Professional Documents
Culture Documents
4-3.3 - Control Sys Specs
4-3.3 - Control Sys Specs
SECTION 3.3
Scope of Work
The scope of work in this specification shall include the design, construction, and
transportation of all material, installation, commissioning and testing of control desk, PLC
and marshalling cabinet, measuring instruments etc. as described in specification.
All required labour materials, machinery, tools and other appliances should be furnished by
the contractor. The work shall be carried out completely, properly satisfactory, continuously
and expeditiously in all aspects without effecting normal pumping operation.
The scope of work shall include the following but not limited to them:
1. Control desk shall include (one/two channel) chart reorder, for flow,
pressure, level, chlorine residual, indications for RPM and valve position
indicators, set points, auto/manual/SCADA/off, remote/local, selector
switches, main pumps start, stop, lower, raise push button, valves open
close push buttons etc.
4. Marshalling cabinet shall include all analogue, status, alarm and command
signals, set points to and from NWCC including zoner barrier for analogue
I/O interposing relay, terminals and internal wiring.
6. Providing of distribution board for mimic and control desk and connecting
to existing UPS.
10. Pump’s suction and delivery pressure gauge of burden tube type with
measuring range (0-1) and (0-15) bar respectively including isolating cock
and drain tape.
12. 900 mm Electromagnetic flow meters and transmitters for new mains
13. Temperature monitoring and alarm panel, for pumps and motors bearing
14. Single wire armored multi pair; PVC sheathed cabling and installation
accessories and connection to all control and signalling equipment.
A. Local Panels
This level of control is the lowest level, each motorised valve and pump set shall have
an adjacent control panel, which provide localised facilities for maintenance or similar
purposes. Local control will generally be provided for the field application in case of
operation as backup to the automatic control system or those inherently local in design
philosophy; control transfer switches on these panels should be set to "REMOTE" to
permit centralised control from one of two control centres.
B. Control Centres
The signals that should be brought to the Marshalling panel for future use by other
contractors are as listed below as minimum, final list of signals shall be submitted for
KAHRAMAA's approval. The Marshalling panel shall be located in a room next to
control room
1) Transmission main
Measurements
Set Points
- Distillate Flow Rate
- Valve Position
2-Ground Reservoirs
Measurements
Set Points
3-Pump (Individual)
Measurements
- Motor Current
- Motor Speed
- Motor Pressure
Digital Inputs-Statuses
Digital Inputs-Alarms
4-Rising Main
Measurements
- Pressure
- Chlorine Residual
- Valve, Position
-Flow (Instantaneous & Totalized)
Digital Inputs-Statuses
Digital Outputs-Commands
Measurements
- Water Level
- Inlet Valve Position
- Set Point Value of Flow Rate
Set Points
Digital Inputs-Statuses
Digital Inputs-Alarms
- Water Level, High
- Water Level, Low
- Water Level, High-High
- Inlet Valve, Failed
- Outlet Valve, Failed
- Bypass Valve, Failed
Digital Outputs- on/off Commands
- Inlet Valve Open
- Inlet Valve Close
- Inlet Valve Stop
- Outlet Valve, Open
- Outlet Valve, Close
- Bypass Valve, Open
- Bypass Valve, Close
6-Water Outlet
Measurements
- Water Flow to Site Consumption (each site)
- Water Flow to West Bay distribution main
- Water Flow to Gharrafa distribution main
Digital Inputs-Statuses
9-Common Equipment
Digital Inputs - Statuses
The following functions shall be carried out by the instruments and control system.
Measurement, transmission, indication, recording and logging of process variables
such as, pressure flow level residual. Further data processing such as advance
calculation, optimisation, etc.
These signals are fed into the PLC system. Switching from automatic to
manual shall be bump less type.
x) Frequency HZ Hertz
xi) Speed (rotational) rpm revolution per minute
All instruments shall meet the requirements of this design criteria and this
However, supplier shall develop his own design, based on the requirements
stated in this specification and any other documents referred to and in complete
uniformity with the design of the plant, and shall be fully responsible for the
technical and economical aspects of his design and the materials and documents
to be provided.
All local control panels needed for operator local control shall be
included in the delivery as well as connection to the PLC system.
All instruments without exception shall be tropicalised and where ever installed
they shall be suitable for operation in the environmental conditions.
Where applicable each instrument chassis shall be easily withdrawable form its
Scales shall be clearly marked with black numerals and graduations on a white
background. Instruments of the same type and range shall have identical scales.
All instrumentations installed outdoor in the site shall be equipped with suitable
sunshade.
- Each differential transmitter shall be equipped with a drain plug on both sides.
- It shall be possible to rearrange the transmitter from a remote point using hand-
held terminal.
- The dials for all gauges shall be 150mm nominal in diameter and shall have
micrometer adjustable pointers, white laminated plastic dials with black
numerals and marking and 270 degree rotation.
- The material of element shall be selected to suit the potable water and shall
generally be 316 stainless steel.
- Over pressure protection shall be 1.3 times the maximum tube rating to prevent
permanent set or loss of calibration from continuous over pressure.
