Professional Documents
Culture Documents
The following is a list of all autocad Schedules drawing files available in DAR:
Schedule Description Schedule No.
Air Handling System Preliminary Checks
System Cleanliness SCHD-1
Air regulation devices SCHD-2
Initial start of fans & air handling units SCHD-3
Mechanical checks SCHD-4
Air handling unit SCHD-5
SCHD-6
Chilled Water System Preliminary Checks
Flushing & chemical cleaning SCHD-7
State of system SCHD-8
Check of system before filling SCHD-9
Piping and Valves (A/C and Heating) SCHD-10
Mechanical checks for pumps SCHD-11
Mechanical checks for motorized valves & float switches SCHD-12
Electrical checks SCHD-13
Initial start of pump SCHD-14
SCHD-15
Refrigerating System Preliminary Checks
System cleanliness SCHD-16
Mechanical Checks SCHD-17
System Check before starting SCHD-18
SCHD-19
Equipment Checks
Water chiller SCHD-20
Water chillers SCHD-21
Water chillers SCHD-22
Water chiller SCHD-23
Cooling tower SCHD-24
Boiler SCHD-25
Heat exchanger SCHD-26
Heat transfer coils SCHD-27
Pump test sheet SCHD-28
Axial fan SCHD-29
Propeller fan SCHD-30
Schedule Description Schedule No.
Roof extract fan SCHD-31
Centrifugal fans SCHD-32
Schedule Description Schedule No.
Fan coil unit SCHD-33
Packaged roof top A/C unit SCHD-34
Package air conditioner (water or glycol cooled) SCHD-35
Air cooled ducted split unit SCHD-36
Dry cooler SCHD-37
Cold room condensing unit SCHD-38
Closed expansion tanks SCHD-39
Electric unit heater SCHD-40
Duct heater test report SCHD-41
Electric water heater SCHD-42
Roof water tanks SCHD-43
Underground water tanks SCHD-44
Cold water booster pump set SCHD-45
Balancing valve / flow meter SCHD-46
Water balancing SCHD-47
Air Balancing
Outlet test report SCHD-48
VAV air outlet test report SCHD-49
Ducts, air outlets and miscellaneous SCHD-50
Air balancing test sheet SCHD-51
Main plant air balancing test sheet SCHD-52
System diagram SCHD-53
Color Coding
Equipment Identification color code (HVAC) SCHD-54
Equipment Identification color code (PLUMBING) SCHD-55
Pumping Stations
Pumping station commissioning (Sheet 1 of 6) SCHD-56
Pumping station commissioning (Sheet 2 of 6) SCHD-57
Pumping station commissioning (Sheet 3 of 6) SCHD-58
Pumping station commissioning (Sheet 4 of 6) SCHD-59
Pumping station commissioning (Sheet 5 of 6) SCHD-60
Pumping station commissioning (Sheet 6 of 6) SCHD-61
Kitchens
Kitchen and Food Service Equipment SCHD-62
Kitchen and Food Service Equipment – Floor SCHD-63
Gas and fittings – floor SCHD-64
Schedule Description Schedule No.
