Name of Contractor: …………………………………… File No.

2363

reference Title Unit Price quantity unit Total


1 PRELIMINARIES AND GENERAL REQUIREMENTS
Non-Recurring Preliminary Costs (Mobilization)
1.1 Incurred at the commencement of the Works
Provision of all necessary offices and facilities for the Employer and the Engineer complete with all services, furniture, equipment and EA 0
1.1.1 fixtures as specified.
1.1.2 Provision of all necessary offices, stores and facilities for Contractors' site staff in adequate manner as per the Works required. EA 0
1.1.3 Provision of sign boards as per ADCE design and requirement NIU 0
1.1.4 Provision of Sign board on top of the tower crane of dimensions (3.00 M X 1.22 M) as specified. EA 0
1.1.5 Provision of site hoarding as specified with ADCE logo (Stickers 12 pieces). . EA 0
1.1.6 Submittal of Performance Bond as per the Conditions of the Contract. EA 0
1.1.7 Submittal of all insurances as per the Conditions of the Contract. EA 0
Submittal of Programme for the Works and cash flow , whereby Contractor to submit Construction progarmmme (baseline) to the Engineer EA 0
1.1.8 for approval
Allow for all obligations in accordance with the Contract, which are not mentioned above. The Contractor shall detail and price below any EA 0
1.1.9 other obligations indicating the relevant clause reference in the Contract Documents.
1.2 Recurring Preliminary Costs incurred during the Execution of the Works

EA 0
1.2.1 Maintenance of all necessary offices and facilities for the Employer and the Engineer including all services, furniture, equipment and fixtures.
1.2.2 Maintenance of Contractor's site staff office, stores, and facilities. EA 0
1.2.3 Provision of Contractors site management, administrative and supervisory staff in adequate manner as per the Works needs. EA 0
1.2.4 Provision of all required equipment and tools for the successful execution of the Works such as but not limited to :
1.2.4.1 Light Equipment and tools EA 0
1.2.4.2 Scaffolding EA 0
1.2.4.3 Machinery, cranes, lifting plant, site transport. EA 0
1.2.4.4 Plant required for specific trades. EA 0
1.2.4.5 Maintenance of all above plant . EA 0
1.2.5 Provision of all necessary site power and lighting for the Works. EA 0
1.2.6 Provision of all necessary water for the Works. EA 0
1.2.7 Provision of all necessary sanitation for the Works. EA 0
Provision of safety and security requirements during progress of Works including watching, lighting, safety signs, fire fighting requirements, EA 0
1.2.8 first aid tools, safety shoes, protection helmets, safety belts and protection barriers/handrails, etc.

EA 0
1.2.9 Provide, erect and maintain of all necessary scaffolds, access ways, ladders and the like for the safe and successful completion of the Works.
1.2.10 Provision of all required progress site reports, photos, and other documentation as per the Conditions of the Contract. EA 0
1.2.11 Provision of all required shop drawings and samples as specified and required by the Engineer. EA 0
1.2.12 Provision of all required Quality Assurance and Quality Control as required by the Contract. EA 0
Provision for all inspections and testing necessary for the acceptance of the Works in accordance with the Specifications and the Conditions EA 0
1.2.13 of the Contract.
1.2.14 Maintaining site hoarding and sign boards. EA 0
1.2.15 Cleaning up and removal of rubbish during the progress of the Works to the satisfaction of the Engineer. EA 0
1.2.16 The programme shall be updated each month to reflect actual progress at site EA 0
1.2.17 Provision for reservation parking during execution of the project and paying DOT related charges/fees EA 0
Allow for all obligations in accordance with the Contract, which are not mentioned above. The Contractor shall detail and price below any EA 0
1.2.18 other obligations indicating the relevant clause reference in the Contract Documents.
1.3 Non-Recurring Preliminary Costs (Demobilization) incurred at the Completion of the Works
Demobilization and removal of all offices and facilities for the Employer and the Engineer including all services, furniture, equipment and EA 0
1.3.1 fixtures.
1.3.2 Demobilization and removal of all offices, stores and facilities. EA 0
1.3.3 Demobilization and removal of all equipment and tools. EA 0
1.3.4 Provision of all required As Built drawings, Operation and Maintenance Manuals and guarantees. EA 0
Clearing up and making good site establishment after completion of the Works and demobilization. This includes re-instating surrounding EA 0
1.3.5 areas affected by the construction works.
Allow for all obligations in accordance with the Contract, which are not mentioned above. The Contractor shall detail and price below any EA 0
1.3.6 other obligations indicating the relevant clause reference in the Contract Documents.
2 SITE CONSTRUCTION
2.1 Soil investigation

Geotechnical investigations/ Allow for drilling 8 Nos. of boreholes, Nos. 4 to a depth of 50m , and Nos. 4 to a depth of 40m each with at least EA 0
2.1.1 two meters in the rock strata and submitting a complete soil investigation report by an approved and ADCE registered and specialized firm.
2.1.2 Geophysical investigation/Allow for performing geophysical investigations as per relevant authorities requirements, rules and regulations. EA 0
Fixed total amount of AED 62,900.00 to be paid by the awarded contractor related to 3rd party verification and approval fees during design EA 0
2.1.3 stage.
2.2 Dewatering

Allow for design ,installing, maintaining and taking away upon completion, dewatering system as designed by a specialist firm registered
with ADCE and approved by the consultant engineer and local authorities, to lower the water level at least one meter below bottom level of EA 0
foundations and to keep all excavations free from water from whatever source. And to keep the site in a safe and secure working conditions
2.2.1 all the time. And should never stop until a written approval from the consultant engineer
2.3 Site Clearance

EA 0
2.3.1 The Contractor shall allow for the removal from site of all rubbish and debris and any existing foundations prior to commencement of Works.
2.4 Existing Utilities
Allow for carefully relocating/shifting any existing utilities in work areas including hand excavating trial holes and all necessary earthwork
2.4.1 supports.
Where utilities are to remain in place provide adequate means of support and protection during excavation and shoring operations, pilling EA 0
2.4.2 works and construction stages.
2.5 Shoring
2.5.1 permanent shoring

Allow for secant piling shoring system with min. dia 800 mm to be used as permanent shoring, as designed by a specialist firm registered
with ADCE and approved by the consultant engineer and local authorities, constructed using sulfate resistant Portland cement or as EA 0
recommended by soil investigation report and having a minimum 28-day compressive strength of 45 N/Sq.mm as per drawings and
2.5.1.1 specification . Steel reinforcement shall be provided as per drawings and specifications.

The cost includes submittal of structural design calculations and shop drawings, obtaining approval from Municipality,
mobilization/demobilization, guide wall, primary/secondary piles, chipping off piles heads, capping beam, bracing piping system, dismantling LM 0
2.5.1.2 and disposing off when suitable, side anchors, distressing when suitable. 147
2.6 Excavation
2.6.1 Excavate to reduce levels to the required levels shown on drawings for any type of foundations ... 17767 MTQ 0
2.7 Disposal
2.7.1 Remove surplus excavated material from site 17767 MTQ 0
2.8 ANTI-TERMITE TREATMENT
2.8.1 Allow for anti-termite treatment to all below and above ground levels as specified. 3229 MTK 0
2.9 Piling
Execute and install cast in situ reinforced Concrete Piles using temporary casing system as designed by a specialist firm registered with
2.9.1 ADCE and approved by the consultant engineer and local authorities, and per drawings and specification.
2.9.2 The Contractor shall be responsible for the adequacy of the pile foundations installed to carry the working loads safely and securely.
The Contractor shall be responsible to calculate the depth of piles based on the geotechnical report and to the consultant’s engineer and
2.9.3 Municipality Engineer's approval.
2.9.4 Mobilization and of plant and equipment to site. EA 0
Cast in situ piles including concrete of 50 N/sq.mm. boring through any type of soil, reinforcement cages and removal of surplus material
2.9.5 arising off site.
2.9.5.1 P1- 750 mm dia. pile, minimum capacity as per Drawings. 10 NIU 0
2.9.5.2 P2- 900 mm dia. pile, minimum capacity as per Drawings. 68 NIU 0
2.9.6 Pile Testing
2.9.6.1 Allow for load testing on piles in accordance with the specification.
2.9.6.1.1 Static Load Testing
2.9.6.1.1.1 P1 of 750 mm dia. 1 NIU 0
2.9.6.1.1.2 P2 of 900 mm dia. 1 NIU 0
2.9.6.1.2 Dynamic Load Testing
2.9.6.1.2.1 P1 of 750 mm dia. 1 NIU 0
2.9.6.1.2.2 P2 of 900 mm dia. 1 NIU 0
2.9.6.1.3 Allow for integrity test for all piles
2.9.6.1.3.1 P1 of 750 mm dia. 10 NIU 0
2.9.6.1.3.2 P2 of 900 mm dia. 68 NIU 0
2.9.6.2 Allow for chipping off the extra concrete from piles to the required height retaining the steel reinforcement using an approved method.
2.9.6.2.1 P1 of 750 mm dia. 10 NIU 0
2.9.6.2.2 P2 of 900 mm dia. 68 NIU 0
2.9.6.3 demobilization of plant and equipment from site on completion. EA 0
2.11 PAVING
Ditto but for Gate Barrier Supply and fix heavy-duty Gate barrier with extruded aluminum arms white enameled with red light-reflecting
stripes and controlled by ANPR camera technology and provided with a safety magnetic loop detector and "No Entry & Stop" Sign where
2.11.1 appropriate.
2.11.1.1 Gate Barrier at Ground Floor Entrance 2 NIU 0
2.11.2 Interlock paving to Ground Floor 392 MTK 0
2.11.3 Supply and paint Precast curbstone as per municipality and roads dept. 128 LM 0
2.11.4 Road/traffic markings as specified and as per municipality and roads dept. EA 0
2.11.5 Sundries
2.11.5.1 Allow for any other miscellaneous work in connection with site construction. EA 0
3 CONCRETE WORKS
3.1 FINISHING OF EXPOSED SURFACES OF SECANT PILES
Prepare and apply 100 mm thick shotcrete in accordance with the Specification including all necessary reinforcements and thickening as MTK 0
3.1.1 required to absorb the irregularities and alignment of substructure surfaces. 1916
3.2 SUBSTRUCTURE
3.2.1 Concrete work in accordance with specification
3.2.1.1 Plain Concrete
3.2.1.1.1 Plain concrete using Moderate sulphate resistant cement in accordance with specifications and drawings.
3.2.1.1.1.1 100 mm thick, blinding concrete 133 MTQ 0
3.2.1.2 Reinforced Concrete
Reinforced concrete for sub-structure, grade and strength of concrete as per structure drawing and specification all includes, formwork,
3.2.1.2.1 Reinforcement grade 460 N/mm2, Corrosion Inhibitor and all necessary works. The design mix to be approved by the Engineer.
3.2.1.2.1.1 Pile Cap 334 MTQ 0
3.2.1.2.1.2 Raft Slab 668 MTQ 0
3.2.1.2.1.3 Retaining Wall 552 MTQ 0
3.2.1.2.1.4 Columns 101 MTQ 0
3.2.1.2.1.5 Walls, Water Tank and Core Walls 383 MTQ 0
3.2.1.2.1.6 Beams 47 MTQ 0
3.2.1.2.1.7 Slab of any Thickness 1077 MTQ 0
3.2.1.2.1.8 Staircase and landing 26 MTQ 0
3.2.1.2.1.9 Ramp Slab 153 MTQ 0
3.2.1.2.2 Sundries
3.2.1.2.2.1 Allow for crystalline waterproofing add mixture to water tank base slab and wall. EA 0
3.2.1.3 Substructure Waterproofing
3.2.1.3.1 One layer of polythene sheets laid on compacted fill, 1200 gauge 1325 MTK 0
3.2.1.3.2 Pile head treatment using waterproofing membrane 20mm thickness epoxy mortar.
3.2.1.3.2.1 To pile, 750mm dia. 10 NIU 0
3.2.1.3.2.2 To pile, 900mm dia. 68 NIU 0
One layer of synthetic membrane made of plasticized PVC 2mm thickness including non-woven Geotextile for concrete faces in contact with
3.2.1.3.3 soil.
3.2.1.3.3.1 Geotextile 370g/m2 Laid horizontally 1276 MTK 0
3.2.1.3.3.2 Geotextile 370g/m2 Laid vertically 2254 MTK 0
3.2.1.3.3.3 PVC membrane Laid horizontally 1276 MTK 0
3.2.1.3.3.4 PVC membrane Laid vertically 2254 MTK 0
3.2.1.3.3.5 50 mm Cement Sand screed in accordance with specification and drawings
3.2.1.3.3.5.1 Above the foundation waterproofing 1276 MTK 0
3.2.1.4 Water Tank Lining
Supply and fix in place GRP Lining for all inner surfaces of water tank including the water tank ceiling and neck as specified. The Contractor MTK 0
3.2.1.4.1 should furnish certificate supporting that the materials used are suitable for potable water usage. 274
3.2.1.4.2 10 x 10 mm Angle fillet non-toxic elastic mortar. 50 LM 0
3.2.1.4.3 GRP Ladder to Fire Water Tank & Domestic Water Tank. 2 NIU 0
3.3 SUPERSTRUCTURE
3.3.1 Concrete work in accordance with specification
Reinforced concrete for super-structure grade ad strength of concrete as per drawings and specification all includes formwork, Reinforcement
3.3.1.1 grade 460 N/mm2 and all necessary works. The design mix to be approved by the Engineer
3.3.1.1.1 Columns & Planted Columns 162 MTQ 0
3.3.1.1.2 Walls, Core walls and Plinth Walls 443 MTQ 0
3.3.1.1.3 Beams 87 MTQ 0
3.3.1.1.4 Slabs of any thickness and grade 1858 MTQ 0
3.3.1.1.5 Staircase and landing 48 MTQ 0
3.3.1.1.6 Step and ramp 7 MTQ 0
3.3.1.1.7 Parapet 4 MTQ 0
3.3.1.1.8 Sundries
Allow for all joints including isolation, control, construction and contraction joints or the like as required all in accordance with the drawings EA 0
3.3.1.1.8.1 and specification excluding expansion joints.
3.3.1.1.8.2 Concrete for Roof equipment / Tanks foundation, complete item as per drawing and details 18 MTQ 0
3.3.1.1.8.3 Precast Concrete cover for OTS Cover 23 MTK 0
4 MASONRY
Precast concrete blocks laid with cement sand mortar including all necessary fixings and accessories, complete; in accordance with
4.1 Specifications and drawings
4.2 Hollow Blocks - Internal Wall
4.2.1 100 mm thick, hollow block walls 2724 MTK 0
4.2.2 150 mm thick, hollow block walls 70 MTK 0
4.2.3 200 mm thick, hollow block walls 2886 MTK 0
4.2.4 250 mm thick , hollow block walls 81 MTK 0
4.2.5 300 mm thick, hollow block walls 271 MTK 0
4.2.6 400 mm thick, hollow block walls 126 MTK 0
4.3 Insulated Blocks - External Wall
4.3.1 100 mm thick block walls 53 MTK 0
4.3.2 200 mm thick block walls 1570 MTK 0
4.3.3 250 mm thick block walls 16 MTK 0
4.3.4 300 mm thick block walls 116 MTK 0
4.3.5 400 mm thick block walls 4 MTK 0
4.4 Cavity Walls
4.4.1 100 mm hollow block wall + Gap + 100 mm hollow block wall 253 MTK 0
4.4.2 100 mm hollow block wall + Gap + 150 mm hollow block wall 4 MTK 0
4.4.3 100 mm hollow block wall + Gap + 200 mm hollow block wall 146 MTK 0
4.4.4 150 mm hollow block wall + Gap + 150 mm hollow block wall 5 MTK 0
4.4.5 200 mm hollow block wall + Gap + 200 mm hollow block wall 30 MTK 0
4.5 Lintels including concrete, reinforcement, shuttering all in accordance to drawings and specifications.
4.5.1 Size 200 x 200 mm 167 LM 0
4.5.2 Size 200 x 300 mm 185 LM 0
4.6 Sundries
4.6.1 Allow for joint filling sealant two part polysulphide sealant. EA 0
4.6.2 Allow for isolation and expansion joint as required by a compressed sheet of wood fiber impregnated with bitumen emulsion. EA 0
5 METALWORKS
5.1 Non-Structural Metalwork
5.1.2 Balustrades and Handrails
5.1.2.1 Powder coated Aluminum handrail for staircases, fixed to steps complete as per drawings. Qurtuba 167 LM #VALUE!
5.1.2.2 Powder coated Aluminum handrail for staircases, wall mounted complete as per drawings. Qurtuba 154 LM #VALUE!
5.1.3 Ladders
Supply and fix Die Cast Aluminum Cat ladder including all necessary fixing accessories; all accordance with the drawings and Specification NIU #VALUE!
5.1.3.1 to Roof Qurtuba 1
5.1.4 Louvers
5.1.4.1 Supply and fix Aluminum Louver Wall including all necessary fixing accessories; all accordance with the drawings to Ground Floor Qurtuba 404 MTK #VALUE!
5.1.4.2 Allow for Aluminum Louver door as access to Roof Qurtuba 3 NIU #VALUE!
5.1.4.3 Supply and install Acoustic louver as shown in the Drawings Qurtuba 12 MTK #VALUE!
5.1.5 Aluminum Cladding
Supply and fix fire rated aluminum composite panel all complete including frames, rockwool insulation and all necessary fixing accessories; MTK #VALUE!
5.1.5.1 all in accordance with the drawings, civil specifications, and ADCD requirements. Qurtuba 2423
Allow for steel support to box aluminum cladding all complete including necessary fixing accessories as per drawings. (Aluminum cladding NIU #VALUE!
5.1.5.2 measured separately) Qurtuba 146
5.1.5.3 Other Items
5.1.5.3.1 Supply and install Fresh air intake sand trap louver as shown in the Drawings Qurtuba 14 MTK #VALUE!
5.1.6 Balcony Railing
5.1.6.1 Supply and fix aluminum balcony railing all complete including all necessary finish and fixings as per drawings. Qurtuba 109 LM #VALUE!
5.1.7 Metal Grating
5.1.7.1 400 mm wide floor drain grating and angle frame for parking ramps Qurtuba 27 LM #VALUE!
5.1.7.2 Sundries
5.1.7.2.1 Access panel and hatches including fittings, fixing accessories etc.. Complete as per drawings and specifications. Qurtuba EA #VALUE!
Provide and fix in the main entrance lobby, a 60x40x.02 cm stainless steel signage plate to declare the Building Name, Building No. and NIU 0
5.1.7.2.2 ADCP the property manager. 1
6 WOOD AND PLASTICS
6.1 KITCHEN CABINETS
Kitchen Cabinet: Supply and fix 18mm thick MDF with Laminate and PVC edge Kitchen cabinet includes frames, fixing, painting,
6.1.1 ironmongery etc.. all complete in accordance with the drawings and Specification.
6.1.1.1 K01
6.1.1.1.1 For upper cabinet in 350 mm depth 3 LM 0
6.1.1.1.2 For lower cabinet in 600 mm depth 3 LM 0
6.1.1.1.3 Kitchen Counter Tops - Gray sardo 3 LM 0
6.1.1.1.4 Kitchen Counter Backsplash - 70mm high Gray sardo 3 LM 0
6.1.1.2 K02
6.1.1.2.1 For upper cabinet in 350 mm depth 89 LM 0
6.1.1.2.2 For lower cabinet in 600 mm depth 51 LM 0
6.1.1.2.3 Kitchen Counter Tops - Gray sardo 88 LM 0
6.1.1.2.4 Kitchen Counter Backsplash - 70mm high Gray sardo 51 LM 0
6.1.1.2.5 Kitchen Counter Top under wall - 900 mm high Gray sardo 36 LM 0
6.1.1.3 K03
6.1.1.3.1 For upper cabinet in 350 mm depth 48 LM 0
6.1.1.3.2 For lower cabinet in 600 mm depth 37 LM 0
6.1.1.3.3 Kitchen Counter Tops - Gray sardo 90 LM 0
6.1.1.3.4 Kitchen Counter Backsplash - 70mm high Gray sardo 37 LM 0
6.1.1.3.5 Kitchen Counter Top under wall - 900 mm high Gray sardo 65 LM 0
6.1.1.4 K04
6.1.1.4.1 For upper cabinet in 350 mm depth 76 LM 0
6.1.1.4.2 For lower cabinet in 600 mm depth 53 LM 0
6.1.1.4.3 Kitchen Counter Tops - Gray sardo 53 LM 0
6.1.1.4.4 Kitchen Counter Backsplash - 70mm high Gray sardo 53 LM 0
6.1.1.5 K05
6.1.1.5.1 For upper cabinet in 350 mm depth 9 LM 0
6.1.1.5.2 For lower cabinet in 600 mm depth 6 LM 0
6.1.1.5.3 Kitchen Counter Tops - Gray sardo 15 LM 0
6.1.1.5.4 Kitchen Counter Backsplash - 70mm high polished granite 6 LM 0
6.1.1.5.5 Kitchen Counter Top under wall - 900 mm high Gray sardo 8 LM 0
6.2 BUILT-IN WARDROBES
6.2.1 Supply and fix in place factory made wardrobes including ironmongeries, as specified.
6.2.2 Wooden Cupboard 01 18 NIU 0
6.2.3 Wooden Cupboard 02 20 NIU 0
6.2.4 Wooden Cupboard 03 14 NIU 0
6.2.5 Wooden Cupboard 04 2 NIU 0
6.3 CABINETS
Supply and fix 18mm thick MDF with Laminate and PVC edge 1100mm depth washing machine cabinet includes frames, fixing, painting, NIU 0
6.3.1 ironmongery etc.. all complete in accordance with the drawings and Specification. 18
6.3.2 Supply and fix of Water meter cabinet all complete as per drawings and specifications 11 NIU 0
6.5 COUNTERS
6.5.1 Fabricate and fix counter at main entrance as per drawings. EA 0
6.6 BUILDING SIGNAGE
Supply and installation of External and Internal Building Signage including all signage accessories and fixing accessories all accordance with
6.6.1 the signage drawings.
6.6.1.1 S1-02 26 NIU 0
6.6.1.2 S1-03 33 NIU 0
6.6.1.3 S2-02 23 NIU 0
6.6.1.4 S2-03 33 NIU 0
6.6.1.5 S3-01 57 NIU 0
6.6.1.6 S3-03 18 NIU 0
6.6.1.7 S3-04 3 NIU 0
6.6.1.8 S3-05 36 NIU 0
6.6.1.9 S3-06 48 NIU 0
6.6.1.10 S3-07 1 NIU 0
6.6.1.11 S3-08 4 NIU 0
6.6.1.12 S3-10 24 NIU 0
6.6.1.13 S3-14 20 NIU 0
6.6.1.14 S3-15 21 NIU 0
6.6.1.15 S3-22 4 NIU 0
6.6.1.16 S4-01 1 NIU 0
6.6.1.17 S4-02 21 NIU 0
7 THERMAL AND MOISTURE PROTECTION
7.1 ROOFING SYSTEM
7.1.1 Roof waterproofing system as per drawing including Cement tile finish. 1097 MTK 0
7.2 WET AREAS
7.2.1 Two Coats of Flexible, One Component , Polyurethane, Liquid Applied, elastomeric waterproofing coating
7.2.2 Laid horizontally (Toilet, Bath, Kitchen, & Balcony) 953 MTK 0
7.2.3 250mm Laid vertically (including wall behind bathtubs and full height on shower side) 328 MTK 0
7.2.4 50 mm Cement Sand screed in accordance with specification and drawings above the waterproofing of wet areas 953 MTK 0
7.3 Waterproof for Exposed Ground Floor Slab
7.3.1 One layer of synthetic membrane made of plasticized PVC 1.5mm thickness including non-woven Geotextile
7.3.2 Geotextile 370g/m2 Laid horizontally including ramp 423 MTK 0
7.3.3 PVC membrane Laid horizontally 423 MTK 0
7.4 THERMAL & MOISTURE INSULATION OF SURFACES BEHIND EXTERNAL CLADDING
7.4.1 Supply and fix on concrete and/or block work behind external cladding, vapor barrier paint. EA 0
7.5 Fire Stopping
7.5.1 Fire stopping inside ducts, dampers and cable trays. EA 0
7.5.2 Voids between fire rated floor slabs and exterior curtain walls and openings Through Floors and Walls. EA 0
7.5.3 SUNDRIES:

EA 0
7.5.3.1 Provide Expansion joint cover all complete from floor to floor, floor to wall and corner wall as necessary as per drawing and specification..
7.5.3.2 Dress roof finishes around Mechanical Equipment footing. EA 0
8 DOORS AND WINDOWS
The rates for all doors shall include plywood sub-frame, architrave, transoms, stops, glazing, decorations, ironmongery, thresholds, civil
8.1 defense approval for fire rated doors … etc all in accordance with drawings and specification.
Wooden Doors: Supply and 50mm thickness timber flush doors fix flush wooden door with paint finish with frame including finishes, etc..
8.1.1 complete in accordance with the Drawing and Specification.
8.1.1.1 Single Leaf, hinged door, Size 1.10 x 2.35, Type DT01, 60min Fire Rated 48 NIU 0
8.1.1.2 Single Leaf, hinged door, Size 0.90 x 2.20, Type DT02 51 NIU 0
8.1.1.3 Single Leaf, hinged door, Size 0.90 x 2.20, Type DT03, 60min Fire Rated 4 NIU 0
8.1.1.4 Single Leaf, hinged door, Size 0.80 x 2.20, Type DT04 119 NIU 0
8.1.1.5 Single Leaf, hinged door, Size 1.00 x 2.20, Type DT05 4 NIU 0
8.1.1.6 Single Leaf, hinged door, Size 0.90 x 2.20, Type DT06, 60min Fire Rated 6 NIU 0
Single Leaf, hinged door, Size 1.00 x 2.20, Type DT07 NIU 0
8.1.1.7 60min Fire Rated 13
Single Leaf, hinged door, Size 1.10 x 2.20, Type DT08 NIU 0
8.1.1.8 60min Fire Rated 15
Double Leaf, hinged door, Size 1.60 x 2.20, Type DT09 NIU 0
8.1.1.9 60min Fire Rated 10
Double Leaf, hinged door, Size 1.00 x 2.20, Type DT10 NIU 0
8.1.1.10 60min Fire Rated 1
Single Leaf, hinged door, Size 0.70 x 2.20, Type DT11 NIU 0
8.1.1.11 60min Fire Rated 3
8.1.1.12 Double Leaf, hinged door, Size 1.80 x 2.2, Type DT12 48 NIU 0
Steel Doors: Supply and fix of Steel doors, including finishes, ironmongery, etc.... complete in accordance with the Drawing and
8.1.2 Specification.
8.1.2.1 Single Leaf, hinged door, Size 1.10 x 2.20, Type DS01, 90min Fire Rated 15 NIU 0
8.1.2.2 Single Leaf, hinged door, Size 0.90 x 2.20, Type DS02, 90min Fire Rated 9 NIU 0
8.1.2.3 Double Leaf, hinged door, Size 1.60 x 2.50, Type DS03, 90min Fire Rated 4 NIU 0
8.1.2.4 Single Leaf, hinged door, Size 1.00 x 1.90, Type DS04 1 NIU 0
8.1.3 Aluminum Doors: Supply and fix Aluminum Doors including Ironmongery complete in accordance with the Drawings and Specifications.
8.1.3.1 Double Leaf, hinged door, Size 2.50 x 3.50, Type DA01 1 NIU 0
8.1.3.2 Double Leaf, hinged door, Size 2.50 x 3.00, Type DA02 2 NIU 0
8.1.3.3 Double Leaf, hinged door, Size 2.50 x 2.20, Type DA04 1 NIU 0
8.2 Glass Partition
8.2.1 Supply and fix Tempered Glass Partition to Bathrooms including all necessary fixing and accessories all accordance with the drawings.
8.2.2 2100mm height Glass Partition 102 LM 0
Curtain Wall: Supply and fix Glazing Panels all complete including insulation and all necessary fixing accessories; all accordance with the
8.3 drawings and Specification. (Curtain Wall size As Per Curtain Wall Details)
8.3.1 Curtain Wall 2295 MTK 0
8.4 Glass Balustrade
8.4.1 1.20 m high glass parpet wall to Roof 122 LM 0
9 FINISHES
9.1 I- INTERNAL FINISHES
9.1.1 Flooring
9.1.1.1 Cement and sand screed to floor to receive finishes
9.1.1.1.1 50mm thick to receive Paint 886 MTK 0
9.1.1.1.2 100mm thick under Wardrobe 87 MTK 0