- The differential shall be adjustable and the switch shall have a repeatability
of (+,-) 0.5% of overall range.
- DP- pressure transmitter shall be used in water tower & Reservoirs for the level
measurement and transmission. Reservoirs and water tower level transmitters
shall be installed in the drain/washout line.
- The requirement for differential pressure and pressure transmitters used for level
measurement is as stated in clauses 3-3-5.2 and 3-3-5.3 .
Level Switches
- Level switches shall be mainly float- operated type suitable for use in potable
water such as Mobrey level switch or equivalent.
The electric motors shall have a time rating of 15 minutes, or twice the valve
stroking time, whichever is the longer.
Motor burn-out protection shall be provided by direct sensing of motor
temperature by a thermostat embedded in the motor winding. The trip shall not
be self resetting but shall include a changeover volt-free contact for remote
indication of motor tripped.
The actuator gear box shall be of the totally enclosed oil bath lubricated type,
and provided with the appropriate filling and drain plugs. The drive shall
incorporate a lost motion hammer blow feature. The output shaft shall be hollow
to accept a rising stem. Thrust bearing of the ball or roller type shall be provided
in such a way that the gear case can be opened for inspection or disassembled
without releasing the stem. Thrust bearing of the ball or roller type shall be
provided in such a way that the gear case can be opened for inspection or
disassembled without releasing the stem thrust or taking the valve out of service.
The hand wheel shall be provided for emergency operation engaged when the
motor is declutched by a lever or similar means, the drive being restored to
power automatically on starting the motor. The hand wheel drive shall be
mechanically independent of the motor drive, and any gearing shall be such as to
permit emergency manual operation in a reasonable time.
The valve actuator shall be furnished with a drive bushing easily detachable for
machining to suit the valve stem or gear box input shaft. The drive bushing shall
preferably be positioned to enable standard length valve stems to be used.
Electric actuators shall be provided with open and close torque and position
limit switches with changeover volt-free contacts at each end
Of travel for remote indication and interlocking. Means shall be provided to
prevent the open torque switch tripping while the initial unseating hammer-blow
effect is applied.
Mechanical dial indicator shall be provided to indicate whether the valve is fully
open, fully closed or in an intermediate position.
Provision shall be made in the design for the addition of a sealed potentiometer
of at least three watts rating,5k ohm resistance for continuous remote position
transmission where required by the specification. When so fitted, the mechanical
dial indicator shall also show continuous valve movement.
Unless otherwise specified, valve actuator shall be fitted with a three phase
mains isolator. The isolator shall be capable of interrupting the actuator motor
stalled current and shall have facilities for padlocking in the ON or OFF
positions.
The reversing contactor starter and local controls shall be integral with the valve
actuator. The starter shall comprise mechanically and electrically interlocked
reversing contactors of appropriate rating to the motor size, fed from a 240 volt
control transformer. The common connection of the contactor coils at the
transformer shall be earthed so that the contactors drop out in the event of
leakage to earth. The primary winding shall have taps for single and three phase
supplies and shall be separated from the secondary by an earthed screen. Two
primaries and one secondary fuse shall be provided of an easily replaceable
cartridge type.
Local controls shall comprise push button switches for OPEN, CLOSE and
STOP, and a LOCAL/REMOTE selector switch padlockable in any of the
following positions:
a) Local control
b) Remote control
c) Stop Locked off-no electrical operation.
Multi-turn actuators shall include integral control gear for the drive motor, local
and remote position indication and control facility, and motor protection by
torque limit switch and overhead detection.
Actuators whose position is under closed loop control shall be capable of
receiving a 4-20 mA position signal and driving automatically to the set point.
Actuators for control valves shall be equipped with built in current position
transmitter internally powered for transmitting of 4-20 mA signal for remote
valve position indication.
A All field signals shall be brought into the panel into grouped terminals. Initiating
contacts, which shall be voltage free changeover from field switches shall
operate directly into a multiple relay, the contacts of which shall then be wired
to the control logic, indications or alarm system as may be required.
B Analogue signals shall be routed directly to the primary loop within the interface
section of this panel.
C All analogue signals between chlorination building and pumping station room
(control room) should be through signal isolation cards.
GENERAL
A Indicators
Panel mounted indicators shall be not less than 100mm diameter (or high/wide
for edgewise instruments), and shall have a 270 movement, conform to BS 89
and shall have an accuracy to BS 89 Class index 1.0 or better. DIN type format
shall be provided.
B Recorders
Panel mounted recorders shall have charts of not less than 100mm width, shall
be of the potentiometric type, shall conform to BS 90 and shall have an accuracy
of not less than +1%. Chart speed shall be programmable flow recorder shall
have flow recording by paper and digital storage. Chart paper shall have
recording range 0-100% and 24 hours time marks. DIN type format shall be
provided. Flow recorders shall have digital flow indication, recording,
totalization and transmission of total flow.
C Setting stations
Panel mounted setting stations shall be of a similar format to the indicators fitted
to the panel. Where appropriate, they shall be enclosed in the same housing as
the indicating instrument whose measured value they are controlling.
