Professional Documents
Culture Documents
Standard Method of Measurement For Building Works, Ghana GHANA Library Authority International Standard Book Number (Isbn)
Standard Method of Measurement For Building Works, Ghana GHANA Library Authority International Standard Book Number (Isbn)
net/publication/335833654
CITATIONS READS
0 20,256
2 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Gabriel Nani on 16 September 2019.
of Measurement
Tel: 233 24 217 4209
padmorelibrary@gmail.com
Our Ref. No: PAD 3/2
TH
M Your Ref. No.
the form stated; that is at the back of the title page which is the copyright page and the barcode should
appear at the bottom (right side) of the back cover as well. After publication, two (2) copies of the
Date: 6 DECEMBER 2017
for Building
Works, Ghana
book(s) should be sent to the Library in compliance with the Book and Newspaper Registration Act of
SM
1961(Act 73) as Legal Deposit and also for inclusion into the Ghana National Bibliography. Please
Note: 2 copies of the first edition should be submitted at the Library by the end of FEBRUARY
2018. Failure to submit your Legal Deposit implies that your number will be cancelled and
reallocated.
ERIC
FOR LIBRARIAN
ISBN: 978-9988-2-6826-8
9 7 8 9 9 8 8 2 6 8 2 6 8
All rights reserved. No part of this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means without prior permission of the copyright owners.
Users are free to seek clarifications on any aspect of this document from the authors. The
authors also welcome comments and corrections (typographical, formating, content etc) on
this publication. The clarifications and comments shall be addressed to
1. Kwadzo Hohoabu
Architectural and Engineering Services Ltd.
P. O. Box 3969
Accra, Ghana
Email: hoabs1959@yahoo.com
Tel: +233 244 81 89 68
1.0 INTRODUCTION
Currently in Ghana, there are multiplicity of standard methods of measurement in use.
While academic institutions use Standard Method of Measurement, seventh edition (SMM7)
published by the RICS to teach, the use of the fifth edition (SMM5), sixth edition (SMM6) and
seventh edition (SMM7) are found in the Ghanaian quantity surveying practice. The use of
these methods, especially SMM5, however came with several amendments that are generally
accepted as standard quantity surveying practice in Ghana. Standard Method of Measurement
of Building Works, Ghana (SMMG) has been developed, taking into consideration, the
existing Ghanaian quantity surveying practice and other innovations for best measurement
practice. SMMG, therefore, seeks to standardise the rules of measurement of building works
for teaching, training and practice. In doing so, references were made to all the available rules
currently in use in Ghana and the New Rules of Measurement (NMR 2) published by the
RICS.
In the development of the standard method of measurement, the following principles provided
guidelines:
a) Ease of locating information and rules: this was achieved through consistency, order,
layout and numbering of work sections, work items, work characteristics and the rules of
measurement.
b) Emphasis on cost significance of work items: this was achieved by careful consideration
of the various works to be measured and accepting those with major cost impact on the
construction cost and those that are minimal. Those with minimal cost impact were
considered as ‘deemed included’ in work items of major cost impact.
c) Simplicity in use of the SMMG and bills of quantities: this was achieved through the
choice and arrangement of words and terms within the structure of the SMMG.
d) Thoroughness in coverage of work: this was achieved through extensive consultation
with relevant literature, construction industry practitioners and personal industry
experience. Decisions were made on the distinction between what is included as building
works and what may be beyond this scope. In this respect, a logical approach was adopted
to include all relevant work items.
e) Cost analysis/planning: included in the considerations is the resultant bills of quantities
lending themselves to cost planning and cost analysis.
f) Promotion of good practice: this was achieved by considering the basis of each item
included in SMMG whether or not it results in the essentials of good practice and whether
or not the measurement of such items may result in value to the stakeholders.
g Conciseness and preciseness of rules and information: this was achieved by carefully
crafting the prescriptions for providing general information and descriptions to exclude
unnecessary details and eliminate ambiguity (not open to wide interpretation).
