Professional Documents
Culture Documents
.Study of Quality Control and Site Execution On Monolithic Buildings Using Mivan Technology
.Study of Quality Control and Site Execution On Monolithic Buildings Using Mivan Technology
Abstract:
Quality Control is a subcategory of Quality Management sector and Quality Assurance of the project. Quality Control plays an
essential role in any construction project as it makes sure the proper method of execution is followed, good quality of construction
material, maintaining the Indian Standards and ensuring the work followed is according to it. Site Execution refers to methods,
specifications and design practices that are encountered during the construction of a project. The main objective of this research work
is the management of the problems encountered during the construction phase and to overcome the practical problems in the site
execution. This research involves various tests performed on aggregates, cement and concrete. Tests like Silt Content, Water
Absorption and Specific Gravity, Crushing Strength test, Sieve Analysis, Impact Strength Test, Dry Loose Bulk Density test, Initial
Setting and Final Setting time test, Compressive strength test, Slump cone test, tests on bricks and tiles etc. The quality of the
materials used after testing are as per IS codes, but still few problems are encountered during the execution part. We faced problems
during soil exploration and concreting. These problems have been further managed by different methods. As technology is developing
at a fast rate, New methods and techniques are discovered in the construction process of a structure. So, new testing methods and
quality maintaining procedures can also be introduced.
Keywords: Concrete, Quality Assurance, Quality Control, Quality Management, Site Execution, Soil Exploration.
I. INTRODUCTION: surveying, excavation, PCC, formwork, footings, pedestal,
starters, columns, beam, slabs, mivan and blockwork. The
Quality Control is key for major construction works, it estimates quality of construction work depends on the quality of the
the quality characteristics of a constituent, Quality control also products we have used in construction work. At present, the use
demonstrates the differences between the results obtained by of modern construction techniques has evolved a lot of scope for
different tests performed and desired results as per code future reference. So, here comes the use of mivan formwork for
provisions in order to make any kind of development to advance high-rise buildings meeting all the standards compared to the
new technologies which will correct any problems or conventional type of formwork. The mivan site execution
differences. One way of controlling the quality of any material involves a sequence of the process like wall markings, checking
used for construction is based on the inspection of the final of post kicker alignment, slab post levels, wall reinforcement,
product obtained based on all conditions which are to be shuttering, slab reinforcement, deck levels, internal wall
satisfied. It aim's to filter the products based on quality before alignment, external wall alignment, PMC checking. Site
they are used in any construction activities because the poor investigation is the preliminary stage in the site execution. It
quality of any material results in further costs and delays the involves different operations which are to be executed based on
work which has to be done on time, along with this reputation the design specifications. This can be done in three stages.
for contractors will go down when there are any defects in any
construction material which are to be repaired later increases
• Preliminary investigation.
maintenance costs and also decreases sustainability of the
• Detailed site investigation.
material may sometimes result in failure of the structure. So
• Post or supplementary investigation.
quality control is necessary. The basic functions involved in
quality control are to execute characteristics of a material and
In the first stage, geotechnical investigation such as subsoil
durability of the material to achieve the quality of construction
exploration and suitable conditions of soil are found out along
which is appropriate in the design and specifications for all
with the groundwater table and the zone of area depending upon
constructional activities which are to be performed under the
this planning or design is performed. After the investigation of
contract either on or off-site. There are many tests conducted in
land, the following processes take place like designing of the
the QC laboratory. According to IS code standard specifications,
structure, collecting and storing of quality material, scheduling
these tests are conducted and inspected whether they satisfy
of the activities involved in construction. Constructing the
code limits.Site execution involves different operations based on
structure following all the design criteria as planned and
the design given by the respected authorities depending on the
executing all the works included in it safely and completing
land, design of plan and all the other external factors. There are
them in the given time.
sequential operations involved in this site execution like
Table.7. Results of specific gravity test. Table.10. The results of DLBD test.
TRAIL 1 TRAIL 2 Volume of the container: V 0.0147 Cum
Weight of the pycnometer: W1 597 597 Weight of container: W1 8.54 Kgs
Weight of pycnometer with aggregate: W2 1386 1390 Weight of container + aggregate: W2 30.220 Kgs
Weight of pycnometer with aggregate and water: 1857 1859
W3 Weight of aggregate: (W2 – W1) 21.430 Kgs
Weight of pycnometer and pure water: W4 1368 1368 Dry loose bulk density: (W2 – W1)/V 1458 Kgs/Cum
Specific gravity of aggregate: 2.63 2.63
(W2-W1)/(W2-W1) –(W3-W4) Calculations: =
Average specific gravity: 2.63 Where,
code reference: sampling and testing as per IS2386 Part II – V= volume of the container
1963. W1 = weight of the empty container
Calculations: W2 = weight of the container along with the aggregate sample
− ∏= 3.1415, r = 0.12m, h = 0.3m
Specific gravity of aggregate=
( − )−( − ) V = 3.1415*0.12*0.3(m3)
where, V = 0.0147m3
W1 = weight of the empty pycnometer − . − .
=
W2 = weight of the pycnometer with aggregate .
W3 =weight of the pycnometer with aggregate and water −
DLBD = = 1458 kg/cum
W4 = weight of the pycnometer with water
− After performing all the above test’s, the results obtained as
Specific gravity of aggregate = (−)−(−) = within the limits of Indian Standard s. Execution is a phase
2.36 where the project is put into implementation, the project
planning is practically evolved on-site as per design and
Table.8. Results of the elongation test: specifications. The process of site execution should be
Elongation silt (mm) Total weight retained Total weight continuously monitored and scrutinised. The site overview is
passing recorded and given to the project manager. The site execution
involves a sequence of activities to be performed, starting from
40-31.5 0 0
initiation to closure of the project. The site engineer plays a
31.5-25 0 0 major role in the execution of a project. the activities carried out
25-20 0 0 in a project are interlinked with every department on site.
20-16 0 0
According to the design given by the architectures, the
implementation or execution is done by the site engineer. The
16-12.5 0 29 site execution works that we have done is based on Mivan
12.5-10 35 206 technology in which we have are Pre-Concreting, Concreting,
10-6.3 42 254 Post-Concreting.
Total: 77 489
Pre-Concreting:
Elongation index = 13.60 The processes involved are Wall Reinforcement, Shuttering,
Code reference: IS 2386 part I for sampling and testing Slab Reinforcement, Deck levels Checking, Internal wall
Limits: no such limits are mentioned, but arbitrarily limited to alignment and Internal plumb, Pre quicker alignment and
25%. External plumb, PMC checking.
7. CONCLUSION
8. REFERENCES