Signal isolation cards shall be used in an analogue loop where the signal is to be
fed to another equipment e.g. flow signal feeding to chlorination equipment.
Signal isolation cards shall be used in an analogue loop where the signal is to be
fed to equipment, e.g. Flow signal feeding to chlorination equipment
E Mimic display
The mimic diagram shall be based upon the mottled effect mosaic tile principle,
with all artwork, design etc., carried out by the Contractor. Colours, symbols
and layout shall be based on the relevant British Standards.
The surface of the diagram shall be flat with no projections, free of bow, glare
and scratch resistant. The colours used shall be change and fade resistant.
Adjacent
Mimics shall fit closely together with only a hairline crack exposed.
The size of the mimic schematic diagram and of lettering shall be such that it is
clearly visible/readable to the operator when seated at the control desk.
The mimic panel shall be capable of accommodating requirements for future
pumps, reservoirs, etc.
The mimic panel shall be recessed in the wall with rear opening having hinged
doors and with bottom cable entry. The existing mimic panel frame shall be
used and modified according to the requirements.
The whole diagram shall be surrounded with a bezel to ensure a neat overall
appearance. The layout of the diagram shall be approved by the Engineer before
manufacture.
Each light shall be of the L.E.D type with either a descriptive label affixed
beneath the light fitting or an engraving on the screen of the fitting.
G Alarm Announciators
Each alarm condition shall be indicated on an alarm announciator having the
following basic features:
a) Audible alarm sounds upon the initiation of any alarm condition. The
audible signal shall be muted upon depression of the "ALARM ACCEPT"
push-button.
f) Depression of the "ALARM RESET" push- button shall not reset any
alarms which have not been accepted and shall only reset alarms whose
initiating contacts have cleared.
g) Any subsequent alarm that occurs after the "ALARM ACCEPT" push-
button has been depressed shall be considered as a new alarm condition,
irrespective of the state of other alarm legends.
H Clocks
A digital 24 hr. synchronous clock having numerals no less than 100mm high
shall be fitted at the top centre of the Main Instrument panel.
If legends are engraved on the push-buttons they shall be clear and concise and
shall be approved by the Engineer before manufacture.
The PLC-system for the complete plant (existing and new pumps) shall perform
the functions of control, and will provide the operator to allow a partial controls
and easy operation of the plant over any period of time. The PLC shall be
selected from approved Manufacturers' list
As this system is vital for the plant operation the architecture is to be designed in
order to eliminate bottlenecks, to guarantee availability and reliability to ease
and minimise maintenance intervention.
The Contractor shall provide all configuration and software required to enable
the system to perform its specified functions. PLC programming shall be
carried out by the manufacturer licensed specialist.
The PLC memory shall have the capacity to accommodate program and PLC
chassis shall have the facility for digital and analogue input & output cards etc
for future pumps.
Contractor is responsible for giving all special tools which is necessary for
system.
- Loop-control
The power supply to the controller shall incorporate over-voltage, surge and
spike protection.
Digital inputs and outputs shall operate at 24V dc via a power supply external to
the PLC.
The system shall be so designed that the Works can continue operating in
manual mode in the event of a major failure of the PLC.
Manual starting and stopping of every drive shall be possible without the PLC
operational. This shall apply also to the operation of all motorised valves,
solenoids and drives.
Power house load-shedding also has to be pre-planned in PLC-system basically
as follow:
In case of general-power failure, system must in form operator to switch on
category "A" in which, emergency loads can be switched on as per electrical
single line diagrams. There should be another category called "B" to permit
operator to run on another Electrical motor list and consumptions stand-by
during failure of each motor specified in category" A" PLC software shall
incorporate status feedback checks on plant controlled and raise an appropriate
alarm to signal "not running when required" where necessary. Similarly valve
actuator positions shall be checked for opened or closed status after the
appropriate drive commands.
The contractor shall design, supply, install and commission the PLC system
according to the drawings and to the satisfaction of the Engineer.
Regarding the process requirements and the related sequences for start/Stop of
the pumps and Open/Close of the valves the contractor shall design and carry
out the programming on the PLC system according to the details and
instructions introduced in the control and Instrumentation drawings.
2- Valve shall be closed by the signal generated from High High level switch
(as backup override switch) if the high level signal (from level switch) fails
to stop the pump in both Manual or Automatic mode.
3- Valve shall be actuated only when "Valve Failed" alarm is not initiated.
1- Pump shall start when suction valve is open and the discharge valve is
closed.
2- Pump shall be started in "Auto" or "Man" from control room or NWCC.
3- Pump start shall be inhibited by reservoir "low low level switch" (if
initiated).
4- Reservoir's "override switch" shall provide ready to start for the pumps in
the event of maintenance work on the reservoir(s) when low water level (or
empty reservoir) happens.
5- First Duty pump shall start on one of the WT'S low level switching
6- Second duty pump shall start when two of low level switches of the water
tower are initiated and first duty pump has already started and is running.
7- Standby pump shall start if the duty pumps fail to start.