h) Adoptability to the Ghanaian construction industry: this was achieved through the
process of involving all stakeholders in the development of document. There is however,
4.5 Quantities
a) Work shall be measured net as fixed in position except where otherwise stated in the
applicable rule to the work.
b) In taking-off, dimensions recorded shall be taken to two decimal places in metres. Where,
taken to two decimal places may obliterate the dimension, it shall be taken as 0.01 metre.
c) In the bills of quantities, quantities shall be taken to the nearest whole unit, except that
any quantity less than one unit shall be given as one unit.
d) Quantities measured in tonnes shall be given in two decimal places. Where such quantities
corrected to two decimal places will obliterate the item, it shall be given as 0.01 tonnes.
e) Unless otherwise stated, where minimum deductions for voids are dealt with, they shall
refer to openings and wants which are within the boundaries of the measured area.
g) The requirement to measure separate items for widths not exceeding certain limits shall
not apply where these widths are caused by voids and wants.
h) Where a quantity of any work cannot be accurately determined during preparation of
the bills of quantities, such work shall be described as provisional and subsequently re-
measured.
4.6 Descriptions
a) Dimensions shall be stated in descriptions generally in the sequence of length, width and
height/ depth/thickness. Where ambiguity could arise, the dimensions shall be identified.
b) Headings to groups of items in the bills of quantities shall be read as part of the descriptions
of the items to which they apply.
c) Each work section of bills of quantities shall begin with a description stating the nature
and location of work unless evident from the drawn or other information required to be
provided by these rules.
4. 7 Drawn Information
a) Drawn information shall include block plan, site plan, building plan, sections, elevations
and other relevant constructional details.
b) Component drawings shall show information necessary for the manufacture and assembly
of a component.
c) Where reference is to be made to drawings, a dimensioned diagram may be included and
it shall show the shape and dimensions of the features covered by an item of work.
d) Schedules which provide required information shall be deemed to be drawings as required
under these rules.
f) For example plain insitu concrete (1:3:6 - 40 mm aggregate) blinding shall be coded
3.1.1.0.0.
g) An asterisk (*) within a coding reference represents all entries in the column in which it
appears.
h) The digit zero within a coding reference indicates that the user has not made use of any of
the characteristics listed in the column under reference.
i) Where a ‘characteristic’ of an item was not listed in the “Sectional Main Bill Item Rules
and Information”, but inserted by the user, the letter ‘n’ shall be used in the appropriate
positions in the coding.
j) See “format and structure of bills of quantities” for decision on usage of codification
method.
k) When an item was not covered and cannot be identified with any of the twenty-six (26)
work sections in this document, it shall be billed under a separate section called "Not
Covered Items" coded as SMG 27. The item shall be coded 27.n.n.n.n. In the case of
multiplicity, they shall be distinguished with serial numbers as 27.n.n.n.n/1, 27.n.n.n.n/2
and so on.
l) Code numbers used as item numbers in bills of quantities shall not form part of the item
description or be taken into account in the interpretation of the contract.
m) Within a particular work section, ‘Applicable rules’ shall be referenced as in the example
below:
Example: applicable rule ‘3’ under the preliminaries section shall be referenced as SMG1/AR3.
4.11 Item of work where Drawn and Specification Information are not
available
a) Where an item of work can be described and given in accordance with these rules, but the
quantity of work required cannot be accurately determined, an estimate of the quantity
shall be given and identified as “provisional quantity”.
b) Where an item of work cannot be adequately described or given in accordance with these
rules, it shall be given as “provisional sum” and identified as either “defined” or “un-
defined” work as appropriate (Reference to SMG 26).
