including
over laps and wastage, where they are not welded (FF)
8.000 12.0 16
for longer beams (middle) 5 6 8.31 249.3
EXTRA AT T0P 5 2 2.30 23
for longer beams (end) 2 5 8.31 83.1
EXTRA AT T0P 2 2 2.30 9.2
cross beams 2 4 18.78 150.24
EXTRA AT T0P 2 7 1.50 21
STIRRUPS LONGER SPAN 7 35 1.45 355.250
SHORTER SPAN 2 84 1.05 176.400
slab
LONGER SIDE STRAIGHT BARS 6 10 8.36 501.600
BENT UP BARS 6 10 9.40 564.000
over hang 1 3 10.44 31.320
1 3 11.48 34.440
top hanger 7 4 8.36 234.080
extra at top 6 10 1.50 90.000
6 10 0.90 54.000
8.000 12.0
FOOTING MESH 4 10 1 40.00
COLUMNS MAIN REINFORCEMENT 2 4 5.75 46.00
2 4 4 32.00
STIRUPPS 2 24 0.76 36.48
2 15 0.76 22.80
59.280 118.00
8mm 59.28 0.394 23.36
12mm 118.00 0.888 104.78
128.14 0.128 MT
10 10/2/2011 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
Machine mixing, vibrating, curing etc., (GF)
staircase-FOOTING 4 0.90 0.90 0.30 0.97
11 11/2/2011 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
Machine mixing, vibrating, curing etc., (GF)
staircase-COLUMNS 2 0.23 0.23 4.55 0.48
2 0.23 0.23 2.75 0.29
0.77
12 12/2/2011 P.C.C (1:4:8) using 40mm size HBG metal including cost, Seignorage
and Conveyance Cost of all materials from apprpved source, all
leads etc., conforming with standard specifications.(GF)
1 1.94 0.565 0.15 0.16
13 13/2/2011 R.R.Masonry in C.M.(1:6) using Hard rough stone other than granite
including cost and conveyance of all materials to site, all labour charges
such as mixing mortar, laying curing etc.
1 1.94 0.565 1.25 1.37
14 15/2/2011 Supplying, fitting and placing HYSD bar reinforcement, complete as per
drawings and technical specifications for Bars below 36 mm dia including
over laps and wastage, where they are not welded (GF)
BEAM ABOVE RR 8.000 12.0
MAIN STEEL 1 5 2.5 12.5
STIRUPPS 1 14 0.65 9.100
Stair - Main Reinforcement 1 9.00 4.76 42.84
extra at top landing 2 9.00 1.945 35.01
distribution reinforcement 1 18.00 1.15 20.700
distribution reinforcement- landing 1 14.00 2.50 35.000
beam at landing 1 6.00 2.50 15
stirrups for beam 1 15.00 1.05 15.750
80.550 105.350
8mm 80.55 0.394 31.74
12mm 105.35 0.888 93.55
125.29 0.125 MT
15 16/02/2011 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
Machine mixing, vibrating, curing etc., (GF)
staircase-beam 1 0.23 0.23 2.50 0.13
1 2.50 0.23 0.30 0.17
0.30
Staircase Slab 1 1.200 3.485 0.125 0.52
1 2.50 1.00 0.125 0.31
0.83
16 18/2/2011 Supplying, fitting and placing HYSD bar reinforcement, complete as per
drawings and technical specifications for Bars below 36 mm dia including
over laps and wastage, where they are not welded (GF)
8.000 12.0
Stair - Main Reinforcement 1 9 4.99 44.91
extra at top landing 1 9 2.175 19.575
distribution reinforcement 1 18 1.15 20.700
distribution reinforcement- landing 1 14 2.5 35.000
beam at landing 1 6 2.5 15
stirrups for beam 1 15 1.05 15.750
extra beams - main 2 5 1.18 11.8
71.450 91.29
8mm 71.45 0.394 28.15
12mm 91.29 0.888 81.06
109.21 0.109 MT
17 20/2/2011 V.R.C.C (1:1 1/2 :3) 20mm size HBG, machine crushed chips including cost,
seignorage and conveyance of all materials and labour charges such as
Machine mixing, vibrating, curing etc., (GF)
Staircase Slab 1 1.200 3.506 0.125 0.53
1 2.50 1.23 0.125 0.38
0.91
staircase-BEAM 1 2.50 0.23 0.30 0.17
2 1.10 0.23 0.30 0.15
0.32
18 21/2/2011 Brick Masonry in C.M (1:6) using II class bricks having crushing strength