Various
Electrical work – floor SCHD-65
Sanitary and laboratory drainage – floor SCHD-66
Water supply – floor SCHD-67
Fire fighting & compressed air systems – floor SCHD-68
Piping & Valves (plumbing) – floor SCHD-69
General SCHD-70
Plumbing Fixtures
Plumbing fixtures (1) SCHD-71
Plumbing fixtures (2) SCHD-72
Plumbing fixtures (3) SCHD-73
Plumbing fixtures (4) SCHD-74
Plumbing fixtures (5) SCHD-75
PRELIMINARY CHECKS
FOR AIR HANDLING SYSTEM
1- System Cleanliness
Check
Check List Mark Remarks
Check the following for cleanliness:
1 Air intake screens
2 Fan & other equipment chamber
3 Floor drains & drainage traps
4 Fan internals
5 Cooler batteries
6 Cooling coil trays
7 Dampers
8 Ducting
9 Sensing element
10 Machine room
∆
∆
∆
REV. NO DATE REVISION APPROVED
Check
Check List Remarks
Mark
Check that the following are fitted and not
1 damaged:
Tuning vanes
Straigntening vanes
Themal insulation
Acoutical linings
Battery fins
Sensing elements
∆
∆
∆
REV. NO DATE REVISION APPROVED
Check
Check List Remarks
Mark
On activating the motor starter check
∆
∆
∆
REV. NO DATE REVISION APPROVED
4- Mechanical Checks
1 External cleanliness
2 All components, bolts, fixings are secured
∆
∆
∆
REV. NO DATE REVISION APPROVED
LOCATION: POWER:
FLA:
LOCATION: POWER:
FLA:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
GUIDELINE DETAIL NO. SCH-5
Project:
System & Building:
System total vol.:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
DATE
GUIDELINE DETAIL NO. SCH-7
Mechanical & Industrial Department
PRELIMINARY CHECKS
FOR CHILLED WATER SYSTEM
2 – State of System
∆
∆
∆
REV. NO DATE REVISION APPROVED
PRELIMINARY CHECKS
FOR CHILLED WATER SYSTEM
∆
∆
∆
REV. NO DATE REVISION APPROVED
FLOOR
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
PRELIMINARY CHECKS
FOR CHILLED WATER SYSTEM
∆
∆
∆
REV. NO DATE REVISION APPROVED
7 – Electrical Checks
A.5 That all connections are tight on bus bars and wiring
A.6 That the internal links on the starter are correct
A.7 That all the power and control wiring has been
completed in detail to the circuit diagram
A.8 That the fuse ratings are correct
A.9 That the starter overloads are set correctly in relation to
the motor name-plate full load current
A.10 That the insulation test on the motor have been
performed satisfactorily
A.11 That all cover plates are fitted
B With the electrical supply available:
B.1 Check the control circuit fuse to ensure that it is rated
to the cables
B.2 Check the starter operation
B.3 Check for positive operation of all contactors, relays
and interlocks
∆
∆
∆
REV. NO DATE REVISION APPROVED
PRELIMINARY CHECKS
FOR CHILLED WATER SYSTEM
∆
∆
∆
REV. NO DATE REVISION APPROVED
1 – System Cleanliness
1 External cleanliness
2 External condenser surface
3 Condenser fan chamber
4 Sensing elements
5 Compressor
6 Safety and control devices
∆
∆
∆
REV. NO DATE REVISION APPROVED
REFRIGERATING SYSTEM
PRELIMINARY CHECKS
2- Mechanical Checks
∆
∆
∆
REV. NO DATE REVISION APPROVED
REFRIGERATING SYSTEM
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION: CAPACITY:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
REF. NO.:
LOCATION:
DESIGN OUTPUT CAPACITY:
∆
∆
∆
REV. NO DATE REVISION APPROVED
Test Report
REF. NO.:
LOCATION: RATING:
Primary Water:
Entering water pressure
Leaving water pressure
DELTA P
Entering water temp.
Leaving water temp.
DELTA T
Flow rate
Secondary Water:
Entering water pressure
Leaving water pressure
DELTA P
Entering water temp.
Leaving water temp.
DELTA T
Flow rate
∆
∆
∆
REV. NO: DATE REVISION APPROVED
REF. NO.:
LOCATION: CAPACITY:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION: POWER
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
GUIDELINE DETAIL NO. SCH-31
Test Report
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION:
Evaporator:
Total air flow rate
Total SP
Outside air flow rate
outside air DB/WB
Return air flow rate
Return air DB/WB
Mixed air DB/WB
Leaving air DB/WB
Fan RPM
Votage
Current (each phase)
Condenser /Compressor:
Low ambient control
Suction pressure / temp.
Condenser pressure / temp.
Crankcase heater amps.
Compr. Volts
Compr. Amps (all phases)
Low pressure / high pressure cutout setting
Fan RPM (each fan)
Cond. Fan HP
∆
∆
∆
REV. NO: DATE REVISION APPROVED
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO DATE REVISION APPROVED
Evaporator:
Measure motor current (each phase)
Measure motor voltage
Measure duct inlet / outlet S.P
Measure fan RPM
Measure F.A flow rate
Measure R.A flow rate
Measure total air flow rate
Measure outlet air velocity
No. of fins & spacing
Coil face area
Measure coil face velocity
Measure DELTA T across the coil
Drain fan
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO DATE REVISION APPROVED
COLD ROOM
CONDENSING UNIT
REF. NO.: TONNAGE:
LOCATION: POWER:
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION: CAPACITY:
Safety valve
Check valve
CW and HW shut-off valves
Outer container of high grade steel
Insulation
Immersion heater of sheathed wire element
Check the electrical supply
Check heater operation
Check entering water temp.
