You are on page 1of 81

National Highways of Infrastructure Development

Corporation Ltd
Consultancy Services for preparation of Detailed Project Report and providing pre-
construction activities for Construction of 2-laning with hard shoulder configuration of Lunglei
to Chhumkhum from Design Chainage Km 0.00 to Km 40.00 for Lunglei-Tlabung section of
NH-302 in the State of Mizoram Under ‘Bharatmala Pariyojana’ on EPC Mode.

DETAILED PROJECT REPORT

VOLUME – VI: RATE ANALYSIS


Revised Chainage (CH: 0+000 to CH: 37+420)

JULY- 2020

CM ENGINEERING & SOLUTION


Engineering, Planning and Project Management
House No. –1473A, Maruti Vihar, Gurgaon, Haryana – 122002, Tel – 0124 –4255138/9811406386
CONTENTS

Sl. No Chapter Description

1 FOREWORD

2 BASIC RATE OF -

(A) Usage Rates of Plant & Machinery

(B) Labour

(C) Material

3 CHAPTER-1 CARRIAGE OF MATERIALS

4 CHAPTER-2 SITE CLEARANCE


EARTH WORK, EROSION CONTROL AND
5 CHAPTER-3
DRAINAGE
SUB-BASES, BASES (NON- BITUMINOUS) AND
6 CHAPTER-4
SHOULDERS
7 CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
TRAFFIC SIGNS, MARKINGS & OTHER ROAD
10 CHAPTER-8
APPURTENANCES
14 CHAPTER-12 FOUNDATIONS

15 CHAPTER-13 SUB-STRUCTURE

16 CHAPTER-14 SUPER-STRUCTURE

17 CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS


Chapter – 01
INTRODUCTION

1.0 General

The present consultancy assignment envisages for Consultancy Services for preparation of
Detailed Project Report and providing pre-construction activities for Construction of 2-
laning with hard shoulder configuration of NH-302 (From Lunglei to Tlabung) under
‘Bharatmala Pariyojana’ in the state of Mizoram

This volume of the Detailed Project deals with the rate analysis of various items of work.
The items of work for which rate analysis has been carried out are based on detailed
engineering design of roads and structures

2.0 Unit Rates

The unit rates for construction materials were analysed on the basis of materials study
undertaken, the prices of construction materials collected from various sources, and the
anticipated haulage distance to the gravity centre of the project. The “Standard Data Book for
Analysis of Rates” by MOST and the PWD Schedule of Rates (SOR) -2016 of Mizoram PWD
National Highway Analysis of rates for items not given in the Standard Data Book has been
carried out based on Consultant's experience of similar nature of projects.

Project cost estimate is prepared based on SOR-2016; however WPI from May 2016 to Dec
2019 (110.40 % to 122.80 %) is included in the project cost to bring the current rate of project
cost.

In proposed project cost is also included 12% of GST,

As SOR -2016 is already built-up with 6 % of Taxes like Vat, Excise etc. therefore input item
6.0% of taxes excluded and to bring the input items tax free.

The sources of material are as follows:


Bitumen : Guwahati, Assam (530.00 Km)
Emulsion : Guwahati, Assam (530.00 Km)
Steel : Guwahati, Assam (530.00 Km)
Cement : Jaintia Hills, Meghalaya (480.00 Km)
Borrow Soil : Borrow areas along the project
Aggregates : Airport Quarry /Quarry in Project Corridor
GSB : Chawilung Quarry in Project Corridor
Course Sand : Tuichawng River & Darzokai River bed Material
Fine Sand : Tuichawng River & Darzokai River bed Material

One Hot Mix Plant has been proposed to be erected at mid of the project road during
construction. An Avg. lead of 2.0 km has been assumed form the HMP. The lead
considerations for the different materials are as follows:
Sr. P-1 P-2 P-3 P-4 P-5 P-6
Material Unit Location
No. Dist Dist Dist Dist Dist Dist
1 Bitumen Km Aizawl 167 181 195 209 209 234
2 Emulsion Km Aizawl 167 181 195 209 209 234
3 Steel Km Aizawl 167 181 195 209 209 234
4 Cement Km Aizawl 167 181 195 209 209 234
5 Boulder/ Km Project Corridor
Masonry Stone 10 10 10 10 10 10
HP Pipe Km Chawnte 127 141 155 169 169 194
6 Aggregates Km Chawilung &
Maudarh quarry 55 69 83 97 97 97
7 GSB Km Tuichawng River
& Darzokai River
/Quarry in
Project Corridor 34 48 62 76 61 61
8 Coarse Sand Km Tuichawng River
& Darzokai River 58 72 86 100 61 61
9 Fine Sand Km Tuichawng River
& Darzokai River 34 48 62 76 61 61
Labour
Labour rates for rate analysis have been based on Schedule of Rates (SOR) -2016 of
Mizoram PWD National Highway
Machineries
The rates of machineries have been taken Schedule of Rates (SOR) -2016 of Mizoram PWD
National Highway.
Rates of the following items taken from INAM Pro and OIL site on the month of Dec-2019

Source Jaintia Hills Guwahati Guwahati Guwahati


Distance 480 530 530 530
Base Location Aizawl Aizawl Aizawl Aizawl
Material Cement Steel Bitumen Emulsion
Basic in Rs. 4950.0 48559.0 27500.0 23220.0
Carriage of Materials
4224.0 4664.0 4664.0 4664.0
in Rs.
Total in Rs. 9174.0 53223.0 32164.0 27884.0

Haulage rate for material from Guwahati to Aizawl for surface road is considered based on
Assam PWD SOR2018-19 i.e Rs.8.80

2.2 The rates of skilled and unskilled workers have been taken from Mizoram PWD National
Highway SOR-2016. The basic rates of plant and machineries have been collected from the
manufacturer along with taxes, salvage value, economic life and fuel consumption.

2.3 The materials study revealed distinct sources for coarse and fine aggregates and haulage
distance for borrow earth as discussed in detail.
2.4 During analysis of unit rates an overhead component of 10% for Road Works and 20 % for
Bridge Works has been considered to account for the establishment cost and cost of
financing to the contractor. In addition, a contractor’s profit of 10% has been included. In all
cases, fully mechanised construction techniques have been assumed.
BASIC RATES FOR USAGE OF RATES OF PLANT AND MACHINERY,
LABOUR AND MATERIAL

(A) Usage Rates of Plant and Machinery

Output of 2019 2016


Sl. No. Description of Machine Activity Output Unit
Machine Rate with WPI Rate

P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 730.65 699.00
Batching and Mixing Plant (a)
P&M-002 Concrete Mixing cum/hour 20 hour 4600.29 4401.00
30 cum capacity
Batching and Mixing Plant (b)
P&M-003 Concrete Mixing cum/hour 13 hour 3823.65 3658.00
15 - 20 cum capacity
Applying bitumen
P&M-004 Bitumen Pressure Distributor sqm/hour 1750 hour 2724.01 2606.00
tack coat