9.1.1.2 Supply and fix Stone Tile thickness, pattern and types shown on the drawings all complete in accordance with drawings and specifications.
9.1.1.2.1 F06 - 600x1200 mm Pianco Laza Marble Floor Tile (Entrance Lobby, Ground Floor Lift Lobby, Lobby, Entrance Approach) 97 MTK 0
9.1.1.2.2 Supply and fix Porcelain tiles as per finishing schedule including leveling screed, mortar bedding and grout, etc… to Engineer's Approval.
F01 600x600mm Full body rectified porcelain floor tiles. (Basement Lift Lobby, Typical Lift Lobby, Retail, Retail Entrance, Guard Room, MTK 0
9.1.1.2.3 Office, Living and Dining Room, Flat Corridor, Bedroom, Dressing, Store). 2564
9.1.1.2.4 F02 600x600mm Non Slip full body rectified porcelain floor tiles (Kitchen/Pantry). 1835 MTK 0
9.1.1.2.5 F02a 300x300mm Non-slip full body rectified porcelain tiles (Bathroom, Toilet and Washrooms). 458 MTK 0
9.1.1.3 Supply and fix Ceramic tiles as per finishing schedule including leveling screed, mortar bedding and grout, etc… to Engineer's Approval.
9.1.1.3.1 F05 300x300 Semi Glazed flooring Ceramic (Garbage Room). 26 MTK 0
Paint Flooring - Prepare, supply and apply Epoxy Coating finish on screed (screed measured separately) all complete in accordance with
9.1.1.4 drawings and specifications.
9.1.1.4.1 F03 - For Stairs and Service Corridors 476 MTK 0
F04 - For Service Areas (HV Room, Transformer Room, Control Room, ECC Room, Gas Room, Electrical Room, Tel Room, Generator MTK 0
9.1.1.4.2 Room, and Etc..) 325
9.1.1.4.3 F07 - For Service Areas on Basement Floors (Pump Room, Electrical Room, Tel Room) 85 MTK 0

F08 - Traffic Deck Coating System consists of Abrasion resistant Epoxy resin floor coating skid resistant with non slip aggregates, multi layer
flexible polyurethane resin based coating reinforced with glass flake epoxy as shown on the drawing and finishing schedule and approved by
9.1.1.4.4 Engineer
9.1.1.4.4.1 Parking Bays 1162 MTK 0
9.1.1.4.4.2 Drive way 1240 MTK 0
9.1.1.4.4.3 Ramps 496 MTK 0
9.1.1.4.4.4 Walk Way / Platform 330 MTK 0
9.1.2 SKIRTING
S01 80mm high Porcelain Tiles (Foyer, Flat Corridor, Living/Dining Room, Bedroom, Dressing Room, Maid's Room, Janitor's Room, LM 0
9.1.2.1 Storage) 2061
9.1.2.2 S02 Epoxy Paint to Staircase 12 LM 0
9.1.2.3 S03 Epoxy Coating System (Fire Lift Lobby and other Service Areas) 387 LM 0
9.1.2.4 THRESHOLD
9.1.2.5 30mm thk Marble Threshold Width as per drawings. 428 LM 0
9.1.3 WALL FINISHES
9.1.3.1 Cement sand plaster 20 mm thick for walls.
9.1.3.1.1 To concrete, block walls to receive paint. 11744.605445 MTK 0
9.1.3.1.2 To concrete, block walls to receive porcelain and ceramic tiles 4709 MTK 0

9.1.3.2 Supply and fix Stone Tile thickness, pattern and types shown on the drawings all complete in accordance with drawings and specifications.

MTK 0
9.1.3.2.1 W06 Statuario Marble Wall Tiles (Entrance Lobby, Reception, Ground Floor Lift Lobby, and Ground Floor Lobby and Mezzanine Corridor). 278
9.1.3.3 Supply and fix Porcelain tiles as per finishing schedule including all necessary fixing to Engineer's Approval. MTK 0
9.1.3.3.1 W02 600x300mm Full body Porcelain wall tiles (Kitchen/Pantry). 1177 MTK 0
9.1.3.3.2 W02a 300x200mm Full body Porcelain Wall Tiles (Bathroom, Toilet and Washroom). 2132 MTK 0
9.1.3.3.3 W07 600x1200mm Full Body Porcelain Wall Tile to Basement, Mezzanine and Typical Lift Lobby. 1264 MTK 0
9.1.3.4 Supply and fix Ceramic tiles as per finishing schedule including all necessary fixing to Engineer's Approval.
9.1.3.4.1 W05 300x300mm Ceramic wall tiles (Garbage Room). 136 MTK 0
9.1.3.5 Painting and Decoration
9.1.3.5.1 Prepare, supply and apply Paint finish to wall all complete in accordance with drawings and specifications.
9.1.3.5.1.1 W01 Acrylic Emulsion Paint (Retail, Guard's Room, Office, Living and Dinning, Flat Corridor, Bedroom, Dressing and Store). 6291 MTK 0
9.1.3.5.1.2 W03 Acrylic smooth flexible satin paint (Stairs and Service Corridor) 1458 MTK 0
9.1.3.5.1.3 W04 Semi Epoxy Textured Coating (Service Areas) 1349 MTK 0
9.1.3.5.1.4 W08 Anti Carbonation Paint (Basement Walls) 2695 MTK 0
9.1.4 Ceiling Finishes
9.1.4.1 Cement sand plaster 15 mm thick for ceiling.
9.1.4.1.1 Soffits to received paint 2816 MTK 0
9.1.4.2 Painting and Decoration
Prepare, supply and apply Paint finish on plastered ceiling / gypsum board ceiling (plaster & Gypsum board measured separately) all
9.1.4.2.1 complete in accordance with drawings and specifications.
9.1.4.2.1.1 C02 Washable Emulsion Paint for plaster ceiling 1910 MTK 0
9.1.4.2.1.2 C07 Paint on Alkali Resistant Primer (Service Rooms/Area and Stairs) 906 MTK 0
9.1.4.2.1.3 C08 Anti Carbonation Paint on fair faced concrete at Basement 3172 MTK 0
9.1.4.2.1.4 Washable Emulsion Paint for Gypsum Board Ceiling as per specification and drawing to Engineer's Approval 2211 MTK 0

Anti fungus paint for wall above false ceiling, ceiling and lift core wall consists of One coat of primer based on special high quality, alkali
resistant acrylic binder + Two Separate coats superior quality, special acrylic based black emulsion paint with crack tolerance to fungal MTK 0
9.1.4.2.1.5 growth as approved by the Engineer 6626
9.1.4.3 False ceilings
Supply and fix Ceiling finish, pattern and types as per details includes grooves etc.. All complete in accordance with drawings and
9.1.4.3.1 specifications.
C01 Gypsum Plaster Board to receive Paint Finish (paint measured separately) to Entrance Lobby, Lift Lobby (Basements, Ground Floor and MTK 0
9.1.4.3.1.1 Typical Floor), Entrance Approach, Retail Entrance, Living/Dining, Flat Corridor, Bedroom, Dressing and Store. 1159
9.1.4.3.1.2 C03 600x600 Aluminum Tile Ceiling to Toilet, Bathroom, Kitchen, Pantry and Guard's Room 451 MTK 0
9.1.4.3.1.3 C03 Moisture Resistant Gypsum Board to Toilet, Bathroom, Kitchen, Pantry and Guard's Room 502 MTK 0
9.1.4.3.1.4 C04 600x600 Gypsum Tile Ceiling to Retail and Office 647 MTK 0
9.1.4.3.1.5 C04 Gypsum Board Ceiling to Retail and Office 288 MTK 0
9.1.4.3.1.6 C05 600x1200 Gypsum Tile Ceiling to Corridors 277 MTK 0
9.1.4.3.1.7 C06 Gypsum Board Ceiling to Ground Floor Cooridor 17 MTK 0
9.1.4.3.1.8 C10 Cement Fiber Board 18 MTK 0
9.1.4.3.1.9 Allow for Gypsum Bulkhead to Basement Lift Lobby (paint measured separately) 91 LM 0
9.1.4.3.1.9.1 Ditto to Ground Floor Lift Lobby (paint measured separately) 129 LM 0
9.1.4.3.1.9.2 Ditto to Residential inside Flat 270 LM 0
9.1.4.3.1.10 Allow for Cement fiber board Bulk head to Ground floor 17 LM 0
9.2 II- EXTERNAL FINISHES
9.2.1 Floors
9.2.1.1 Granite Steps to Ground Floor Pedestrian Ramp and Entrance approach 35 MTK 0
9.2.1.2 Granite Steps to Entrance 13 LM 0
9.2.1.3 Interlock paving to Ground Floor 392 MTK 0
9.2.2 Walls
9.2.2.1 20mm thick plaster to concrete, block walls and walls for External Wall and OTS to received paint 622 MTK 0
9.2.2.2 Paint for External Walls 622 MTK 0
9.3 Vanity Counter Top

9.3.1 Supply and fix Pianco Laza Countertop complete with all necessary fixing accessories; all accordance with the drawings and specification
9.3.1.1 250mm wide Vanity Counter Top including 280mm high Facia to Bathrooms and Toilets 82 LM 0
9.3.1.2 250mm Cistern Counter Top To Bathrooms 73 LM 0
9.3.2 III- SUNDRIES
9.3.2.1 CAR PARKING
9.3.2.2 Columns protection. 48 NIU 0
9.3.2.3 Walls protection. EA 0
9.3.2.4 Ready made rubber speed humps. EA 0
9.3.2.5 Pre-cast wheel stopper length as per drawings 63 NIU 0
9.3.2.6 Concaved traffic mirrors 9 NIU 0
10 PLUMBING AND DRAINAGE
10.1 WATER SUPPLY SYSTEM
Supply, install, testing and commissioning of all cold water piping complete with support and all necessary fittings, valves and accessories;
10.1.1 all in accordance with drawings and specification
Complete internal concealed piping in Poly Propylene Random pipes for cold water supply with all necessary fittings, supports and
10.1.1.1 accessories. Rates shall include all flushing, cleaning, testing and commissioning. For Outer Diameter:
10.1.1.1.1 20Ø LM 0
10.1.1.1.2 25Ø LM 0
10.1.1.1.3 32Ø LM 0
10.1.1.1.4 40Ø LM 0
10.1.1.1.5 50Ø LM 0
10.1.1.1.6 63Ø LM 0
10.1.1.1.7 75Ø LM 0
10.1.1.1.8 90Ø LM 0

Complete water supply filling lines, transfer pipes, overflow pipes, boosted water riser and gravity riser piping with UPVC pressure pipes,
suitable for system working pressure, with all necessary fittings, supports and accessories as specified and shown on drawings. Rates shall
10.1.1.2 include all flushing, cleaning, testing and commissioning. For Outer Diameter:
10.1.1.2.1 20Ø LM 0
10.1.1.2.2 25Ø LM 0
10.1.1.2.3 32Ø LM 0
10.1.1.2.4 40Ø LM 0
10.1.1.2.5 50Ø LM 0
10.1.1.2.6 63Ø LM 0
10.1.1.2.7 75Ø LM 0
10.1.1.2.8 90Ø LM 0
10.1.1.2.9 110Ø LM 0
10.1.1.2.10 All exposed Pipes on roof, plant rooms and basement shall be insulated and protected with cladding as specified LM 0
10.1.1.3 PEX pipes complete with sleeves for all cold water droppers from above false ceiling to the fixtures LM 0

Supply, install, testing and commissioning of all hot water piping Stabilized PPR, PN-20 complete with insulation, supports and all necessary
fittings, valves and accessories; all in accordance with drawings and specification. Rates shall include all flushing, cleaning, testing and
10.1.2 commissioning. For Outer Diameter:
10.1.2.1 20Ø
10.1.2.2 25Ø LM 0
10.1.2.3 Hot water pipe insulation as specified complete with vapour barrier
10.1.2.4 PEX pipes complete with sleeves for all hot water droppers from above false ceiling to the fixtures LM 0

Complete external piping connections, from ADDC Main to underground water tank, including all Meters, cabinets, accessories and valves,
as specified, and required by ADDC and to the approval of the Engineer. Rates shall include all flushing, cleaning, testing and EA 0
10.1.3 commissioning as specified.
10.1.4 Each bathroom, toilet and kitchen shall have Chromium plated, Concealed main isolating valve for ease of maintenance. NIU 0
10.1.5 Each Sanitary ware shall have Chromium plated, isolating valve for ease of maintenance. Valves shall be same as fitting's mixers type. NIU 0
10.1.6 Water Tanks:

Supply, installation, testing and commissioning of Water tanks; GRP panel type; including associated tank ancillaries, insulation, vent pipes
level switches, heavy duty cover, float valves, GRP ladder, concrete base, fittings, supports and all necessary accessories and connections;
10.1.6.1 complete all in accordance with the drawings, specifications and as per ADDC regulations.
10.1.6.1.1 Raw water tank 18 MTQ 0
10.1.6.1.2 Filtered water tank 18 MTQ 0
10.1.6.1.3 Fiber glass pressure break tank for filter back wash 1 MTQ 0
All fittings and accessories for underground water tanks including vent float valves,associated pipe work etc.(Internal and External ladder
10.1.6.2 and Access door by civil contractor) as shown in the drawings,specifications and as per ADDC regulations.
10.1.6.2.1 Basement fire & domestic water tank 2 SET 0
10.1.7 Pumps:
Supply, install test and commission electrical water transfer pump set as specified, automatically operated, as shown and indicated on the SET 0
10.1.7.1 approved drawings, complete with its related valves, accessories, wiring and control panel. 1
Supply, install test and commission Booster pump set ;complete with all related valves, accessories, fittings wiring and control panel as SET 0
10.1.7.2 shown on the drawings and as per specifications. 1
Supply, install test and commission Circulation pump set ; complete with all related valves, accessories, fittings, wiring and control panel as SET 0
10.1.7.3 shown on the drawings and as per specifications. 1
Supply, install SS Submersible Pump for water cleaning. Complete with control panel, valves etc. as shown on the drawings and as per SET 0
10.1.7.4 specifications. 1
10.1.8 Filtration System:
Supply, install test and commission of central filtration system including sand filters/ multimedia filter complete with filtration pump set and SET 0
10.1.8.1 all associated valves, accessories, fittings, wiring and control panel as shown on the drawings and as per specifications. 1
10.1.8.2 Ultra Violet sterilizer with valves and aluminum protection cover. 2 SET 0
10.1.9 Water Meters:
Supply and install the following water meters with plus reader, electric wires, all necessary pipes, fitting, valves, etc. as specified and NIU 0
10.1.9.1 required by ADDC.
Allow for installation of main incomer water meter and all associated valves,chamber,cover, cabinet, accessories, controls and as required by SET 0
10.1.9.1.1 ADDC 1
10.1.9.1.2 Water Supply sub-metering and Associated Works
10.1.9.1.2.1 a) Associated valves, piping etc as Shown in the Drawings for ADDC Submeter.(Cabinet ref Arch Details and included in Civil Work). 54 SET 0
10.1.9.1.2.2 b) Supply and Installation of Sub-meters. 54 NIU 0
10.1.9.2 Allow for emergency water tanks filling line with associated cabinet, inlets, valves, fittings and accessories and as required by ADDC EA 0
10.1.10 Pressure Reducing Valve station:
10.1.10.1 Supply and install pressure reducing valves sizes and locations as specified and shown on the drawings. 3 SET 0
10.1.10.2 Ditto for garbage rooms washing line NIU 0
10.1.11 Bib tap for roof, garbage room, plant rooms and basement complete with isolating valves, back flow preventer, support and accessories EA 0
10.1.12 Valves
Concealed valves including fiitings, fixings and supports, all necessary accessories and connections; complete all in accordance with the
10.1.12.1 specifications
10.1.12.1.1 20Ø NIU 0
10.1.12.1.2 25Ø NIU 0
10.1.12.1.3 32Ø NIU 0
10.1.12.2 Main Isolating valves
10.1.12.2.1 32Ø NIU 0
10.1.12.2.2 40Ø NIU 0
10.1.12.2.3 50Ø NIU 0
10.1.12.2.4 63Ø NIU 0
10.1.12.2.5 75Ø NIU 0
10.1.12.2.6 90Ø NIU 0
10.1.12.2.7 110Ø NIU 0
10.1.12.3 Allow for Water hammer arrestor in every wet area NIU 0
10.1.12.4 Allow for Automatic air vents as shown on drawings, specification and where required for proper system operation NIU 0
10.1.12.5 Allow for flexible connectors NIU 0
10.1.12.6 Allow for pressure gauges as shown on drawings and as specified NIU 0
10.1.13 Electric Water heaters

supply, install test and commission ceiling mounted, horizontal type, electric water heater, sizes and locations as shown on drawings ,
complete with connections for fresh water supply and delivery lines to various sanitary fixtures. With all associated isolation, check, safety
10.1.13.1 and drain valves as specified
10.1.13.1.1 80 L Capacity 52 NIU 0
10.1.13.1.2 50 L Capacity 62 NIU 0
10.1.14 Supply, install complete irrigation system including fittings, supports, valves, accessories etc as per drawings and specification.
10.1.15 Allow for installation of sanitary fixtures and accessories. Angle Valve, flexible connections and installation
10.1.15.1 WC EA 0
10.1.15.2 Wash basin EA 0
10.1.15.3 Shower EA 0
10.1.15.4 Bath tub EA 0
10.1.15.5 Kitchen Sink EA 0
10.1.16 Allow for ADDC fees EA 0
10.1.17 Allow for all builders work in connection with the installation EA 0
10.1.18 Allow for providing all keys, tools, spares, parts and schematic EA 0
10.1.19 Allow for all necessary identifications EA 0
10.1.20 Allow for the preparation of all necessary installation drawings EA 0
10.1.21 Allow for the preparation of all necessary operations and maintenance manuals EA 0
10.1.22 Allow for testing and commissioning of all works EA 0
10.1.23 Allow for Emergency operation and maintenance contract for irrigation system during defect liability period EA 0
10.2 Drainage System:
10.2.1 Above ground Drainage pipework:
Supply, installation, testing and commissioning of Soil, waste and vent UPVC pipe work for above ground drainage with all associated
10.2.1.1 fittings, supports and accessories as shown on drawings, required by authorities and as specified
10.2.1.1.1 50Ø LM 0
10.2.1.1.2 80Ø LM 0
10.2.1.1.3 110Ø LM 0
10.2.1.1.4 160Ø LM 0
10.2.1.1.5 200Ø LM 0
10.2.1.2 Below ground drainage pipework:
Supply and install buried internal and external drainage pipework in uP.V.C pipes class 16 as specified and shown on the approved drainage
10.2.1.2.1 drawings.
10.2.1.2.1.1 80Ø LM 0
10.2.1.2.1.2 110Ø LM 0
10.2.1.2.1.3 160Ø LM 0
10.2.1.2.1.4 200Ø LM 0
10.2.3 Commercial Kitchens waste water pipework:
Supply, installation, testing and commissioning of grease waste water HDPE pipe work for with all associated fittings, supports and
10.2.3.1 accessories as shown on drawings, required by authorities and as specified
10.2.3.1.1 50Ø LM 0
10.2.3.1.2 80Ø LM 0
10.2.3.1.3 110Ø LM 0
10.2.3.1.4 160Ø LM 0
10.2.4 Storm water Drainage pipework:
Supply, installation, testing and commissioning of Rain water UPVC pipe work with all associated fittings, supports and accessories as
10.2.4.1 shown on drawings, required by authorities and as specified
10.2.4.1.1 80Ø LM 0
10.2.4.1.2 110Ø LM 0
10.2.4.1.3 200Ø LM 0
10.2.5 Condensate drain pipework:
Supply, installation, testing and commissioning of UPVC pipe work for condensate drainage with all associated insulation, fittings,
10.2.5.1 supports and accessories as shown on drawings, required by authorities and as specified
10.2.5.1.1 50Ø LM 0
Construct manholes with covers in specified sizes and depths including all excavations, Backfilling, disposal of surplus, bedding, benching, NIU 0
10.2.6 branching, water proofing, 200mm solid block as per drawing, reinforced concrete at the top level around the frame.
Cover and frame of the manholes shall be light duty, and with double seal for manholes subject to pedestrian traffic and heavy duty with GRP
10.2.6.1 seal for manholes subject to vehicular traffic.
10.2.7 Supply and install Rain water outlets as specified and to engineer/ architect approval 10 NIU 0
10.2.8 Supply and install Floor drain with covers as specified and to engineer/ architect approval NIU 0
10.2.9 Supply and install Catch basins with heavy duty grating and sediment bucket as specified and to engineer/ architect approval 12 NIU 0
10.2.10 Supply and install manholes with heavy duty grating and sediment bucket as specified and to engineer/ architect approval NIU 0
10.2.11 Supply and install Gulley trap with covers as specified, shown on drawings and required by authorities NIU 0
10.2.12 Supply and install Grating channel as specified and shown on the drawings. NIU 0
10.2.13 Supply and install balcony drain with cover as specified and to engineer/ architect approval NIU 0
10.2.14 Supply and install landscape drain points as specified and to engineer/ architect approval NIU 0
Supply and install Sand trap with covers and all related pipes, fittings and accessories as specified, shown on drawings and required by NIU 0
10.2.15 authorities 1
Supply and install oil interceptor with covers and all related pipes, fittings and accessories as specified, shown on drawings and required by NIU 0
10.2.16 authorities 1
Supply and install Grease interceptor with covers and all related pipes, fittings and accessories as specified, shown on drawings and required NIU 0
10.2.17 by authorities
Supply and install Pressure reducing manhole with covers and all related pipes, fittings and accessories as specified, shown on drawings and NIU 0
10.2.18 required by authorities 1
10.2.19 Supply and install Clean outs on every change of direction and as required NIU 0
10.2.20 Supply and install Velocity breakers on all drainage risers as specified NIU 0
10.2.21 Supply and install Waste water sump pit with cover, with all related civil works, water proofing, piping connections, and accessories NIU 0
10.2.23 Supply and install Vent Cowl as specified and shown on the drawings. NIU 0
10.2.24 Supply & Installation of Accoustic drainage pipes as shown in the Drawings and in accordance with the Specifications. NIU 0
10.2.25 Sump Pumps
Supply, install test and commission electrical storm water water sump pump set as specified, automatically operated, as shown and indicated SET 0
10.2.25.1 on the approved drawings, complete with its related valves, accessories, wiring and control panel. 1
10.2.26 Allow for ADSSC fees EA 0
10.2.27 Allow for service relocation fees EA 0
10.2.28 Allow for all builders work in connection with the installation EA 0
10.2.29 Allow for providing all keys, tools, spares, parts and schematic EA 0
10.2.30 Allow for all necessary identifications EA 0
10.2.31 Allow for the preparation of all necessary installation drawings EA 0
10.2.32 Allow for the preparation of all necessary operations and maintenance manuals EA 0
10.2.33 Allow for testing and commissioning of all works EA 0
10.4 Toilet, Bathroom and Kitchen
Sanitary Wares and Accessories
Supply and fix complete sanitary fixtures includes but not limited to washbasins, water closets, mixers, hand spray, shower spray, towel ring,
towel rail, toilet paper holder, soap holder, robe hook, floor drain, etc…. all complete as per specification and drawings.
Bathroom Type 01 (Ground Floor Male and Female Toilet) 2 NIU 0
Bathroom Type 02 (Handicaped Toilet) 1 NIU 0
Bathroom Type 03 (Guard's Room Bathroom) 1 NIU 0
Bathroom Type 04 Mezzanine Toilet 4 NIU 0
Bathroom Type 05 Mezzanine Toilet 3 NIU 0
Bathroom Type 06 Apartment Bathroom 10 NIU 0
Bathroom Type 07 Apartment Bathroom 18 NIU 0
Bathroom Type 08 Apartment Bathroom 10 NIU 0
Bathroom Type 09 Apartment Washroom 18 NIU 0
Bathroom Type 10 Apartment Bathroom 10 NIU 0
Bathroom Type 11 Apartment Washroom 30 NIU 0
Bathroom Type 12 Apartment Bathroom 2 NIU 0
Bathroom Type 13 Apartment Bathroom 2 NIU 0
Mezzanine Female Washroom 1 NIU 0
Mezzanine Handycapped Toilet 1 NIU 0
Mirrors
Frameless mirrors to vanities as shown on the drawings including plywood, backing, metal angle supports and wood blocking as per
drawings.
600mm x 1200mm 86 NIU 0
450mm x 1100mm 2 NIU 0
1300mm x 1200mm 3 NIU 0
1450mm x 1200mm 3 NIU 0
1000mm x 1200mm 20 NIU 0
Kitchen
Kitchen Sink & Water Tap complete with drain, plug and single lever mixer 62 NIU 0
Conventional Hood 58 NIU 0
11 Fire fighting works
Supply and install CO2 type portable Fire Extinguishers, including hangers, hose, and accessories , all as specified in compliance with NFPA NIU 0
11.1 and UAE fire and life safety code.
Supply and install Dry powder type portable Fire Extinguishers, including hangers, hose, and accessories , all as specified in compliance with NIU 0
11.2 NFPA and UAE fire and life safety code.
Fire hose cabinet , Automatic hose reel with swing cabins, hoses and spray nozzle,landing valve with built in PRV etc.., complete as NIU 0
11.3 specified, and to the Civil Defence requirements. 22
11.4 Fire blanket; complete with support and all necessary accessories; all in accordance with drawings and specification NIU 0
11.5 Fire brigade 4-way inlet breeching with cabinet as specified and per Civil Defence requirements 1 NIU 0
11.6 Wet Riser system
Supply and install test and commission wet riser pipes with fittings, valves, air vents etc., complete, as specified and to NFPA requirement
11.6.1 and the Civil Defence regulation, all components to be UL listed and FM approved. Pipes, fittings and accessories
11.6.1.1 25Ø LM 0
11.6.1.2 65Ø LM 0
11.6.1.3 150Ø LM 0
11.6.2 Pressure reducing valves 25Ø for hose real connection NIU 0

LM 0
11.6.3 Wet riser test and drain line with all associated supports, couplings, fittings and accessories as required by NFPA and Civil defence regulation
11.7 Automatic Sprinkler system