Check leaving water temp.
Cut-in temp.
Cut-out temp.
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO DATE REVISION APPROVED
REF. NO.:
LOCATION:
∆
∆
∆
REV. NO: DATE REVISION APPROVED
Remarks
APPROVED
Mechanical & Industrial Department
BALANCING VALVE / FLOW METER
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV NO. DATE: REVISION APPROVED
(CONSTANT VOLUME)
SYSTEM NO.:
AREA SERVED:
NO. SIZE FACTOR DESIGN DESIGN VEL. TEST NO. 1 TEST NO. 2 TEST NO. 3 ACTUAL FINAL ACTUAL REMARKS &
C.F.M OR S.P. VEL. OR S.P. VEL. OR S.P. VEL. OR S.P. VEL. OR S.P. FINAL C.F.M % OF DESIGN
TOTAL:
DATE:
∆
∆
∆
REV. NO DATE REVISION APPROVED
M
Mechanical & Industrial Department
e
c
h
a
n
i
c
VAV AIR OUTLET
Test Report
∆
∆
∆
REV. NO DATE REVISION APPROVED
AIR HANDLING UNIT ( FAN, UNIT COOLER, ELECTRIC HEATER) REF. NO: …………………………
LOCATION:
∆
∆
∆
REV. NO DATE REVISION APPROVED
WITNESSED BY:
DATE: .
GRILLE LOCATION DESIGN DESIGN GRILLE/DIFF. FREE AREA AREA MEASURED CALC. MEASURED % DUTY
VOL. VEL. TYPE SIZE (OR HOOD) VEL. VOL.
REF. NO.
∆
∆
∆
REV. NO DATE REVISION APPROVED
HP/KW:
PULLEY DIA FAN: MOTOR FLC
REF LOCATION DUCT SIZE DUCT DESIGN DESIGN MEASURED VEL MEASURED % DESIGN
AREA VOL. VEL. VOL.
1
3
4
TOTAL VOL.
STATIC PRESSURE:
BEFORE FAN:
FAN MEASURED DUTY
AFTER FAN:
∆
∆
∆
REV. NO DATE REVISION APPROVED
LOCATION:
SYSTEM:
∆
∆
∆
REV. NO DATE REVISION APPROVED
HVAC
EQUIPMENT BASIC COLOR
AIR HANDLING UNIT BLUE
FAN GREEN
HOT WATER STORAGE HEATER ORANGE
BOILER ORANGE
CHILLER BLUE
EXPANSION TANK WHITE
PACKAGE A/C UNIT BLUE
DESERT COOLER BLUE
COOLING TOWER BLUE
CHILLED WATER PUMP BLUE
HOT WATER PUMP ORANGE
HOT/CHILLED WATER PUMP GREEN
CONDENSER WATER PUMP BLUE
DRY COOLER BLUE
CONDENSING UNIT BLUE
BLOW DOWN TANK ORANGE
PRESSURE REDUCING STATION ORANGE
FLASH TANK ORANGE
CONDENSATE RECEIVER ORANGE
BOILER FEED PUMP ORANGE
1- Where factory paint finished the above color code is not to be considered.
2- Construct color code & identification schedule. Frame & mount with glass. Install in prominent location in central
plant and mechanical floor.
∆
∆
∆
REV. NO: DATE REVISION APPROVED
PLUMBING
EQUIPMENT BASIC COLOR
WATER SOFTENER BLUE
FILTER BLUE
FUEL PUMP BROWN
HOT WATER CIRCULATION PUMP ORANGE
DOMESTIC WATER PUMP BLUE
FIRE PUMP RED
COMPRESSOR YELLOW
PRESSURE TANK YELLOW
HALON CYLINDER RED
O2 CYLINDER GREEN
NO2 CYLINDER BLACK
GAS CYLINDER BLACK
VACUUM PUMP VIOLET
ULTRA VIOLET UNIT BLUE
REVERSE OSMOSIS UNIT BLUE
1- Where factory paint finished the above color code is not to be considered.
2- Construct color code & identification schedule. Frame & mount with glass. Install
in prominent location in central plant and mechanical floor.