conforming with standard specifications including cost and conveyance
of all material and water to work site and all operational incidental labour
charges such as scaffolding, mixing of mortar, construction of masonry
lift charges etc., computed for finished item of work.(GF)
staircase-STEPS 22 1.20 0.14 0.15 0.55
staircase-SIDE WALLS 1 24.85 0.115 0.90 2.57
staircase-ENTRANCE STEPS 1 1.20 0.90 0.20 0.22
1 1.20 0.60 0.20 0.14
1 1.20 0.30 0.20 0.07
3.55
19 23/2/2011 Plastering 12 mm thick in Single coat in CM (1:4) with Sponge finishing
including cost and conveyance of all materials and water to work site
and all operational incidental labour charges such as scaffolding, mixing
mortar, curing etc., complete for finished item of work.(GF)
staircase-STEPS 22 1.20 0.43 11.35
staircase-SIDE WALLS 1 24.85 1.915 47.59
staircase-ENTRANCE STEPS 1 1.20 1.50 1.80
2 0.90 0.30 0.54
staircase-LANDING 2 2.40 1.10 5.28
1 1.20 0.565 0.68
staircase-COLUMNS 2 0.92 3.30 6.07
2 0.92 2.38 4.38
staircase-BEAMS 2 2.40 0.58 2.78
staircase-RR Masonry 1 1.94 2.50 4.85
85.32
20 26/02/2011 Painting to new outer walls with 2 coats of Snowcem paint of
approved brand and shade over a primary coat, after throughly brushing
the surface to remove dust and removing of loose powdered materials
and all operational incidental labour charges etc., completed for finished
item of work.(GF)
staircase-SIDE WALLS 1 24.85 1.92 47.59
staircase-ENTRANCE STEPS 2 0.90 0.30 0.54
staircase-LANDING 2 2.40 1.10 5.28
1 1.20 0.57 0.68
staircase-COLUMNS 2 0.92 3.30 6.07
2 0.92 2.38 4.38
staircase-BEAMS 2 2.40 0.58 2.78
67.32
21 1/3/2011 Brick Masonry in C.M (1:6) using II class bricks having crushing strength
conforming with standard specifications including cost and conveyance
of all material and water to work site and all operational incidental labour
charges such as scaffolding, mixing of mortar, construction of masonry
lift charges etc., computed for finished item of work for superstructure.(FF)
12 2.73 0.23 2.00 15.07
2 7.00 0.23 2.00 6.44
parapet wall 1 50.46 0.115 0.90 5.22
~deduct Door-D 1 1.00 0.23 2.10 -0.48
Window-W 12 1.52 0.23 1.22 -5.12
21.13
22 2/3/2011 Supplying, fitting and placing HYSD bar reinforcement, complete as per
drawings and technical specifications for Bars below 36 mm dia including
over laps and wastage, where they are not welded (GF)
31 10/3/2011 S&F best Sal wood frame of size 3" X 4" for all windows including cost
and conveyance of all materials and S&F best sal wood flush doors of
2 leaves of size 0.6 x 2.1m of 11/2" thick of flush type including cost and
conveyance of all materials, cutting,making, polishing
to frame, 4 tower bolts of 100mm length, 4 nos of butt hinges of 75mm
handles of 125mm and labour charges etc, completing as directed
by departmental officers 12 12 no.s
32 10/3/2011 Supplying and fixing of WINDOW Grills with frame made up of flat section
20x5mm with 10mm square rods as safety bars at 75 mm c/c
including favricating and welding charges of size 36 36 no.s
33 11/3/2011 Painting to new outer walls and Roof with 2 coats of Snowcem paint of
approved brand and shade over a primary coat, after throughly brushing
the surface to remove dust and removing of loose powdered materials
and all operational incidental labour charges etc., completed for finished
item of work.