c) Where a provisional sum is given for defined work, the contractor shall be deemed to
have made due allowance for pricing, programming and planning preliminaries for the
4. Tools
3. Others 1. State details
15. Main contractor’s 1. Key management staff 1. State details 22. Key management staff
management staff includes: directors, construction
managers/engineers, surveyors,
general/ trades supervisors and
the like, who may be permanent
or visit site from time to time
23. Prices for management staff
must include extra-ordinary
support costs and staff travels
(for example personnel
recruitment, day transport
cost, visit to employers offices,
overseas visits and the like)
2. Hoists
3. Transport
4. Earthmoving plant
5. Concrete plant
6. Piling plant
7. Paving and surfacing plant
8. Others
Description guide Applicable rules (AR)
Characteristic 1 Characteristic 2 Characteristic 3 Auxiliary characteristic(s)
19. Main contractor’s 1. Temporary roads 1. State details 1. If any is to be made available by the employer, state
temporary works details and conditions
2. Temporary walkways
3. Scaffolding
4. Hoardings, fencing and the like
5. Hardstanding
6. Traffic management 27. Traffic management as
directly related to the works
including traffic marshalls,
traffic lights and the like
7. Others
20. Main contractor’s 1. Management staff 1. State details 28. Main contractor’s additional
additional cost items cost items are preliminary
2. Services and facilities
costs not included anywhere in
3. Mechanical plant the preliminaries bills, but the
contractor finds them pertinent.
4. Temporary works
29. Contractor may include
further details of additional cost
items as part of tender/ price
submission
5. Others
SMG 2: EARTHWORKS
(site preparation/ excavating/ filling)
5. Coated macadam or 28. Degraded or friable rock that can be scraped out by the
asphalt excavator bucket does not constitute rock
29. Trimming exposed faces of rock is deemed included
6. Others
30. Breaking up hard surface pavings is measured in accordance
with the rule for ‘removal of hard surface pavings’; under ‘surface
preparation’ in this section
6. Excavating alongside 1. State type, size and 1. State details of precaution 31. These items are measured where there is a risk of the existing
existing services (m) depth of service required service being affected by the excavation process
7. Excavating across existing 32. The method of protection is left to the discretion of the
services (nr) contractor
33. If in doubt the user must measure an item giving the nature of
the live service
q) All square, raking and curved cutting are deemed included in the t) Section of reinforcement bar other than plain circular shall be given.
formwork item
u) Tests of the reinforcement bar shall be given
r) All boxings, recesses, rebates, chamfers, ribs, and the like are deemed
v) Restrictions on bending of reinforcement shall also be given
included in the formwork item
s) Kind and quality of steel reinforcement shall be given
Sectional Main Bill Item Rules and Information
Description guide Applicable rules (AR)
Characteristic 1 Characteristic 2 Characteristic 3 Auxiliary characteristic(s)
1. Concrete 1. Blinding (m3) 1. Sloping 1. Foundations include attached column bases
3 and attached pile caps
2. Foundations (m )
3. Isolated foundations (m3) 2. Isolated foundations include isolated column
bases, isolated pile caps and machine bases
4. Casings to grillages (m3)
3. Beds include plinths and thickenings of beds
5. Beds (m3)
4. Coffered and troughed slabs include margins
6. Slabs (m3) of all widths
7. Coffered or troughed slabs (m3) 5. Walls include attached columns and piers
8. Walls (m3) 6. Walls include solid balustrades and the like
9. Filling to hollow walls (m3) 7. Work is deemed to include that in all
thicknesses and sections
8. Pricing is deemed to include pouring of
concrete to any background
10. Beams (m3) 1. Isolated 9. Beams include ground beams, copings and the
3 like in any depth
11. Beam casings (m )
2. Attached
12. Arches (m3) 10. Attached beams are measured below the slab
13. Columns (m3) 11. Columns are only measured as such when
3 isolated or their lengths on plan do not exceed
14. Column casings (m )
four times their thicknesses
12. Columns are deemed to include kickers
3
15. Steps and staircases (m ) 13. Shall be deemed to include strings and
associated landings
16. Upstands (m3) 14. Upstands exclude kickers
17. Filling 1. Mortices (nr) 1. State size and shape
2. Holes (m3) 2. Cross-reference drawing
3. Chases (m)