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 976.29 934.00
Concrete Paver Finisher with Paving of concrete
P&M-006 cum / hour 20 hour 5797.14 5546.00
40 HP Motor surface
Concrete Pump of 45 & 30
P&M-007 Pumping of concrete cum / hour 33 / 22 hour 448.43 429.00
cum capacity
For Pouring
P&M-008 Concrete Bucket capacity in cum 1 hour 31.36 30.00
concrete
Concrete Mixer (a)
P&M-009 Concrete Mixing cum/hour 2.5 hour 390.94 374.00
0.4/0.28cum
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 383.62 367.00
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 3028.18 2897.00
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 2026.80 1939.00
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 838.32 802.00
Spreading/Cutting/ 300/
P&M-014 Dozer D - 80 - A 12 cum/hour hour 5958.11 5700.00
Clearing 150/250
Spreading/Cutting/ 200/
P&M-015 Dozer D - 50 - A 15 cum/hour hour 3658.49 3500.00
Clearing 120/150
Applying emulsion
P&M-016 Emulsion Pressure Distributor sqm/hour 1750 hour 1917.05 1834.00
tack coat
Front End loader 1 cum Soil loading /
P&M-017 cum/hour 60 /25 hour 2090.57 2000.00
bucket capacity Aggregate loading
Generation of
P&M-018 Generator (a) 125 KVA KVA 100 hour 1427.86 1366.00
electric Energy
Generation of
P&M-019 Generator( b) 63 KVA KVA 50 hour 875.95 838.00
electric Energy
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 2147.01 2054.00
Hotmix Plant - 120 TPH DBM/BM/SDC/
P&M-021 cum/hour 40 hour 56276.99 53839.00
capacity Premix
Hotmix Plant - 100 TPH DBM/BM/SDC/
P&M-022 cum/hour 30 hour 41618.99 39816.00
capacity Premix
Hotmix Plant - 60 to 90 TPH DBM/BM/SDC/
P&M-023 cum/hour 25 hour 33285.99 31844.00
capacity Premix
Hotmix Plant - 40 to 60 TPH DBM/BM/SDC/
P&M-024 cum/hour 17 hour 35798.85 34248.00
capacity Premix
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 5274.50 5046.00
Hydraulic Excavator of 1 cum Soil Ordinary/ Soil
P&M-026 cum/hour 60 /60 /60 hour 3135.85 3000.00
bucket Marshy/ Soil
Integrated Stone Crusher Unsuitable
P&M-027 Crushing of Spalls TPH 100 hour 17851.34 17078.00
100THP
Integrated Stone Crusher
P&M-028 Crushing of Spalls TPH 200 hour 35424.64 33890.00
200THP

Basic Rate - 2
Output of 2019 2016
Sl. No. Description of Machine Activity Output Unit
Machine Rate with WPI Rate
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 714.97 684.00
capacity in
P&M-030 Mastic Cooker Mastic Wearing coat 1 hour 139.02 133.00
tonne
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 762.01 729.00
Clearing /Spreading 200/200/5
P&M-032 Motor Grader 3.35 m blade cum/hour hour 4853.25 4643.00
/GSB /WBM 0/50
Mixing and laying
P&M-033 Mobile slurry seal equipment sqm/hour 2700 hour 3953.26 3782.00
slurry seal

Paver Finisher Hydrostatic Paving of DBM/


P&M-034 cum/hour 40 hour 5763.69 5514.00
with sensor control 100 TPH BM/SDC/ Premix

Paver Finisher Mechanical Paving of WMM


P&M-035 cum/hour 40/30 hour 2001.72 1915.00
100 TPH /Paving of DLC
Piling Rig with Bantonite 0.75 m dia to 1.2 m
P&M-036 Rm/hour 2 to 3 hour 11200.21 10715.00
Pump dia Boring
attachment
Rolling of Asphalt
P&M-037 Pneumatic Road Roller cum/hour 25 hour 2609.03 2496.00
Surface
Pneumatic Sinking
P&M-038 Pneumatic Sinking Plant cum/hour 1.5 to 2.00 hour 8754.25 8375.00
of wells
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 1911.82 1829.00
Prestressing Jack with Pump Stressing of steel
P&M-040 hour 218.46 209.00
& access wires/stands
P&M-041 Ripper Scarifying cum/hour 60 hour 57.49 55.00
P&M-042 Rotavator Scarifying cum/hour 25 hour 32.40 31.00
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 348.08 333.00
Smooth Wheeled Roller 8 Soil Compaction
P&M-044 cum/hour 70/25 hour 996.15 953.00
tonne /BM Compaction
Rolling of Asphalt
P&M-045 Tandem Road Roller cum/hour 30 hour 2337.25 2236.00
Surface
Transportation of Capacity in
P&M-046 Tipper - 5 cum 5.5 km 760.97 728.00
soil, GSB, WMM, cum
Hotmix etc.
Transportation of Capacity in tonne.
P&M-047 Tipper - 5 cum 5.5 12.54 12.00
soil, GSB, WMM, cum km
Hotmix etc.
Transportation of Capacity in
P&M-048 Tipper - 5 cum 5.5 hour 1063.05 1017.00
soil, GSB, WMM, cum
Hotmix etc.
Transportation of
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 1762.35 1686.00
Concrete Mix to site
Transportation of tonne.
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 64.81 62.00
Concrete Mix to site km
Transportation of
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 1627.51 1557.00
Concrete Mix to site
Transportation of tonne.
P&M-052 Transit Mixer 3.0 cum cum/hour 3 74.22 71.00
Concrete Mix to site km
P&M-053 Tractor Pulling capacity in HP 50 hour 811.14 776.00
Rate of Tractor +
P&M-054 Tractor with Rotavator hour 779.78 746.00
Rotavator
Rate of Tractor +
P&M-055 Tractor with Ripper hour 805.91 771.00
Ripper

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 760.97 728.00

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 1069.32 1023.00

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 12.54 12.00
tonne.k

Basic Rate - 3
Output of 2019 2016
Sl. No. Description of Machine Activity Output Unit
Machine Rate with WPI Rate
Earth or soil / GSB /
P&M-059 Vibratory Roller 8 tonne cum/hour 100/60/60 hour 3082.54 2949.00
WBM

