Republic of the Philippines

Department of Education
Region IV- A CALABARZON
Division of Laguna
District of Nagcarlan – Rizal
ACTION PLAN ON THE IMPLEMENTATION OF THE PROJECT TIM (Teachers’ Innovative Materials) in ENSCIMA
Objectives Strategies/Activities Date Persons involved Expected Output Remarks
Identify problems and needs in 1. Identification of the problems October 6, 2017 Teachers, Principal Problems and
teaching ENSCIMA and needs needs met in
a. Meeting with the ENSCIMA teaching
teachers and principal of the ENSCIMA were
schools. clearly identified.
b. Walkthrough on TG and LM
Analyze the identified problems 2. Analysis of the problem October 6, 2017 ENSCIMA Teachers, Identified
in teaching ENSCIMA a. brainstorming Master Teacher/ problems were
b. Discussion of the identified Principal analyzed.
problems will be given priority
Set the objectives for the 3. Objective Setting October 6, 2017 ENSCIMA Teachers, Objectives were
identified problems Master Teacher/ clearly discussed
Principal and analyzed
Select topics which are 4. Selection of the topics October 6, 2017 ENSCIMA Teachers, Topics were
commonly identified difficult for a. Brainstorming Master Teacher/ carefully selected
the intervention and b. identified topics in the First – Principal
preparation of learning resource Fourth Quarter
materials.
Choose a suitable format and 5. Format Selection October 6, 2017 ENSCIMA Teachers, Formats and
procedures for the delivery and a. Literary text Master Teacher/ procedure were
preparation of the learning b. Manipulative Principal clearly selected
resource materials on the c. Projected Materials
chosen topics. d. Use of CD’s
e. Film Viewing
Produce learning resource 6. Content Arrangement October 6 - 14, ENSCIMA Teachers, Production of the
materials on the identified topic a. Giving emphasis on content 2017 Master Teacher/ localized resource
specified Principal learning materials
b. mechanics
c. Style Guide
Evaluate the learning materials 7. Editing October 14 -20 , ENSCIMA Teachers, Learning
as to its functions a. Ask the help of the experts 2017 Master Teacher/ Resource
Principal Materials were
properly checked
and evaluated
Assess the validity and reliability 8. Testing October 21, 2017 Selected Grade 7 – Validity and
of the localized learning a. Actual presentation of the Grade 10 students, reliability of the
resource materials to students projects students ENSCIMA Teachers, localized
Master Teacher/ learning resource
Principal materials were
successfully
tested among 30
students in G 7 –
G 10
Evaluation of the produced 9. Evaluation October 21 – ENSCIMA Teachers, Properly and
localized learning resource a. Testing on the effectiveness and October 30, 2017 Master Teacher/ successfully
materials functionality of the localized Principal evaluated
learning materials.