Supply and install test and commission automatic sprinkler system with associated pipes, fittings, valves, air vents etc., complete, as
specified and to NFPA requirement and Civil Defence regulation all components to be UL listed and FM approved. Pipes, fittings and
11.7.1 accessories
11.7.1.1 25Ø LM 0
11.7.1.2 32Ø LM 0
11.7.1.3 40Ø LM 0
11.7.1.4 50Ø LM 0
11.7.1.5 65Ø LM 0
11.7.1.6 80Ø LM 0
11.7.1.7 100Ø LM 0
11.7.1.8 150Ø LM 0
11.7.2 Sprinkler heads complete with all necessary, supports, fittings and accessories
11.7.2.1 Concealed sprinkler NIU 0
11.7.2.2 Pendant sprinklers NIU 0
11.7.2.3 Upright sprinkler head NIU 0
11.7.2.4 sidewall sprinkler head NIU 0
11.7.3 Zone control valves NIU 0
11.7.4 Pressure reducing station NIU 0
11.7.5 Pressure reducing valve NIU 0
11.7.6 Check valves NIU 0
11.7.7 OS & Y Gate valve NIU 0
11.7.8 Alarm check valves 1 NIU 0
11.7.9 Sprinkler drain riser with drain valves NIU 0
11.7.10 Sprinkler test and drain valves NIU 0
11.7.11 Automatic air vent 4 NIU 0
11.7.12 Flow meters NIU 0
11.7.13 Pressure gauges NIU 0
11.8 Fire Fighting Pump Set:

Supply, install, testing and commissioning of the following systems including associated valve set, pipe header and pressure vessel; complete
with driving motor, control panels, base and anti-vibration mounting, fittings, supports, wiring and controls, insulation and all necessary
11.8.1 ancillaries, accessories and connections; complete as detailed on drawing and as per specification and as detailed below.
11.8.1.1 Electric driven main pump. UL listed/ FM approved 1 EA 0
11.8.1.2 Diesel Pump with all associated accessories, fuel meanagement system and fuel tank. UL listed/ FM approved 1 EA 0
11.8.1.3 Jockey Pump . 1 EA 0
11.9 Pre-Engineered automatic fire suppression systems

Supply, install , testing and commissioning of automatic clean agent system in electrical rooms with all associated piping, fittings,
valves,supports, cylinders, accessories, control panels and interfaces to man fire alarm system all in compliance with NFPA requirement, EA 0
11.9.1 Civil defence regulations and as shown on drawings and specifications and where required by Civil Defence 1
11.9.1.1 Allow for room pressure integrity tests for all rooms protected with automatic clean agent system 1 EA 0
11.9.1.2 Allow for all interfaces and required motorized dampers for HVAC systems NIU 0

Supply, install , testing and commissioning of automatic Foam Suppression system in Generator rooms with all associated piping, fittings,
valves, supports, gauges, cylinders, accessories, control panels and interfaces to man fire alarm system all in compliance with NFPA EA 0
11.9.2 requirement, Civil defence regulations and as shown on drawings and specifications and where required by Civil Defence 1
11.1 200 mm Dia Black Steel Exhaust Pipe work and accessories for Diesel Fire Pump . LM 0
11.11 Diesel Engine Fuel filling line LM 0
11.12 Allow for all Builder's work in connection with Fire Fighting System's installation. 1 EA 0
11.13 Allow for fees related to Civil defence approvals, Third party approvals …etc. 1 EA 0
11.14 Allow for supports, including fixings, anchors insulating block and anti vibration devices. 1 EA 0
11.15 Allow for identification labels including plates, discs, labels, charts and color coding. 1 EA 0
11.16 Allow for protective and decorative painting 1 EA 0
11.17 Allow for firestopping in accordance with drawings,specificaiton and lcoal authorities requirements 1 EA 0
11.18 Allow for providing tools and spare partss including maintenance kit, loose keys and consumables. 1 EA 0
11.19 Allow for liaison, co-ordination and attendanceon concerned Authorities work to meet the requirement of the specification 1 EA 0
11.2 Close-out Documents: 1 EA 0
Allow for all submittals, samples, shop drawings, coordination drawings, As-built Drawings, warranty certificates, testing & commissioning, EA 0
11.20.1 operation and maintenance manuals 1
12 AIR CONDITIONING AND VENTILATION SYSTEMS
12.1 Chilled Water Pumps:
Supply and install chilled water pump set with all associated pipes, fittings, valves, insultion, cladding, varaible frequency drives, control SET 0
12.1.1 panels, inertia base and vibration isolators complete as specified and shown on drawings . 1
12.1.2 Chilled water Pressurization Unit with all associated pipes, fittings, valves, tanks, accessories and controls 1 SET 0
12.1.3 Automatic chemical dosing system with all the necessary tanks, pots, piping, fittings, valves, accessories, controls, etc. 1 SET 0
Manual dosing system as specified & shown on the drawings including all valves, fittings, insulation, supports & pipe connections etc . to SET 0
12.1.4 main flow and return pipes. 1
12.1.5 Air and dirt separator complete with all associated pipes, fittings, valves and accessories 1 SET 0
12.1.6 Instrumentation as specified and shown on the drawings - supply, install, test and commission all instrumentation and accessories, etc. 1 EA 0
12.2 Fan Coil Units:
Supply, install testing and commissioning of fan coil units complete as specified, shown on drawings and with all the associated anti-
12.2.1 vibration mounts, plenums, thermostats, wiring controls and accessories as deemed necessary for the proper functioning of the unit.
12.2.2 3rd Basement Floor Fan Coil Units
12.2.2.1 3B1 1 NIU 0
12.2.2.2 3B2 1 NIU 0
12.2.2.3 3B3 1 NIU 0
12.2.3 2nd Basement Floor Fan Coil Units NIU 0
12.2.3.1 2B1 1 NIU 0
12.2.3.2 2B2 1 NIU 0
12.2.3.3 2B3 1 NIU 0
12.2.4 1st Basement Floor Fan Coil Units
12.2.4.1 1B1 1 NIU 0
12.2.4.2 1B2 1 NIU 0
12.2.4.3 1B3 1 NIU 0
12.2.4.4 1B4 1 NIU 0
12.2.5 Ground Floor Fan Coil Units
12.2.5.1 G1 1 NIU 0
12.2.5.2 G2 1 NIU 0
12.2.5.3 G3 1 NIU 0
12.2.5.4 G4 1 NIU 0
12.2.5.5 G5 1 NIU 0
12.2.5.6 G6 1 NIU 0
12.2.5.7 G7A 1 NIU 0
12.2.5.8 G7B 1 NIU 0
12.2.5.9 G8 1 NIU 0
12.2.5.10 G9 1 NIU 0
12.2.5.11 G10 1 NIU 0
12.2.5.12 G11 1 NIU 0
12.2.5.13 G12 1 NIU 0
12.2.6 Mezzanine Floor Fan Coil Units
12.2.6.1 M1 1 NIU 0
12.2.6.2 M2 1 NIU 0
12.2.6.3 M3 1 NIU 0
12.2.6.4 M4 1 NIU 0
12.2.6.5 M5 1 NIU 0
12.2.6.6 M6 1 NIU 0
12.2.6.7 M7 1 NIU 0
12.2.6.8 M8 1 NIU 0
12.2.6.9 M9 1 NIU 0
12.2.6.10 M10 1 NIU 0
12.2.6.11 M11 1 NIU 0
12.2.6.12 M12 1 NIU 0
12.2.6.13 M13 1 NIU 0
12.2.6.14 M14 1 NIU 0
12.2.7 Typical Floor (1st&3rd) Fan Coil Units
12.2.7.1 F1 2 NIU 0
12.2.7.2 F2 2 NIU 0
12.2.7.3 F3 2 NIU 0
12.2.7.4 F4 2 NIU 0
12.2.7.5 F5 2 NIU 0
12.2.7.6 F6 2 NIU 0
12.2.7.7 F7 2 NIU 0
12.2.7.8 F8 2 NIU 0
12.2.7.9 F9 2 NIU 0
12.2.7.10 F10 2 NIU 0
12.2.7.11 F11 2 NIU 0
12.2.7.12 F12 2 NIU 0
12.2.7.13 F13 2 NIU 0
12.2.7.14 F14 2 NIU 0
12.2.7.15 F15 2 NIU 0
12.2.7.16 F16 2 NIU 0
12.2.7.17 F17 2 NIU 0
12.2.7.18 F18 2 NIU 0
12.2.7.19 F19 2 NIU 0
12.2.7.20 F20 2 NIU 0
12.2.7.21 F21 2 NIU 0
12.2.7.22 F22 2 NIU 0
12.2.8 Typical Floor (2nd&4th) Fan Coil Units
12.2.8.1 T1 2 NIU 0
12.2.8.2 T2 2 NIU 0
12.2.8.3 T3 2 NIU 0
12.2.8.4 T4 2 NIU 0
12.2.8.5 T5 2 NIU 0
12.2.8.6 T6 2 NIU 0
12.2.8.7 T7 2 NIU 0
12.2.8.8 T8 2 NIU 0
12.2.8.9 T9 2 NIU 0
12.2.8.10 T10 2 NIU 0
12.2.8.11 T11 2 NIU 0
12.2.8.12 T12 2 NIU 0
12.2.8.13 T13 2 NIU 0
12.2.8.14 T14 2 NIU 0
12.2.8.15 T15 2 NIU 0
12.2.8.16 T16 2 NIU 0
12.2.8.17 T17 2 NIU 0
12.2.8.18 T18 2 NIU 0
12.2.8.19 T19 2 NIU 0
12.2.8.20 T20 2 NIU 0
12.2.8.21 T21 2 NIU 0
12.2.8.22 T22 2 NIU 0
12.2.9 Fifth Floor Fan Coil Units
12.2.9.1 5F1 1 NIU 0
12.2.9.2 5F2 1 NIU 0
12.2.9.3 5F3 1 NIU 0
12.2.9.4 5F4 1 NIU 0
12.2.9.5 5F5 1 NIU 0
12.2.9.6 5F6 1 NIU 0
12.2.9.7 5F7 1 NIU 0
12.2.9.8 5F8 1 NIU 0
12.2.9.9 5F9 1 NIU 0
12.2.9.10 5F10 1 NIU 0
12.2.9.11 5F11 1 NIU 0
12.2.9.12 5F12 1 NIU 0
12.2.9.13 5F13 1 NIU 0
12.2.9.14 5F14 1 NIU 0
12.2.9.15 5F15 1 NIU 0
12.2.9.16 5F16 1 NIU 0
12.2.9.17 5F17 1 NIU 0
12.2.9.18 5F18 1 NIU 0
12.2.9.19 5F19 1 NIU 0
12.2.9.20 5F20 1 NIU 0
12.2.9.21 5F21 1 NIU 0
12.2.9.22 5F22 1 NIU 0
12.2.10 Roof Floor Fan Coil Units
12.2.10.1 R1 1 NIU 0
12.2.10.2 R2 1 NIU 0
12.2.10.3 R3 1 NIU 0
12.2.10.4 R4A 1 NIU 0
12.2.10.5 R4B (STAND-BY) 1 NIU 0
12.3 Air Cutain

Supply and install air curtain including motors, filters, all necessary anti-vibration mountings and supports, dampers,electrical/control wiring,
conduits and controls, accessories and connections to duct work; complete as shown on equipment schedule and all in accordance with the
12.3.1 Specifications .
12.3.1.1 AC-1 1 NIU 0
12.3.1.2 AC-2 1 NIU 0
12.3.1.3 AC-3 1 NIU 0
12.3.1.4 AC-4 1 NIU 0
12.4 Fresh Air Handling units

Supply, install testing and commissioning of FAHU's including supply & extract fans heat recovery wheel, horse shoe heat pipes , cooling
coil,panel and bag filter, standby motors, valves strainers, pressure gauge, thermometers, control and associated accessories, connection to
ducts, connection to chilled water pipe work and electrical connection to local outlets, including supports and vibration isolators flexible
12.4.1 connectors. as specified and shown on drawings
12.4.2 FAHU-01 1 NIU 0
12.4.2 FAHU-02 1 NIU 0
12.5 Air Handling units

Supply, install, testing and commissioning of AHU's including supply fans , cooling coil, filters, valves, strainers, pressure gauge,
thermometers, control and associated accessories, connection to chilled water pipe work and electrical connection to local outlets as specified
12.5.1 and shown on drawings.
12.5.2 AHU-ST 1 NIU 0
12.6 Fans
Supply, install testing and commissioning of all fans complete with associated hangers, supports, dampers, wiring, control panels, flexible
12.6.1 connectors and accessories as specidied and shown on drawings and in compiliance with Civil Defence regulations
12.6.2 Smoke management fans:
12.6.2.1 Pressuriuzation fans
12.6.2.1.1 SPF-01 1 NIU 0
12.6.2.1.2 SPF-02 1 NIU 0
12.6.2.1.3 LPF-01 1 NIU 0
12.6.2.2 Corridor smoke management fans
12.6.2.2.1 SEF-01 1 NIU 0
12.6.2.2.2 MAF-01 1 NIU 0
12.6.2.2.3 MAF-02 1 NIU 0
12.6.2.3 Car park ventilation and smoke management fans
12.6.2.3.1 3BEF1 1 NIU 0
12.6.2.3.2 3BEF2 1 NIU 0
12.6.2.3.3 2BEF1 1 NIU 0
12.6.2.3.4 2BEF2 1 NIU 0
12.6.2.3.5 1BEF1 1 NIU 0
12.6.2.3.6 1BEF2 1 NIU 0
12.6.2.3.7 3BFF1 1 NIU 0
12.6.2.3.8 3BFF2 1 NIU 0
12.6.2.3.9 2BFF1 1 NIU 0
12.6.2.3.10 2BFF2 1 NIU 0
12.6.2.3.11 1BFF1 1 NIU 0
12.6.2.3.12 1BFF2 1 NIU 0
12.6.3 Ventilation Fans
12.6.3.1 Transformer room ventilation fan 1 NIU 0
12.6.3.2 Garbage room ventilation fan 1 NIU 0
12.7 Chillers
Supply, install testing and commissioning of air cooled packaged chillers complete with all valves ,strainers , flanged pipe connections to
12.7.1 header , protective devices , controls ,electrical connection etc..as specified and mounted on anti vibration isolators.
12.7.1.1 Chiller- 1 1 NIU 0
12.7.1.2 Chiller -2 1 NIU 0
12.8 Ductwork and Accessories
Sheet metal ductworks; complete with thermal insulation, canvas and coating, supports, anti-vibration mounts and all necessary accessories;
12.8.1 all in accordance with drawings and specification
12.8.1.1 Insulated Supply and return air ductwork MTK 0
12.8.1.2 Insulated treated fresh air ductwork MTK 0
12.8.1.3 Insulated extract air ductwork MTK 0
12.8.1.4 non-insulated ductwork MTK 0
12.8.1.5 Fire rated ductwork MTK 0
12.8.1.6 Insulated, Fire rated ductwork MTK 0
12.8.1.7 Commercial Kitchen extract ductwork MTK 0
12.8.2 Volume control dampers NIU 0
12.8.3 Fire dampers NIU 0
12.8.4 Motorized dampers NIU 0
12.8.5 Motorized fire dampers NIU 0
12.8.6 Motorized smoke dampers NIU 0
12.8.7 MSFD NIU 0
12.8.8 Non-return dampers NIU 0
12.8.9 Duct access doors NIU 0
12.8.10 Aluminum Cladding for exposed ducts in roof, plant rooms, basement, and exposed installations MTK 0
12.8.11 Electrostatic filters at all kitchen extract riser ducts before connecting to the FAHUs heat recovery wheel NIU 0
12.8.12 Sound attenuators NIU 0
12.8.13 Acoustic Liner LM 0
12.8.14 Flexible ducts MTK 0
12.9 Grilles, Diffusers and registers
Air distribution outlets including plenum boxes, thermal insulations, acoustic insulation dampers, fittings, fixings in positions all complete as NIU 0
12.9.1 specified and as shown on drawings.
12.9.2 Supply 4-Ways diffusers with associated plenums, flexible ducts, supports and accessories NIU 0
12.9.3 Return 4-Ways diffusers complete as shown on drawings and as specified NIU 0
12.9.4 Supply Register complete as shown on drawings and as specified LM 0
12.9.5 Return Grilles complete as shown on drawings and as specified LM 0
12.9.6 Extract air grilles complete as shown on drawings and as specified LM 0
12.9.7 Toilet round disc type extract diffuser. NIU 0
12.9.8 Supply linear slot diffusers with associated plenums, flexible ducts, supports and accessories LM 0
12.9.9 Return Linear slot diffusers LM 0
12.9.10 Supply linear bar grilles with associated plenums, flexible ducts, supports and accessories LM 0
12.9.11 Return Linear bar grilles LM 0
12.9.12 Intake and Extract louvers MTK 0
12.9.13 Sand trap Louvers MTK 0
12.1 Chilled water pipes and accessories

Chilled Water pipes (Seamless black steel as specified) with all the necessary fittings, hangers, supports, flexible connection etc., along with
12.10.1 thermal insulation to pipe work canvas, foster, aluminum jacketing wherever applicable etc. as shown on the drawings and specified.
12.10.1.1 20Ø LM 0
12.10.1.2 25Ø LM 0
12.10.1.3 32Ø LM 0
12.10.1.4 40Ø LM 0
12.10.1.5 50Ø LM 0
12.10.1.6 65Ø LM 0
12.10.1.7 75Ø LM 0
12.10.1.8 100Ø LM 0
12.10.1.9 125Ø LM 0
12.10.1.10 150Ø LM 0
12.10.1.11 200Ø LM 0
12.10.2 Chilled water valves
12.10.2.1 Gate vlaves NIU 0
12.10.2.2 Butterfly valves NIU 0
12.10.2.3 Check valves NIU 0
12.10.2.4 Control valves with modulating actuator NIU 0
12.10.2.5 Strainer NIU 0
12.10.2.6 Metering orifice NIU 0
12.10.2.7 Automatic air vents NIU 0
12.10.2.8 Pressure gauges NIU 0
12.10.2.9 Flow Switch NIU 0
12.10.2.10 Thermometer NIU 0
12.11 FCU Controls
Supply, install, test and commissioning of standalone control and thermostat for all FCUs as shown in the schedule, drawings and EA 0
12.11.1 specifications.
12.12 HVAC control and monitoring system
Supply, install, test and commissioining of complete HVAC control and monitoring system for chiller, chilled water pumps, FAHUs, AHU, EA 0
12.12.1 Fans,..etc as specified and as shown in the drawings complete with DDCs, wiring, piping,sensors, and connect to equipments,..ect. 1
12.13 Hangers, supports, brackets etc. for pipe and ductwork. EA 0
12.14 Insulated Condensate drain connections. LM 0
12.15 Sound reduction enclosure for the chillers compressors. EA 0
12.16 Controls with all necessary accessories & associated wiring EA 0
12.17 Anti vibration mounts EA 0
12.18 Allow for all builder works related to air conditioning system EA 0
12.19 Allow for all protective and decoratvie painting and cleaning of pipes, fittings, etc and equipments. EA 0
12.2 Allow for all identification labels, plates, charts,of all HVAC services and equipment. EA 0
12.21 Allow for coordination with other trade shop drawings. EA 0
12.22 Allow for shop drawings & engineering works related to air conditioning system. EA 0
12.23 Allow for firestopping in accordance with drawings,specificaiton and lcoal authorities requirements EA 0
12.24 Provision for maintenance of HVAC System during guarantee period EA 0
12.25 Allow for instructing training Client's personnel on all aspects of the operation of HVAC equipment and systems. EA 0
12.26 Allow for air and chilled water balancing of complete HVAC systems by third partycommissioning agent EA 0
Coordinating with other trades including additional material and labour to produce a fully and operable installation (interfacing work with fire EA 0
12.27 alarm system)
12.28 Close-out Documents: EA 0
Allow for all submittals, samples, shop drawings, As-built Drawings, warranty certificates, testing & commissioning, operation and EA 0
12.28.1 maintenance manuals , Providing necessary spare parts.
13 ELEVATORS AND CRADLE
13.1 ELEVATORS

Design, Supply and install the complete lift system; including but not limited to all machine and control room equipment's operating system,
hoist way equipment's, door and entrance equipment's, lift car equipment's, monitoring system, intercom and distress signal system, drivers
and control, control assemblies, rail system, wire ropes, stopping devices, car frame and finishes, protective devices, interface with security
system, electric connection, all accessories / ancillaries and all necessary work to complete and operation the whole system; all accordance
13.1.1 with specification.

Passenger Elevator : - 1350 Kg , 18 persons capacity 1.75 meter / sec ,103 stop, 10 openings, 2000 wide x 1500mm depth clear cabin size, NIU 0
13.1.1.1 hydroelectric computerised control (indirect side acting) as Specified 1
Service / Fire fighting Elevator - 1600 Kg , 21 persons capacity 1.75 meter / min , 10 stop, 10 openings, 1600 wide x 2100.mm depth clear NIU 0
13.1.1.2 cabin size, hydroelectric computerised control (indirect side acting) as Specified 1
13.1.2 SUNDRIES
13.1.2.1 Allow for production of all working drawings, calculations,specification, operation and maintenance manuals EA 0
13.1.2.2 Allow for all general builder's work in connection with the lift installation EA 0
13.1.2.3 Allow for testing and commissioning lift installation EA 0
13.1.2.4 Provision for maintenance as specified EA 0
13.2 CRADLE
13.2.1 Building Maintenance Unit
Supply, install, test and commissioning of building maintenance unit davit system as specified and as shown in the drawings with all EA 0
13.2.1.1 accessories and controls. 1
13.2.1.2 SUNDRIES
13.2.1.2.1 Allow for production of all working drawings, calculations,specification, operation and maintenance manuals 1 EA 0
13.2.1.2.2 Allow for all general builder's work 1 EA 0
13.2.1.2.3 Allow for testing and commissioning 1 EA 0
13.2.1.2.4 Provision for one year maintenance 1 EA 0
14 GARBAGE DISPOSAL SYSTEM
14.1 GARBAGE CHUTE
Supply, install complete waste management system as shown in the drawings and specifications complete with automatic cleaning system, EA 0
14.1.1 pipe work, fire protection sprinkler, disinfection unit,..etc. 1
14.1.2 Provision for shop drawings and submittals EA 0
14.1.3 Provision for As Built drawings and Mannuals EA 0
14.1.4 Provision for connection fee for automatic waste collection system EA 0
14.1.5 Provision for testing and commissioning EA 0
14.1.6 Provision for warranty and maintenance as specified EA 0
14.1.7 Provision for electrical works as specified EA 0
14.1.8 Provision for plumbing works as specified EA 0
14.1.9 Provision for civil works as specified EA 0
15 CENTRAL GAS SYSTEM
Supply, install and test natural gas system piping as per drawings, specifications and ADNOC regulations by ADNOC approved
15.1 subcontractor.
15.1.1 Filling Line 1 EA 0
15.1.1.1 Main incomming valve station 1 EA 0
15.1.1.2 Main riser from ground to roof MS pipe
15.1.2 Distribution Dropers & Fittings (SC 40 MS pipes)
15.1.2.1 40mm dia pipe 1 EA 0
15.1.2.2 25mm dia pipe 1 EA 0
15.1.2.3 Fittings , Supports and Clamps etc.. 1 EA 0
15.1.3 Kitchen branch pipes and fittings (Copper pipes) 1 EA 0
15.1.4 Gas Detection System
15.1.4.1 Gas leak detection system cabling 1 EA 0
15.1.5 Gas leak detection panels at each floor lift lobby. EA 0
15.1.6 Work incidental to mechanical engineering installations
15.1.6.1 Allow for co-ordination with other service installations 1 EA 0
15.1.6.2 Allow for cutting or forming holes, mortices, chases or the like and making good finishes 1 EA 0
15.1.6.3 Allow for building in or cutting and pinning brackets or the like and making good finishes 1 EA 0
15.1.6.4 Allow for shallow excavations for below-ground installations including encasing in concrete where necessary 1 EA 0
15.1.6.5 Allow for plinth and support for machinery and fittings unless measured elsewhere in detail 1 EA 0
15.1.7 SUNDRIES
15.1.7.1 Allow for submittals and shop drawings 1 EA 0
15.1.7.2 Allow for as built drawings and mannuals 1 EA 0
15.1.7.3 Allow for connection charges to ADNOC . 1 EA 0
15.1.7.4 Allow Emergency operation and maintenance contract during defect liability period 1 EA 0
16 ELECTRICAL WORKS
Standard abbreviation have been used in this bill which are well known to the Electric Industry. Claims resulting from misinterpretation of
16.1 these abbreviations will not be considered.