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 1042.15 997.00

P&M-061 Water Tanker Water Transport capacity in KL 6 km 70.03 67.00

P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 2483.59 2376.00

2019 2016
Sl. No. Description of Machine Unit
Rate with WPI Rate
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 1091.28 1044.00
Batch type cold mixing plant 100-120 TPH capacity producing an average
P&M-064 hour 16567.74 15850.00
output of 75 tonne/hour
P&M-065 Belt conveyor system hour 3610.41 3454.00
P&M-066 Boat to carry at least 20 persons hour 417.07 399.00
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 8962.26 8574.00
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 14875.42 14231.00
P&M-069 Cold milling machine @ 20 cum per hour hour 3141.08 3005.00
P&M-070 Crane 5 tonne capacity hour 1237.62 1184.00
P&M-071 Crane 10 tonne capacity hour 1288.83 1233.00
P&M-072 Crane 15 tonne capacity hour 1318.10 1261.00
P&M-073 Crane 20 tonne capacity hour 1635.87 1565.00
P&M-074 Crane 40 T capacity hour 1897.19 1815.00
P&M-075 Crane with grab 0.75 cum capacity hour 2041.44 1953.00
P&M-076 Compressor with guniting equipment along with accessories hour 1103.82 1056.00
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 hour 15518.27 14846.00
tonnes/hour.
P&M-078 Epoxy Injection gun hour 516.37 494.00
P&M-079 Generator 33 KVA hour 835.18 799.00
P&M-080 Generator 100 KVA hour 1541.79 1475.00
P&M-081 Generator 250 KVA hour 2833.76 2711.00
Induction, de-induction and erection of plant and equipment including all
P&M-082 hour 0.00
components and accessories for pneumatic method of well sinking.
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 454.70 435.00
P&M-084 Jack for Lifting 40 tonne lifting capacity. day 815.32 780.00
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 7821.85 7483.00
P&M-086 Plate compactor hour 372.12 356.00
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 1826.11 1747.00
P&M-088 Texturing machine (for rigid pavement) hour 1367.23 1308.00
P&M-089 Truck Trailor 30 tonne capacity hour 2282.90 2184.00
P&M-090 Truck Trailor 30 tonne capacity t.km 10.45 10.00
P&M-091 Tunnel Boring machine hour 4204.13 4022.00
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 1468.62 1405.00
P&M-093 Wet Mix Plant 100 TPH hour 2808.68 2687.00
P&M-094 Wet Mix Plant 75 TPH hour 2695.78 2579.00

Basic Rate - 4
(B) Labour

2019 2016
Sl. No. Description of Labour Unit Rate with WPI Rate

L-01 Blacksmith (IInd class) day 609.40 550.00

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 831.00 750.00

L-03 Blaster (Stone cutter) day 609.40 550.00

L-04 Carpenter I Class day 831.00 750.00

L-05 Chiseller (Head Mazdoor) day 609.40 550.00

L-06 Driller (Jumper) day 609.40 550.00

L-07 Diver day 831.00 750.00

L-08 Fitter (II class) day 609.40 550.00

L-09 Mali day 554.00 500.00

L-10 Mason (IInd class) day 609.40 550.00

L-11 Mason (Ist class) day 831.00 750.00

L-12 Mate / Supervisor day 831.00 750.00

L-13 Mazdoor day 554.00 500.00

L-14 Mazdoor/Dresser (Semi Skilled) day 609.40 550.00

L-15 Mazdoor/Dresser/Sinker (Skilled-II) day 609.40 550.00

L-16 Medical Officer day 997.20 900.00

L-17 Operator (grouting) day 609.40 550.00

L-18 Painter (II class) day 609.40 550.00

L-19 Para medical personnel day 720.20 650.00

Basic Rate - 5
(C) Materials
2018 2016
Sl. No. Description Unit
Rate Rate
M-001 Stone Boulder of size 150 mm and below at Crusher Plant cum 1275.31 1151.00
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 1185.56 1070.00
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 1131.27 1021.00
M-004 Coarse sand at Mixing Plant cum 1489.15 1344.00
M-005 Coarse sand at Quarry Site cum 1489.15 1344.00
M-006 Fine sand at Quarry Site cum 1320.74 1192.00
M-007 Binding Material for WBM at Work Site cum 593.89 536.00
M-008 Gravel/Quarry spoil at Site Cum 1310.76 1183.00
M-009 Granular Material for GSB works at Quarry Cum 1310.76 1183.00
M-010 Granular Material for GSB works at Mixing Plant Cum 1310.76 1183.00
M-011 0.00
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 1310.76 1183.00

Rate at
Sl. No Description Usage Unit Rate at Plant
Plant
Sub-base
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm Cum 1967.22 1882.00
course
Sub-Base
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm Cum 2220.18 2124.00
course
Sub-Base
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm Cum 2294.40 2195.00
course
Sub-Base
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm Cum 1959.91 1875.00
course
Sub-Base
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm Cum 1827.15 1748.00
course
Sub-Base
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm Cum 2019.49 1932.00
course
Sub-Base
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm Cum 1827.15 1748.00
course
Sub-Base
M-020 Close graded Granular sub-base Material 2.36 mm Cum 1404.86 1344.00
course
Stone crusher dust finer than 3mm with not more than 10% passing Wearing
M-021 Cum 1116.36 1068.00
0.075 sieve. course
Sub-
M-022 Coarse graded Granular sub-base Material 2.36 mm & below Cum 1129.95 1081.00
Base/Bas
e course
Sub-Base
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron Cum 1437.26 1375.00
course
Sub-
M-024 Coarse graded Granular sub-base Material 2.36 mm to 75 micron Cum 1580.47 1512.00
Base/Bas
e course
Sub-Base
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm Cum 1959.91 1875.00
course
Sub-
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm Base/Bas Cum 1782.21 1705.00
e course
Sub-Base
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm Cum 2041.44 1953.00
course
Sub-Base
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm Cum 1967.22 1882.00
course
Sub-Base
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm Cum 1967.22 1882.00
course
Base
M-030 Aggregates below 5.6 mm Cum 2232.72 2136.00
course

Basic Rate - 6
Rate at
Sl. No Description Usage Unit Rate at Plant
Plant
Base
M-031 Aggregates 22.4 mm to 2.36 mm Cum 2019.49 1932.00
course
Base
M-032 Aggregates 22.4 mm to 5.6 mm Cum 2167.92 2074.00
course
Base
M-033 Aggregates 45 mm to 2.8 mm Cum 2167.92 2074.00
course
Base
M-034 Aggregates 45 mm to 22.4 mm Cum 2220.18 2124.00
course
Base
M-035 Aggregates 53 mm to 2.8 mm Cum 2167.92 2074.00
course
Base
M-036 Aggregates 53 mm to 22.4 mm Cum 2167.92 2074.00
course
Base
M-037 Aggregates 63 mm to 2.8 mm Cum 2167.92 2074.00
course
Base
M-038 Aggregates 63 mm to 45 mm Cum 2167.92 2074.00
course
Base
M-039 Aggregates 90 mm to 45 mm Cum 2167.92 2074.00
course
Base
M-040 Aggregates 10 mm to 5 mm Cum 2529.58 2420.00
course
Wearing
M-041a Aggregates 11.2 mm to 0.09 mm Cum 2703.10 2586.00
course
Base
M-041b Aggregates 11.2 mm to 0.09 mm Cum 2407.29 2303.00
course
Wearing
M-042 Aggregates 13.2 mm to 0.09 mm Cum 2675.92 2560.00
course
Wearing
M-043 Aggregates 13.2 mm to 5.6 mm Cum 2703.10 2586.00
course
Base
M-044 Aggregates 13.2 mm to 10 mm Cum 2355.02 2253.00
course
Base
M-045 Aggregates 20 mm to 10 mm Cum 2220.18 2124.00
course
Base
M-046 Aggregates 25 mm to 10 mm Cum 2220.18 2124.00
course
Base
M-047 Aggregates 19 mm to 6 mm Cum 2220.18 2124.00
course
Base
M-048 Aggregates 37.5 mm to 19 mm Cum 2167.92 2074.00
course
Base
M-049 Aggregates 37.5 mm to 25 mm Cum 2167.92 2074.00
course
Wearing
M-050 Aggregates 6 mm nominal size Cum 2703.10 2586.00
course
Cement
M-051 Aggregates 10 mm nominal size Cum 2576.62 2465.00
concrete
Wearing
M-052a Aggregates 13.2/12.5 mm nominal size Cum 2651.88 2537.00
course
Base
M-052b Aggregates 13.2/12.5 mm nominal size Cum 2407.29 2303.00
course
Wearing
M-053 Aggregates 20 mm nominal size Cum 2576.62 2465.00
course/Co
ncrete
Cement
M-054 Aggregates 25 mm nominal size Cum 2454.32 2348.00
concrete
M-055 Cement 2253.00
Aggregates 40 mm nominal size Cum 2355.02
concrete