8- All pumps shall stop when high level switch is activated.
9- Pumps shall not be started in the event of "Valve Failed" alarm.
10- Pumps shall not be started if the Common reservoir outlet valves are closed
(Both valves should be open).
11- Pumps shall not be started if pressure in common suction line is low.
12- Pumps shall stop in the event of Rising Mains "Flow High".
13- Pumps shall stop when Reservoirs Low Low level switch is initiated.
V1) Variable Speed Pumps Control Programme for pumping water to Rising
Main. The Control philosophy shall be based on pressure control
The system shall be designed to function with both full or empty rising main.
There shall be three duties and three standby pumps to control and maintain a
suitable pressure in rising main as per recommendations of Pump Supplier and suit
conditions of flow, pressure etc.
Duty Speed
In automode, speed of motor shall be adjusted to the meet the required pre-set
pressure and pumps shall start and stop at pre-defined speeds. These speeds shall
be chosen to provide the most efficient operation for the system pumping at a
maximum head of 43 meter. Contractor shall liaise with pump manufacturer to
ascertain the recommended operating speeds & the PLC software programme
should be designed accordingly.
Control signals
Speed control signals shall be sent to each inverter. These signals shall vary
continuously and the pump speeds shall be continuously altered as required by the
control system with no delay or dead bands.
Variable speed pumps control programme
1- Pump shall start when suction valve is open and the discharge valve is
closed.
2– Pump shall be started in “Auto” or “Manual” from control room or
NWCC.
3– Pump start shall be inhibited by reservoir “ Low Low Level Switch” (if
initiated)
4– Reservoir’s “override switch” shall provide ready to start for the pumps in
the event for maintenance work on the reservoir(s) when low water level
(or empty reservoir) happens.
5– 1st.duty pump shall start by selecting Automode.
6– 2nd.duty pump shall start if the demand exceeds the capacity of 1st.duty
pump.
7– 3rd.duty pump shall start if the demand exceeds the capacity of 1st and 2nd
.duty pump.
11– Pump shall not be started if pressure in common suction line is low.
12– Pump shall trip in the event of Rising Mains “Flow High”.
13– Pumps shall trip when Reservoirs Low Low level switch is initiated.
Interfaces between duty pumps (first, second and third duty pump), between
duty pump and standby pump, between valves and pumps, between valves and
interlocks such as water tower levels, between pumps and interlocks, etc. shall
be programmed by the contractor on the PLC system according to the drawings
and the section.
2- Valve shall be operated when water tower inlet valve closed and by pass
valve is open (pumping directly into network) or for testing pumps.
4- Valve shall not be ready for operation in the event of "valve failed" alarm
A General
Instrument and control panels shall be free-standing floor-mounting cabinets of
the cubicle, console or desk-pattern.
The height of cubicles shall not be greater than 2100 mm overall. The design
dimensions of console or control panels shall be determined according to their
intended function.
The panel design with equipment manufacturer's details shall be submitted to the
Engineer for approval prior to manufacture.
B Panel Construction
Panels shall be made of sheet steel of adequate thickness and suitable braced to
form a rigid structure. Panel fronts shall be flat and free from bow or ripple.
Exterior corners and edges shall be rounded to give a smooth overall
appearance.
A first class method of construction shall be employed and no design involving
the use of externally visible assemble bolts and screws nor any design resulting
in dust or water collecting crevices will be accepted.
Unless otherwise shown on the specification Drawings, each panel shall be
mounted on a self-draining steel plinth with a recessed kicking strip at the front.
A chequer plate floor shall be fitted not less than 230 mm above the floor level.
Removable side covers to the gland plates shall be incorporated, or any other
arrangement that shall give adequate access to the underside of the gland plates
and at the same time ensure a vermin proof construction.
Panels shall be supplied with hinged access doors fitted with lockable car-type
handles operable from inside even when locked. Doors shall be rigid and of
folded construction and provided with close fitting flexible seals to prevent
ingress of dust and vermin. Hinges shall be of the lift-off pattern and one hinge
shall engage before the other for ease of fitting. Where necessary removable
access covers secured by quick release fasteners shall be provided to ensure ease
of maintenance to all installed apparatus.
No equipment other than front-of -panel items shall be mounted on internal
panel surfaces and adequate provision shall be included for mounting-plates and
brackets which shall if necessary be hinged or otherwise arranged to give quick
and easy access when required to equipment securing screws terminals and
wiring.
The design of panels shall be such as to ensure adequate ventilation and air
circulation without permitting the entry of vermin and as far as possible, the
ingress of dust.
Temporary closures for panel openings shall be provided as necessary to prevent
ingress of dust and vermin during transit and installation. The panels shall be
further protected against damage prior to take-over.
C Panel Finish
The panel finish shall be hard, smooth, durable finish, free of blemishes and of
pleasing appearance. Before painting, all external welds and any rough areas
shall be smoothed, and all surfaces shall be free from rust, scale or grease. If
rust-proof steel work has not been used in the Construction, the panel shall be
treated with a passivating agent such as phosphoric acid. All internal surfaces
shall have a minimum of three coats of paint of which the first shall be an
approved anti-rusting priming coat and the final coat shall be an opaque gloss
white enamel.