~walls outside plastering quantity Sqm 327.25
34 11/3/2011 Painting to new walls with 2 coats of ready mixed oil bound wahsable
distemper of approved brand and shade over a base coat of appropriate
primer of approved brand, making 3 coats in all to give an even shade
after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, and all operational incidental labour charges
etc.,complete for finished item of work as per SS 911 for internal walls
walls inside plastering quantity 287.22
Sqm
35 12/3/2011 Painting to new steel work with 2 coats of first quality synthetic Enamel
Paint of approved brand and shade over a base of red oxide primer
including cost and conveyance of all materials to work site, completes
for finished item of work
~Window -'W1 12 1.52 1.22 22.25
22.25
Sqm
36 12/3/2011 Painting to New wood work with 2 coats of ready mixed first quality
Enamel paint of approved brand and shade over a coat of wood primer
of approved brand making 3 coats in all including cost and conveyance
of all materials to work site and all operational incidental labour charges
completes for finished item of work
~flush doors 2 1 2.1 4.20
~windows 24 1.52 1.22 44.51
48.71
Sqm
1.87 1.87
0.17 0.17
1.68 1.68
1.38
1.53 1.53
1.17 1.17
2.03 2.03
0.3 0.3
0.3 0.3
1.5 1.5
11.93 10.55
66.06
110.16 203.22
110.16 203.22
SCHEDULE-A
NAME OF THE WORK: MAINTENANCE WORKS TO CLASS ROOMS IN PVG BLOCK OF M.R.A.G.R GOVERNMENT
POLYTECHNIC, VIZIANAGARAM
Tenderer/Contractor PRINCIPAL
VERNMENT
MAINTENANCE WORKS TO CLASS ROOMS IN PVG BLOCK OF
M.R.A.G.R. GOVERNMENT POLYTECHNIC, VIZIANAGARAM
A B S T R A C T E S T I M A T E
DETAILED ESTIMATE
S.no Description No L B H Quantity
1 White washing one coat with whiting of approved quality to give an even
shade after thoroughly brushing the surface to remove all dirt and
remains of loose powdered materials including cost of all materials, labour
charges and incidental such as scaffolding, lift charges etc., complete
for finished item of work, but excluding conveyance charges of materials
GROUND FLOOR
L1, L2 & L3 ROOMS CEILING 3 7.35 7.35 162.07
DRAWING HALL CEILING 1 14.94 7.35 109.81
LIBRARY OUTER PORTION 1 9.50 8.87 84.27
CORRIDER CEILING 1 35.70 2.80 99.96
LOBBY CEILING 1 7.60 3.50 26.60
1 5.18 2.77 14.35
TOILET CEILING 1 7.39 3.50 25.87
BEAM PORTIONS 6 7.35 1.00 44.10
STAIRCASE BOTTOM 1 4.20 1.55 6.51
ELECTRICAL STORE 1 3.00 3.50 10.50
FIRST FLOOR
L5, L6, L7 & L8 ROOMS CEILING 4 7.35 7.35 216.09
DRAWING HALL CEILING 1 18.80 8.87 166.76
CORRIDER CEILING 1 35.70 2.80 99.96
LOBBY CEILING 1 5.18 2.77 14.35
BEAM PORTIONS 8 7.35 1.00 58.80
STAIRCASE BOTTOM 2 4.20 1.52 12.77
1152.77
Sqm
2 Painting to old walls with 2 coats of ready mixed oil bound wahsable
distemper of approved brand and shade to give an even shade
after thourughly brushing the surface to remove all dirt and remains of
loose powdered materials, and all operational incidental labour charges
etc.,complete for finished item of work as per SS 911 for internal walls
GROUND FLOOR
L1, L2 & L3 ROOMS WALLS 3 29.40 3.60 317.52
DRAWING HALL WALLS 1 44.58 3.60 160.49
LIBRARY OUTER PORTION 1 27.87 3.60 100.33
CORRIDER WALLS 2 35.70 3.60 257.04
LOBBY WALLS 2 7.60 3.60 54.72
END WALL OF CORRIDOR 2 2.80 3.60 20.16
