n the following table the activities with their precedence sequence and expected time 

(days) are listed


for a project on which Carl Betterton's construction company is working:
Activity Immediate Predecessor(s) Time (days)
A − 3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E, F 8
The correct precedence diagram for the project is shown in