All external surfaces shall have not less than five coats of paint of which the first
shall be an approved priming coat, and the second and
Third suitable undercoats, all of which shall be rubbed smooth when dry before
application of the next Coat. The two final coats shall be of stove enamel paint
gloss or semi-matt finish to a colour and finish to be advised by the Engineer.
Stoving shall be carried out in accordance with the recommendations of the
paint manufacturer.
D Panel Wiring
Panel wiring shall be carried out in PVC insulated multistrand cable to the
appropriate British Standard and of adequate grade and rating. Cable shall be
coloured black for a.c. supply circuits and grey for d.c. supply circuits. Circuits
in which the operating voltage exceeds 110 volts shall be neatly and securely
fixed by insulated cleats or bunched and securely fixed tubing Earth wiring for
instrument cases and to all apparatus shall be insulated. All wiring shall be
arranged so that access to any apparatus or connection point is not impeded.
Wiring for future
equipment shall be secured as far as possible and no wire left with bare ends.
Wiring caring low level d.c. signals shall be segregated from a.c. circuits and
screened if recommended by the manufacturer of the associated instrument. The
maximum potential between any two points within the panel shall not exceed
250 volts.
Any panel-mounted device to which connections are made by means of a plug
and socket instead of a terminal block shall be wired in flexible cable of
adequate rating between the free plug or socket and a fixed terminal block.
Identification ferrules shall be fitted at both ends of all wires not otherwise
permanently identified and the numbers or letters used shall correspond with the
appropriate wiring diagram. The ferrules shall be of insulating material with
permanent black characters on a glossy white or yellow background unaffected
by oil solvent or water. They shall be so arranged that they can read logically
form left to right when viewed normally.
F Panel Earthing
A continuous copper earth bar of not less than 25mm x 3mm section shall run
the full length of each panel and be bonded electrically to the main frame. It
shall be provided with suitable brass terminals of not less than 7 mm for
connection to the metal cladding or armouring of all incoming and outgoing
cables and to the site earthing system. Suitable terminals shall also be provided
for connecting the earthing wiring of instrument cases and equipment.
G Panel Protection
All live connections shall be efficiently shrouded and it shall be possible to reset
MCB's with the circuit live without danger of contact with live metal. The
MCB's shall be rated to give maximum protection to the apparatus in circuit and
the rating shall be inscribed on the MCB.
MCB's and links in the same circuit shall be mounted opposite each other in
separate rows and shall not alternate in the same row. At least 10 percent spare
MCB's and links shall be provided Descriptive circuit labels shall be fitted
adjacent to all MCB's and links, the layout of which shall correspond with the
wiring diagram.
H Panel Isolation
Isolating switches, clearly labelled, shall be provided for all incoming power
supplies, they shall be of the quick make and break type with spring-loaded
contacts that close fully without requiring full operation of handle, which shall
be so interlocked with the cover that it cannot be operated when the cover is
open. The ON and OFF positions of each switch shall be unambiguously
indicated. Wiring from each isolator to its distribution board shall be capable of
carrying safely the isolator rated current unless a fused isolator is
employed. Plug-in isolating links or devices of an approved type shall also be
provided in any circuit that may still be live when the power supply isolators are
in the OFF position, as
A All items of Plant shall be subject to inspection and testing before despatch.
Unless otherwise authorised by the Engineer the Contractor shall arrange routine
and functional tests to demonstrate to the Engineer conformity with the
Specification.
The cost of all visits for the purpose of witnessing tests on major items of plant
shall be borne by the Contractor. The cost shall include airfares,
accommodations and subsistence allowance for two persons representing
KAHRAMAA.
C Where witness tests are not required, the test certificates and performance curves
shall be forwarded to the Engineer within two weeks after instructions to waive
witness tests have been received. On each test certificate, sufficient information
to enable the Engineer to issue a release certificate including the Specification
Contract number and details, shall be given for ready identification of the
material or equipment to which the certificate refers.
No inspection or passing by the Engineer or the Engineer's Representative of the
work, Plant or materials covered by this Contract, whether carried out or
supplied by the Contractor, shall not release him from any of his obligations
under the Contract.
D Any equipment used in the testing of the Plant shall in all respects comply with
the appropriate safety regulations and /or requirements regarding electrical
apparatus for the safety of the Plant and the men working thereon.
E As and when the Engineer is satisfied that any plant is in accordance with the
specification and has passed the pre-set workshop tests, he will notify the
Contractor in writing to that effect.
F The net cost of abortive visits for the purpose of witnessing tests, or of further
visits to inspect plant previously found to be defective, or otherwise unable to
meet the specified requirements or of any other expenses incurred for the same
reason by the Engineer will be charged to the Contractor unless it can be shown
that he look all reasonable steps to avoid such occurrences.
G Calibration certificates for instruments used for such tests shall be produced for
the Engineer's approval and, if necessary, instruments shall be recalibrated
before the commencement of the tests.