ELECTRICAL STORE 1 20.54 3.60 73.94
STAIRCASE RAILING 2 4.20 1.92 16.13
STAIRCASE LANDING WALL 1 3.52 3.60 12.67
STAIRCASE SIDE WALLS 2 4.58 2.77 25.37
COLUMN AT STAIRCASE 2 1.80 3.60 12.96
TOILET 1 21.78 3.00 65.34
DEDUCT - DOORS 5 1.20 2.10 -12.60
WINDOWS 4 1.20 0.60 -2.88
VENTILATORS 4 0.90 0.60 -2.16
FIRST FLOOR
L5, L6, L7 & L8 ROOMS WALLS 4 29.40 3.60 423.36
DRAWING HALL WALLS 1 55.34 3.60 199.22
CORRIDER WALLS 2 35.70 2.80 199.92
END WALL OF CORRIDOR 2 4.33 3.60 31.18
STAIRCASE RAILING 2 4.20 1.92 16.13
STAIRCASE LANDING WALL 1 3.52 3.60 12.67
STAIRCASE SIDE WALLS 2 4.58 2.77 25.37
DEDUCT - DOORS 6 1.20 2.10 -15.12
WINDOWS 2 1.20 0.60 -1.44
VENTILATORS 4 0.90 0.60 -2.16
1988.16
Sqm
L/CE H.C.E.S PRINCIPAL
DATA STATEMENT
MRAGR GOVERNMENT POLYTECHNIC, VIZIANAGARAM
1
Painting to old walls with 2 coats of ready mixed oil bound wahsable distemper of
approved brand and shade to give an even shade after thourughly brushing the surface to
remove all dirt and remains of loose powdered materials, including cost and conveyance
of all materials to work site and all operational, incidental, labour charges etc. complete
for finished item of work as per SS 911 for internal walls
PRIMARY COAT:
Cost of washable Oil Bound Distemper Lts 1.7 60 102.00
1st class painter Nos 0.36 285.00 102.60
II class painter Nos 0.84 260 218.40
Sundries including brushes, soap, putty e 1% 4.23
Add MA 20% 64.20
Add TOT 4% 19.66
Total cost / 10 sqm 512.00
2 White washing one coat with whiting of approved quality to give an even shade after thoroughly
brushing the surface to remove all dirt and remains of loose powdered materials including cost of all
materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished
item of work, but excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / kg 1.20 25.00 30.00
B. LABOUR
Brick Layers / Painter day 0.11 285.00 31.35
Mazdoor (unskilled) day 0.22 215.00 47.30
Sundries including brushes, ladders, etc., 0.50%
0.39
Add MA 20% 15.73
Add TOT 4% 4.99
Total cost / 10 sqm 130.00
MATERIAL
OTG for RR Masonary 225 1 cum Blasting (cum) 70 1 cum
6mm HBG 655 1 cum Machine Crushing(%) 25
10 mm HBG 820 1 cum
20mm HBG 1175 1 cum Scaffolding-brck masry 40 1 cum
40mm HBG 745 1 cum
Gravel 80 1 cum
Sand for Mortar 325 1 cum
sand for Filling 250 1 cum
Cement final 5424 1 MT vitrified tiles 723 sqm
cement 5400 CERAMIC TILES 374 sqm
M.S. Rods(6mm) 39000 1 MT Earth Work Excavation 45.5 1 cum
M.S. Flats 40000 1 MT Sand filling charges 14 1 cum
M.S. Angles, Channels & Structural s 40000 1 MT Vibration 43 1 cum
HYSD Bars 42000 1 MT Machine Nixing 45 1 cum
Bricks ( 19 x9 x9) 3100 1000 no
Cuddapah slab (.457 x.457) black 1076 10 sqm binding wire 55 kg
0.075
0.075
5 0 4 0 0.075 0.075 0.075
1 Panalled Window glazed (1.52 x 1.22 ) (2 SHUTTERS) PANELLED WINDOW WITH GLAZED (2 SHUTTERS)
SIZE 1.520 1.220 1.854
0.0503 Frame 1 cum 0.00 FRAME 0.075 0.100
0.0196 Shutter 1 cum 0.00 SHUTTER 0.075 0.038
1.0023 Glass Panels 1 Sqm 0.00 DIA OF ROD 16.000 1.578
26.39 16mm dia rods 1 kg 0.00 FRAME
4 Butt Hinges(75mm) 0.00 3 VERTICALS 1.220 0.075 0.100 0.02745
4 Tower Bolts(100 m 18 72.00 2 HOR MULLION 1.520 0.075 0.100 0.0228
1.22
0.92
1.07
2 Handles(125mm) 23 46.00 0.05025 CUM
1.854 Labour charges 0.00 SHUTTER