Basic Rate - 7
2019 2016
Sl. No Description Unit
Rate with WPI Rate
M-056 GI pipe 100 mm dia metre 1097.55 1050.00
M-057 Acrylic polymer bonding coat litre 348.08 333.00
M-058 Alluminium Paint litre 416.02 398.00
M-059 Alluminium alloy plate 2mm Thick sqm 21323.77 20400.00
M-060 Alluminium alloy/galvanized steel tonne 78129.68 74745.00
Alluminium sheeting fixed with encapsulated lens type reflective sheeting
M-061 including 2% towards lettering, cost of angle iron, cost of drilling holes, nuts, sqm 21290.32 20368.00
bolts etc. and signs as applicable
M-062 Alluminium studs 100 x 100 mm fitted with lens reflectors nos 1287.79 1232.00
M-063 Barbed wire kg 122.30 117.00
M-064 Bearing (Cost of parts) nos
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of
M-066 nos 24162.76 23116.00
elastomer bonded to 6 nos. internal reinforcing steel laminates by the process
M-067 of vulcanization,)
Bearing (Forged steel roller bearing of 250 tonne) nos
Bearing (Pot type bearing assembly consisting of a metal piston supported by a
disc, PTFE pads providing sliding surfaces against stainless steel mating
M-068 nos
together with cast steel assemblies/fabricated structural steel assemblies duly
painted with all components)
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos
M-071 Bentonite kg 865.49 828.00
M-072 Binding wire kg 114.98 110.00
M-073 Bitumen ( Cationic Emulsion ) (Ex-Aizawl) tonne 60000.00 60000.00

Bitumen (60-70 grade) (Ex-Aizawl) ( Basic rate = Rs 27500/ MT +transportation


M-074 tonne 32164.00
from Guwahati to Aizawl (530Km xRs.8.80) Rs.4664= Rs 32164)

M-075 Bitumen (80-100 grade ) (Ex-Aizawl) tonne 54497.92 52137.00


M-076 Bitumen (Cutback ) (Ex-Aizawl) tonne 75626.23 72350.00
Emulsion (Ex-Aizawl) ( Basic rate = Rs 23220/ MT +transportation from
M-077 tonne 27884.00
Guwahati to Aizawl (530Km xRs.8.80) Rs.4664= Rs 27884)
M-078 Bitumen (modified graded) (Ex-Aizawl) tonne 91067.15 87122.00
M-079 Brick (Ex Aizawl) each 12.54 12.00
M-080 C.I. shoes for the pile kg 122.30 117.00
Cement (53 grade) (Ex-Aizawl) ( Basic rate = Rs 4950/ MT +transportation
M-081 tonne 9174.00 8015.00
from Jaintia Hills to Aizawl (=480Km xRs.8.80) Rs.4224= Rs 9174)
Cold twisted bars (HYSD Fe 500 Bars) ( Basic rate = Rs 48559/ MT
M-082 +transportation from Guwahati to Aizawl (530Km x Rs.8.80) Rs.4664= Rs tonne 53223.00 40830.07
53223)
M-083 Collar for joints 300 mm dia nos 897.90 859.00
M-084 Compressible Fibre Board(20mm thick) sqm 1067.23 1021.00
M-085 Connectors/ Staples each 1359.91 1301.00
M-086 Copper Plate(12m long x 250mmwide) kg 1333.78 1276.00
M-087 Corrosion resistant Structural steel tonne 76047.48 72753.00
M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 79.44 76.00
M-089 Credit for excavated rock found suitable for use cum 90.94 87.00
M-090 Curing compound liter 891.63 853.00
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 4244.89 4061.00
M-092 Earth Cost or compensation for earth taken from private land cum 39.72 38.00
Elastomeric slab seal expansion joint assembly manufactured by using
M-093 metre 12086.61 11563.00
chloroprene, elastomer for elastomeric slab unit conforming to clause 915.1 of
IRC: 83 (part II),

Basic Rate - 8
2019 2016
Sl. No Description Unit
Rate with WPI Rate
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 3857.09 3690.00
Epoxy compound with accessories for preparing epoxy mortar (available at Dr.
M-095 kg 858.18 821.00
Fixit
M-096 Epoxy mortar kg 808.00 773.00
M-097 Epoxy primer kg 1099.64 1052.00
M-098 Epoxy resin-hardener mix for prime coat kg 1070.37 1024.00
M-099 Flag of red color cloth 600 x 600 mm each 107.66 103.00
M-100 Flowering Plants each 224.74 215.00
M-101 Galvanized MS flat clamp nos 251.91 241.00
Galvanized steel wire crates of mesh size 100 mm x 100 mm woven with 3mm
M-102 sqm 348.08 333.00
dia. GI wire in rolls of required size.
M-103 Galvanized structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 88.85 85.00
M-104 Gelatin 80% (with accessories) kg 327.17 313.00
M-105 Geo grids sqm 355.40 340.00
M-106 Geomembrane sqm 617.76 591.00
M-107 Geonets sqm 328.22 314.00
M-108 Geotextile sqm 432.75 414.00
M-109 Geotextile filter fabric sqm 432.75 414.00
M-110 GI bolt 10 mm Dia nos 70.03 67.00
M-111 Grouting pump with agitator hour 487.10 466.00
M-112 Grass (Doob) kg 29.27 28.00
M-113 Grass (Fine) kg 21.95 21.00
M-114 HDPE pipes 75mm dia metre 353.31 338.00
M-115 HDPE pipes 90mm dia metre 348.08 333.00
M-116 Hedge plants each 348.08 333.00
M-117 Helical pipes 600mm diameter metre 46090.71 44094.00
M-118 Hot applied thermoplastic compound litre 487.10 466.00
M-119 HTS strand tonne 106446.00 163314.00
M-120 Joint Sealant Compound kg 1711.13 1637.00
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 31.36 30.00