B.O.Q should be read in conjunction with all relative drawings, specifications as a whole. Quantities mentioned hereinafter are intended for
the guidance of the contractor, who shall be deemed to have satisfied himself of the exact quantities. Any difference between actual quantities
and those mentioned in the B.O.Q. shall be entered in the page headed "Contractors Adjustment Sheet" appearing at the end of this BOQ
16.2 other quantities mentioned here are deemed as correct.
16.3 Allow for testing thoroughly the complete system before being put into operation EA 0
Allow for builders work required for electrical installation including ducts, trenches, concrete bases, chasing and channeling in walls, floors EA 0
16.4 and ceiling, manholes and covers etc.., to the satisfaction of the Engineer.
Allow for following up with ADDC for electrical power supply connection, testing & commissioning and pay connection fees included EA 0
16.5 ADDC KWH meter.
16.6 Meduim voltage -22kv- distribution panel

Supply, install, test, commission and maintain Medium voltage (22kv) distribution panel QRM type ( 2inc. LBS + 1outgoing CB) as specified NIU 0
16.6.1 and as indicated on the drawings, complete with necessary accessories and ancillary works and materials required for complete installation. 1
16.7 TRANSFORMER
Supply, install test and commission transformer 1500KVA, 22KV/400V, 50Hz, Dry type with all necessary connections to main DBs and HV NIU 0
16.7.1 panel as per ADDC regulation and as shown on the drawings. 1
High voltage cabe between HV panel and transformers, 22 KV size 3Cx120 sq.mm CU.XLPE/STA/PVC Complete with termination and all EA 0
16.8 auxilary matrial as per ADDC specifications
16.9 Emergency Diesel Generator Plants

Supply, install, testing and commissioning of 200KVA (at 50 degree C ambinet) 0.8 P.F., 400 Volts, Diesel Generators in accordance with
technical specification complete with necessary accessories and anxillaries works such as, but not limited to the following: Silencors, flexible
joints, exhaust pipes, fuel tanks, fuel pipes, battery, battery chargers, canvas make up duct, isolators,cercuit breaker, pumps, monitoring and
16.9.1 protection erection materials and special tools.
16.9.1.1 Stand by Generator set (200 KVA,0.8 pf) 1 NIU 0
16.9.1.2 ATS 400 A ,400V,50HZ,4POLE 1 NIU 0
16.1 Low Voltage Switchgear and Distribution Board
Supply, install, test, commission and maintain low voltage switchgear complete with all components as specified and as shown on the
16.10.1 drawings including all necessary works and fittings required for the complete installation including all incoming and outgoing feeders
16.11 Main Distribution Board MDB ( MDB-1 ) 1 NIU 0
16.11.1 Sheet steel free standing front access IP 54 electro galvanized sheet steel constructed as to BSEN60439-1 Form 4 Type 6
16.11.1.1 Incomings

1 x 2500A, 4P, ACB, 50KA with protection SCC + O.C and earth fault 1xvm+S.S-RYB lamps + TP Fuses 3xAM+CTS (2500/5A) + P.F
16.11.1.1.1 meter
16.11.1.2 Outgoing:
16.11.1.2.1 1 x 1600A TP ACB 50KA at 400V AC 50HZ
16.11.1.2.2 1 x 1000A TP ACB 50KA at 400V AC 50HZ
16.11.1.2.3 1 x 800A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.4 2 x 400A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.5 1 x 300A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.6 1 x 250A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.7 2 x 200A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.8 1 x 80A TP MCCB 50KA at 400V AC 50HZ
16.12 EMDB (8 ways) 1 NIU 0
16.12.1 Sheet steel free standing front access IP 54 electro galvanized sheet steel constructed as to BSEN60439-1 Form 4 Type 6
16.12.1.1 Incoming;

16.12.1.1.1 1 x 400A, 4P, MCCB, 50KA with protection SCC + O.C and earth fault 1xvm+S.S-RYB lamps + TP Fuses 3xAM+CTS(400/5A) + P.F meter
16.12.1.2 Outgoing:
16.12.1.2.1 1 x 200A TP MCCB 50KA at 400V AC 50HZ
16.12.1.2.2 2 x 100A TP MCCB 50KA at 400V AC 50HZ
16.12.1.2.3 6 x 80A TP MCCB 50KA at 400V AC 50HZ
16.13 Sub Main Distribution Board
Wall mounted IP21, electro galvanized sheet steel constructed as to BSEN60439-1 Form 2 as per latest local authority regulation as
16.13.1 specifiedkindly be informed that panel as follow: and indicated in load schedule drawings.
16.13.1.1 SMDB-G 1 NIU 0
16.13.1.2 SMDB-OFF 1 NIU 0
16.13.1.3 SMDB-T 5 NIU 0
16.13.1.4 ESMDB-LC 1 NIU 0
16.13.1.5 ESMDB-MEC-B 1 NIU 0
16.13.1.6 ESMDB-G 1 NIU 0
16.13.1.7 ESMDB-LIFT 1 NIU 0
16.13.1.8 MCC 1 NIU 0
16.13.1.9 ESMDB-R 1 NIU 0
16.14 CAPACITOR BANKS
Supply, installation, testing , commissioning of Power Factor correction Units with harmonic filters as specified with rating 250 KVAR NIU 0
16.14.1 P.F.C. 1
16.15 Final DB and Consumer Units
Recessed Mounting, electro galvanized sheet steel constructed as per latest local authority regulation, as specified and indicated in load
15.15.1 schedule drawings. Kindly be informed that panel as follow:
15.15.1.1 DB-G 1 NIU 0
15.15.1.2 DB-EX 1 NIU 0
15.15.1.3 DB-B1 1 NIU 0
15.15.1.4 DB-B2 1 NIU 0
15.15.1.5 DB-B3 1 NIU 0
15.15.1.6 DB-TFX (FLATS) 48 NIU 0
15.15.1.7 EDB-MB1 1 NIU 0
15.15.1.8 EDB-MB2 1 NIU 0
15.15.1.9 EDB-MB3 1 NIU 0
15.15.1.10 EDB-G 1 NIU 0
15.15.1.11 EDB-S1 1 NIU 0
15.15.1.12 EDB-S2 1 NIU 0
15.15.1.13 EDB-B 1 NIU 0
15.15.1.14 ECU-M 1 NIU 0
15.15.1.15 ECU-T 5 NIU 0
15.15.1.16 ECU-R 1 NIU 0
15.15.1.17 ECU-B1 1 NIU 0
15.15.1.18 ECU-B2 1 NIU 0
15.15.1.19 ECU-B3 1 NIU 0
16.16 LOW VOLTAGE CABLES - XLPE CABLES
Supply and install, Test, Commission and maintain main and sub feeder copper cables as shown on drawings including termination, cable
16.16.1 ties, and all necessary accessories and related ancillaries works specified as a required by the drawings
16.16.1.1 1C x 630mm2 XLPE / AWA / PVC EA 0
16.16.1.2 4C x 240mm2+1C x 120mm2 XLPE / SWA / PVC EA 0
16.16.1.3 4C x 150mm2+1C x 70mm2 XLPE / SWA / PVC EA 0
16.16.1.4 4C x 120mm2+1C x 70mm2 XLPE / SWA / PVC EA 0
16.16.1.5 4C x 50mm2+1C x 25mm2 XLPE / SWA / PVC EA 0
16.16.1.6 4C x 35mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.16.1.7 4C x 25mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.16.1.8 4C x 16mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.16.1.9 4C x 10mm2+1C x 10mm2 XLPE / SWA / PVC EA 0
16.16.1.10 2C x 10mm2 XLPE / SWA / PVC EA 0
Supply and install, Test, Commission and maintain main and sub feeder copper fire rated cables as shown on drawings including termination,
16.17 cable ties, and all necessary accessories and related ancillaries works specified as a required by the drawings
16.17.1 4C x 240mm2+1C x 120mm2 XLPE / SWA / PVC EA 0
16.17.2 4C x 50mm2+1C x 25mm2 XLPE / SWA / PVC EA 0
16.17.3 4C x 35mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.17.4 4C x 25mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.17.5 4C x 10mm2+1C x 10mm2 XLPE / SWA / PVC EA 0
16.18 Busbar Trunking Specification Section

Supply, install, test, commission and maintain low voltage busway system complete with all special fittings, elbow,joints, hanging and
mounting components, materials and ancillary works required for the complete operative system in accordance with the specification and
16.18.1 drawings.
16.18.1.1 1600A,4W+E Plug In Busway 60 LM 0
16.18.1.2 Tap Off Unit 250A 5 NIU 0
16.19 SUPPORT COMPONENTS CABLES (CABLE TRAYS AND ACCESSORIES)
Supply and installation of the cable trays and accessories including required supports as persite requirement, hardwares, etc... As shown in the
16.19.1 drawings
16.19.1.1 600 mm wide EA 0
16.19.1.2 450 mm wide EA 0
16.19.1.3 300 mm wide EA 0
16.19.1.4 225 mm wide EA 0
16.19.1.5 150 mm wide EA 0
16.19.1.6 100 mm wide EA 0
16.19.1.7 Ventillated cable tray covers as specified and as shown in the drawings EA 0
16.2 SOCKET OUTLETS
Supply, install, test, commission and maintain socket outlets including boxes, conduits, conduits fittings, wiring, plugs and accessories
16.20.1 connecting from the branch circuit and back to the panel board as specified and as required by the drawings.
16.20.1.1 Double poles + earth 13A Single switch socket 74 NIU 0
16.20.1.2 Double pole + earth 13A Duplex switch socket 479 NIU 0
16.20.1.3 Double pole + earth 13A Single switch socket, W.P. 22 NIU 0
16.20.1.4 Double pole + earth 13A Duplex switch socket, W.P. 2 NIU 0
16.20.1.5 Double pole switch for E.W.H with outlet 103 NIU 0
16.20.1.6 Cooker Unit 1phase 32A 49 NIU 0
16.20.1.7 Double pole switch for washing machine with flexible outlet 48 NIU 0
16.20.1.8 Double pole switch for dish washer with flexible outlet 48 NIU 0
16.20.1.9 Double pole + earth 13A Duplex switch socket Installed inside ONU Enclosure 48 NIU 0
16.21 DISCONNECT SWITCHES
Supply, install, test, commission and maintain W.P. disconnect switches including conduits, conduit fittings, wiring, vertical risers,
16.21.1 termination disconnect switch, accessories and all necessary ancillary works as specified and required by the drawings.
16.21.1.1 400A TPN 200V 50 HZ water proof 1 NIU 0
16.21.1.2 125A TPN 400V 50 HZ water proof 1 NIU 0
16.21.1.3 80A TPN 400V 50 HZ water proof 2 NIU 0
16.21.1.4 63A TPN 400V 50 HZ water proof 2 NIU 0
16.21.1.5 60A TPN 400V 50 HZ water proof 2 NIU 0
16.21.1.6 40A TPN 400V 50 HZ water proof 3 NIU 0
16.21.1.7 32A TPN 400V 50 HZ water proof 13 NIU 0
16.21.1.8 20A TPN 400V 50 HZ water proof 1 NIU 0
16.21.1.9 20A SPN 230V 50 HZ water proof 20 NIU 0
16.21.1.10 20A SPN 230V 50 HZ water proof for (FCU) Complete with cabling 133 NIU 0
16.22 LIGHTING POINT
Supply, install, test, commission and maintenance of lighting point as specified and as required by the drawings, exhaust fan point, bell point . NIU 0
16.22.1 Lighting outlet point made by copper wires size 3x2.5 Sq. mm, ready to work 1268
16.23 LIGHTING SWITCHES
Supply, install, test, commission and maintain lighting switches including boxes, conduits fitting, switches, termination conduits and wiring
16.23.1 from switches to branch circuits as specified and as required by the drawings
16.23.1.1 One way switch, one gang - 10A / IP 21 flush 420 NIU 0
16.23.1.2 One way switch, two gang - 10A / IP 21 flush 5 NIU 0
16.23.1.3 One way switch, three gang - 10A / IP 21 flush 1 NIU 0
16.23.1.4 One way switch, one gang - 10A / IP 44 flush (W.P) 9 NIU 0
16.23.1.5 One way switch, two gang - 10A / IP 44 flush (W.P) 1 NIU 0
16.23.1.6 Two ways switch, one gang - 10A / IP 21 flush 10 NIU 0
16.23.1.7 Push button for light including inpulse relay 25 NIU 0
16.23.1.8 Electronic bell 48 NIU 0
16.23.1.9 Push button for bell 48 NIU 0
16.23.1.10 One way switch, one gang - Explosion Proof Type 1 NIU 0
16.24 LIGHTING FIXTURES

Supply, install, test, commission and maintenance of lighting fixtures including but not limited to, lamps mounting brackets, accessories etc
16.24.1 and all necessary auxiliary works as specified and as required by the drawings for type description refer to the lighting fixture schedule.
16.24.1.1 Type F1 170 NIU 0
16.24.1.2 Type F2 52 NIU 0
16.24.1.3 Type F3 207 NIU 0
16.24.1.4 Type F4 10 NIU 0
16.24.1.5 Type F7 101 NIU 0
16.24.1.6 Type F24 1 NIU 0
16.24.1.7 Type D1 52 NIU 0
16.24.1.8 Type D2 142 NIU 0
16.24.1.9 Type D3 187 NIU 0
16.24.1.10 Type D4 10 NIU 0
16.24.1.11 Type D5 120 NIU 0
16.24.1.12 Type D8 76 NIU 0
16.24.1.13 Type D9 20 NIU 0
16.24.1.14 Type D10 31 NIU 0
16.24.1.15 Type D11 5 NIU 0
16.24.1.16 Type D16 48 NIU 0
16.24.1.17 Type W3 15 NIU 0
16.24.1.18 Type W4 54 NIU 0
16.24.1.19 Type W10 13 NIU 0
16.24.1.20 Type B1 12 NIU 0
16.24.1.21 Type R1 4 NIU 0
16.24.1.22 Type LS1 170 NIU 0
16.25 EARTHING SYSTEM
16.25.1 POWER

Supply, install, test, commission and maintain complete protective earthing (PE) system including earthing pits, earthing electrodes, equalizer
bars, earth continuity conductor and earthing conductor to switchboards complete with all accessories, fixing, test links, suspensions, drilling
16.25.1.1 and cutting for complete installation as per ADDC regulations also as specified and required by the drawings.
16.25.1.1.1 Earthing pits EA 0
16.25.1.1.2 Number of electrodes 3mt EA 0
16.25.1.1.3 Equalizer bars EA 0
16.25.1.1.4 Earth conductor 240 sq.mm EA 0
16.25.1.1.5 Earth conductor 16 sq.mm EA 0
16.25.1.1.6 Rod to Cable Clamp EA 0
16.25.2 LOW CURRENT & CONTROL ROOM
16.25.2.1 Earthing pits EA 0
16.25.2.2 Number of electrodes 3mt EA 0
16.25.2.3 Equalizer bars EA 0
16.25.2.4 Earth conductor 120 sq.mm EA 0
16.25.2.5 Rod to Cable Clamp EA 0
16.26 LIGHTNING PROTECTION

Supply, install, test, commission and maintain complete lighting protection system including all accessories required for the complete
installation as specified and as required by the drawings complete with earth pits complete with earth electrode,cable, clamps, and earth pit
chamber with cover ,copper strip 25 / 3 mm lightening conductor with all accessories like square tape clamps ,fixing tape clips/ copper
conuctor equipment clap, test link, test clap etc.. Connection of lighteneing down conductor to structural column with clamps , air terminal
network , bare cooper conductore or tape and all necessary materials for complete installation as specified and as required by ADDC
16.26.1 regulations and BSEN62305
16.26.1.1 Air Terminal EA 0
16.26.1.2 Earth Pits EA 0
16.26.1.3 Earth Electrode 3mt EA 0
16.26.1.4 Test Clamp EA 0
16.26.1.5 Rod to Cable Clamp EA 0
16.26.1.6 Square Clamp EA 0
16.26.1.7 Copper Tape 25 x 3mm EA 0
16.26.1.8 Conduct 120 sq.mm EA 0
16.27 PROGRAMMABLE LIGHTING CONTROL SYSTEM

Supply, install, test, commission and maintain programmable lighting control system including not limited to lighting control panel, relays,
panel boxes, conduits, conduit fittings, earthing,
termination, enclosures, switches,low voltage push button, wiring, accessories, interface unit with fire alarm system and all necessary
16.27.1 ancillary works as specified and as required by the drawings
16.27.1.1 LCP.B3 1 NIU 0
16.27.1.2 LCP.B2 1 NIU 0
16.27.1.3 LCP.B1 1 NIU 0
16.27.1.4 LCP.G 1 NIU 0
16.27.1.5 LCP.EX 1 NIU 0
16.27.1.6 LCP.EM 1 NIU 0
16.27.1.7 LCP.ET 5 NIU 0
16.27.1.8 Day light motoin sensor 1 NIU 0
16.27.1.9 Occupancy / movement sensor 55 NIU 0
16.27.1.10 Timer EA 0
16.27.1.11 Photo cell , installed on wall fence sunlight . EA 0
16.27.1.12 Interfaces with other systems as specified and as per the drawings EA 0
16.27.1.13 Conduit and wiring for the above EA 0
16.28 FIRE ALARM SYSTEM

Supply, install, test, commission and maintain fire alarm system including, but not limited to hardware and software , keyboard, relays, fire
telephone, fire pump monitoring and alarm emergency generator monitoring, elevator recall control and relays, interface unit with lifts, BMS,
HVAC, CCTV, access control system, lighting control system, central battery and emergency light system, auto dial to local authority, mimic
panel, battery and battery charger, all interfaces with other trades, Graphic command centre with PC., printer etc. and all necessary
accessories, ancillary material required for the complete installation as specified, as required by UAE fire and life safety code of practice and
16.28.1 as per the drawings
16.28.1.1 Main FACP 6 Loop 1 NIU 0
16.28.1.2 Intelligent addressable smoke detector with built in isolator base 214 NIU 0
16.28.1.3 Intelligent addressable Multi detector with built in isolator base 48 NIU 0
16.28.1.4 Intelligent addressable smoke detector with built in isolator base and sounder 53 NIU 0
16.28.1.5 Intelligent Addressable heat detector with built in isolator base 18 NIU 0
16.28.1.6 Addressable manual station 36 NIU 0
16.28.1.7 Addressable manual station water proof 19 NIU 0
16.28.1.8 Fire alarm sounder with flasher 25 NIU 0
16.28.1.9 Fire alarm sounder with flasher water proof 21 NIU 0
16.28.1.10 Monitor module for sprinkler valve tamper switches & water flow switches EA 0
16.28.1.11 Control module EA 0
16.28.1.12 Input / output interface EA 0
16.28.1.13 Conduiting and wiring for the above EA 0
16.28.1.14 mimic Panel 1 NIU 0
16.29 CARBON MONOXIDE CONTROL

Supply, install, test, commission and maintain carbon monoxide control and alarm system including, but not limited to, power supplies and all
necessary complete ancillary works and accessories required for the complete installation as specified and as required by the drawings and
16.29.1 authority requirements.
16.29.1.1 carbon monoxide alarm monitoring station 1 NIU 0
16.29.1.2 carbon monoxide sensors 11 NIU 0
16.29.1.3 Input / output interface with other systems EA 0
16.29.1.4 Conduiting and fire rated cables for the above EA 0
16.29.1.5 Excluding the existing conduit works installed at site EA 0
16.3 BGM AND VOICE EVACUATION ALARM SYSTEM

Supply, install, test, commission and maintain back ground music and voice evacuation system including, but not limited to rack with all
components, power amplifiers,distribution cabinets, accessories, etc., distribution network, conduit, trunking, fire rated wiring, battery, EA 0
interface with fire alarm system and all accessories required for the complete installation as specified, as required by local civil defence and
16.30.1 UAE fire and life safety code of practice and as per the drawings
16.31 Loud Speakers

Supply, install, test, commission and maintain loud speakers including conduits, conduit fittings, cable trunking, terminations, shielded
twisted cables, all necessary accessories and ancillary works as shown on drawings starting from the loud speakers and back to the central
16.31.1 control rack
16.31.1.1 Digital audio signaling processor unit with battery and battery charger 1 NIU 0
16.31.1.2 Multi desk compact disc players 1 NIU 0
16.31.1.3 Tuner AM/FM antenna 1 NIU 0
16.31.1.4 Celing speaker 6W 54 NIU 0
16.31.1.5 Box speaker 6W (Paging only) for stairs 21 NIU 0
16.31.1.6 Fire telephone jack 28 NIU 0
16.31.1.7 Power amplifiers EA 0
Emergency voice evacuation speaker with integral flashing NIU 0
16.31.1.8 strobe 11
16.31.1.9 Interfaces with other systems as specified and as per the drawings EA 0
16.31.1.10 Rack cabinet 19'' EA 0
16.31.1.11 Conduiting and wiring for the above EA 0
16.32 TELEPHONE SYSTEM

Supply, install, testing of telecom system as specified and as shown in the drawings ,including but not limited to, patch panels ,SC/APC
splitters,LC/APC splitters,back bone cables etc. all the required containments of trunking, trays, conduits boxes and all necessary accessories
and ancillary works as specified and as required by Telecommunication Regulatory Association (TRA) guideline and as shown on the
16.32.1 drawings.
16.32.1.1 Telecom rack 800x800mm 2 NIU 0
16.32.1.2 Mini ODF Splice Cabinet (special point) 2 NIU 0
16.32.1.3 Flat Optical Network Unit Cabinet (ONU) 54 NIU 0
16.32.1.4 Horizontal cables (4pair UTP Cat 6 cables ) EA 0
16.32.1.5 4 Core fibre optic cables,single mode EA 0
16.32.1.6 Multicore fibre optic cables,single mode EA 0
16.32.1.7 Telecom dual outlet (RJ45) 256 NIU 0
16.32.1.8 Conduits for the above EA 0
16.33 SMATV SYSTEM

Supply , install,test,commission and maintain SMATV system (IF) as specified and as shown on the drawing including ,but not limited to
dishes, witches,cables, amplifiers, conduits, sockets ,all the necessary accessories and ancillary materials required for the complete EA 0
16.33.1 installation as specified and as required by the drawings
16.34 MATV outlet 148 NIU 0
16.34.1 Conducting, trunking, containments and wiring for the above system. EA 0
16.35 CLOSED CIRCUIT TELEVISION (CCTV)

Supply, install, test, commission and maintain IP CCTV system including, but not limited to, main security rack, security LAN,POE switches,
network video recording management (NVR), graphical unit interface (GUI) work stations,pcs., keyboard, fiber and CAT6A cables, conduits, EA 0
conduit fittings, connectors, UPS,monitors 46 inch, cabling, trunking, etc., interface unit with fire alarm, B.M.S, access control and all the
necessary accessories and ancillary materials required for the complete installation as specified and as MCC requirements and as shown on
16.35.1 the drawings.
16.36 CCTV Cameras

Supply, install, test, commission and maintain IP CCTV cameras including, but not limited to, decorative camera housing, mounting brackets,
lenses, heavy gauge PVC conduits, conduit fittings back to main console and all necessary accessories and ancillary materials required for the
16.36.1 complete installation as specified and as required by the drawings
16.36.1.1 Automatic number plate recognition camera (ANPR) and interface with the gate barrier control system 2 NIU 0
16.36.1.2 Elevator camera 2 NIU 0
16.36.1.3 Indoor IP fixed dome color camera 19 NIU 0
16.36.1.4 Outdoor IP fixed dome color camera 4 NIU 0
16.36.1.5 Conduits for the above EA 0
16.36.1.6 CCTV central system including security rack, PC, monitor EA 0
16.37 ACCESS CONTROL SYSTEM
16.37.1 Specification (Section 13700)

Supply, install, test, commission and maintain access control system as specified and as indicated on the drawings including, but not limited
to, hardware and software,all cabling, conduits, trunking,PC . and all the necessary accessories and ancillary materials required for the EA 0
16.37.1.1 complete installation as specified and as required on the drawings.
16.38 Access Control Unit

Supply, install, test, commission and maintain access control units as specified and as indicated on the drawings including all cabling,
conduits, conduit fittings and accessories required for the complete installation for the following items and interface with FA and CCTV
16.38.1 systems
16.38.1.1 Door manager with backup battery 5 NIU 0
16.38.1.2 Card reader unit 10 NIU 0
16.38.1.3 Electro magnetic lock 10 NIU 0
16.38.1.4 Exit Bush button 10 NIU 0
16.38.1.5 Door contact 10 NIU 0
16.38.1.6 Interfaces with other systems as specified and as per the drawings EA 0
16.38.1.7 System software with graphical user interface (GUI) EA 0
16.38.1.8 Proximity Card reader 250 NIU 0
16.38.1.9 Conduit and wiring for the above EA 0
16.39 EMERGENCY LIGHT AND CENTRAL BATTERY SYSTEM

Supply,install,test,commission & maintain central battery system including, but not limited to central battery panels, control modules,
batteries, battery charger, conduits, cable trunk, fire rated cable, conduit, conduit fitting, trunking ,interface unit with fire alarm system
,lighting control and BMS systems, etc, and all necessary complete ancillary works & accessories required for the complete installation as
required by UAE fire code, as specified and as required by the drawings.
16.39.1
16.39.1.1 4W Recessed Decorative LED Emergency Light non maintained for corridor and main entrance (IP20) 106 NIU 0
16.39.1.2 4W Surface LED Emergency Light non maintained for indoor area, (IP20) 93 NIU 0
16.39.1.3 4W Surface LED Emergency Light non maintained for wet area, (IP54) 65 NIU 0
16.39.1.4 4W Ceiling or Wall Mounted LED Exit Light for Outdoor Area (IP44) 20 NIU 0
16.39.1.5 4W Ceiling or Wall Mounted LED Exit Light for indoor area ,(IP20) 5 NIU 0
16.39.1.6 4W LED Directional emergency light non maintained , (IP20) 36 NIU 0
16.39.1.7 4W LED Directional emergency light non maintained, (IP44) 15 NIU 0
16.39.1.8 8W LED Emergency Light Surface Non Mounted for parking area 26 NIU 0
16.39.1.9 Advanced Central monitoring PC with Bacnet BMS integration EA 0
16.39.1.10 Central Battery Panel including battery rack 1 NIU 0
16.39.1.11 Emergency lighting points 366 NIU 0
16.4 DIGITAL AUDIO/VIDEO INTERCOM SYSTEM
16.40.1 Specification (Section 16720)

Supply , install, test , commission and maintain Audio / Video intercom system,including but not limited to main entrance panels, power
station ,handsets/wall sets, video shunt unit,power supply and all the required accessories, supports as specified and as shown on the
16.40.1.1 drawings.
16.40.1.1.1 Main entrance panel 4 NIU 0
16.40.1.1.2 Color video intercom flat unit 49 NIU 0
16.40.1.1.3 Conducting, trunking, containments and wiring for the above system. EA 0
16.41 Central Energy and Water Monitoring system:

Supply, install, test and commissioning of complete central energy and water
Metering and monitoring System as per ESTIDAMA requirements, specifications
and drawings, including the following but not limited to, EA 0
Digital Power Monitoring Meters, M bus Master data logger/Ethernet gateway
Central Monitoring Software, Communication network & Cabling
Workstation, Testing & Commissioning, Dash board
16.41.1
16.42 EXTERNAL SERVICES FOR MECHANICAL WORKS
16.42.1 Empty conduits and draw wires between AHUs / FCUs and thermostats ( For wiring by others) EA 0
16.42.1.1 Empty conduits and draw wires between sensors and controls of AC system ( For wiring by others) EA 0
16.43 COMMON ITEMS FOR ENTIRE ELECTRICAL WORKS
16.43.1 Allow for Submittals and Shop drawing. EA 0
16.43.2 Allow for ASBUILT drawings EA 0
16.43.3 Allow for "O & M " Manuals EA 0
16.43.4 Allow for Spares to be handed over to client. EA 0
16.43.5 Allow for Training for the Clients staff EA 0
16.43.6 Allow for maintenance of the complete Electrical installation as specified
16.43.7 Allow for painting and Identification EA 0
16.43.8 Allow for testing and commissioning EA 0
17 CONTRACTOR'S ADJUSTMENT SHEET
17.1 Contractor's Adjustment Sheet (Missing Items in BOQ) EA 0
17.1.1 Item 1 EA 0
17.1.2 Item 2 EA 0
17.1.3 Item 3 EA 0
18 SCHEDULE OF RATES FOR DAYWORKS
18.1 Labour
18.1.1 Scaffolders 0 HUR 0
18.1.2 Steelfixers 0 HUR 0
18.1.3 Plumbers 0 HUR 0
18.1.4 Carpenters and Joiners 0 HUR 0
18.1.5 Plasterers 0 HUR 0
18.1.6 Masons 0 HUR 0
18.1.7 Painters 0 HUR 0
18.1.8 Plant and machinery operators and drivers (Light Duty) 0 HUR 0
18.1.9 Plant and machinery operators and drivers (Heavy Duty) 0 HUR 0
18.1.10 Electricians 0 HUR 0
18.1.11 A/C Mechanics 0 HUR 0
18.1.12 Welders 0 HUR 0
18.1.13 Helpers 0 HUR 0
18.1.14 Labourers 0 HUR 0
18.2 Materials
18.2.1 Contractor's percentage on the net cost of material 0 EA 0
18.3 Equipment & Tools
18.3.1 Wheeled offset excavator with backhoe and shovel (JCB type) 0 HUR 0
18.3.2 Pick up truck up to 3 T capacity 0 HUR 0
18.3.3 Dumper 2 T 0 HUR 0
18.3.4 Concrete vibrator 0 HUR 0
18.3.5 Soil compactor 0 HUR 0
18.3.6 Compressor 0 HUR 0
18.3.7 Tower Crane (.. .. .. .. .. capacity) 0 HUR 0
18.3.8 Mobile crane (.. .. .. .. .. capacity) 0 HUR 0
18.3.9 Generator 0 HUR 0
18.3.10 Scaffolding 0 DAY 0
18.3.11 Gas cutting set with all accessories 0 HUR 0
18.3.12 Dewatering pump with all required accessories 0 DAY 0
18.4 Work Outside Normal Work Hours
18.4.1 Percentage uplift to labour costs for working outside normal site hours ON ENGINEER'S INSTRUCTION. 0 EA 0
19 Consultant Fees
19.1 Consultant Fees 0.04 EA 0
Name of Contractor: …………………………………… File No. 2363

reference Title Unit Price quantity unit Total


1 PRELIMINARIES AND GENERAL REQUIREMENTS
Non-Recurring Preliminary Costs (Mobilization)
1.1 Incurred at the commencement of the Works
Provision of all necessary offices and facilities for the Employer and the Engineer complete with all services, furniture, equipment and EA 0
1.1.1 fixtures as specified.
1.1.2 Provision of all necessary offices, stores and facilities for Contractors' site staff in adequate manner as per the Works required. EA 0
1.1.3 Provision of sign boards as per ADCE design and requirement NIU 0
1.1.4 Provision of Sign board on top of the tower crane of dimensions (3.00 M X 1.22 M) as specified. EA 0
1.1.5 Provision of site hoarding as specified with ADCE logo (Stickers 12 pieces). . EA 0
1.1.6 Submittal of Performance Bond as per the Conditions of the Contract. EA 0
1.1.7 Submittal of all insurances as per the Conditions of the Contract. EA 0
Submittal of Programme for the Works and cash flow , whereby Contractor to submit Construction progarmmme (baseline) to the Engineer EA 0
1.1.8 for approval
Allow for all obligations in accordance with the Contract, which are not mentioned above. The Contractor shall detail and price below any EA 0
1.1.9 other obligations indicating the relevant clause reference in the Contract Documents.
1.2 Recurring Preliminary Costs incurred during the Execution of the Works

EA 0
1.2.1 Maintenance of all necessary offices and facilities for the Employer and the Engineer including all services, furniture, equipment and fixtures.
1.2.2 Maintenance of Contractor's site staff office, stores, and facilities. EA 0
1.2.3 Provision of Contractors site management, administrative and supervisory staff in adequate manner as per the Works needs. EA 0
1.2.4 Provision of all required equipment and tools for the successful execution of the Works such as but not limited to :
1.2.4.1 Light Equipment and tools EA 0
1.2.4.2 Scaffolding EA 0
1.2.4.3 Machinery, cranes, lifting plant, site transport. EA 0
1.2.4.4 Plant required for specific trades. EA 0
1.2.4.5 Maintenance of all above plant . EA 0
1.2.5 Provision of all necessary site power and lighting for the Works. EA 0
1.2.6 Provision of all necessary water for the Works. EA 0
1.2.7 Provision of all necessary sanitation for the Works. EA 0
Provision of safety and security requirements during progress of Works including watching, lighting, safety signs, fire fighting requirements, EA 0
1.2.8 first aid tools, safety shoes, protection helmets, safety belts and protection barriers/handrails, etc.