M.A 0.00 4 VER STYLES 1.070 0.075 0.038 0.012198
V.A.T 4 HOR RAILS 0.648 0.075 0.038 0.007382
Total 118.00 0.01958 CUM
0.075
0.075
5 0 4 0 0.075 0.075 0.075 0.075
2 Panalled Window(1.52 x 1.22 ) (3 SHUTTERS) PANELLED WINDOW WITH GLAZED (3 SHUTTERS)
SIZE 1.520 1.220 1.854
0.0594 Frame 1 cum 0.00 FRAME 0.075 0.100
0.0432 Shutter 1 cum 0.00 SHUTTER 0.075 0.038
0.7084 Glass Panels 1 Sqm 0.00 DIA OF ROD 16.000 1.578
33.59 16mm dia rods 1 kg 0.00 FRAME
6 Butt Hinges(75mm) 8 48.00 4 VERTICALS 1.220 0.075 0.100 0.0366
6 Tower Bolts(100 m 18 108.00 2 HOR MULLION 1.520 0.075 0.100 0.0228
3 Handles(125mm) 23 69.00 0.0594 CUM
1.854 Labour charges 0.00 SHUTTER
M.A 0.00 6 VER STYLES 1.070 0.075 0.038 0.018297
V.A.T 6 HOR RAILS 0.407 0.075 0.038 0.006954
3 MIDDLE FLANK 0.307 0.971 0.020 0.017909
Total 225.00 0.04316 CUM
H V 1.52
0.075
0.075
5 0 4 0 0.075 0.075 0.075 0.075
3 Panalled Window GLAZED (1.52 x 1.22 ) (3 SHUTTERS) PANELLED WINDOW WITH GLAZED (3 SHUTTERS)
SIZE 1.520 1.220 1.854
0.0594 Frame 1 cum 0.00 FRAME 0.075 0.100
0.0253 Shutter 1 cum 0.00 SHUTTER 0.075 0.038
0.817 Glass Panels 1 Sqm 0.00 DIA OF ROD 16.000 1.578
26.39 16mm dia rods 1 kg 0.00 FRAME
6 Butt Hinges(75mm) 8 48.00 4 VERTICALS 1.220 0.075 0.100 0.0366
6 Tower Bolts(100 m 18 108.00 2 HOR MULLION 1.520 0.075 0.100 0.0228
3 Handles(125mm) 23 69.00 0.0594 CUM
1.854 Labour charges 0.00 SHUTTER
M.A 0.00 6 VER STYLES 1.070 0.075 0.038 0.018297
V.A.T 6 HOR RAILS 0.407 0.075 0.038 0.006954
Total 225.00 0.025251 CUM
1.000
H V 0.075 0.85 0.075
3 3 7 -5
1 Pannelled door (1 x 2 )(SINGLE 4 HOR PARTS) PANELLED DOOR (SINGLE 4 HOR PARTS)
SIZE 1.000 2.000 2.000
0.0398 Frame 1 cum 0.00 FRAME 0.075 0.100 PLANK
0.0567 Shutter 1 cum 0.00 SHUTTER 0.127 0.038 0.020
1 door stopper 34 34.00
1 MS aldrop 300mm 124 124.00 FRAME
3 MS Butt Hinges(1 23 69.00 2 VERTICALS 2.000 0.075 0.100 0.03
2.000
1.925
2 MSTower Bolts(20 28 56.00 1 HOR MULLION 1.300 0.075 0.100 0.00975
1 Handle (150mm) 34 34.00 0.03975 CUM
0.3225
2.000 Labour charges 0.00 SHUTTER
M.A 0.00 2 VER STYLES 1.925 0.127 0.038 0.01858
V.A.T 5 HOR RAILS 0.850 0.127 0.038 0.020511 0.127
Total 317.00 4 PLANKS 0.626 0.353 0.020 0.017653
0.3225
0.056744 CUM
1
0.3225
0.127
0.127
0.127
0.596
1.200
H V 0.075 0.525 0.525
4 -1 7 -5
2 Pannelled door (1.2 x 2 )(DOUBLE SINGLE 4 HOR PARTS) PANELLED DOOR (DOUBLE SINGLE 4 HOR PARTS)
SIZE 1.200 2.000 2.400
0.039 Frame 1 cum 0.00 FRAME 0.075 0.100 PLANK
0.0795 Shutter 1 cum 0.00 SHUTTER 0.127 0.038 0.020
1 door stopper 0.00
1 MS aldrop 300mm 124 124.00 FRAME
6 MS Butt Hinges(1 23 138.00 2 VERTICALS 2.000 0.075 0.100 0.03
2.000
4 MSTower Bolts(20 28 112.00 1 HOR MULLION 1.200 0.075 0.100 0.009
1.925
1 Handle (150mm) 34 34.00 0.039 CUM
0.3225
2.400 Labour charges 0.00 SHUTTER
M.A 0.00 4 VER STYLES 1.925 0.127 0.038 0.03716
V.A.T 10 HOR RAILS 0.525 0.127 0.038 0.025337 0.127
Total 408.00 8 PLANKS 0.301 0.353 0.020 0.016976
0.3225
2.0
1.92
0.3225
0.079473 CUM
0.127
0.127
0.127
0.271
lintels
no 4 8 8
length 1.46 1.98 1.98
ring si 0.23 0.15 0.752
12 23.36 63.36 63.36 150.08 133.27104
8 6.768 8.272 8.272 23.312 9.20824
142.48
sunshades
no 4
length 1.98
width 0.6
length no t len
10 0.88 14 49.28 30.5536
8 1.98 5 39.6 15.642
46.20
0.92 0.92
### ###
###
### ###
0.92
###
###
###