M-122 LDO for steam curing litre 60.63 58.00


M-123 M.S. Clamps nos 98.26 94.00
M-124 M.S. Clamps kg 98.26 94.00
M-125 M.S. shoes @ 35 Kg per pile of 15 m kg 122.30 117.00
M-126 Mild Steel bars (ISI) tonne 63521.85 60770.00
Modular strip/box seal expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and up to 140mm assembly comprising of
M-127 edge beams, central beam,2 modules chloroprene seal, anchorage elements, metre 16198.75 15497.00
support and control system, all steel sections protected against corrosion and
installed by the manufacturer or his authorized representative
Modular strip/box seal expansion joint catering to a horizontal movement
beyond 140mm and up to 210mm box/box seal joint assembly containing 3
M-128 modules/cells and comprising of edge beams, two central beams, chloroprene metre 32424.68 31020.00
seal, anchorage elements, support and control system, all steel sections
protected against corrosion and installed by the manufacturer or his authorized
M-129 Nipples 12mm nos 86.76 83.00

Basic Rate - 9
2019 2016
Sl. No Description Unit
Rate with WPI Rate
M-130 Nuts and bolts kg 307.31 294.00
M-131 Paint litre 391.98 375.00
M-132 Pavement Marking Paint litre 1099.64 1052.00
M-133 Paving Fabric sqm 122.30 117.00
M-134 Perforated geosynthetic pipe 150 mm dia metre 548.77 525.00
M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 559.23 535.00
M-136 Pesticide kg 116.03 111.00
M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 1067.23 1021.00
M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 36.58 35.00
M-139 Plastic tubes 50 cm dia, 1.2 m high nos 1711.13 1637.00
M-140 Polymer braids metre 70.03 67.00
M-141 Pre molded Joint filler,25 mm thick for expansion joint. sqm 719.15 688.00
M-142 Pre-coated stone chips of 13.2 mm nominal size cum 2778.36 2658.00
Preformed continuous chloroprene elastomer or closed cell foam sealing
M-143 element with high tear strength, vulcanized in a single operation for the full metre 1363.05 1304.00
length of a joint to ensure water tightness.
M-144 Pre-molded asphalt filler board sqm 1363.05 1304.00
M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 348.08 333.00
M-146 Primer kg 358.53 343.00
M-147 Quick setting compound kg 518.46 496.00
M-148 Random Rubble Stone (for masonry works) cum 874.90 837.00
M-149 RCC Pipe NP 4 heavy duty non pressure pipe 1000 mm dia metre 13624.22 13034.00
M-150 RCC Pipe NP 4 heavy duty non pressure pipe 1200 mm dia metre 17309.89 16560.00
M-151 RCC Pipe NP 4 heavy duty non pressure pipe 300 mm dia metre 2892.30 2767.00
M-152 Reflectorising glass beads kg 209.06 200.00
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper
M-153 metre 70.03 67.00
Strips)
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanized
M-154 metre 59.58 57.00
carbon steel strips)
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass
M-155 metre 44.95 43.00
reinforced polymer/fibre reinforced polymer/polymeric strips)
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless
M-156 metre 64.81 62.00
steel strips)
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Alluminium metre 44.95 43.00
M-158 strips)
Rivets each 79.44 76.00
M-159 Sand bags (Cost of sand and Empty cement bag) nos 29.27 28.00
M-160 Sapling 2 m high 25 mm dia each 59.58 57.00
M-161 Scrap tyres of size 900 x 20 nos 865.49 828.00
M-162 Seeds kg 35.54 34.00
M-163 Selected earth cum 295.82 283.00
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 82.58 79.00
M-165 Sheathing duct metre 260.28 249.00
M-166 Shrubs each 417.07 399.00
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 348.08 333.00
M-168 Sodium vapour lamp each 12504.72 11963.00
M-169 Square Rubble Coursed Stone cum 874.90 837.00

Basic Rate - 10
2019 2016
Sl. No Description Unit
Rate with WPI Rate
Steel circular hollow pole of standard specification for street lighting to mount
M-170 each 36235.78 34666.00
light at 5 m height above deck level
Steel circular hollow pole of standard specification for street lighting to mount
M-171 each 53144.28 50842.00
light at 9 m height above road level
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 209.06 200.00
M-173 Steel helmet and cushion block on top of pile head during driving. kg 736.92 705.00
M-174 Steel pipe 25 mm external dia as per IS:1239 metre 107.66 103.00
M-175 Steel pipe 50 mm external dia as per IS:1239 metre 243.55 233.00
M-176 Steel wire rope 20 mm kg 221.60 212.00
M-177 Steel wire rope 40 mm kg 221.60 212.00
M-178 Strip seal expansion join metre 13994.25 13388.00
M-179 Structural Steel tonne 94963.96 90850.00
M-180 Super plasticizer admixture IS marked as per 9103-1999 kg 310.45 297.00
Synthetic Geogrids as per clause 3102.8 and approved design and
M-181 sqm 295.82 283.00
specifications.
M-182 Through and bond stone {Size (0.24x0.24x0.39)m or 0.0224 Cu.m} each 61.67 59.00
M-183 Tie rods 20mm diameter nos 348.08 333.00
M-184 Tiles size 300 x 300 mm and 25 mm thick each 139.02 133.00
M-185 Timber cum 25084.70 23998.00
M-186 Traffic cones with 150 mm reflective sleeve nos 432.75 414.00
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 4973.46 4758.00
M-188 Unslaked lime tonne 11280.69 10792.00
M-189 Water KL 337.63 323.00
M-190 Water based cement paint litre 428.57 410.00
M-191 Welded steel wire fabric kg 77.35 74.00
M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 109.75 105.00
M-193 Wooden ballies 2" Dia for bracing each 358.53 343.00
M-194 Wooden ballies 8" Dia and 9 m long each 1035.88 991.00
M-195 Wooden packing cum 17065.29 16326.00
M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 79.44 76.00
M-197 RCC Pipe NP 3 heavy duty non pressure pipe 1000 mm dia metre 10468.51 10015.00
M-198 RCC Pipe NP 3 heavy duty non pressure pipe 1200 mm dia metre 14460.45 13834.00

Overheads for Road Works 10 %

Contractors profit for Road Works 10 % for input of Overheads or Contractors profit
please type in column C as like below
Overheads for Bridge Works 25 %
Overheads for Bridge Works Type symbol of apostrophe(') then input value
30 %
(Rehabilitation) then one space then symbol of percentage (%)
Contractors profit for Bridge Works 10 % for example '08 %

Lead from Mixing Plant to working


20.00 km
site (Concrete works)
Lead from Mixing Plant to working
20.00 km
site (Pavement works)
Lead for E/W borrow area to site 5.00 km
Lead for fly ash from source to site 0 km