During erection of the Plant, the Engineer will inspect the installation from time
to time in the presence of the Contractor's Supervisor to establish conformity
with the requirements of the Specification.
A The Contractor shall undertake all necessary commissioning and testing to set the
Plant to work. When the Contractor is satisfied that the Plant is operating
correctly, he shall inform the Engineer, that he is ready for the Test on
completion.
B All labour, materials, power apparatus and equipment of every kind as may be
required for the tests shall be provided by the Contractor. Unless specific
approval has been obtained from the Engineer, special tools and test equipment
supplied under the Contract shall not be used for these tests.
The Contractor shall demonstrate the correct operation and accuracy of all the
equipment supplied under the Contract in the manner indicated below or as
otherwise directed by or agreed with the Engineer:
i) Pressure instruments
The correct operation of level transmitters shall be proved at 0%, 25% 50%,75%
and 100% full scale for rising and falling level to prove that a correct output
signal is produced at these values.
v) Flow instruments
Magnetic flow meters shall be proved by applying a flow simulator to the flow
converter or amplifier at values corresponding to 0%, 25%, 50%, 75% and
100% full scale for increasing and decreasing flows. Any indicator fitted on the
flow converter or amplifier shall be correctly calibrated and receiving
instruments shall be proved to respond correctly.
Flow tests covering the whole installed flow measuring system. e.g.
displacement tests, shall be carried out, when required in accordance
with the Particular Specification by the Contractor in conjunction with the
Engineer, who will arrange the availability of associated Plant. The tests shall be
carried out at various flow rates and of sufficient duration to establish the system
accuracy to the satisfaction of the Engineer. During the course of these tests,
accuracy’s of all instruments associated with each measurement shall be proved
to conform with the Specification.
vi) All push buttons, control switches and equipment state indicating lamps shall be
shown to function correctly utilising the actual plant concerned wherever
possible.
vii) All alarm and trips shall be tested by operation of the primary initiating device.
viii) All receiving instruments, analogue and digital displays, recorders, lamp and
alarm indications, control functions, etc. and transmission systems shall be
shown to operate correctly utilising the plant or equipment concerned. If line
monitoring equipment is not included in telemetry equipment, the Contractor
shall provide such equipment and connect so that the performance of the
communication link may be observed during the tests. Any equipment supplied
under the Contract that requires readjustment during the above tests shall, after
read- adjustment, again be demonstrated by the Contractor to the satisfaction of
the Engineer.
After the Engineer has signified his approval of the complete control and
instrumentation installation, the Contractor shall demonstrate that the equipment
operates continuously in a satisfactory manner for a period of seven consecutive
days or for any other such period as may be previously agreed with the
Engineer. During the whole of this period the Contractor shall operate and adjust
the Plant supplied under the Contract as instructed by the Engineer.
The seven day period of operation shall complete the Tests on Completion for
those sections of the Plant involved.
GENERAL
b) The design of the associated civil works, structures, equipment and services
to proceed.
c) The erection of the Plant and installation of pipe work and cabling
according to the agreed work programme.
Contractor shall prepare a document routing and distribution procedure such that
KAHRAMAA will automatically receive the Technical Documentation as they
are developed by supplier.
Contractor shall schedule the delivery of Technical Documentation to
KAHRAMAA in a manner congruent with the detailed schedule of performing
the works such that the documentation requiring other documentation as pre-
requisite will be preceded by such pre-requisites.
KAHRAMAA will not be responsible for delays arising out of withholding his
Approvals due to unavailability of pre-requisite Documents.
All weights and measures shall be given in SI system of measurement. All
written materials shall be in English.
All drawings of reduced size regardless of what purpose they are provided for
shall be submitted to KAHRAMAA in one additional reproducible each.
Contractor shall in addition to the above provide KAHRAMAA with the
necessary number of copies and transparencies of the interim Technical
Documentation for Approval and/or review together with revisions there to.
All drawings to be submitted by the Contractor shall be of one of the following
sizes: A0, A1, A2, or A4.
b) One set of reproducible transparent copies of all final drawings, as per time
Schedule.
c) One set of PC secondary storage’s, as per Time Schedule,
The said storage’s shall be compatible with the hardware
and software being used by KAHRAMAA.
- Instrument list
- Complete technical data sheets for all instruments, valves & equipment.
- Flow elements, control valves and safety relief valves calculation sheets.
- Instrument location layouts for all field instruments and junction boxes with
exact location and elevation for tapping points, instrument locations, cable
routes and termination points
- Cable schedule
- Concept of:
Digital (on-of) control systems (PLC's interlocks)
= Software:
. Hardware:
MANUALS
3-3-10.2 GENERAL
All manuals shall include reduced scale arrangement drawings and diagrams and
a detailed index.
Provisions shall be made for additions and deletions which may be indicated by
operational experience. Where these amendments are indicated to be necessary
during Initial operation before Final Acceptance, Supplier shall supply the
amended sections.
The operating manuals shall be comprehensive, but shall also include the basic
and most common instructions in brief summary form.