EA 0
1.2.9 Provide, erect and maintain of all necessary scaffolds, access ways, ladders and the like for the safe and successful completion of the Works.
1.2.10 Provision of all required progress site reports, photos, and other documentation as per the Conditions of the Contract. EA 0
1.2.11 Provision of all required shop drawings and samples as specified and required by the Engineer. EA 0
1.2.12 Provision of all required Quality Assurance and Quality Control as required by the Contract. EA 0
Provision for all inspections and testing necessary for the acceptance of the Works in accordance with the Specifications and the Conditions EA 0
1.2.13 of the Contract.
1.2.14 Maintaining site hoarding and sign boards. EA 0
1.2.15 Cleaning up and removal of rubbish during the progress of the Works to the satisfaction of the Engineer. EA 0
1.2.16 The programme shall be updated each month to reflect actual progress at site EA 0
1.2.17 Provision for reservation parking during execution of the project and paying DOT related charges/fees EA 0
Allow for all obligations in accordance with the Contract, which are not mentioned above. The Contractor shall detail and price below any EA 0
1.2.18 other obligations indicating the relevant clause reference in the Contract Documents.
1.3 Non-Recurring Preliminary Costs (Demobilization) incurred at the Completion of the Works
Demobilization and removal of all offices and facilities for the Employer and the Engineer including all services, furniture, equipment and EA 0
1.3.1 fixtures.
1.3.2 Demobilization and removal of all offices, stores and facilities. EA 0
1.3.3 Demobilization and removal of all equipment and tools. EA 0
1.3.4 Provision of all required As Built drawings, Operation and Maintenance Manuals and guarantees. EA 0
Clearing up and making good site establishment after completion of the Works and demobilization. This includes re-instating surrounding EA 0
1.3.5 areas affected by the construction works.
Allow for all obligations in accordance with the Contract, which are not mentioned above. The Contractor shall detail and price below any EA 0
1.3.6 other obligations indicating the relevant clause reference in the Contract Documents.
2 SITE CONSTRUCTION
2.1 Soil investigation

Geotechnical investigations/ Allow for drilling 8 Nos. of boreholes, Nos. 4 to a depth of 50m , and Nos. 4 to a depth of 40m each with at least EA 0
2.1.1 two meters in the rock strata and submitting a complete soil investigation report by an approved and ADCE registered and specialized firm.
2.1.2 Geophysical investigation/Allow for performing geophysical investigations as per relevant authorities requirements, rules and regulations. EA 0
Fixed total amount of AED 62,900.00 to be paid by the awarded contractor related to 3rd party verification and approval fees during design EA 0
2.1.3 stage.
2.2 Dewatering

Allow for design ,installing, maintaining and taking away upon completion, dewatering system as designed by a specialist firm registered
with ADCE and approved by the consultant engineer and local authorities, to lower the water level at least one meter below bottom level of EA 0
foundations and to keep all excavations free from water from whatever source. And to keep the site in a safe and secure working conditions
2.2.1 all the time. And should never stop until a written approval from the consultant engineer
2.3 Site Clearance

EA 0
2.3.1 The Contractor shall allow for the removal from site of all rubbish and debris and any existing foundations prior to commencement of Works.
2.4 Existing Utilities
Allow for carefully relocating/shifting any existing utilities in work areas including hand excavating trial holes and all necessary earthwork
2.4.1 supports.
Where utilities are to remain in place provide adequate means of support and protection during excavation and shoring operations, pilling EA 0
2.4.2 works and construction stages.
2.5 Shoring
2.5.1 permanent shoring

Allow for secant piling shoring system with min. dia 800 mm to be used as permanent shoring, as designed by a specialist firm registered
with ADCE and approved by the consultant engineer and local authorities, constructed using sulfate resistant Portland cement or as EA 0
recommended by soil investigation report and having a minimum 28-day compressive strength of 45 N/Sq.mm as per drawings and
2.5.1.1 specification . Steel reinforcement shall be provided as per drawings and specifications.

The cost includes submittal of structural design calculations and shop drawings, obtaining approval from Municipality,
mobilization/demobilization, guide wall, primary/secondary piles, chipping off piles heads, capping beam, bracing piping system, dismantling LM 0
2.5.1.2 and disposing off when suitable, side anchors, distressing when suitable. 147
2.6 Excavation
2.6.1 Excavate to reduce levels to the required levels shown on drawings for any type of foundations ... 17767 MTQ 0
2.7 Disposal
2.7.1 Remove surplus excavated material from site 17767 MTQ 0
2.8 ANTI-TERMITE TREATMENT
2.8.1 Allow for anti-termite treatment to all below and above ground levels as specified. 3229 MTK 0
2.9 Piling
Execute and install cast in situ reinforced Concrete Piles using temporary casing system as designed by a specialist firm registered with
2.9.1 ADCE and approved by the consultant engineer and local authorities, and per drawings and specification.
2.9.2 The Contractor shall be responsible for the adequacy of the pile foundations installed to carry the working loads safely and securely.
The Contractor shall be responsible to calculate the depth of piles based on the geotechnical report and to the consultant’s engineer and
2.9.3 Municipality Engineer's approval.
2.9.4 Mobilization and of plant and equipment to site. EA 0
Cast in situ piles including concrete of 50 N/sq.mm. boring through any type of soil, reinforcement cages and removal of surplus material
2.9.5 arising off site.
2.9.5.1 P1- 750 mm dia. pile, minimum capacity as per Drawings. 10 NIU 0
2.9.5.2 P2- 900 mm dia. pile, minimum capacity as per Drawings. 68 NIU 0
2.9.6 Pile Testing
2.9.6.1 Allow for load testing on piles in accordance with the specification.
2.9.6.1.1 Static Load Testing
2.9.6.1.1.1 P1 of 750 mm dia. 1 NIU 0
2.9.6.1.1.2 P2 of 900 mm dia. 1 NIU 0
2.9.6.1.2 Dynamic Load Testing
2.9.6.1.2.1 P1 of 750 mm dia. 1 NIU 0
2.9.6.1.2.2 P2 of 900 mm dia. 1 NIU 0
2.9.6.1.3 Allow for integrity test for all piles
2.9.6.1.3.1 P1 of 750 mm dia. 10 NIU 0
2.9.6.1.3.2 P2 of 900 mm dia. 68 NIU 0
2.9.6.2 Allow for chipping off the extra concrete from piles to the required height retaining the steel reinforcement using an approved method.
2.9.6.2.1 P1 of 750 mm dia. 10 NIU 0
2.9.6.2.2 P2 of 900 mm dia. 68 NIU 0
2.9.6.3 demobilization of plant and equipment from site on completion. EA 0
2.11 PAVING
Ditto but for Gate Barrier Supply and fix heavy-duty Gate barrier with extruded aluminum arms white enameled with red light-reflecting
stripes and controlled by ANPR camera technology and provided with a safety magnetic loop detector and "No Entry & Stop" Sign where
2.11.1 appropriate.
2.11.1.1 Gate Barrier at Ground Floor Entrance 2 NIU 0
2.11.2 Interlock paving to Ground Floor 392 MTK 0
2.11.3 Supply and paint Precast curbstone as per municipality and roads dept. 128 LM 0
2.11.4 Road/traffic markings as specified and as per municipality and roads dept. EA 0
2.11.5 Sundries
2.11.5.1 Allow for any other miscellaneous work in connection with site construction. EA 0
3 CONCRETE WORKS
3.1 FINISHING OF EXPOSED SURFACES OF SECANT PILES
Prepare and apply 100 mm thick shotcrete in accordance with the Specification including all necessary reinforcements and thickening as MTK 0
3.1.1 required to absorb the irregularities and alignment of substructure surfaces. 1916
3.2 SUBSTRUCTURE
3.2.1 Concrete work in accordance with specification
3.2.1.1 Plain Concrete
3.2.1.1.1 Plain concrete using Moderate sulphate resistant cement in accordance with specifications and drawings.
3.2.1.1.1.1 100 mm thick, blinding concrete 133 MTQ 0
3.2.1.2 Reinforced Concrete
Reinforced concrete for sub-structure, grade and strength of concrete as per structure drawing and specification all includes, formwork,
3.2.1.2.1 Reinforcement grade 460 N/mm2, Corrosion Inhibitor and all necessary works. The design mix to be approved by the Engineer.
3.2.1.2.1.1 Pile Cap 334 MTQ 0
3.2.1.2.1.2 Raft Slab 668 MTQ 0
3.2.1.2.1.3 Retaining Wall 552 MTQ 0
3.2.1.2.1.4 Columns 101 MTQ 0
3.2.1.2.1.5 Walls, Water Tank and Core Walls 383 MTQ 0
3.2.1.2.1.6 Beams 47 MTQ 0
3.2.1.2.1.7 Slab of any Thickness 1077 MTQ 0
3.2.1.2.1.8 Staircase and landing 26 MTQ 0
3.2.1.2.1.9 Ramp Slab 153 MTQ 0
3.2.1.2.2 Sundries
3.2.1.2.2.1 Allow for crystalline waterproofing add mixture to water tank base slab and wall. EA 0
3.2.1.3 Substructure Waterproofing
3.2.1.3.1 One layer of polythene sheets laid on compacted fill, 1200 gauge 1325 MTK 0
3.2.1.3.2 Pile head treatment using waterproofing membrane 20mm thickness epoxy mortar.
3.2.1.3.2.1 To pile, 750mm dia. 10 NIU 0
3.2.1.3.2.2 To pile, 900mm dia. 68 NIU 0
One layer of synthetic membrane made of plasticized PVC 2mm thickness including non-woven Geotextile for concrete faces in contact with
3.2.1.3.3 soil.
3.2.1.3.3.1 Geotextile 370g/m2 Laid horizontally 1276 MTK 0
3.2.1.3.3.2 Geotextile 370g/m2 Laid vertically 2254 MTK 0
3.2.1.3.3.3 PVC membrane Laid horizontally 1276 MTK 0
3.2.1.3.3.4 PVC membrane Laid vertically 2254 MTK 0
3.2.1.3.3.5 50 mm Cement Sand screed in accordance with specification and drawings
3.2.1.3.3.5.1 Above the foundation waterproofing 1276 MTK 0
3.2.1.4 Water Tank Lining
Supply and fix in place GRP Lining for all inner surfaces of water tank including the water tank ceiling and neck as specified. The Contractor MTK 0
3.2.1.4.1 should furnish certificate supporting that the materials used are suitable for potable water usage. 274
3.2.1.4.2 10 x 10 mm Angle fillet non-toxic elastic mortar. 50 LM 0
3.2.1.4.3 GRP Ladder to Fire Water Tank & Domestic Water Tank. 2 NIU 0
3.3 SUPERSTRUCTURE
3.3.1 Concrete work in accordance with specification
Reinforced concrete for super-structure grade ad strength of concrete as per drawings and specification all includes formwork, Reinforcement
3.3.1.1 grade 460 N/mm2 and all necessary works. The design mix to be approved by the Engineer
3.3.1.1.1 Columns & Planted Columns 162 MTQ 0
3.3.1.1.2 Walls, Core walls and Plinth Walls 443 MTQ 0
3.3.1.1.3 Beams 87 MTQ 0
3.3.1.1.4 Slabs of any thickness and grade 1858 MTQ 0
3.3.1.1.5 Staircase and landing 48 MTQ 0
3.3.1.1.6 Step and ramp 7 MTQ 0
3.3.1.1.7 Parapet 4 MTQ 0
3.3.1.1.8 Sundries
Allow for all joints including isolation, control, construction and contraction joints or the like as required all in accordance with the drawings EA 0
3.3.1.1.8.1 and specification excluding expansion joints.
3.3.1.1.8.2 Concrete for Roof equipment / Tanks foundation, complete item as per drawing and details 18 MTQ 0
3.3.1.1.8.3 Precast Concrete cover for OTS Cover 23 MTK 0
4 MASONRY
Precast concrete blocks laid with cement sand mortar including all necessary fixings and accessories, complete; in accordance with
4.1 Specifications and drawings
4.2 Hollow Blocks - Internal Wall
4.2.1 100 mm thick, hollow block walls 2724 MTK 0
4.2.2 150 mm thick, hollow block walls 70 MTK 0
4.2.3 200 mm thick, hollow block walls 2886 MTK 0
4.2.4 250 mm thick , hollow block walls 81 MTK 0
4.2.5 300 mm thick, hollow block walls 271 MTK 0
4.2.6 400 mm thick, hollow block walls 126 MTK 0
4.3 Insulated Blocks - External Wall
4.3.1 100 mm thick block walls 53 MTK 0
4.3.2 200 mm thick block walls 1570 MTK 0
4.3.3 250 mm thick block walls 16 MTK 0
4.3.4 300 mm thick block walls 116 MTK 0
4.3.5 400 mm thick block walls 4 MTK 0
4.4 Cavity Walls
4.4.1 100 mm hollow block wall + Gap + 100 mm hollow block wall 253 MTK 0
4.4.2 100 mm hollow block wall + Gap + 150 mm hollow block wall 4 MTK 0
4.4.3 100 mm hollow block wall + Gap + 200 mm hollow block wall 146 MTK 0
4.4.4 150 mm hollow block wall + Gap + 150 mm hollow block wall 5 MTK 0
4.4.5 200 mm hollow block wall + Gap + 200 mm hollow block wall 30 MTK 0
4.5 Lintels including concrete, reinforcement, shuttering all in accordance to drawings and specifications.
4.5.1 Size 200 x 200 mm 167 LM 0
4.5.2 Size 200 x 300 mm 185 LM 0
4.6 Sundries
4.6.1 Allow for joint filling sealant two part polysulphide sealant. EA 0
4.6.2 Allow for isolation and expansion joint as required by a compressed sheet of wood fiber impregnated with bitumen emulsion. EA 0
5 METALWORKS
5.1 Non-Structural Metalwork
5.1.2 Balustrades and Handrails
5.1.2.1 Powder coated Aluminum handrail for staircases, fixed to steps complete as per drawings. 167 LM 0
5.1.2.2 Powder coated Aluminum handrail for staircases, wall mounted complete as per drawings. 154 LM 0
5.1.3 Ladders
Supply and fix Die Cast Aluminum Cat ladder including all necessary fixing accessories; all accordance with the drawings and Specification NIU 0
5.1.3.1 to Roof 1
5.1.4 Louvers
5.1.4.1 Supply and fix Aluminum Louver Wall including all necessary fixing accessories; all accordance with the drawings to Ground Floor 404 MTK 0
5.1.4.2 Allow for Aluminum Louver door as access to Roof 3 NIU 0
5.1.4.3 Supply and install Acoustic louver as shown in the Drawings 12 MTK 0
5.1.5 Aluminum Cladding
Supply and fix fire rated aluminum composite panel all complete including frames, rockwool insulation and all necessary fixing accessories; MTK 0
5.1.5.1 all in accordance with the drawings, civil specifications, and ADCD requirements. 2423
Allow for steel support to box aluminum cladding all complete including necessary fixing accessories as per drawings. (Aluminum cladding NIU 0
5.1.5.2 measured separately) 146
5.1.5.3 Other Items
5.1.5.3.1 Supply and install Fresh air intake sand trap louver as shown in the Drawings 14 MTK 0
5.1.6 Balcony Railing
5.1.6.1 Supply and fix aluminum balcony railing all complete including all necessary finish and fixings as per drawings. 109 LM 0
5.1.7 Metal Grating
5.1.7.1 400 mm wide floor drain grating and angle frame for parking ramps 27 LM 0
5.1.7.2 Sundries
5.1.7.2.1 Access panel and hatches including fittings, fixing accessories etc.. Complete as per drawings and specifications. EA 0
Provide and fix in the main entrance lobby, a 60x40x.02 cm stainless steel signage plate to declare the Building Name, Building No. and NIU 0
5.1.7.2.2 ADCP the property manager. 1
6 WOOD AND PLASTICS
6.1 KITCHEN CABINETS
Kitchen Cabinet: Supply and fix 18mm thick MDF with Laminate and PVC edge Kitchen cabinet includes frames, fixing, painting,
6.1.1 ironmongery etc.. all complete in accordance with the drawings and Specification.
6.1.1.1 K01
6.1.1.1.1 For upper cabinet in 350 mm depth 3 LM 0
6.1.1.1.2 For lower cabinet in 600 mm depth 3 LM 0
6.1.1.1.3 Kitchen Counter Tops - Gray sardo 3 LM 0
6.1.1.1.4 Kitchen Counter Backsplash - 70mm high Gray sardo 3 LM 0
6.1.1.2 K02
6.1.1.2.1 For upper cabinet in 350 mm depth 89 LM 0
6.1.1.2.2 For lower cabinet in 600 mm depth 51 LM 0
6.1.1.2.3 Kitchen Counter Tops - Gray sardo 88 LM 0
6.1.1.2.4 Kitchen Counter Backsplash - 70mm high Gray sardo 51 LM 0
6.1.1.2.5 Kitchen Counter Top under wall - 900 mm high Gray sardo 36 LM 0
6.1.1.3 K03
6.1.1.3.1 For upper cabinet in 350 mm depth 48 LM 0
6.1.1.3.2 For lower cabinet in 600 mm depth 37 LM 0
6.1.1.3.3 Kitchen Counter Tops - Gray sardo 90 LM 0
6.1.1.3.4 Kitchen Counter Backsplash - 70mm high Gray sardo 37 LM 0
6.1.1.3.5 Kitchen Counter Top under wall - 900 mm high Gray sardo 65 LM 0
6.1.1.4 K04
6.1.1.4.1 For upper cabinet in 350 mm depth 76 LM 0
6.1.1.4.2 For lower cabinet in 600 mm depth 53 LM 0
6.1.1.4.3 Kitchen Counter Tops - Gray sardo 53 LM 0
6.1.1.4.4 Kitchen Counter Backsplash - 70mm high Gray sardo 53 LM 0
6.1.1.5 K05
6.1.1.5.1 For upper cabinet in 350 mm depth 9 LM 0
6.1.1.5.2 For lower cabinet in 600 mm depth 6 LM 0
6.1.1.5.3 Kitchen Counter Tops - Gray sardo 15 LM 0
6.1.1.5.4 Kitchen Counter Backsplash - 70mm high polished granite 6 LM 0
6.1.1.5.5 Kitchen Counter Top under wall - 900 mm high Gray sardo 8 LM 0
6.2 BUILT-IN WARDROBES
6.2.1 Supply and fix in place factory made wardrobes including ironmongeries, as specified.
6.2.2 Wooden Cupboard 01 18 NIU 0
6.2.3 Wooden Cupboard 02 20 NIU 0
6.2.4 Wooden Cupboard 03 14 NIU 0
6.2.5 Wooden Cupboard 04 2 NIU 0
6.3 CABINETS
Supply and fix 18mm thick MDF with Laminate and PVC edge 1100mm depth washing machine cabinet includes frames, fixing, painting, NIU 0
6.3.1 ironmongery etc.. all complete in accordance with the drawings and Specification. 18
6.3.2 Supply and fix of Water meter cabinet all complete as per drawings and specifications 11 NIU 0
6.5 COUNTERS
6.5.1 Fabricate and fix counter at main entrance as per drawings. EA 0
6.6 BUILDING SIGNAGE
Supply and installation of External and Internal Building Signage including all signage accessories and fixing accessories all accordance with
6.6.1 the signage drawings.
6.6.1.1 S1-02 26 NIU 0
6.6.1.2 S1-03 33 NIU 0
6.6.1.3 S2-02 23 NIU 0
6.6.1.4 S2-03 33 NIU 0
6.6.1.5 S3-01 57 NIU 0
6.6.1.6 S3-03 18 NIU 0
6.6.1.7 S3-04 3 NIU 0
6.6.1.8 S3-05 36 NIU 0
6.6.1.9 S3-06 48 NIU 0
6.6.1.10 S3-07 1 NIU 0
6.6.1.11 S3-08 4 NIU 0
6.6.1.12 S3-10 24 NIU 0
6.6.1.13 S3-14 20 NIU 0
6.6.1.14 S3-15 21 NIU 0
6.6.1.15 S3-22 4 NIU 0
6.6.1.16 S4-01 1 NIU 0
6.6.1.17 S4-02 21 NIU 0
7 THERMAL AND MOISTURE PROTECTION
7.1 ROOFING SYSTEM
7.1.1 Roof waterproofing system as per drawing including Cement tile finish. 1097 MTK 0
7.2 WET AREAS
7.2.1 Two Coats of Flexible, One Component , Polyurethane, Liquid Applied, elastomeric waterproofing coating
7.2.2 Laid horizontally (Toilet, Bath, Kitchen, & Balcony) 953 MTK 0
7.2.3 250mm Laid vertically (including wall behind bathtubs and full height on shower side) 328 MTK 0
7.2.4 50 mm Cement Sand screed in accordance with specification and drawings above the waterproofing of wet areas 953 MTK 0
7.3 Waterproof for Exposed Ground Floor Slab
7.3.1 One layer of synthetic membrane made of plasticized PVC 1.5mm thickness including non-woven Geotextile
7.3.2 Geotextile 370g/m2 Laid horizontally including ramp 423 MTK 0
7.3.3 PVC membrane Laid horizontally 423 MTK 0
7.4 THERMAL & MOISTURE INSULATION OF SURFACES BEHIND EXTERNAL CLADDING
7.4.1 Supply and fix on concrete and/or block work behind external cladding, vapor barrier paint. EA 0
7.5 Fire Stopping
7.5.1 Fire stopping inside ducts, dampers and cable trays. EA 0
7.5.2 Voids between fire rated floor slabs and exterior curtain walls and openings Through Floors and Walls. EA 0
7.5.3 SUNDRIES:

EA 0
7.5.3.1 Provide Expansion joint cover all complete from floor to floor, floor to wall and corner wall as necessary as per drawing and specification..
7.5.3.2 Dress roof finishes around Mechanical Equipment footing. EA 0
8 DOORS AND WINDOWS
The rates for all doors shall include plywood sub-frame, architrave, transoms, stops, glazing, decorations, ironmongery, thresholds, civil
8.1 defense approval for fire rated doors … etc all in accordance with drawings and specification.
Wooden Doors: Supply and 50mm thickness timber flush doors fix flush wooden door with paint finish with frame including finishes, etc..
8.1.1 complete in accordance with the Drawing and Specification.
8.1.1.1 Single Leaf, hinged door, Size 1.10 x 2.35, Type DT01, 60min Fire Rated 48 NIU 0
8.1.1.2 Single Leaf, hinged door, Size 0.90 x 2.20, Type DT02 51 NIU 0
8.1.1.3 Single Leaf, hinged door, Size 0.90 x 2.20, Type DT03, 60min Fire Rated 4 NIU 0
8.1.1.4 Single Leaf, hinged door, Size 0.80 x 2.20, Type DT04 119 NIU 0
8.1.1.5 Single Leaf, hinged door, Size 1.00 x 2.20, Type DT05 4 NIU 0
8.1.1.6 Single Leaf, hinged door, Size 0.90 x 2.20, Type DT06, 60min Fire Rated 6 NIU 0
Single Leaf, hinged door, Size 1.00 x 2.20, Type DT07 NIU 0
8.1.1.7 60min Fire Rated 13
Single Leaf, hinged door, Size 1.10 x 2.20, Type DT08 NIU 0
8.1.1.8 60min Fire Rated 15
Double Leaf, hinged door, Size 1.60 x 2.20, Type DT09 NIU 0
8.1.1.9 60min Fire Rated 10
Double Leaf, hinged door, Size 1.00 x 2.20, Type DT10 NIU 0
8.1.1.10 60min Fire Rated 1
Single Leaf, hinged door, Size 0.70 x 2.20, Type DT11 NIU 0
8.1.1.11 60min Fire Rated 3
8.1.1.12 Double Leaf, hinged door, Size 1.80 x 2.2, Type DT12 48 NIU 0
Steel Doors: Supply and fix of Steel doors, including finishes, ironmongery, etc.... complete in accordance with the Drawing and
8.1.2 Specification.
8.1.2.1 Single Leaf, hinged door, Size 1.10 x 2.20, Type DS01, 90min Fire Rated 15 NIU 0
8.1.2.2 Single Leaf, hinged door, Size 0.90 x 2.20, Type DS02, 90min Fire Rated 9 NIU 0
8.1.2.3 Double Leaf, hinged door, Size 1.60 x 2.50, Type DS03, 90min Fire Rated 4 NIU 0
8.1.2.4 Single Leaf, hinged door, Size 1.00 x 1.90, Type DS04 1 NIU 0
8.1.3 Aluminum Doors: Supply and fix Aluminum Doors including Ironmongery complete in accordance with the Drawings and Specifications.
8.1.3.1 Double Leaf, hinged door, Size 2.50 x 3.50, Type DA01 1 NIU 0
8.1.3.2 Double Leaf, hinged door, Size 2.50 x 3.00, Type DA02 2 NIU 0
8.1.3.3 Double Leaf, hinged door, Size 2.50 x 2.20, Type DA04 1 NIU 0
8.2 Glass Partition
8.2.1 Supply and fix Tempered Glass Partition to Bathrooms including all necessary fixing and accessories all accordance with the drawings.
8.2.2 2100mm height Glass Partition 102 LM 0
Curtain Wall: Supply and fix Glazing Panels all complete including insulation and all necessary fixing accessories; all accordance with the
8.3 drawings and Specification. (Curtain Wall size As Per Curtain Wall Details)
8.3.1 Curtain Wall 2295 MTK 0
8.4 Glass Balustrade
8.4.1 1.20 m high glass parpet wall to Roof 122 LM 0
9 FINISHES
9.1 I- INTERNAL FINISHES
9.1.1 Flooring
9.1.1.1 Cement and sand screed to floor to receive finishes
9.1.1.1.1 50mm thick to receive Paint 886 MTK 0
9.1.1.1.2 100mm thick under Wardrobe 87 MTK 0

9.1.1.2 Supply and fix Stone Tile thickness, pattern and types shown on the drawings all complete in accordance with drawings and specifications.
9.1.1.2.1 F06 - 600x1200 mm Pianco Laza Marble Floor Tile (Entrance Lobby, Ground Floor Lift Lobby, Lobby, Entrance Approach) 97 MTK 0
9.1.1.2.2 Supply and fix Porcelain tiles as per finishing schedule including leveling screed, mortar bedding and grout, etc… to Engineer's Approval.
F01 600x600mm Full body rectified porcelain floor tiles. (Basement Lift Lobby, Typical Lift Lobby, Retail, Retail Entrance, Guard Room, MTK 0
9.1.1.2.3 Office, Living and Dining Room, Flat Corridor, Bedroom, Dressing, Store). 2564
9.1.1.2.4 F02 600x600mm Non Slip full body rectified porcelain floor tiles (Kitchen/Pantry). 1835 MTK 0
9.1.1.2.5 F02a 300x300mm Non-slip full body rectified porcelain tiles (Bathroom, Toilet and Washrooms). 458 MTK 0
9.1.1.3 Supply and fix Ceramic tiles as per finishing schedule including leveling screed, mortar bedding and grout, etc… to Engineer's Approval.
9.1.1.3.1 F05 300x300 Semi Glazed flooring Ceramic (Garbage Room). 26 MTK 0
Paint Flooring - Prepare, supply and apply Epoxy Coating finish on screed (screed measured separately) all complete in accordance with
9.1.1.4 drawings and specifications.
9.1.1.4.1 F03 - For Stairs and Service Corridors 476 MTK 0
F04 - For Service Areas (HV Room, Transformer Room, Control Room, ECC Room, Gas Room, Electrical Room, Tel Room, Generator MTK 0
9.1.1.4.2 Room, and Etc..) 325
9.1.1.4.3 F07 - For Service Areas on Basement Floors (Pump Room, Electrical Room, Tel Room) 85 MTK 0

F08 - Traffic Deck Coating System consists of Abrasion resistant Epoxy resin floor coating skid resistant with non slip aggregates, multi layer
flexible polyurethane resin based coating reinforced with glass flake epoxy as shown on the drawing and finishing schedule and approved by
9.1.1.4.4 Engineer
9.1.1.4.4.1 Parking Bays 1162 MTK 0
9.1.1.4.4.2 Drive way 1240 MTK 0
9.1.1.4.4.3 Ramps 496 MTK 0
9.1.1.4.4.4 Walk Way / Platform 330 MTK 0
9.1.2 SKIRTING
S01 80mm high Porcelain Tiles (Foyer, Flat Corridor, Living/Dining Room, Bedroom, Dressing Room, Maid's Room, Janitor's Room, LM 0
9.1.2.1 Storage) 2061
9.1.2.2 S02 Epoxy Paint to Staircase 12 LM 0
9.1.2.3 S03 Epoxy Coating System (Fire Lift Lobby and other Service Areas) 387 LM 0
9.1.2.4 THRESHOLD
9.1.2.5 30mm thk Marble Threshold Width as per drawings. 428 LM 0
9.1.3 WALL FINISHES
9.1.3.1 Cement sand plaster 20 mm thick for walls.
9.1.3.1.1 To concrete, block walls to receive paint. 11744.605445 MTK 0
9.1.3.1.2 To concrete, block walls to receive porcelain and ceramic tiles 4709 MTK 0

9.1.3.2 Supply and fix Stone Tile thickness, pattern and types shown on the drawings all complete in accordance with drawings and specifications.