Basic Rate - 11
CHAPTER-1
CARRIAGE OF MATERIALS
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-1
Item
Descriptions Unit SOR 2016
No.
Loading and unloading of stone boulder/stone aggregates/sand/
1.1 kanker/moorum. (Placing tipper at loading point, loading with front end loader, cum 229.00
dumping, turning for return trip, excluding time for haulage and return trip)
1.2 Loading and Unloading of Boulders by Manual Means cum 287.00
1.3 Loading and Unloading of Cement or Steel by Manual Means and stacking. tonne 401.00
1.4 Loading and Unloading of Bitumen by Manual Means Mt 175.00
1.5 Loading and Unloading of NP2/NP3/NP4 Hume Pipe of all diameter. No 692.00
1.6 Cost of Haulage Excluding Loading and Unloading
For Short Haul for a distance upto 100 km
tonne.
(i) Surfaced Road 13.80
km
tonne.
(ii) Unsurfaced Gravelled Road 15.80
km
tonne.
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. 21.50
km
1.7 Cost of Haulage Excluding Loading and Unloading
For Long Haul for a distance beyond 100 km
tonne.
(i) Surfaced Road 11.80
km
tonne.
(ii) Unsurfaced Gravelled Road 13.89
km
tonne.
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. 18.90
km

~~oOo~~

Chapter 1 - 12
CHAPTER-2
SITE CLEARANCE
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-2
Item
Descriptions Unit SOR 2016
No.
Cutting of Trees, including Cutting of Trunks, Branches and Removal
2.1 (Cutting of trees, including cutting of trunks, branches and removal of stumps,
roots, stacking of serviceable material with all lifts and up to a lead of 1000 mtrs
and earth filling in the depression/pit.)
(i) Girth from 300 mm to 600 mm each 520.00
(ii) Girth from 600 mm to 900 mm each 938.00
(iii) Girth from 900 mm to 1800 mm each 5236.00
(iv) Girth above 1800 mm each 10476.00
2.2 Clearing Grass and Removal of Rubbish hectare 35528.00
Clearing and Grubbing Road Land. (Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to
2.3 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable
materials and stacking of serviceable material to be used or auctioned up to a
lead of 1000 metres including removal and disposal of top organic soil not
exceeding 150 mm in thickness.)
(i) By Manual Means:-
A In area of light jungle hectare 107566.00
B In area of thorny jungle hectare 144075.00
(ii) By Mechanical Means
A In area of light jungle hectare 37025.00
B In area of thorny jungle hectare 45577.00

~~oOo~~

Chapter 2 - 13
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-3
Item
Descriptions Unit SOR 2016
No.
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of shoring
3.11 and bracing, removal of stumps and other deleterious matter, dressing of sides and
bottom, backfilling the excavation earth to the extent required and utilising the
remaining earth locally for road work.)
(i) Ordinary soil
A Manual Means (Depth upto 3 m) cum 568.00
B Mechanical Means (Depth upto 3 m) cum 95.00
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 711.00
B Mechanical Means cum 125.00
(iii) Hard rock ( requiring blasting )
A Manual Means cum 1212.00
(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 1239.00
Construction of Embankment with Material Deposited from Roadway Cutting
3.15 (Construction of embankment with approved materials deposited at site from cum 242.00
roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and
3.16 earthen shoulders with approved material obtained from borrow pits with all lifts & cum 617.00
leads, transporting to site, spreading, grading to required slope and compacted to
meet requirement of table No. 300-2)
3.17 Compacting Original Ground
Compacting original ground supporting subgrade (Loosening of the ground upto
Case-I a level of500 mm below the subgrade level, watered, graded and compacted in cum 141.00
layers to meet requirement of table 300-2 for subgrade construction.)
Seeding and Mulching (Preparation of seed bed on previously laid top soil,
3.21 furnishing and placing of seeds, fertilizer, mulching material, applying bituminous sqm 307.00
emulsion at the rate of0.23 litres per sqm and laying and fixing jute netting, including
watering for 3 months all as per clause 308)
Excavation in Hilly Areas in Ordinary Soil By Mechanical Means (Excavation in
3.30 ordinary soil in hilly area by mechanical means including cutting and trimming of side
slopes and disposing of excavated earth with all lifts and lead .)
Case-I : Disposal of cut material with all lifts and lead upto 1000 metres. cum 214.00
Case-II: Disposing cut material on the valley side cum 97.00
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring
Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by
3.31
mechanical means including cutting and trimming of slopes and disposal of cut
material.)
Case-I : Disposal of cut material with all lifts and lead upto 1000 metres. cum 324.00
Case-II: Disposing cut material on the valley side cum 167.00
Excavation in Hilly Areas in laminated rock (requiring blasting) By Mechanical
Means (Excavation for roadway in hilly areas in laminated rock (requiring blasting)
3.32 which are not suitable for construction of masonry and pavement by drilling,
blasting and breaking, trimming of bottom and side slopes in accordance with
requirements of lines, grades and cross sections, loading and disposal of cut road
with in all lifts and leads upto 1000 metres.)
Case-I : Disposal of cut material with all lifts and lead upto 1000 metres. cum 430.00
Case-II: Disposing cut material on the valley side cum 320.00
~~oOo~~

Chapter 3 - 14
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-4
Item
No.
Descriptions Unit SOR 2016
4.1 Granular Sub-Base (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing the material,
mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site,
A spreading in uniform layers with motor grader on prepared surface and compacting
with vibratory power roller to achieve the desired density, complete as per clause
401 )
(i) for Grading- I Material cum 4004.00
(ii) for Grading- II Material cum 4090.00
(iii) for Grading-III Material cum 3966.00
(iv) for Grading-IV Material cum 3759.00
(v) for Grading-V Material cum 3977.00
(vi) for Grading-VI Material cum 4188.00
Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base (Providing, laying and spreading Material on a prepared
4.5 sub grade, adding the designed quantity of cement to the spread Material, mixing
in place with rotavator, grading with the motor grader and compacting with the road
roller at OMC to achieve the desired unconfined compressive strength and to form
a layer of sub-base/base.)
(i) For Sub-Base course cum 4325.00
(ii) For Base course cum 4181.00
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying
of bitumen over cleaned dry surface of crushed cement concrete base at the rate
4.10 of 25 kg per 10 sqm by a bitumen pressure distributor, spreading of key sqm 56.00
aggregates at the rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling
the surface as per clause 506.3.8)
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with
4.11 water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, cum 4131.00
laying in uniform layers with paver in sub- base / base course on well prepared
surface and compacting with vibratory roller to achieve the desired density.)

~~oOo~~

Chapter 4 - 15
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-5
Item
Descriptions Unit SOR 2016
No.
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared
5.1 surface of granular Base including clearing of road surface and spraying primer at
the rate shown in 500-1 using mechanical means.)
i) Low Porosity sqm 25.00
ii) Medium Porosity sqm 42.00
iii) High Porosity sqm 52.00
Tack coat (Providing and applying tack coat with bitumen emulsion using emulsion
5.2 pressure distributor at required rate on the prepared bituminous/granular surface
cleaned with mechanical broom.)
i) Normal Bituminous Surface sqm 12.00
ii) Dry and Hungry Bituminous Surface sqm 14.00
iii) Granular Surface Treated with Primer sqm 16.00
iv) Granular Surface Not Treated with Primer sqm 19.00
v) Cement Concrete Base sqm 17.00
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting
5.4
the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction as per MoRTH specification
clause No. 507 complete in all respects.)
(i) for Grading I ( 40 mm nominal size ) cum 11345.00
(ii) for Grading II (19 mm nominal size) cum 11414.00
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to
5.5 5.6 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic
paver finisher with sensor control to the required grade, level and alignment, rolling
with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects)
Case-I Using Bitumen 60/70 grade
(i) for Grading-I ( 13 mm nominal size ) cum 12280.00
(ii) for Grading-II (10 mm nominal size) cum 12365.00
5.16 Crack Prevention Courses
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing
and laying of a stress absorbing membrane over a cracked road surface, with crack
width 6 to 9 mm after cleaning with a mechanical broom, using modified binder
(ii) sqm 160.00
complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading
11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface
for uniform spread of aggregates and surface finished to conform to clause 902.)