The use of all controls provided shall be explained and the sequence of
operation shall be stated for all the tasks which plant operating staff must
normally perform.
All instruction manuals as a minimum shall contain reduced size prints of all
major drawings including process flow diagrams and piping and instrument
diagrams.
. Start up
. Normal operation
. Normal shut down
. Emergency shut down
. Loss of feed
. Loss of critical Equipment
. Loss of A.C. power
. Loss of D.C. power
- Drawings
All major drawings including process and flow diagrams, piping and instrument
diagrams, electrical single line diagrams as well as the necessary Vendors,
drawings shall be included.
- The procedures for routing checks, adjustments and calibrations shall be listed
and a format shall be recommended for the regular recording of this data.
- The use of computer diagnostic and trace routines shall be explained from the
user's point of view and examples shall be given.
- User’s manual for all instruments and control equipment and all software
packages shall be given.
- Maintenance manuals shall be comprehensive it shall included reduced scale
exploded view drawings. Detailed part list, recommended spare parts and a
detailed index.
The format of the Maintenance manuals should generally cover the following
aspects but not be limited to:
- Wiring and dimensional outline drawings and foundation plans, specially giving
size, location and rates of various Equipment.
- Exploded view drawings showing working parts and internals with parts list
covering all the individual components of instrument, electrical and special
Equipment.
- Drawings for all Equipment and accessories, showing sufficient details for
disassembly and assembly during maintenance.
A The contractor shall prepare, for approval by the Engineer a comprehensive list
of spare parts together with Spare Part Inter chaingable requirements (S P I R )
and special tools which are required for two years maintenance (after expiry of
contract maintenance period) and servicing of all items of plant and equipment.
All Spares and tools shall be of high quality and to be supplied in accordance
with the list. Details of the manufacturer(s) shall be submitted to the Engineer
for his approval.
1 No. processor for PLC and 1No.of power supply, 2 No. each input and output
cards for the PLC.
All spare parts shall be suitably treated and packed by the manufacturers for
long storage under the climate conditions prevailing in Qatar. Every part or
assembly subject to deterioration through exposure to moisture, damp or dust be
individually protected by a sealed enclosure, each single part of assembly shall
be individually labelled with information in English identifying:
a. The machine or piece of equipment for which the part is intended.
b. The description and functions of the part.
c. The part reference number.
The labelling shall remain legible after long periods of storage and shall be
visible
from the outside of protectively sealed enclosures. Each single part of assembly
shall be individually labelled with information in English:
3-3.12 TRAINING
The contractor shall prepare, for approval by the Engineer, a training plan for the
operating, maintaining and trouble shooting control system, instruments and
PLC equipment. The plan shall include as a minimum period of 3 weeks
training, location, and number of personnel to be trained.
3-3-13 Details/Schedule of the Minimum Instruments and signal in Field/Local, MCC Panel, Control
Desk, Work Station, Mimic Panel, Annuanciator, NWCC Marshalling Box
S.No Item Field/Local MCC Panel Control Work Station Mimic Panel Annuanciator NWCC Marshalling
. Description Desk Box
a Rising main Local pressure Not Display of • Display of Display of • High alarm • Display
Pressure display & applicable instantaneou instantaneous instantaneous • Low Alarm • Set value
pressure switch s pressure pressure pressure on • High alarm
on recorder • Set value indicator • Low Alarm
b Distillate inlet Local flow Not Display of • Display of Display of • No • Display of
Flows Display ,pressure applicable instantaneou instantaneous instantaneous flow instantaneous flow with
indication s flow on flow with flow and • High alarm totalizing
recorder totalizing pressure on Low Alarm • No flow alarm
with • set point to indicator • set point to
totalizing & control incoming control incoming flow
pressure flow • High alarm
indication • pressure • Low Alarm
indication • Pressure indication
S.No Item Field/Local MCC Panel Control Work Station Mimic Panel Annuanciator NWCC Marshalling
. Description Desk Box
d Ground Not applicable Low-low Display & Display & log of Display of • High -High Display of continuous
Reservoirs indication log of continuous level instantaneous alarm level
Level (all continuous • High -High level on • High- level • High -High
compartment level on alarm indicator Alarm alarm
) recorder • High- level • Low – • High- level Alarm
Alarm level alarm • Low –level
• Low – • Low- alarm
level alarm low level • Low-low level
Low-low level alarm alarm
alarm
e Residual local display of Not Display & Display of pH, Display Residual pH, Residual Chlorine,
Chlorine pH, Residual applicable log of pH, Residual Residual Chlorine Low Temperature value,
monitor Chlorine, Residual Chlorine, Chlorine on & High alarm Conductivity, Residual
Temperature, Chlorine, Temperature, indicator Chlorine Low & High
Conductivity, Temperatur Conductivity, alarm
Residual Chlorine e, Residual
Low & High Conductivit Chlorine Low &
alarm y, Residual High alarm &
Chlorine instantaneous
Low , High value graph
alarm &
instantaneou
s value of
residual
chlorine on
recorder
S.No Item Field/Local MCC Panel Control Work Station Mimic Panel Annuanciator NWCC Marshalling