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
GUIDELINE DETAIL NO. SCH-58
∆
∆
∆
REV. NO DATE REVISION APPROVED
FLOOR
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO DATE REVISION APPROVED
FLOOR
∆
∆
∆
REV. NO DATE REVISION APPROVED
ELECTRICAL WORKS
FLOOR
∆
∆
∆
REV. NO DATE REVISION APPROVED
FLOOR
∆
∆
∆
REV. NO DATE REVISION APPROVED
WATER SUPPLY
FLOOR
∆
∆
∆
REV. NO DATE REVISION APPROVED
FIRE FIGHTING
AND
COMPPRESSED AIR SYSTEMS
FLOOR
∆
∆
∆
REV. NO DATE REVISION APPROVED
GUIDELINE DETAIL NO. SCH-68
FLOOR
∆
∆
∆
REV. NO DATE REVISION APPROVED
GUIDELINE DETAIL NO. SCH-69
GENERAL
∆
∆
∆
REV. NO DATE REVISION APPROVED
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO: DATE REVISION APPROVED
1 Shower tray
Supply valves
Spray head
Grid waste
Any damage to fixture
Mastic sealant complete
Installation complete
∆
∆
∆
REV. NO: DATE REVISION APPROVED
GUIDELINE DETAIL NO. SCH-73
Urinal type UR 1
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO: DATE REVISION APPROVED
∆
∆
∆
REV. NO: DATE REVISION APPROVED
1 Suction and discharge piping hydrostatically tested at 200 psi (13.8 bars) or at
50 psi (3.4 bars) in excess of system's maximum maintained pressure
2 Suction piping flushed at a flow rate not less than that indicated in tables (1) and
(2) attached.
3 Representatives of the manufacturers of the pumps, engine, controller and
transfer switch (where applicable) are present for the field acceptance tests.
4 Check all electrical and control wiring, interwiring and emergency power
supply.
5 Check if a copy of manufacturer's certified pump test characteristic curve/s is
available during the test.
6 Check cleanliness of pumps, pipes, valves,…etc.
∆ DA
∆ TE
∆
REV. NO: REVISION APPROVED
4 590 (2233)
5 920 (3482)
6 1360 (5148)
8 2350 (8895)
10 3670 (13891)
12 5290 (20023)
TABLE (2)
1 1/2 100
2 250
3 400
4 450
6 500
FIRE FIGHTING PUMPS
2. FIELD ACCEPTANCE TESTS
Measure voltage
Measure flow rate
Measure discharge pressure
Check for objectionable overheating
NOTE: Above tests shall be repeated at minimum, rated and peak loads. Duration of all tests shall not be less
than one hour
∆
∆
∆
REV. NO: DATE REVISION APPROVED
NOTE: A minimum of six automatic and six manual operations is required to be performed.
∆
∆
∆
REV. NO: DATE REVISION APPROVED
DATE OF TEST:
∆16 D Check manual pull stations if properly installed and properly protected…etc.
∆ A
∆ T
REV. NO: E REVISION APPROVED
PAGE 1/6
(HYDRAULIC METHOD)
LOCATIO
PROJECT: N
Project:
Notes: 1- Repeat this procedure for each branch starting from the last branch
and moving backwards until reaching the riser.
2- Flushing shall be in the direction of flow.
∆
∆
∆
REV. NO: DATE REVISION APPROVED
DATE
∆
∆
∆
REV. NO: DATE REVISION APPROVED
DATE
GUIDELINE DETAIL NO. SCH-81
Pipe size in inches (mm) Flow rate (gpm) Flow rate (L/min)
1 Verify that all pipe sizes and routes are in accordance with the approval
2 Verify that all nozzles are of the approved types and sizes
3 Verify that the supporting system is in accordance with the approval
4 Verify that the orientation of each nozzle is in accordance with the approval
5 Verify if during the assembly, the pipes were inspected internally for oil or any
particulate matter that might affect the flow
6 Type of gas used for flow test (either Nitrogen or an inert gas)
7 Nitrogen or inert gas introduced at the clean agent cylinder connection
8 Nitrogen or inert gas introduced at a pressure equal to the system's operating
pressure
9 Visual indicators provided to verify that nitrogen or inert gas has discharged out
of each and every nozzle in the system
10 Upon performing the flow test, any indication for obstruction is observed (if so,
describe under "Remarks")
∆ DATE
∆
∆
REV.∆NO: REVISION APPROVED
∆
∆
REV. NO: DATE REVISION APPROVED