~~oOo~~

Chapter 5 - 16
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-8
Item
Descriptions Unit SOR 2016
No.
Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
8.4 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly
fixed to the ground by means of properly designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per
approved drawing)
(i) 90 cm equilateral triangle each 12720.00
(ii) 60 cm equilateral triangle each 7723.00
(iii) 60 cm circular each 10994.00
(iv) 80 mm x 60 mm rectangular each 16069.00
(v) 60 cm x 45 cm rectangular each 10659.00
(vi) 60 cm x 60 cm square each 12978.00
Direction and Place Identification signs upto 0.9 sqm size board. (Providing
and erecting direction and place identification retro-reflectorised sign asper IRC:67
made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over
8.5 aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a sqm 29850.00
mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by
means of properly designed foundation with M15 grade cement concrete 45 x 45 x
60 cm, 60 cm below ground level as per approved drawing)
Road Marking with Hot Applied Thermoplastic Compound with
Reflectorising Glass Beads on Bituminous Surface (Providing and laying of hot
8.13 applied thermoplastic compound 2.5 mm thick including reflectorising glass beads sqm 1545.00
@ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied
glass beads as per IRC:35 .The finished surface to be level, uniform and free from
streaks and holes.)
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of
8.14 standard design as per IRC:8-1980, fixing in position including painting and
printing etc)
(i) 5th kilometre stone (precast) each 6785.00
(ii) Ordinary Kilometer stone (Precast) each 4061.00
(iii) Hectometer stone (Precast) each 1094.00
Road Delineators (Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above ground level, painted
8.15 black and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 each 5674.00
mm dia circular reflectorised panels at the top, buried or pressed into the ground
and confirming toIRC-79 and the drawings.)
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of
8.16 standard design as per IRC:25-1967, fixed in position including finishing and each 1093.00
lettering but excluding painting)
8.23 Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal
beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70
cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75
A x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, metre 7022.00
all steel parts and fitments to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post
with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810)
~~oOo~~

Chapter 8 - 17
CHAPTER-12
FOUNDATIONS
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-12
Item No. Descriptions Unit SOR 2016

Excavation for Structures (Earth work in excavation of foundation of structures


as per drawing and technical specification, including setting out, construction of
12.1
shoring and bracing, removal of stumps and other deleterious matter, dressing
of sides and bottom and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 646.00
(ii) 3 m to 6 m depth cum 807.00
(iii) Above 6 m depth cum 1106.00
B Mechanical Means
(i) Depth upto 3 m cum 132.00
(ii) Depth 3 m to 6 m cum 151.00
(iii) Depth above 6m cum 199.00
II Ordinary rock (not requiring blasting) 4
A Manual Means
(i) Depth upto 3 m cum 920.00
B Mechanical Means cum 123.00
III Hard rock ( requiring blasting )
A Manual Means cum 1933.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 1523.00
V Marshy soil (upto 3 m depth)
A Manual means cum 2076.00
B Mechanical Means cum 502.00
VI Back Filling in Marshy Foundation Pits cum 1292.00
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6
12.2
nominal mix. Rate may be taken as per items 13.4.)
Sand Filling in Foundation Trenches as per Drawing & Technical
12.3 cum 2419.00
Specification
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in
12.4 foundation with crushed stone aggregate 40 mm nominal size mechanically cum 9046.00
mixed, placed in foundation and compacted by vibration including curing for 14
days.)
Brick masonry work in cement mortar 1:3 in foundation complete excluding
12.5 cum 13099.00
pointing and plastering, as per drawing and technical specifications
12.6 A Cement mortar 1:3 (1cement :3 sand) cum 6774.00
B Cement mortar 1:2 (1cement :2 sand) cum 8063.00
C Cement mortar 1:4 (1cement :4 sand) cum 5869.00
D Cement mortar 1:6 (1cement :6 sand) cum 5188.00
Stone masonry work in cement mortar in foundation complete as drawing and
12.7
Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) in cement mortar 1:3 cum 8090.00
(b) Random Rubble Masonry in cement mortar 1:3 cum 7633.00
(c) Square Rubble Coursed rubble masonry( first sort ) in cement mortar 1:4 cum 7698.00
(d) Random Rubble Masonry in cement mortar 1:4 cum 7202.00
(e) Square Rubble Coursed rubble masonry( first sort ) in cement mortar 1:6 cum 7403.00
(f) Random Rubble Masonry in cement mortar 1:6 cum 6878.00
Plain/Reinforced cement concrete in open foundation complete as per
12.8
drawing and technical specifications
A PCC Grade M15 cum 9683.00

Chapter 12 - 18
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-12
Item No. Descriptions Unit SOR 2016
B PCC Grade M20 cum 10618.00
C RCC Grade M20
Case I: Using concrete mixer cum 10776.00
Case II: With Batching Plant, Transit Mixer and Concrete Pump cum 14555.00
D PCC Grade M25
Case I: Using concrete mixer cum 11316.00
Case II: With Batching Plant, Transit Mixer and Concrete Pump cum 15092.00
E RCC Grade M25
Case I: Using concrete mixer cum 11483.00
Case II: With Batching Plant, Transit Mixer and Concrete Pump cum 15253.00
F PCC Grade M30
Case I: Using concrete mixer cum 11367.00
Case II: With Batching Plant, Transit Mixer and Concrete Pump cum 15127.00
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete
12.25 as per drawing and technical specifications and removal of excavated earth metre 79991.00
with all lifts and lead upto 1000 m. (Pile diameter-1200 mm)
Cement concrete for reinforced concrete in pile cap complete as per
12.38
drawing and Technical Specification
D RCC Grade M35
Case I: Using concrete mixer cum 11779.00
Case II: With Batching Plant, Transit Mixer and Concrete Pump cum 15613.00
12.39 Levelling course for Pile cap cum 9258.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in
12.40 tonne 85102.00
foundation complete as per drawing and technical specifications
Supplying, fitting and placing un-coated Mild steel reinforcement complete
12.41 tonne 100672.00
in foundation as per drawing and technical specification