MTK 0
9.1.3.2.1 W06 Statuario Marble Wall Tiles (Entrance Lobby, Reception, Ground Floor Lift Lobby, and Ground Floor Lobby and Mezzanine Corridor). 278
9.1.3.3 Supply and fix Porcelain tiles as per finishing schedule including all necessary fixing to Engineer's Approval. MTK 0
9.1.3.3.1 W02 600x300mm Full body Porcelain wall tiles (Kitchen/Pantry). 1177 MTK 0
9.1.3.3.2 W02a 300x200mm Full body Porcelain Wall Tiles (Bathroom, Toilet and Washroom). 2132 MTK 0
9.1.3.3.3 W07 600x1200mm Full Body Porcelain Wall Tile to Basement, Mezzanine and Typical Lift Lobby. 1264 MTK 0
9.1.3.4 Supply and fix Ceramic tiles as per finishing schedule including all necessary fixing to Engineer's Approval.
9.1.3.4.1 W05 300x300mm Ceramic wall tiles (Garbage Room). 136 MTK 0
9.1.3.5 Painting and Decoration
9.1.3.5.1 Prepare, supply and apply Paint finish to wall all complete in accordance with drawings and specifications.
9.1.3.5.1.1 W01 Acrylic Emulsion Paint (Retail, Guard's Room, Office, Living and Dinning, Flat Corridor, Bedroom, Dressing and Store). 6291 MTK 0
9.1.3.5.1.2 W03 Acrylic smooth flexible satin paint (Stairs and Service Corridor) 1458 MTK 0
9.1.3.5.1.3 W04 Semi Epoxy Textured Coating (Service Areas) 1349 MTK 0
9.1.3.5.1.4 W08 Anti Carbonation Paint (Basement Walls) 2695 MTK 0
9.1.4 Ceiling Finishes
9.1.4.1 Cement sand plaster 15 mm thick for ceiling.
9.1.4.1.1 Soffits to received paint 2816 MTK 0
9.1.4.2 Painting and Decoration
Prepare, supply and apply Paint finish on plastered ceiling / gypsum board ceiling (plaster & Gypsum board measured separately) all
9.1.4.2.1 complete in accordance with drawings and specifications.
9.1.4.2.1.1 C02 Washable Emulsion Paint for plaster ceiling 1910 MTK 0
9.1.4.2.1.2 C07 Paint on Alkali Resistant Primer (Service Rooms/Area and Stairs) 906 MTK 0
9.1.4.2.1.3 C08 Anti Carbonation Paint on fair faced concrete at Basement 3172 MTK 0
9.1.4.2.1.4 Washable Emulsion Paint for Gypsum Board Ceiling as per specification and drawing to Engineer's Approval 2211 MTK 0

Anti fungus paint for wall above false ceiling, ceiling and lift core wall consists of One coat of primer based on special high quality, alkali
resistant acrylic binder + Two Separate coats superior quality, special acrylic based black emulsion paint with crack tolerance to fungal MTK 0
9.1.4.2.1.5 growth as approved by the Engineer 6626
9.1.4.3 False ceilings
Supply and fix Ceiling finish, pattern and types as per details includes grooves etc.. All complete in accordance with drawings and
9.1.4.3.1 specifications.
C01 Gypsum Plaster Board to receive Paint Finish (paint measured separately) to Entrance Lobby, Lift Lobby (Basements, Ground Floor and MTK 0
9.1.4.3.1.1 Typical Floor), Entrance Approach, Retail Entrance, Living/Dining, Flat Corridor, Bedroom, Dressing and Store. 1159
9.1.4.3.1.2 C03 600x600 Aluminum Tile Ceiling to Toilet, Bathroom, Kitchen, Pantry and Guard's Room 451 MTK 0
9.1.4.3.1.3 C03 Moisture Resistant Gypsum Board to Toilet, Bathroom, Kitchen, Pantry and Guard's Room 502 MTK 0
9.1.4.3.1.4 C04 600x600 Gypsum Tile Ceiling to Retail and Office 647 MTK 0
9.1.4.3.1.5 C04 Gypsum Board Ceiling to Retail and Office 288 MTK 0
9.1.4.3.1.6 C05 600x1200 Gypsum Tile Ceiling to Corridors 277 MTK 0
9.1.4.3.1.7 C06 Gypsum Board Ceiling to Ground Floor Cooridor 17 MTK 0
9.1.4.3.1.8 C10 Cement Fiber Board 18 MTK 0
9.1.4.3.1.9 Allow for Gypsum Bulkhead to Basement Lift Lobby (paint measured separately) 91 LM 0
9.1.4.3.1.9.1 Ditto to Ground Floor Lift Lobby (paint measured separately) 129 LM 0
9.1.4.3.1.9.2 Ditto to Residential inside Flat 270 LM 0
9.1.4.3.1.10 Allow for Cement fiber board Bulk head to Ground floor 17 LM 0
9.2 II- EXTERNAL FINISHES
9.2.1 Floors
9.2.1.1 Granite Steps to Ground Floor Pedestrian Ramp and Entrance approach 35 MTK 0
9.2.1.2 Granite Steps to Entrance 13 LM 0
9.2.1.3 Interlock paving to Ground Floor 392 MTK 0
9.2.2 Walls
9.2.2.1 20mm thick plaster to concrete, block walls and walls for External Wall and OTS to received paint 622 MTK 0
9.2.2.2 Paint for External Walls 622 MTK 0
9.3 Vanity Counter Top

9.3.1 Supply and fix Pianco Laza Countertop complete with all necessary fixing accessories; all accordance with the drawings and specification
9.3.1.1 250mm wide Vanity Counter Top including 280mm high Facia to Bathrooms and Toilets 82 LM 0
9.3.1.2 250mm Cistern Counter Top To Bathrooms 73 LM 0
9.3.2 III- SUNDRIES
9.3.2.1 CAR PARKING
9.3.2.2 Columns protection. 48 NIU 0
9.3.2.3 Walls protection. EA 0
9.3.2.4 Ready made rubber speed humps. EA 0
9.3.2.5 Pre-cast wheel stopper length as per drawings 63 NIU 0
9.3.2.6 Concaved traffic mirrors 9 NIU 0
10 PLUMBING AND DRAINAGE
10.1 WATER SUPPLY SYSTEM
Supply, install, testing and commissioning of all cold water piping complete with support and all necessary fittings, valves and accessories;
10.1.1 all in accordance with drawings and specification
Complete internal concealed piping in Poly Propylene Random pipes for cold water supply with all necessary fittings, supports and
10.1.1.1 accessories. Rates shall include all flushing, cleaning, testing and commissioning. For Outer Diameter:
10.1.1.1.1 20Ø LM 0
10.1.1.1.2 25Ø LM 0
10.1.1.1.3 32Ø LM 0
10.1.1.1.4 40Ø LM 0
10.1.1.1.5 50Ø LM 0
10.1.1.1.6 63Ø LM 0
10.1.1.1.7 75Ø LM 0
10.1.1.1.8 90Ø LM 0

Complete water supply filling lines, transfer pipes, overflow pipes, boosted water riser and gravity riser piping with UPVC pressure pipes,
suitable for system working pressure, with all necessary fittings, supports and accessories as specified and shown on drawings. Rates shall
10.1.1.2 include all flushing, cleaning, testing and commissioning. For Outer Diameter:
10.1.1.2.1 20Ø LM 0
10.1.1.2.2 25Ø LM 0
10.1.1.2.3 32Ø LM 0
10.1.1.2.4 40Ø LM 0
10.1.1.2.5 50Ø LM 0
10.1.1.2.6 63Ø LM 0
10.1.1.2.7 75Ø LM 0
10.1.1.2.8 90Ø LM 0
10.1.1.2.9 110Ø LM 0
10.1.1.2.10 All exposed Pipes on roof, plant rooms and basement shall be insulated and protected with cladding as specified LM 0
10.1.1.3 PEX pipes complete with sleeves for all cold water droppers from above false ceiling to the fixtures LM 0

Supply, install, testing and commissioning of all hot water piping Stabilized PPR, PN-20 complete with insulation, supports and all necessary
fittings, valves and accessories; all in accordance with drawings and specification. Rates shall include all flushing, cleaning, testing and
10.1.2 commissioning. For Outer Diameter:
10.1.2.1 20Ø
10.1.2.2 25Ø LM 0
10.1.2.3 Hot water pipe insulation as specified complete with vapour barrier
10.1.2.4 PEX pipes complete with sleeves for all hot water droppers from above false ceiling to the fixtures LM 0

Complete external piping connections, from ADDC Main to underground water tank, including all Meters, cabinets, accessories and valves,
as specified, and required by ADDC and to the approval of the Engineer. Rates shall include all flushing, cleaning, testing and EA 0
10.1.3 commissioning as specified.
10.1.4 Each bathroom, toilet and kitchen shall have Chromium plated, Concealed main isolating valve for ease of maintenance. NIU 0
10.1.5 Each Sanitary ware shall have Chromium plated, isolating valve for ease of maintenance. Valves shall be same as fitting's mixers type. NIU 0
10.1.6 Water Tanks:

Supply, installation, testing and commissioning of Water tanks; GRP panel type; including associated tank ancillaries, insulation, vent pipes
level switches, heavy duty cover, float valves, GRP ladder, concrete base, fittings, supports and all necessary accessories and connections;
10.1.6.1 complete all in accordance with the drawings, specifications and as per ADDC regulations.
10.1.6.1.1 Raw water tank 18 MTQ 0
10.1.6.1.2 Filtered water tank 18 MTQ 0
10.1.6.1.3 Fiber glass pressure break tank for filter back wash 1 MTQ 0
All fittings and accessories for underground water tanks including vent float valves,associated pipe work etc.(Internal and External ladder
10.1.6.2 and Access door by civil contractor) as shown in the drawings,specifications and as per ADDC regulations.
10.1.6.2.1 Basement fire & domestic water tank 2 SET 0
10.1.7 Pumps:
Supply, install test and commission electrical water transfer pump set as specified, automatically operated, as shown and indicated on the SET 0
10.1.7.1 approved drawings, complete with its related valves, accessories, wiring and control panel. 1
Supply, install test and commission Booster pump set ;complete with all related valves, accessories, fittings wiring and control panel as SET 0
10.1.7.2 shown on the drawings and as per specifications. 1
Supply, install test and commission Circulation pump set ; complete with all related valves, accessories, fittings, wiring and control panel as SET 0
10.1.7.3 shown on the drawings and as per specifications. 1
Supply, install SS Submersible Pump for water cleaning. Complete with control panel, valves etc. as shown on the drawings and as per SET 0
10.1.7.4 specifications. 1
10.1.8 Filtration System:
Supply, install test and commission of central filtration system including sand filters/ multimedia filter complete with filtration pump set and SET 0
10.1.8.1 all associated valves, accessories, fittings, wiring and control panel as shown on the drawings and as per specifications. 1
10.1.8.2 Ultra Violet sterilizer with valves and aluminum protection cover. 2 SET 0
10.1.9 Water Meters:
Supply and install the following water meters with plus reader, electric wires, all necessary pipes, fitting, valves, etc. as specified and NIU 0
10.1.9.1 required by ADDC.
Allow for installation of main incomer water meter and all associated valves,chamber,cover, cabinet, accessories, controls and as required by SET 0
10.1.9.1.1 ADDC 1
10.1.9.1.2 Water Supply sub-metering and Associated Works
10.1.9.1.2.1 a) Associated valves, piping etc as Shown in the Drawings for ADDC Submeter.(Cabinet ref Arch Details and included in Civil Work). 54 SET 0
10.1.9.1.2.2 b) Supply and Installation of Sub-meters. 54 NIU 0
10.1.9.2 Allow for emergency water tanks filling line with associated cabinet, inlets, valves, fittings and accessories and as required by ADDC EA 0
10.1.10 Pressure Reducing Valve station:
10.1.10.1 Supply and install pressure reducing valves sizes and locations as specified and shown on the drawings. 3 SET 0
10.1.10.2 Ditto for garbage rooms washing line NIU 0
10.1.11 Bib tap for roof, garbage room, plant rooms and basement complete with isolating valves, back flow preventer, support and accessories EA 0
10.1.12 Valves
Concealed valves including fiitings, fixings and supports, all necessary accessories and connections; complete all in accordance with the
10.1.12.1 specifications
10.1.12.1.1 20Ø NIU 0
10.1.12.1.2 25Ø NIU 0
10.1.12.1.3 32Ø NIU 0
10.1.12.2 Main Isolating valves
10.1.12.2.1 32Ø NIU 0
10.1.12.2.2 40Ø NIU 0
10.1.12.2.3 50Ø NIU 0
10.1.12.2.4 63Ø NIU 0
10.1.12.2.5 75Ø NIU 0
10.1.12.2.6 90Ø NIU 0
10.1.12.2.7 110Ø NIU 0
10.1.12.3 Allow for Water hammer arrestor in every wet area NIU 0
10.1.12.4 Allow for Automatic air vents as shown on drawings, specification and where required for proper system operation NIU 0
10.1.12.5 Allow for flexible connectors NIU 0
10.1.12.6 Allow for pressure gauges as shown on drawings and as specified NIU 0
10.1.13 Electric Water heaters

supply, install test and commission ceiling mounted, horizontal type, electric water heater, sizes and locations as shown on drawings ,
complete with connections for fresh water supply and delivery lines to various sanitary fixtures. With all associated isolation, check, safety
10.1.13.1 and drain valves as specified
10.1.13.1.1 80 L Capacity 52 NIU 0
10.1.13.1.2 50 L Capacity 62 NIU 0
10.1.14 Supply, install complete irrigation system including fittings, supports, valves, accessories etc as per drawings and specification.
10.1.15 Allow for installation of sanitary fixtures and accessories. Angle Valve, flexible connections and installation
10.1.15.1 WC EA 0
10.1.15.2 Wash basin EA 0
10.1.15.3 Shower EA 0
10.1.15.4 Bath tub EA 0
10.1.15.5 Kitchen Sink EA 0
10.1.16 Allow for ADDC fees EA 0
10.1.17 Allow for all builders work in connection with the installation EA 0
10.1.18 Allow for providing all keys, tools, spares, parts and schematic EA 0
10.1.19 Allow for all necessary identifications EA 0
10.1.20 Allow for the preparation of all necessary installation drawings EA 0
10.1.21 Allow for the preparation of all necessary operations and maintenance manuals EA 0
10.1.22 Allow for testing and commissioning of all works EA 0
10.1.23 Allow for Emergency operation and maintenance contract for irrigation system during defect liability period EA 0
10.2 Drainage System:
10.2.1 Above ground Drainage pipework:
Supply, installation, testing and commissioning of Soil, waste and vent UPVC pipe work for above ground drainage with all associated
10.2.1.1 fittings, supports and accessories as shown on drawings, required by authorities and as specified
10.2.1.1.1 50Ø LM 0
10.2.1.1.2 80Ø LM 0
10.2.1.1.3 110Ø LM 0
10.2.1.1.4 160Ø LM 0
10.2.1.1.5 200Ø LM 0
10.2.1.2 Below ground drainage pipework:
Supply and install buried internal and external drainage pipework in uP.V.C pipes class 16 as specified and shown on the approved drainage
10.2.1.2.1 drawings.
10.2.1.2.1.1 80Ø LM 0
10.2.1.2.1.2 110Ø LM 0
10.2.1.2.1.3 160Ø LM 0
10.2.1.2.1.4 200Ø LM 0
10.2.3 Commercial Kitchens waste water pipework:
Supply, installation, testing and commissioning of grease waste water HDPE pipe work for with all associated fittings, supports and
10.2.3.1 accessories as shown on drawings, required by authorities and as specified
10.2.3.1.1 50Ø LM 0
10.2.3.1.2 80Ø LM 0
10.2.3.1.3 110Ø LM 0
10.2.3.1.4 160Ø LM 0
10.2.4 Storm water Drainage pipework:
Supply, installation, testing and commissioning of Rain water UPVC pipe work with all associated fittings, supports and accessories as
10.2.4.1 shown on drawings, required by authorities and as specified
10.2.4.1.1 80Ø LM 0
10.2.4.1.2 110Ø LM 0
10.2.4.1.3 200Ø LM 0
10.2.5 Condensate drain pipework:
Supply, installation, testing and commissioning of UPVC pipe work for condensate drainage with all associated insulation, fittings,
10.2.5.1 supports and accessories as shown on drawings, required by authorities and as specified
10.2.5.1.1 50Ø LM 0
Construct manholes with covers in specified sizes and depths including all excavations, Backfilling, disposal of surplus, bedding, benching, NIU 0
10.2.6 branching, water proofing, 200mm solid block as per drawing, reinforced concrete at the top level around the frame.
Cover and frame of the manholes shall be light duty, and with double seal for manholes subject to pedestrian traffic and heavy duty with GRP
10.2.6.1 seal for manholes subject to vehicular traffic.
10.2.7 Supply and install Rain water outlets as specified and to engineer/ architect approval 10 NIU 0
10.2.8 Supply and install Floor drain with covers as specified and to engineer/ architect approval NIU 0
10.2.9 Supply and install Catch basins with heavy duty grating and sediment bucket as specified and to engineer/ architect approval 12 NIU 0
10.2.10 Supply and install manholes with heavy duty grating and sediment bucket as specified and to engineer/ architect approval NIU 0
10.2.11 Supply and install Gulley trap with covers as specified, shown on drawings and required by authorities NIU 0
10.2.12 Supply and install Grating channel as specified and shown on the drawings. NIU 0
10.2.13 Supply and install balcony drain with cover as specified and to engineer/ architect approval NIU 0
10.2.14 Supply and install landscape drain points as specified and to engineer/ architect approval NIU 0
Supply and install Sand trap with covers and all related pipes, fittings and accessories as specified, shown on drawings and required by NIU 0
10.2.15 authorities 1
Supply and install oil interceptor with covers and all related pipes, fittings and accessories as specified, shown on drawings and required by NIU 0
10.2.16 authorities 1
Supply and install Grease interceptor with covers and all related pipes, fittings and accessories as specified, shown on drawings and required NIU 0
10.2.17 by authorities
Supply and install Pressure reducing manhole with covers and all related pipes, fittings and accessories as specified, shown on drawings and NIU 0
10.2.18 required by authorities 1
10.2.19 Supply and install Clean outs on every change of direction and as required NIU 0
10.2.20 Supply and install Velocity breakers on all drainage risers as specified NIU 0
10.2.21 Supply and install Waste water sump pit with cover, with all related civil works, water proofing, piping connections, and accessories NIU 0
10.2.23 Supply and install Vent Cowl as specified and shown on the drawings. NIU 0
10.2.24 Supply & Installation of Accoustic drainage pipes as shown in the Drawings and in accordance with the Specifications. NIU 0
10.2.25 Sump Pumps
Supply, install test and commission electrical storm water water sump pump set as specified, automatically operated, as shown and indicated SET 0
10.2.25.1 on the approved drawings, complete with its related valves, accessories, wiring and control panel. 1
10.2.26 Allow for ADSSC fees EA 0
10.2.27 Allow for service relocation fees EA 0
10.2.28 Allow for all builders work in connection with the installation EA 0
10.2.29 Allow for providing all keys, tools, spares, parts and schematic EA 0
10.2.30 Allow for all necessary identifications EA 0
10.2.31 Allow for the preparation of all necessary installation drawings EA 0
10.2.32 Allow for the preparation of all necessary operations and maintenance manuals EA 0
10.2.33 Allow for testing and commissioning of all works EA 0
10.4 Toilet, Bathroom and Kitchen
Sanitary Wares and Accessories
Supply and fix complete sanitary fixtures includes but not limited to washbasins, water closets, mixers, hand spray, shower spray, towel ring,
towel rail, toilet paper holder, soap holder, robe hook, floor drain, etc…. all complete as per specification and drawings.
Bathroom Type 01 (Ground Floor Male and Female Toilet) 2 NIU 0
Bathroom Type 02 (Handicaped Toilet) 1 NIU 0
Bathroom Type 03 (Guard's Room Bathroom) 1 NIU 0
Bathroom Type 04 Mezzanine Toilet 4 NIU 0
Bathroom Type 05 Mezzanine Toilet 3 NIU 0
Bathroom Type 06 Apartment Bathroom 10 NIU 0
Bathroom Type 07 Apartment Bathroom 18 NIU 0
Bathroom Type 08 Apartment Bathroom 10 NIU 0
Bathroom Type 09 Apartment Washroom 18 NIU 0
Bathroom Type 10 Apartment Bathroom 10 NIU 0
Bathroom Type 11 Apartment Washroom 30 NIU 0
Bathroom Type 12 Apartment Bathroom 2 NIU 0
Bathroom Type 13 Apartment Bathroom 2 NIU 0
Mezzanine Female Washroom 1 NIU 0
Mezzanine Handycapped Toilet 1 NIU 0
Mirrors
Frameless mirrors to vanities as shown on the drawings including plywood, backing, metal angle supports and wood blocking as per
drawings.
600mm x 1200mm 86 NIU 0
450mm x 1100mm 2 NIU 0
1300mm x 1200mm 3 NIU 0
1450mm x 1200mm 3 NIU 0
1000mm x 1200mm 20 NIU 0
Kitchen
Kitchen Sink & Water Tap complete with drain, plug and single lever mixer 62 NIU 0
Conventional Hood 58 NIU 0
11 Fire fighting works
Supply and install CO2 type portable Fire Extinguishers, including hangers, hose, and accessories , all as specified in compliance with NFPA NIU 0
11.1 and UAE fire and life safety code.
Supply and install Dry powder type portable Fire Extinguishers, including hangers, hose, and accessories , all as specified in compliance with NIU 0
11.2 NFPA and UAE fire and life safety code.
Fire hose cabinet , Automatic hose reel with swing cabins, hoses and spray nozzle,landing valve with built in PRV etc.., complete as NIU 0
11.3 specified, and to the Civil Defence requirements. 22
11.4 Fire blanket; complete with support and all necessary accessories; all in accordance with drawings and specification NIU 0
11.5 Fire brigade 4-way inlet breeching with cabinet as specified and per Civil Defence requirements 1 NIU 0
11.6 Wet Riser system
Supply and install test and commission wet riser pipes with fittings, valves, air vents etc., complete, as specified and to NFPA requirement
11.6.1 and the Civil Defence regulation, all components to be UL listed and FM approved. Pipes, fittings and accessories
11.6.1.1 25Ø LM 0
11.6.1.2 65Ø LM 0
11.6.1.3 150Ø LM 0
11.6.2 Pressure reducing valves 25Ø for hose real connection NIU 0

LM 0
11.6.3 Wet riser test and drain line with all associated supports, couplings, fittings and accessories as required by NFPA and Civil defence regulation
11.7 Automatic Sprinkler system

Supply and install test and commission automatic sprinkler system with associated pipes, fittings, valves, air vents etc., complete, as
specified and to NFPA requirement and Civil Defence regulation all components to be UL listed and FM approved. Pipes, fittings and
11.7.1 accessories
11.7.1.1 25Ø LM 0
11.7.1.2 32Ø LM 0
11.7.1.3 40Ø LM 0
11.7.1.4 50Ø LM 0
11.7.1.5 65Ø LM 0
11.7.1.6 80Ø LM 0
11.7.1.7 100Ø LM 0
11.7.1.8 150Ø LM 0
11.7.2 Sprinkler heads complete with all necessary, supports, fittings and accessories
11.7.2.1 Concealed sprinkler NIU 0
11.7.2.2 Pendant sprinklers NIU 0
11.7.2.3 Upright sprinkler head NIU 0
11.7.2.4 sidewall sprinkler head NIU 0
11.7.3 Zone control valves NIU 0
11.7.4 Pressure reducing station NIU 0
11.7.5 Pressure reducing valve NIU 0
11.7.6 Check valves NIU 0
11.7.7 OS & Y Gate valve NIU 0
11.7.8 Alarm check valves 1 NIU 0
11.7.9 Sprinkler drain riser with drain valves NIU 0
11.7.10 Sprinkler test and drain valves NIU 0
11.7.11 Automatic air vent 4 NIU 0
11.7.12 Flow meters NIU 0
11.7.13 Pressure gauges NIU 0
11.8 Fire Fighting Pump Set:

Supply, install, testing and commissioning of the following systems including associated valve set, pipe header and pressure vessel; complete
with driving motor, control panels, base and anti-vibration mounting, fittings, supports, wiring and controls, insulation and all necessary
11.8.1 ancillaries, accessories and connections; complete as detailed on drawing and as per specification and as detailed below.
11.8.1.1 Electric driven main pump. UL listed/ FM approved 1 EA 0
11.8.1.2 Diesel Pump with all associated accessories, fuel meanagement system and fuel tank. UL listed/ FM approved 1 EA 0
11.8.1.3 Jockey Pump . 1 EA 0
11.9 Pre-Engineered automatic fire suppression systems