h Common •Pressure switch •Signal to trip • Low •Low indication •Not applicable • Low •Low alarm
Pump Suction pump indication alarm
Individual •Pressure switch •Signal to trip • Low •Low indication •Not applicable • Low •Low alarm
Pump Suction pump indication alarm
i Pump •Open, close & Not •Open, close •Open, close & • Open, close Failed alarm •Open, close & stop
Delivery stop function applicable & stop stop function & Failed function
Valve •Indication of push button •Open & close indication •Open & close
percentage of •Open & indication indication
opening close •Indication of •Available indication
•Remote & local indication percentage of •Indication of
selector switch •Available opening percentage of opening
indication •Available
•Indication of indication
percentage
of opening
j Pump suction •Open & close Signal to trip •Open & •Open, close • Open, close Failed alarm •Open & close function
valves function pump if valve close push function & Failed •Open, trip & close
•Remote & local is closed button •Open, close indication indication
selector switch •Open & indication •Available indication
close •Available
indication indication
•Available
indication
k Rising Main •Open, close & Signal to trip •Open, close •Open, close & • Open, close Failed alarm •Open, close & stop
outlet Valve stop function pump if valve & stop stop function & Failed function
•Indication of is closed push button •Open, close indication •Open ,trip & close
percentage of •Open & indication indication
opening close •Indication of •Available indication
•Remote & local indication percentage of •Indication of
selector switch •Available opening percentage of opening
indication •Available
•Indication of indication
percentage
of opening
S.No Item Field/Local MCC Panel Control Work Station Mimic Panel Annuanciator NWCC Marshalling
. Description Desk Box
l Recirculation •Open, close & Not •Open, close •Open, close & • Open, close Failed alarm •Open, close & stop
valves stop function applicable & stop stop function & Failed function
•Indication of push button •Open, close indication •Open, trip & close
percentage of •Open & close indication indication
opening indication •Indication of •Available indication
•Remote & local •Available percentage of •Indication of
selector switch indication opening percentage of opening
•Indication of •Available
percentage indication
of opening
m Ground •Manual hand Not •Open & •Open, close • Open, close none •Open & close
Reservoirs operating valve applicable close push indication indication indication
inlet, outlet but remotely button •% of opening •% of opening
valves viewing % of •% of
opening opening
n Reservoir •Manual hand Not Open & Open, close • Open, close none Open & close indication
Equalizing operating valve applicable close indication & Failed
valve indication indication
o Chlorination • Run & Not • Set point • Set point • Run & • Failed • Set point
Equipment stop push applicable potentiomet • High & low stop alarm • High & low indication
button er indication indications • High • Residual chlorine
• Dosing pump • Residual • Residual fume alarm value
running stopped chlorine chlorine value • High & low • High fume indication
& failed monitor and High fume alarm
indication recorder indication
• Duty selector
switch
• Set point
• Recorders with
high & low alarm
Fume detector
p Dewatering • Run & Not Not • Run, Stop & • Run, Stop & • Failed • Run, Stop & failed
pump/ Sump stop push applicable applicable failed indication failed alarm indication
level button • High level indication • High level • High level indication
• Auto & manual indication indication •
selector switch, •
• Duty selector
Switch
• Run, Stop &
failed indication
• High level
indication
s Fire alarm • Operated Not Not • Operated Not applicable • Operat • Operated
• Power supply applicable applicable • Power supply ed • Power supply failed
failed failed • Power • Battery low
• Fire Zone • Battery low supply failed
indication
• Battery low
t UPS On & failed Not Not On & failed Not applicable Failed alarm On & failed indication
indication applicable applicable indication
u PLC • Battery low Not Not • Battery low Not applicable • Battery low • Battery low
• Power supply applicable applicable Power supply • Power supply • Power supply failed
failed failed failed
v Field manual •Open & close Not Open & •Open, close • Open, close Not applicable •Open & close
valves(inside hand wheel applicable close indication indication indication
the reservoir indication
and pump
station
premises )
w Field •Open & close Not •Open & •Open, close • Open, close Failed alarm •Open & close function
motorized function applicable close push function & Failed •Open & close
valves •Remote & local button •Open, close indication indication
selector switch •Open & indication •Available indications
close •Available
indication indication
Available
indication
x VFD Supply on ,off & •Speed •Speed •Speed Lower & Not applicable Failed alarm •Speed Lower & Rise
Available indication Lower & Rise function function
indication •Available Rise push •Speed indication •Speed indication
indication button •Available •Available indication
•Available indication
indication
•Speed
indication
y Station . Not applicable Remote & • Auto, • Manual Control Not applicable Master • Manual Control (
control ( Local selector control desk ( where operator Emergency where operator can set
selector & switch , telemetry can set any activated any pressure /flow
emergency & off pressure /flow value while station on
switch) selector value while run
switch station on run • Auto Control ( only run
• Master • Auto Control on predetermined
Emergency ( only run on pressure /flow value
Switch predetermined • Master emergency stop
pressure /flow button
value