Supply, install , testing and commissioning of automatic clean agent system in electrical rooms with all associated piping, fittings,
valves,supports, cylinders, accessories, control panels and interfaces to man fire alarm system all in compliance with NFPA requirement, EA 0
11.9.1 Civil defence regulations and as shown on drawings and specifications and where required by Civil Defence 1
11.9.1.1 Allow for room pressure integrity tests for all rooms protected with automatic clean agent system 1 EA 0
11.9.1.2 Allow for all interfaces and required motorized dampers for HVAC systems NIU 0

Supply, install , testing and commissioning of automatic Foam Suppression system in Generator rooms with all associated piping, fittings,
valves, supports, gauges, cylinders, accessories, control panels and interfaces to man fire alarm system all in compliance with NFPA EA 0
11.9.2 requirement, Civil defence regulations and as shown on drawings and specifications and where required by Civil Defence 1
11.1 200 mm Dia Black Steel Exhaust Pipe work and accessories for Diesel Fire Pump . LM 0
11.11 Diesel Engine Fuel filling line LM 0
11.12 Allow for all Builder's work in connection with Fire Fighting System's installation. 1 EA 0
11.13 Allow for fees related to Civil defence approvals, Third party approvals …etc. 1 EA 0
11.14 Allow for supports, including fixings, anchors insulating block and anti vibration devices. 1 EA 0
11.15 Allow for identification labels including plates, discs, labels, charts and color coding. 1 EA 0
11.16 Allow for protective and decorative painting 1 EA 0
11.17 Allow for firestopping in accordance with drawings,specificaiton and lcoal authorities requirements 1 EA 0
11.18 Allow for providing tools and spare partss including maintenance kit, loose keys and consumables. 1 EA 0
11.19 Allow for liaison, co-ordination and attendanceon concerned Authorities work to meet the requirement of the specification 1 EA 0
11.2 Close-out Documents: 1 EA 0
Allow for all submittals, samples, shop drawings, coordination drawings, As-built Drawings, warranty certificates, testing & commissioning, EA 0
11.20.1 operation and maintenance manuals 1
12 AIR CONDITIONING AND VENTILATION SYSTEMS
12.1 Chilled Water Pumps:
Supply and install chilled water pump set with all associated pipes, fittings, valves, insultion, cladding, varaible frequency drives, control SET 0
12.1.1 panels, inertia base and vibration isolators complete as specified and shown on drawings . 1
12.1.2 Chilled water Pressurization Unit with all associated pipes, fittings, valves, tanks, accessories and controls 1 SET 0
12.1.3 Automatic chemical dosing system with all the necessary tanks, pots, piping, fittings, valves, accessories, controls, etc. 1 SET 0
Manual dosing system as specified & shown on the drawings including all valves, fittings, insulation, supports & pipe connections etc . to SET 0
12.1.4 main flow and return pipes. 1
12.1.5 Air and dirt separator complete with all associated pipes, fittings, valves and accessories 1 SET 0
12.1.6 Instrumentation as specified and shown on the drawings - supply, install, test and commission all instrumentation and accessories, etc. 1 EA 0
12.2 Fan Coil Units:
Supply, install testing and commissioning of fan coil units complete as specified, shown on drawings and with all the associated anti-
12.2.1 vibration mounts, plenums, thermostats, wiring controls and accessories as deemed necessary for the proper functioning of the unit.
12.2.2 3rd Basement Floor Fan Coil Units
12.2.2.1 3B1 1 NIU 0
12.2.2.2 3B2 1 NIU 0
12.2.2.3 3B3 1 NIU 0
12.2.3 2nd Basement Floor Fan Coil Units NIU 0
12.2.3.1 2B1 1 NIU 0
12.2.3.2 2B2 1 NIU 0
12.2.3.3 2B3 1 NIU 0
12.2.4 1st Basement Floor Fan Coil Units
12.2.4.1 1B1 1 NIU 0
12.2.4.2 1B2 1 NIU 0
12.2.4.3 1B3 1 NIU 0
12.2.4.4 1B4 1 NIU 0
12.2.5 Ground Floor Fan Coil Units
12.2.5.1 G1 1 NIU 0
12.2.5.2 G2 1 NIU 0
12.2.5.3 G3 1 NIU 0
12.2.5.4 G4 1 NIU 0
12.2.5.5 G5 1 NIU 0
12.2.5.6 G6 1 NIU 0
12.2.5.7 G7A 1 NIU 0
12.2.5.8 G7B 1 NIU 0
12.2.5.9 G8 1 NIU 0
12.2.5.10 G9 1 NIU 0
12.2.5.11 G10 1 NIU 0
12.2.5.12 G11 1 NIU 0
12.2.5.13 G12 1 NIU 0
12.2.6 Mezzanine Floor Fan Coil Units
12.2.6.1 M1 1 NIU 0
12.2.6.2 M2 1 NIU 0
12.2.6.3 M3 1 NIU 0
12.2.6.4 M4 1 NIU 0
12.2.6.5 M5 1 NIU 0
12.2.6.6 M6 1 NIU 0
12.2.6.7 M7 1 NIU 0
12.2.6.8 M8 1 NIU 0
12.2.6.9 M9 1 NIU 0
12.2.6.10 M10 1 NIU 0
12.2.6.11 M11 1 NIU 0
12.2.6.12 M12 1 NIU 0
12.2.6.13 M13 1 NIU 0
12.2.6.14 M14 1 NIU 0
12.2.7 Typical Floor (1st&3rd) Fan Coil Units
12.2.7.1 F1 2 NIU 0
12.2.7.2 F2 2 NIU 0
12.2.7.3 F3 2 NIU 0
12.2.7.4 F4 2 NIU 0
12.2.7.5 F5 2 NIU 0
12.2.7.6 F6 2 NIU 0
12.2.7.7 F7 2 NIU 0
12.2.7.8 F8 2 NIU 0
12.2.7.9 F9 2 NIU 0
12.2.7.10 F10 2 NIU 0
12.2.7.11 F11 2 NIU 0
12.2.7.12 F12 2 NIU 0
12.2.7.13 F13 2 NIU 0
12.2.7.14 F14 2 NIU 0
12.2.7.15 F15 2 NIU 0
12.2.7.16 F16 2 NIU 0
12.2.7.17 F17 2 NIU 0
12.2.7.18 F18 2 NIU 0
12.2.7.19 F19 2 NIU 0
12.2.7.20 F20 2 NIU 0
12.2.7.21 F21 2 NIU 0
12.2.7.22 F22 2 NIU 0
12.2.8 Typical Floor (2nd&4th) Fan Coil Units
12.2.8.1 T1 2 NIU 0
12.2.8.2 T2 2 NIU 0
12.2.8.3 T3 2 NIU 0
12.2.8.4 T4 2 NIU 0
12.2.8.5 T5 2 NIU 0
12.2.8.6 T6 2 NIU 0
12.2.8.7 T7 2 NIU 0
12.2.8.8 T8 2 NIU 0
12.2.8.9 T9 2 NIU 0
12.2.8.10 T10 2 NIU 0
12.2.8.11 T11 2 NIU 0
12.2.8.12 T12 2 NIU 0
12.2.8.13 T13 2 NIU 0
12.2.8.14 T14 2 NIU 0
12.2.8.15 T15 2 NIU 0
12.2.8.16 T16 2 NIU 0
12.2.8.17 T17 2 NIU 0
12.2.8.18 T18 2 NIU 0
12.2.8.19 T19 2 NIU 0
12.2.8.20 T20 2 NIU 0
12.2.8.21 T21 2 NIU 0
12.2.8.22 T22 2 NIU 0
12.2.9 Fifth Floor Fan Coil Units
12.2.9.1 5F1 1 NIU 0
12.2.9.2 5F2 1 NIU 0
12.2.9.3 5F3 1 NIU 0
12.2.9.4 5F4 1 NIU 0
12.2.9.5 5F5 1 NIU 0
12.2.9.6 5F6 1 NIU 0
12.2.9.7 5F7 1 NIU 0
12.2.9.8 5F8 1 NIU 0
12.2.9.9 5F9 1 NIU 0
12.2.9.10 5F10 1 NIU 0
12.2.9.11 5F11 1 NIU 0
12.2.9.12 5F12 1 NIU 0
12.2.9.13 5F13 1 NIU 0
12.2.9.14 5F14 1 NIU 0
12.2.9.15 5F15 1 NIU 0
12.2.9.16 5F16 1 NIU 0
12.2.9.17 5F17 1 NIU 0
12.2.9.18 5F18 1 NIU 0
12.2.9.19 5F19 1 NIU 0
12.2.9.20 5F20 1 NIU 0
12.2.9.21 5F21 1 NIU 0
12.2.9.22 5F22 1 NIU 0
12.2.10 Roof Floor Fan Coil Units
12.2.10.1 R1 1 NIU 0
12.2.10.2 R2 1 NIU 0
12.2.10.3 R3 1 NIU 0
12.2.10.4 R4A 1 NIU 0
12.2.10.5 R4B (STAND-BY) 1 NIU 0
12.3 Air Cutain

Supply and install air curtain including motors, filters, all necessary anti-vibration mountings and supports, dampers,electrical/control wiring,
conduits and controls, accessories and connections to duct work; complete as shown on equipment schedule and all in accordance with the
12.3.1 Specifications .
12.3.1.1 AC-1 1 NIU 0
12.3.1.2 AC-2 1 NIU 0
12.3.1.3 AC-3 1 NIU 0
12.3.1.4 AC-4 1 NIU 0
12.4 Fresh Air Handling units

Supply, install testing and commissioning of FAHU's including supply & extract fans heat recovery wheel, horse shoe heat pipes , cooling
coil,panel and bag filter, standby motors, valves strainers, pressure gauge, thermometers, control and associated accessories, connection to
ducts, connection to chilled water pipe work and electrical connection to local outlets, including supports and vibration isolators flexible
12.4.1 connectors. as specified and shown on drawings
12.4.2 FAHU-01 1 NIU 0
12.4.2 FAHU-02 1 NIU 0
12.5 Air Handling units

Supply, install, testing and commissioning of AHU's including supply fans , cooling coil, filters, valves, strainers, pressure gauge,
thermometers, control and associated accessories, connection to chilled water pipe work and electrical connection to local outlets as specified
12.5.1 and shown on drawings.
12.5.2 AHU-ST 1 NIU 0
12.6 Fans
Supply, install testing and commissioning of all fans complete with associated hangers, supports, dampers, wiring, control panels, flexible
12.6.1 connectors and accessories as specidied and shown on drawings and in compiliance with Civil Defence regulations
12.6.2 Smoke management fans:
12.6.2.1 Pressuriuzation fans
12.6.2.1.1 SPF-01 1 NIU 0
12.6.2.1.2 SPF-02 1 NIU 0
12.6.2.1.3 LPF-01 1 NIU 0
12.6.2.2 Corridor smoke management fans
12.6.2.2.1 SEF-01 1 NIU 0
12.6.2.2.2 MAF-01 1 NIU 0
12.6.2.2.3 MAF-02 1 NIU 0
12.6.2.3 Car park ventilation and smoke management fans
12.6.2.3.1 3BEF1 1 NIU 0
12.6.2.3.2 3BEF2 1 NIU 0
12.6.2.3.3 2BEF1 1 NIU 0
12.6.2.3.4 2BEF2 1 NIU 0
12.6.2.3.5 1BEF1 1 NIU 0
12.6.2.3.6 1BEF2 1 NIU 0
12.6.2.3.7 3BFF1 1 NIU 0
12.6.2.3.8 3BFF2 1 NIU 0
12.6.2.3.9 2BFF1 1 NIU 0
12.6.2.3.10 2BFF2 1 NIU 0
12.6.2.3.11 1BFF1 1 NIU 0
12.6.2.3.12 1BFF2 1 NIU 0
12.6.3 Ventilation Fans
12.6.3.1 Transformer room ventilation fan 1 NIU 0
12.6.3.2 Garbage room ventilation fan 1 NIU 0
12.7 Chillers
Supply, install testing and commissioning of air cooled packaged chillers complete with all valves ,strainers , flanged pipe connections to
12.7.1 header , protective devices , controls ,electrical connection etc..as specified and mounted on anti vibration isolators.
12.7.1.1 Chiller- 1 1 NIU 0
12.7.1.2 Chiller -2 1 NIU 0
12.8 Ductwork and Accessories
Sheet metal ductworks; complete with thermal insulation, canvas and coating, supports, anti-vibration mounts and all necessary accessories;
12.8.1 all in accordance with drawings and specification
12.8.1.1 Insulated Supply and return air ductwork MTK 0
12.8.1.2 Insulated treated fresh air ductwork MTK 0
12.8.1.3 Insulated extract air ductwork MTK 0
12.8.1.4 non-insulated ductwork MTK 0
12.8.1.5 Fire rated ductwork MTK 0
12.8.1.6 Insulated, Fire rated ductwork MTK 0
12.8.1.7 Commercial Kitchen extract ductwork MTK 0
12.8.2 Volume control dampers NIU 0
12.8.3 Fire dampers NIU 0
12.8.4 Motorized dampers NIU 0
12.8.5 Motorized fire dampers NIU 0
12.8.6 Motorized smoke dampers NIU 0
12.8.7 MSFD NIU 0
12.8.8 Non-return dampers NIU 0
12.8.9 Duct access doors NIU 0
12.8.10 Aluminum Cladding for exposed ducts in roof, plant rooms, basement, and exposed installations MTK 0
12.8.11 Electrostatic filters at all kitchen extract riser ducts before connecting to the FAHUs heat recovery wheel NIU 0
12.8.12 Sound attenuators NIU 0
12.8.13 Acoustic Liner LM 0
12.8.14 Flexible ducts MTK 0
12.9 Grilles, Diffusers and registers
Air distribution outlets including plenum boxes, thermal insulations, acoustic insulation dampers, fittings, fixings in positions all complete as NIU 0
12.9.1 specified and as shown on drawings.
12.9.2 Supply 4-Ways diffusers with associated plenums, flexible ducts, supports and accessories NIU 0
12.9.3 Return 4-Ways diffusers complete as shown on drawings and as specified NIU 0
12.9.4 Supply Register complete as shown on drawings and as specified LM 0
12.9.5 Return Grilles complete as shown on drawings and as specified LM 0
12.9.6 Extract air grilles complete as shown on drawings and as specified LM 0
12.9.7 Toilet round disc type extract diffuser. NIU 0
12.9.8 Supply linear slot diffusers with associated plenums, flexible ducts, supports and accessories LM 0
12.9.9 Return Linear slot diffusers LM 0
12.9.10 Supply linear bar grilles with associated plenums, flexible ducts, supports and accessories LM 0
12.9.11 Return Linear bar grilles LM 0
12.9.12 Intake and Extract louvers MTK 0
12.9.13 Sand trap Louvers MTK 0
12.1 Chilled water pipes and accessories

Chilled Water pipes (Seamless black steel as specified) with all the necessary fittings, hangers, supports, flexible connection etc., along with
12.10.1 thermal insulation to pipe work canvas, foster, aluminum jacketing wherever applicable etc. as shown on the drawings and specified.
12.10.1.1 20Ø LM 0
12.10.1.2 25Ø LM 0
12.10.1.3 32Ø LM 0
12.10.1.4 40Ø LM 0
12.10.1.5 50Ø LM 0
12.10.1.6 65Ø LM 0
12.10.1.7 75Ø LM 0
12.10.1.8 100Ø LM 0
12.10.1.9 125Ø LM 0
12.10.1.10 150Ø LM 0
12.10.1.11 200Ø LM 0
12.10.2 Chilled water valves
12.10.2.1 Gate vlaves NIU 0
12.10.2.2 Butterfly valves NIU 0
12.10.2.3 Check valves NIU 0
12.10.2.4 Control valves with modulating actuator NIU 0
12.10.2.5 Strainer NIU 0
12.10.2.6 Metering orifice NIU 0
12.10.2.7 Automatic air vents NIU 0
12.10.2.8 Pressure gauges NIU 0
12.10.2.9 Flow Switch NIU 0
12.10.2.10 Thermometer NIU 0
12.11 FCU Controls
Supply, install, test and commissioning of standalone control and thermostat for all FCUs as shown in the schedule, drawings and EA 0
12.11.1 specifications.
12.12 HVAC control and monitoring system
Supply, install, test and commissioining of complete HVAC control and monitoring system for chiller, chilled water pumps, FAHUs, AHU, EA 0
12.12.1 Fans,..etc as specified and as shown in the drawings complete with DDCs, wiring, piping,sensors, and connect to equipments,..ect. 1
12.13 Hangers, supports, brackets etc. for pipe and ductwork. EA 0
12.14 Insulated Condensate drain connections. LM 0
12.15 Sound reduction enclosure for the chillers compressors. EA 0
12.16 Controls with all necessary accessories & associated wiring EA 0
12.17 Anti vibration mounts EA 0
12.18 Allow for all builder works related to air conditioning system EA 0
12.19 Allow for all protective and decoratvie painting and cleaning of pipes, fittings, etc and equipments. EA 0
12.2 Allow for all identification labels, plates, charts,of all HVAC services and equipment. EA 0
12.21 Allow for coordination with other trade shop drawings. EA 0
12.22 Allow for shop drawings & engineering works related to air conditioning system. EA 0
12.23 Allow for firestopping in accordance with drawings,specificaiton and lcoal authorities requirements EA 0
12.24 Provision for maintenance of HVAC System during guarantee period EA 0
12.25 Allow for instructing training Client's personnel on all aspects of the operation of HVAC equipment and systems. EA 0
12.26 Allow for air and chilled water balancing of complete HVAC systems by third partycommissioning agent EA 0
Coordinating with other trades including additional material and labour to produce a fully and operable installation (interfacing work with fire EA 0
12.27 alarm system)
12.28 Close-out Documents: EA 0
Allow for all submittals, samples, shop drawings, As-built Drawings, warranty certificates, testing & commissioning, operation and EA 0
12.28.1 maintenance manuals , Providing necessary spare parts.
13 ELEVATORS AND CRADLE
13.1 ELEVATORS

Design, Supply and install the complete lift system; including but not limited to all machine and control room equipment's operating system,
hoist way equipment's, door and entrance equipment's, lift car equipment's, monitoring system, intercom and distress signal system, drivers
and control, control assemblies, rail system, wire ropes, stopping devices, car frame and finishes, protective devices, interface with security
system, electric connection, all accessories / ancillaries and all necessary work to complete and operation the whole system; all accordance
13.1.1 with specification.

Passenger Elevator : - 1350 Kg , 18 persons capacity 1.75 meter / sec ,103 stop, 10 openings, 2000 wide x 1500mm depth clear cabin size, NIU 0
13.1.1.1 hydroelectric computerised control (indirect side acting) as Specified 1
Service / Fire fighting Elevator - 1600 Kg , 21 persons capacity 1.75 meter / min , 10 stop, 10 openings, 1600 wide x 2100.mm depth clear NIU 0
13.1.1.2 cabin size, hydroelectric computerised control (indirect side acting) as Specified 1
13.1.2 SUNDRIES
13.1.2.1 Allow for production of all working drawings, calculations,specification, operation and maintenance manuals EA 0
13.1.2.2 Allow for all general builder's work in connection with the lift installation EA 0
13.1.2.3 Allow for testing and commissioning lift installation EA 0
13.1.2.4 Provision for maintenance as specified EA 0
13.2 CRADLE
13.2.1 Building Maintenance Unit
Supply, install, test and commissioning of building maintenance unit davit system as specified and as shown in the drawings with all EA 0
13.2.1.1 accessories and controls. 1
13.2.1.2 SUNDRIES
13.2.1.2.1 Allow for production of all working drawings, calculations,specification, operation and maintenance manuals 1 EA 0
13.2.1.2.2 Allow for all general builder's work 1 EA 0
13.2.1.2.3 Allow for testing and commissioning 1 EA 0
13.2.1.2.4 Provision for one year maintenance 1 EA 0
14 GARBAGE DISPOSAL SYSTEM
14.1 GARBAGE CHUTE
Supply, install complete waste management system as shown in the drawings and specifications complete with automatic cleaning system, EA 0
14.1.1 pipe work, fire protection sprinkler, disinfection unit,..etc. 1
14.1.2 Provision for shop drawings and submittals EA 0
14.1.3 Provision for As Built drawings and Mannuals EA 0
14.1.4 Provision for connection fee for automatic waste collection system EA 0
14.1.5 Provision for testing and commissioning EA 0
14.1.6 Provision for warranty and maintenance as specified EA 0
14.1.7 Provision for electrical works as specified EA 0
14.1.8 Provision for plumbing works as specified EA 0
14.1.9 Provision for civil works as specified EA 0
15 CENTRAL GAS SYSTEM
Supply, install and test natural gas system piping as per drawings, specifications and ADNOC regulations by ADNOC approved
15.1 subcontractor.
15.1.1 Filling Line 1 EA 0
15.1.1.1 Main incomming valve station 1 EA 0
15.1.1.2 Main riser from ground to roof MS pipe
15.1.2 Distribution Dropers & Fittings (SC 40 MS pipes)
15.1.2.1 40mm dia pipe 1 EA 0
15.1.2.2 25mm dia pipe 1 EA 0
15.1.2.3 Fittings , Supports and Clamps etc.. 1 EA 0
15.1.3 Kitchen branch pipes and fittings (Copper pipes) 1 EA 0
15.1.4 Gas Detection System
15.1.4.1 Gas leak detection system cabling 1 EA 0
15.1.5 Gas leak detection panels at each floor lift lobby. EA 0
15.1.6 Work incidental to mechanical engineering installations
15.1.6.1 Allow for co-ordination with other service installations 1 EA 0
15.1.6.2 Allow for cutting or forming holes, mortices, chases or the like and making good finishes 1 EA 0
15.1.6.3 Allow for building in or cutting and pinning brackets or the like and making good finishes 1 EA 0
15.1.6.4 Allow for shallow excavations for below-ground installations including encasing in concrete where necessary 1 EA 0
15.1.6.5 Allow for plinth and support for machinery and fittings unless measured elsewhere in detail 1 EA 0
15.1.7 SUNDRIES
15.1.7.1 Allow for submittals and shop drawings 1 EA 0
15.1.7.2 Allow for as built drawings and mannuals 1 EA 0
15.1.7.3 Allow for connection charges to ADNOC . 1 EA 0
15.1.7.4 Allow Emergency operation and maintenance contract during defect liability period 1 EA 0
16 ELECTRICAL WORKS
Standard abbreviation have been used in this bill which are well known to the Electric Industry. Claims resulting from misinterpretation of
16.1 these abbreviations will not be considered.

B.O.Q should be read in conjunction with all relative drawings, specifications as a whole. Quantities mentioned hereinafter are intended for
the guidance of the contractor, who shall be deemed to have satisfied himself of the exact quantities. Any difference between actual quantities
and those mentioned in the B.O.Q. shall be entered in the page headed "Contractors Adjustment Sheet" appearing at the end of this BOQ
16.2 other quantities mentioned here are deemed as correct.
16.3 Allow for testing thoroughly the complete system before being put into operation EA 0
Allow for builders work required for electrical installation including ducts, trenches, concrete bases, chasing and channeling in walls, floors EA 0
16.4 and ceiling, manholes and covers etc.., to the satisfaction of the Engineer.
Allow for following up with ADDC for electrical power supply connection, testing & commissioning and pay connection fees included EA 0
16.5 ADDC KWH meter.
16.6 Meduim voltage -22kv- distribution panel

Supply, install, test, commission and maintain Medium voltage (22kv) distribution panel QRM type ( 2inc. LBS + 1outgoing CB) as specified NIU 0
16.6.1 and as indicated on the drawings, complete with necessary accessories and ancillary works and materials required for complete installation. 1
16.7 TRANSFORMER
Supply, install test and commission transformer 1500KVA, 22KV/400V, 50Hz, Dry type with all necessary connections to main DBs and HV NIU 0
16.7.1 panel as per ADDC regulation and as shown on the drawings. 1
High voltage cabe between HV panel and transformers, 22 KV size 3Cx120 sq.mm CU.XLPE/STA/PVC Complete with termination and all EA 0
16.8 auxilary matrial as per ADDC specifications
16.9 Emergency Diesel Generator Plants

Supply, install, testing and commissioning of 200KVA (at 50 degree C ambinet) 0.8 P.F., 400 Volts, Diesel Generators in accordance with
technical specification complete with necessary accessories and anxillaries works such as, but not limited to the following: Silencors, flexible
joints, exhaust pipes, fuel tanks, fuel pipes, battery, battery chargers, canvas make up duct, isolators,cercuit breaker, pumps, monitoring and
16.9.1 protection erection materials and special tools.
16.9.1.1 Stand by Generator set (200 KVA,0.8 pf) 1 NIU 0
16.9.1.2 ATS 400 A ,400V,50HZ,4POLE 1 NIU 0
16.1 Low Voltage Switchgear and Distribution Board
Supply, install, test, commission and maintain low voltage switchgear complete with all components as specified and as shown on the
16.10.1 drawings including all necessary works and fittings required for the complete installation including all incoming and outgoing feeders
16.11 Main Distribution Board MDB ( MDB-1 ) 1 NIU 0
16.11.1 Sheet steel free standing front access IP 54 electro galvanized sheet steel constructed as to BSEN60439-1 Form 4 Type 6
16.11.1.1 Incomings

1 x 2500A, 4P, ACB, 50KA with protection SCC + O.C and earth fault 1xvm+S.S-RYB lamps + TP Fuses 3xAM+CTS (2500/5A) + P.F
16.11.1.1.1 meter
16.11.1.2 Outgoing:
16.11.1.2.1 1 x 1600A TP ACB 50KA at 400V AC 50HZ
16.11.1.2.2 1 x 1000A TP ACB 50KA at 400V AC 50HZ
16.11.1.2.3 1 x 800A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.4 2 x 400A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.5 1 x 300A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.6 1 x 250A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.7 2 x 200A TP MCCB 50KA at 400V AC 50HZ
16.11.1.2.8 1 x 80A TP MCCB 50KA at 400V AC 50HZ
16.12 EMDB (8 ways) 1 NIU 0
16.12.1 Sheet steel free standing front access IP 54 electro galvanized sheet steel constructed as to BSEN60439-1 Form 4 Type 6
16.12.1.1 Incoming;

16.12.1.1.1 1 x 400A, 4P, MCCB, 50KA with protection SCC + O.C and earth fault 1xvm+S.S-RYB lamps + TP Fuses 3xAM+CTS(400/5A) + P.F meter
16.12.1.2 Outgoing:
16.12.1.2.1 1 x 200A TP MCCB 50KA at 400V AC 50HZ
16.12.1.2.2 2 x 100A TP MCCB 50KA at 400V AC 50HZ
16.12.1.2.3 6 x 80A TP MCCB 50KA at 400V AC 50HZ
16.13 Sub Main Distribution Board
Wall mounted IP21, electro galvanized sheet steel constructed as to BSEN60439-1 Form 2 as per latest local authority regulation as
16.13.1 specifiedkindly be informed that panel as follow: and indicated in load schedule drawings.
16.13.1.1 SMDB-G 1 NIU 0
16.13.1.2 SMDB-OFF 1 NIU 0
16.13.1.3 SMDB-T 5 NIU 0
16.13.1.4 ESMDB-LC 1 NIU 0
16.13.1.5 ESMDB-MEC-B 1 NIU 0
16.13.1.6 ESMDB-G 1 NIU 0
16.13.1.7 ESMDB-LIFT 1 NIU 0
16.13.1.8 MCC 1 NIU 0
16.13.1.9 ESMDB-R 1 NIU 0
16.14 CAPACITOR BANKS
Supply, installation, testing , commissioning of Power Factor correction Units with harmonic filters as specified with rating 250 KVAR NIU 0
16.14.1 P.F.C. 1
16.15 Final DB and Consumer Units
Recessed Mounting, electro galvanized sheet steel constructed as per latest local authority regulation, as specified and indicated in load
15.15.1 schedule drawings. Kindly be informed that panel as follow:
15.15.1.1 DB-G 1 NIU 0
15.15.1.2 DB-EX 1 NIU 0
15.15.1.3 DB-B1 1 NIU 0
15.15.1.4 DB-B2 1 NIU 0
15.15.1.5 DB-B3 1 NIU 0
15.15.1.6 DB-TFX (FLATS) 48 NIU 0
15.15.1.7 EDB-MB1 1 NIU 0
15.15.1.8 EDB-MB2 1 NIU 0
15.15.1.9 EDB-MB3 1 NIU 0
15.15.1.10 EDB-G 1 NIU 0
15.15.1.11 EDB-S1 1 NIU 0
15.15.1.12 EDB-S2 1 NIU 0
15.15.1.13 EDB-B 1 NIU 0
15.15.1.14 ECU-M 1 NIU 0
15.15.1.15 ECU-T 5 NIU 0
15.15.1.16 ECU-R 1 NIU 0
15.15.1.17 ECU-B1 1 NIU 0
15.15.1.18 ECU-B2 1 NIU 0
15.15.1.19 ECU-B3 1 NIU 0
16.16 LOW VOLTAGE CABLES - XLPE CABLES
Supply and install, Test, Commission and maintain main and sub feeder copper cables as shown on drawings including termination, cable
16.16.1 ties, and all necessary accessories and related ancillaries works specified as a required by the drawings
16.16.1.1 1C x 630mm2 XLPE / AWA / PVC EA 0
16.16.1.2 4C x 240mm2+1C x 120mm2 XLPE / SWA / PVC EA 0
16.16.1.3 4C x 150mm2+1C x 70mm2 XLPE / SWA / PVC EA 0
16.16.1.4 4C x 120mm2+1C x 70mm2 XLPE / SWA / PVC EA 0
16.16.1.5 4C x 50mm2+1C x 25mm2 XLPE / SWA / PVC EA 0
16.16.1.6 4C x 35mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.16.1.7 4C x 25mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.16.1.8 4C x 16mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.16.1.9 4C x 10mm2+1C x 10mm2 XLPE / SWA / PVC EA 0
16.16.1.10 2C x 10mm2 XLPE / SWA / PVC EA 0
Supply and install, Test, Commission and maintain main and sub feeder copper fire rated cables as shown on drawings including termination,
16.17 cable ties, and all necessary accessories and related ancillaries works specified as a required by the drawings
16.17.1 4C x 240mm2+1C x 120mm2 XLPE / SWA / PVC EA 0
16.17.2 4C x 50mm2+1C x 25mm2 XLPE / SWA / PVC EA 0
16.17.3 4C x 35mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.17.4 4C x 25mm2+1C x 16mm2 XLPE / SWA / PVC EA 0
16.17.5 4C x 10mm2+1C x 10mm2 XLPE / SWA / PVC EA 0
16.18 Busbar Trunking Specification Section

Supply, install, test, commission and maintain low voltage busway system complete with all special fittings, elbow,joints, hanging and
mounting components, materials and ancillary works required for the complete operative system in accordance with the specification and
16.18.1 drawings.
16.18.1.1 1600A,4W+E Plug In Busway 60 LM 0
16.18.1.2 Tap Off Unit 250A 5 NIU 0
16.19 SUPPORT COMPONENTS CABLES (CABLE TRAYS AND ACCESSORIES)
Supply and installation of the cable trays and accessories including required supports as persite requirement, hardwares, etc... As shown in the
16.19.1 drawings
16.19.1.1 600 mm wide EA 0
16.19.1.2 450 mm wide EA 0
16.19.1.3 300 mm wide EA 0
16.19.1.4 225 mm wide EA 0
16.19.1.5 150 mm wide EA 0
16.19.1.6 100 mm wide EA 0
16.19.1.7 Ventillated cable tray covers as specified and as shown in the drawings EA 0
16.2 SOCKET OUTLETS
Supply, install, test, commission and maintain socket outlets including boxes, conduits, conduits fittings, wiring, plugs and accessories
16.20.1 connecting from the branch circuit and back to the panel board as specified and as required by the drawings.
16.20.1.1 Double poles + earth 13A Single switch socket 74 NIU 0
16.20.1.2 Double pole + earth 13A Duplex switch socket 479 NIU 0
16.20.1.3 Double pole + earth 13A Single switch socket, W.P. 22 NIU 0
16.20.1.4 Double pole + earth 13A Duplex switch socket, W.P. 2 NIU 0
16.20.1.5 Double pole switch for E.W.H with outlet 103 NIU 0
16.20.1.6 Cooker Unit 1phase 32A 49 NIU 0
16.20.1.7 Double pole switch for washing machine with flexible outlet 48 NIU 0
16.20.1.8 Double pole switch for dish washer with flexible outlet 48 NIU 0
16.20.1.9 Double pole + earth 13A Duplex switch socket Installed inside ONU Enclosure 48 NIU 0
16.21 DISCONNECT SWITCHES
Supply, install, test, commission and maintain W.P. disconnect switches including conduits, conduit fittings, wiring, vertical risers,
16.21.1 termination disconnect switch, accessories and all necessary ancillary works as specified and required by the drawings.
16.21.1.1 400A TPN 200V 50 HZ water proof 1 NIU 0
16.21.1.2 125A TPN 400V 50 HZ water proof 1 NIU 0
16.21.1.3 80A TPN 400V 50 HZ water proof 2 NIU 0
16.21.1.4 63A TPN 400V 50 HZ water proof 2 NIU 0
16.21.1.5 60A TPN 400V 50 HZ water proof 2 NIU 0
16.21.1.6 40A TPN 400V 50 HZ water proof 3 NIU 0
16.21.1.7 32A TPN 400V 50 HZ water proof 13 NIU 0
16.21.1.8 20A TPN 400V 50 HZ water proof 1 NIU 0
16.21.1.9 20A SPN 230V 50 HZ water proof 20 NIU 0
16.21.1.10 20A SPN 230V 50 HZ water proof for (FCU) Complete with cabling 133 NIU 0
16.22 LIGHTING POINT
Supply, install, test, commission and maintenance of lighting point as specified and as required by the drawings, exhaust fan point, bell point . NIU 0
16.22.1 Lighting outlet point made by copper wires size 3x2.5 Sq. mm, ready to work 1268
16.23 LIGHTING SWITCHES
Supply, install, test, commission and maintain lighting switches including boxes, conduits fitting, switches, termination conduits and wiring
16.23.1 from switches to branch circuits as specified and as required by the drawings
16.23.1.1 One way switch, one gang - 10A / IP 21 flush 420 NIU 0
16.23.1.2 One way switch, two gang - 10A / IP 21 flush 5 NIU 0
16.23.1.3 One way switch, three gang - 10A / IP 21 flush 1 NIU 0
16.23.1.4 One way switch, one gang - 10A / IP 44 flush (W.P) 9 NIU 0
16.23.1.5 One way switch, two gang - 10A / IP 44 flush (W.P) 1 NIU 0
16.23.1.6 Two ways switch, one gang - 10A / IP 21 flush 10 NIU 0
16.23.1.7 Push button for light including inpulse relay 25 NIU 0
16.23.1.8 Electronic bell 48 NIU 0
16.23.1.9 Push button for bell 48 NIU 0
16.23.1.10 One way switch, one gang - Explosion Proof Type 1 NIU 0
16.24 LIGHTING FIXTURES

Supply, install, test, commission and maintenance of lighting fixtures including but not limited to, lamps mounting brackets, accessories etc
16.24.1 and all necessary auxiliary works as specified and as required by the drawings for type description refer to the lighting fixture schedule.
16.24.1.1 Type F1 170 NIU 0
16.24.1.2 Type F2 52 NIU 0
16.24.1.3 Type F3 207 NIU 0
16.24.1.4 Type F4 10 NIU 0
16.24.1.5 Type F7 101 NIU 0
16.24.1.6 Type F24 1 NIU 0
16.24.1.7 Type D1 52 NIU 0
16.24.1.8 Type D2 142 NIU 0
16.24.1.9 Type D3 187 NIU 0
16.24.1.10 Type D4 10 NIU 0
16.24.1.11 Type D5 120 NIU 0
16.24.1.12 Type D8 76 NIU 0
16.24.1.13 Type D9 20 NIU 0
16.24.1.14 Type D10 31 NIU 0
16.24.1.15 Type D11 5 NIU 0
16.24.1.16 Type D16 48 NIU 0
16.24.1.17 Type W3 15 NIU 0
16.24.1.18 Type W4 54 NIU 0
16.24.1.19 Type W10 13 NIU 0
16.24.1.20 Type B1 12 NIU 0
16.24.1.21 Type R1 4 NIU 0
16.24.1.22 Type LS1 170 NIU 0
16.25 EARTHING SYSTEM
16.25.1 POWER

Supply, install, test, commission and maintain complete protective earthing (PE) system including earthing pits, earthing electrodes, equalizer
bars, earth continuity conductor and earthing conductor to switchboards complete with all accessories, fixing, test links, suspensions, drilling
16.25.1.1 and cutting for complete installation as per ADDC regulations also as specified and required by the drawings.
16.25.1.1.1 Earthing pits EA 0
16.25.1.1.2 Number of electrodes 3mt EA 0
16.25.1.1.3 Equalizer bars EA 0
16.25.1.1.4 Earth conductor 240 sq.mm EA 0
16.25.1.1.5 Earth conductor 16 sq.mm EA 0
16.25.1.1.6 Rod to Cable Clamp EA 0
16.25.2 LOW CURRENT & CONTROL ROOM
16.25.2.1 Earthing pits EA 0
16.25.2.2 Number of electrodes 3mt EA 0
16.25.2.3 Equalizer bars EA 0
16.25.2.4 Earth conductor 120 sq.mm EA 0
16.25.2.5 Rod to Cable Clamp EA 0
16.26 LIGHTNING PROTECTION

Supply, install, test, commission and maintain complete lighting protection system including all accessories required for the complete
installation as specified and as required by the drawings complete with earth pits complete with earth electrode,cable, clamps, and earth pit
chamber with cover ,copper strip 25 / 3 mm lightening conductor with all accessories like square tape clamps ,fixing tape clips/ copper
conuctor equipment clap, test link, test clap etc.. Connection of lighteneing down conductor to structural column with clamps , air terminal
network , bare cooper conductore or tape and all necessary materials for complete installation as specified and as required by ADDC
16.26.1 regulations and BSEN62305
16.26.1.1 Air Terminal EA 0
16.26.1.2 Earth Pits EA 0
16.26.1.3 Earth Electrode 3mt EA 0
16.26.1.4 Test Clamp EA 0
16.26.1.5 Rod to Cable Clamp EA 0
16.26.1.6 Square Clamp EA 0
16.26.1.7 Copper Tape 25 x 3mm EA 0
16.26.1.8 Conduct 120 sq.mm EA 0
16.27 PROGRAMMABLE LIGHTING CONTROL SYSTEM

Supply, install, test, commission and maintain programmable lighting control system including not limited to lighting control panel, relays,
panel boxes, conduits, conduit fittings, earthing,
termination, enclosures, switches,low voltage push button, wiring, accessories, interface unit with fire alarm system and all necessary
16.27.1 ancillary works as specified and as required by the drawings
16.27.1.1 LCP.B3 1 NIU 0
16.27.1.2 LCP.B2 1 NIU 0
16.27.1.3 LCP.B1 1 NIU 0
16.27.1.4 LCP.G 1 NIU 0
16.27.1.5 LCP.EX 1 NIU 0
16.27.1.6 LCP.EM 1 NIU 0
16.27.1.7 LCP.ET 5 NIU 0
16.27.1.8 Day light motoin sensor 1 NIU 0
16.27.1.9 Occupancy / movement sensor 55 NIU 0
16.27.1.10 Timer EA 0
16.27.1.11 Photo cell , installed on wall fence sunlight . EA 0
16.27.1.12 Interfaces with other systems as specified and as per the drawings EA 0
16.27.1.13 Conduit and wiring for the above EA 0
16.28 FIRE ALARM SYSTEM

Supply, install, test, commission and maintain fire alarm system including, but not limited to hardware and software , keyboard, relays, fire
telephone, fire pump monitoring and alarm emergency generator monitoring, elevator recall control and relays, interface unit with lifts, BMS,
HVAC, CCTV, access control system, lighting control system, central battery and emergency light system, auto dial to local authority, mimic
panel, battery and battery charger, all interfaces with other trades, Graphic command centre with PC., printer etc. and all necessary
accessories, ancillary material required for the complete installation as specified, as required by UAE fire and life safety code of practice and
16.28.1 as per the drawings
16.28.1.1 Main FACP 6 Loop 1 NIU 0
16.28.1.2 Intelligent addressable smoke detector with built in isolator base 214 NIU 0
16.28.1.3 Intelligent addressable Multi detector with built in isolator base 48 NIU 0
16.28.1.4 Intelligent addressable smoke detector with built in isolator base and sounder 53 NIU 0
16.28.1.5 Intelligent Addressable heat detector with built in isolator base 18 NIU 0
16.28.1.6 Addressable manual station 36 NIU 0
16.28.1.7 Addressable manual station water proof 19 NIU 0
16.28.1.8 Fire alarm sounder with flasher 25 NIU 0
16.28.1.9 Fire alarm sounder with flasher water proof 21 NIU 0
16.28.1.10 Monitor module for sprinkler valve tamper switches & water flow switches EA 0
16.28.1.11 Control module EA 0
16.28.1.12 Input / output interface EA 0
16.28.1.13 Conduiting and wiring for the above EA 0
16.28.1.14 mimic Panel 1 NIU 0
16.29 CARBON MONOXIDE CONTROL

Supply, install, test, commission and maintain carbon monoxide control and alarm system including, but not limited to, power supplies and all
necessary complete ancillary works and accessories required for the complete installation as specified and as required by the drawings and
16.29.1 authority requirements.
16.29.1.1 carbon monoxide alarm monitoring station 1 NIU 0
16.29.1.2 carbon monoxide sensors 11 NIU 0
16.29.1.3 Input / output interface with other systems EA 0
16.29.1.4 Conduiting and fire rated cables for the above EA 0
16.29.1.5 Excluding the existing conduit works installed at site EA 0
16.3 BGM AND VOICE EVACUATION ALARM SYSTEM

Supply, install, test, commission and maintain back ground music and voice evacuation system including, but not limited to rack with all
components, power amplifiers,distribution cabinets, accessories, etc., distribution network, conduit, trunking, fire rated wiring, battery, EA 0
interface with fire alarm system and all accessories required for the complete installation as specified, as required by local civil defence and
16.30.1 UAE fire and life safety code of practice and as per the drawings
16.31 Loud Speakers

Supply, install, test, commission and maintain loud speakers including conduits, conduit fittings, cable trunking, terminations, shielded
twisted cables, all necessary accessories and ancillary works as shown on drawings starting from the loud speakers and back to the central
16.31.1 control rack
16.31.1.1 Digital audio signaling processor unit with battery and battery charger 1 NIU 0
16.31.1.2 Multi desk compact disc players 1 NIU 0
16.31.1.3 Tuner AM/FM antenna 1 NIU 0
16.31.1.4 Celing speaker 6W 54 NIU 0
16.31.1.5 Box speaker 6W (Paging only) for stairs 21 NIU 0
16.31.1.6 Fire telephone jack 28 NIU 0
16.31.1.7 Power amplifiers EA 0
Emergency voice evacuation speaker with integral flashing NIU 0
16.31.1.8 strobe 11
16.31.1.9 Interfaces with other systems as specified and as per the drawings EA 0
16.31.1.10 Rack cabinet 19'' EA 0
16.31.1.11 Conduiting and wiring for the above EA 0
16.32 TELEPHONE SYSTEM

Supply, install, testing of telecom system as specified and as shown in the drawings ,including but not limited to, patch panels ,SC/APC
splitters,LC/APC splitters,back bone cables etc. all the required containments of trunking, trays, conduits boxes and all necessary accessories
and ancillary works as specified and as required by Telecommunication Regulatory Association (TRA) guideline and as shown on the
16.32.1 drawings.
16.32.1.1 Telecom rack 800x800mm 2 NIU 0
16.32.1.2 Mini ODF Splice Cabinet (special point) 2 NIU 0
16.32.1.3 Flat Optical Network Unit Cabinet (ONU) 54 NIU 0
16.32.1.4 Horizontal cables (4pair UTP Cat 6 cables ) EA 0
16.32.1.5 4 Core fibre optic cables,single mode EA 0
16.32.1.6 Multicore fibre optic cables,single mode EA 0
16.32.1.7 Telecom dual outlet (RJ45) 256 NIU 0
16.32.1.8 Conduits for the above EA 0
16.33 SMATV SYSTEM

Supply , install,test,commission and maintain SMATV system (IF) as specified and as shown on the drawing including ,but not limited to
dishes, witches,cables, amplifiers, conduits, sockets ,all the necessary accessories and ancillary materials required for the complete EA 0
16.33.1 installation as specified and as required by the drawings
16.34 MATV outlet 148 NIU 0
16.34.1 Conducting, trunking, containments and wiring for the above system. EA 0
16.35 CLOSED CIRCUIT TELEVISION (CCTV)

Supply, install, test, commission and maintain IP CCTV system including, but not limited to, main security rack, security LAN,POE switches,
network video recording management (NVR), graphical unit interface (GUI) work stations,pcs., keyboard, fiber and CAT6A cables, conduits, EA 0
conduit fittings, connectors, UPS,monitors 46 inch, cabling, trunking, etc., interface unit with fire alarm, B.M.S, access control and all the
necessary accessories and ancillary materials required for the complete installation as specified and as MCC requirements and as shown on
16.35.1 the drawings.
16.36 CCTV Cameras

Supply, install, test, commission and maintain IP CCTV cameras including, but not limited to, decorative camera housing, mounting brackets,
lenses, heavy gauge PVC conduits, conduit fittings back to main console and all necessary accessories and ancillary materials required for the
16.36.1 complete installation as specified and as required by the drawings
16.36.1.1 Automatic number plate recognition camera (ANPR) and interface with the gate barrier control system 2 NIU 0
16.36.1.2 Elevator camera 2 NIU 0
16.36.1.3 Indoor IP fixed dome color camera 19 NIU 0
16.36.1.4 Outdoor IP fixed dome color camera 4 NIU 0
16.36.1.5 Conduits for the above EA 0
16.36.1.6 CCTV central system including security rack, PC, monitor EA 0
16.37 ACCESS CONTROL SYSTEM
16.37.1 Specification (Section 13700)

Supply, install, test, commission and maintain access control system as specified and as indicated on the drawings including, but not limited
to, hardware and software,all cabling, conduits, trunking,PC . and all the necessary accessories and ancillary materials required for the EA 0
16.37.1.1 complete installation as specified and as required on the drawings.
16.38 Access Control Unit

Supply, install, test, commission and maintain access control units as specified and as indicated on the drawings including all cabling,
conduits, conduit fittings and accessories required for the complete installation for the following items and interface with FA and CCTV
16.38.1 systems
16.38.1.1 Door manager with backup battery 5 NIU 0
16.38.1.2 Card reader unit 10 NIU 0
16.38.1.3 Electro magnetic lock 10 NIU 0
16.38.1.4 Exit Bush button 10 NIU 0
16.38.1.5 Door contact 10 NIU 0
16.38.1.6 Interfaces with other systems as specified and as per the drawings EA 0
16.38.1.7 System software with graphical user interface (GUI) EA 0
16.38.1.8 Proximity Card reader 250 NIU 0
16.38.1.9 Conduit and wiring for the above EA 0
16.39 EMERGENCY LIGHT AND CENTRAL BATTERY SYSTEM

Supply,install,test,commission & maintain central battery system including, but not limited to central battery panels, control modules,
batteries, battery charger, conduits, cable trunk, fire rated cable, conduit, conduit fitting, trunking ,interface unit with fire alarm system
,lighting control and BMS systems, etc, and all necessary complete ancillary works & accessories required for the complete installation as
required by UAE fire code, as specified and as required by the drawings.
16.39.1
16.39.1.1 4W Recessed Decorative LED Emergency Light non maintained for corridor and main entrance (IP20) 106 NIU 0
16.39.1.2 4W Surface LED Emergency Light non maintained for indoor area, (IP20) 93 NIU 0
16.39.1.3 4W Surface LED Emergency Light non maintained for wet area, (IP54) 65 NIU 0
16.39.1.4 4W Ceiling or Wall Mounted LED Exit Light for Outdoor Area (IP44) 20 NIU 0
16.39.1.5 4W Ceiling or Wall Mounted LED Exit Light for indoor area ,(IP20) 5 NIU 0
16.39.1.6 4W LED Directional emergency light non maintained , (IP20) 36 NIU 0
16.39.1.7 4W LED Directional emergency light non maintained, (IP44) 15 NIU 0
16.39.1.8 8W LED Emergency Light Surface Non Mounted for parking area 26 NIU 0
16.39.1.9 Advanced Central monitoring PC with Bacnet BMS integration EA 0
16.39.1.10 Central Battery Panel including battery rack 1 NIU 0
16.39.1.11 Emergency lighting points 366 NIU 0
16.4 DIGITAL AUDIO/VIDEO INTERCOM SYSTEM
16.40.1 Specification (Section 16720)

Supply , install, test , commission and maintain Audio / Video intercom system,including but not limited to main entrance panels, power
station ,handsets/wall sets, video shunt unit,power supply and all the required accessories, supports as specified and as shown on the
16.40.1.1 drawings.
16.40.1.1.1 Main entrance panel 4 NIU 0
16.40.1.1.2 Color video intercom flat unit 49 NIU 0
16.40.1.1.3 Conducting, trunking, containments and wiring for the above system. EA 0
16.41 Central Energy and Water Monitoring system:

Supply, install, test and commissioning of complete central energy and water
Metering and monitoring System as per ESTIDAMA requirements, specifications
and drawings, including the following but not limited to, EA 0
Digital Power Monitoring Meters, M bus Master data logger/Ethernet gateway
Central Monitoring Software, Communication network & Cabling
Workstation, Testing & Commissioning, Dash board
16.41.1
16.42 EXTERNAL SERVICES FOR MECHANICAL WORKS
16.42.1 Empty conduits and draw wires between AHUs / FCUs and thermostats ( For wiring by others) EA 0
16.42.1.1 Empty conduits and draw wires between sensors and controls of AC system ( For wiring by others) EA 0
16.43 COMMON ITEMS FOR ENTIRE ELECTRICAL WORKS
16.43.1 Allow for Submittals and Shop drawing. EA 0
16.43.2 Allow for ASBUILT drawings EA 0
16.43.3 Allow for "O & M " Manuals EA 0
16.43.4 Allow for Spares to be handed over to client. EA 0
16.43.5 Allow for Training for the Clients staff EA 0
16.43.6 Allow for maintenance of the complete Electrical installation as specified
16.43.7 Allow for painting and Identification EA 0
16.43.8 Allow for testing and commissioning EA 0
17 CONTRACTOR'S ADJUSTMENT SHEET
17.1 Contractor's Adjustment Sheet (Missing Items in BOQ) EA 0
17.1.1 Item 1 EA 0
17.1.2 Item 2 EA 0
17.1.3 Item 3 EA 0
18 SCHEDULE OF RATES FOR DAYWORKS
18.1 Labour
18.1.1 Scaffolders 0 HUR 0
18.1.2 Steelfixers 0 HUR 0
18.1.3 Plumbers 0 HUR 0
18.1.4 Carpenters and Joiners 0 HUR 0
18.1.5 Plasterers 0 HUR 0
18.1.6 Masons 0 HUR 0
18.1.7 Painters 0 HUR 0
18.1.8 Plant and machinery operators and drivers (Light Duty) 0 HUR 0
18.1.9 Plant and machinery operators and drivers (Heavy Duty) 0 HUR 0
18.1.10 Electricians 0 HUR 0
18.1.11 A/C Mechanics 0 HUR 0
18.1.12 Welders 0 HUR 0
18.1.13 Helpers 0 HUR 0
18.1.14 Labourers 0 HUR 0
18.2 Materials
18.2.1 Contractor's percentage on the net cost of material 0 EA 0
18.3 Equipment & Tools
18.3.1 Wheeled offset excavator with backhoe and shovel (JCB type) 0 HUR 0
18.3.2 Pick up truck up to 3 T capacity 0 HUR 0
18.3.3 Dumper 2 T 0 HUR 0
18.3.4 Concrete vibrator 0 HUR 0
18.3.5 Soil compactor 0 HUR 0
18.3.6 Compressor 0 HUR 0
18.3.7 Tower Crane (.. .. .. .. .. capacity) 0 HUR 0
18.3.8 Mobile crane (.. .. .. .. .. capacity) 0 HUR 0
18.3.9 Generator 0 HUR 0
18.3.10 Scaffolding 0 DAY 0
18.3.11 Gas cutting set with all accessories 0 HUR 0
18.3.12 Dewatering pump with all required accessories 0 DAY 0
18.4 Work Outside Normal Work Hours
18.4.1 Percentage uplift to labour costs for working outside normal site hours ON ENGINEER'S INSTRUCTION. 0 EA 0
19 Consultant Fees
19.1 Consultant Fees 0.04 EA 0
5 METALWORKS

5.1 Non-Structural Metalwork

5.1.2 Balustrades and Handrails

LM 0

Powder coated Aluminum handrail for


staircases, fixed to steps complete as per
5.1.2.1 drawings. 167

LM 0

Powder coated Aluminum handrail for


staircases, wall mounted complete as per
5.1.2.2 drawings. 154
5.1.3 Ladders
NIU 0

Supply and fix Die Cast Aluminum Cat


ladder including all necessary fixing
accessories; all accordance with the
5.1.3.1 drawings and Specification to Roof 1
5.1.4 Louvers

MTK 0

Supply and fix Aluminum Louver Wall


including all necessary fixing accessories;
all accordance with the drawings to Ground
5.1.4.1 Floor 404
NIU 0

Allow for Aluminum Louver door as access


5.1.4.2 to Roof 3

MTK 0

Supply and install Acoustic louver as shown


5.1.4.3 in the Drawings 12

5.1.5 Aluminum Cladding

MTK 0

Supply and fix fire rated aluminum


composite panel all complete including
frames, rockwool insulation and all
necessary fixing accessories; all in
accordance with the drawings, civil
5.1.5.1 specifications, and ADCD requirements. 2423
NIU 0

Allow for steel support to box aluminum


cladding all complete including necessary
fixing accessories as per drawings.
5.1.5.2 (Aluminum cladding measured separately) 146

5.1.5.3 Other Items

MTK 0

Supply and install Fresh air intake sand trap


5.1.5.3.1 louver as shown in the Drawings 14

5.1.6 Balcony Railing


LM 0

Supply and fix aluminum balcony railing all


complete including all necessary finish and
5.1.6.1 fixings as per drawings. 109

5.1.7 Metal Grating

LM 0

400 mm wide floor drain grating and angle


5.1.7.1 frame for parking ramps 27
5.1.7.2 Sundries

EA 0

Access panel and hatches including


fittings, fixing accessories etc.. Complete as
5.1.7.2.1 per drawings and specifications.
NIU 0

Provide and fix in the main entrance lobby,


a 60x40x.02 cm stainless steel signage plate
to declare the Building Name, Building No.
5.1.7.2.2 and ADCP the property manager. 1