~~oOo~~

Chapter 12 - 19
CHAPTER-13
SUB-STRUCTURE
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-13
Item
Descriptions Unit SOR 2016
No.
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per
13.3 sqm 233.90
Technical specifications
Plain/Reinforced cement concrete in sub-structure complete as per drawing
13.5
and technical specifications
A PCC Grade M15
(p) Height upto 5m cum 10243.00
B PCC Grade M20
(p) Height upto 5m cum 11232.00
C PCC Grade M25
(p) Height upto 5m
Case-I : Using concrete Mixer cum 11999.00
(q) Height 5m to 10m
Case-I : Using concrete Mixer cum 12435.00
(r) Height above 10m
Case - I : Using concrete Mixer cum 12980.00
F RCC Grade M25
(p) Height upto 5m
Case-I : Using concrete Mixer cum 12176.00
G RCC Grade M30
(p) Height upto 5m
Case-I : Using concrete Mixer cum 12221.00
(q) Height 5m to 10m
Case-I : Using concrete Mixer cum 12565.00
(r) Height above 10m
Case-I : Using concrete Mixer cum 13054.00
Supplying, fitting and placing HYSD bar reinforcement in sub-structure
13.6 tonne 85414.00
complete as per drawing and technical specifications
Providing weep holes in Brick masonry/Plain/Reinforced concrete
abutment, wing wall/return wall with 100 mm dia AC pipe, extending through
13.8 each 1812.00
the full width of the structure with slope of 1V :20H towards drawing foce.
Complete as per drawing and Technical specifications
Back filling behind abutment, wing wall and return wall complete as per
13.9
drawing and Technical specification
A Granular material cum 2863.00
B Sandy material cum 2881.00
Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with smaller size towards
13.10 cum 2825.00
the soil and bigger size towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and technical specification.

~~oOo~~

Chapter 13 - 20
CHAPTER-14
SUPER-STRUCTURE
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-14
Item
Descriptions Unit SOR 2016
No.
Furnishing and Placing Reinforced/Prestressed cement concrete in super-
14.1
structure as per drawing and Technical Specification
B RCC Grade M25
Case-I : Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 13221.00
(q) Height 5m to 10m cum 13771.00
(r) Height above 10m cum 14322.00
C RCC Grade M 30
Case-I : Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 13396.00
(q) Height 5m to 10m cum 13954.00
(r) Height above 10m cum 14512.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 13954.00
(q) Height 5m to 10m cum 14512.00
(r) Height above 10m cum 15071.00
Case-II : Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 17714.00
(q) Height 5m to 10m cum 18452.00
(r) Height above 10m cum 19191.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 18452.00
(q) Height 5m to 10m cum 19191.00
(r) Height above 10m cum 19929.00
E PSC Grade M-40
Case-I : Using Concrete Mixer
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 19425.00
(q) Height 5m to 10m cum 20215.00
(r) Height above 10m cum 21005.00
F PSC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of concrete
(i)
(a+b+c)
(p) Height upto 5m cum 18901.00
(q) Height 5m to 10m cum 19716.00
(r) Height above 10m cum 20531.00
For I-beam & slab including launching of precast girders by launching truss
(ii)
upto 40 m span, 21-31% of cost of concrete.
(p) Height upto 5m cum 19716.00
(q) Height 5m to 10m cum 20531.00
(r) Height above 10m cum 21345.00
For cast-in-situ box girder, segmental construction and balanced
(iii)
cantilever, 36-56% of cost of concrete.
(p) Height upto 5m cum 22160.00
(q) Height 5m to 10m cum 23790.00
(r) Height above 10m cum 25419.00
G PSC Grade M-50

Chapter 14 - 21
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-14
Item
Descriptions Unit SOR 2016
No.
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 22481.00
(q) Height 5m to 10m cum 24146.00
(r) Height above 10m cum 25811.00
H PSC Grade M- 55
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 23238.00
(q) Height 5m to 10m cum 24959.00
(r) Height above 10m cum 26680.48
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure
14.2 tonne 88130.00
complete as per drawing and technical specifications
High tensile steel wires/strands including all accessories for stressing,
14.3 stressing operations and grouting complete as per drawing and Technical tonne 206631.00
Specifications
Providing and laying Cement concrete wearing coat M-30 grade including
14.4 cum 21486.00
reinforcement complete as per drawing and Technical Specifications

Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course
on top of deck slab excluding prime coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface, including providing antiskid
14.5 surface with bitumen precoated fine grained hard stone chipping of 9.5 mm sqm 521.00
nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing
of 10 cm center to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over
mastic surface, all complete as per clause 515.)
14.9 Drainage Spouts complete as per drawing and Technical specification metre 1921.00
PCC M15 Grade leveling course below approach slab complete as per drawing
14.10 cum 9312.00
and Technical specification
Reinforced cement concrete approach slab including reinforcement and
14.11 cum 19448.00
formwork complete as per drawing and Technical specification
Burried Joint (Providing and laying a burried expansion joint, expansion gap
being 20 mm, covered with 12 mm thick, 200 mm wide galvanised wieldable
14.17 structural steel plate as per IS: 2062, placed symmetrical to centre line of the metre 2189.00
joint, resting freely over the top surface of the deck concrete, welding of 8 mm
dia. 100 mm long galvanised nails spaced 300 mm c/c along the centre line of
the plate, all as specified in clause 2604.)
14.18 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
(i) metre 8476.00
as per drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint
(ii) metre 381.00
complete as per drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion
joint for fixed ends of simply supported spans not exceeding 10 m to cater for a
(iii) metre 317.00
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications.
Providing and filling joint sealing compound as per drawings and technical
(iv) metre 46.00
specifications with coarse sand and 6% bitumen by weight

Chapter 14 - 22
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-14
Item
Descriptions Unit SOR 2016
No.
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint
varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic
14.19 direction), covered with a closure plate of 200mm x 6mm of wieldable structural metre 2372.00
steel conforming to IS: 2062, asphaltic plug to consist of polymer modified
bitumen binder, carefully selected single size aggregate of 12.5 mm nominal size
and a heat resistant foam caulking/backer rod, all as per approved drawings and
specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an
elastomeric slab steel expansion joint, catering to right or skew (less than 20
deg., moderately curved with maximum horizontal movement upto 50 mm,
14.20 complete as per approved drawings and standard specifications to be installed by metre 17554.00
the manufacturer/supplier or their authorised representative ensuring compliance
to the manufacturer's instructions for installation and clause 2606 of MORTH
specifications for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint
consisting of steel armoured nosing at two edges of the joint gap suitably
14.21 anchored to the deck concrete and a preformed chloroprene elastomer or closed metre 6726.00
cell foam joint sealer compressed and fixed into the joint gap with special
adhesive binder to cater for a horizontal movement upto 40 mm and vertical
movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per
14.22 approved drawings and standard specifications to be installed by the metre 20294.00
manufacturer/supplier or their authorised representative ensuring compliance to
the manufacturer's instructions for installation.)

~~oOo~~

Chapter 14 - 23
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
SCHEDULE OF RATES 2015 FOR NATIONAL HIGHWAYS AND STATE ROADS IN MIZORAM Chapter-15
Item
Descriptions Unit SOR 2016
No.
Providing and laying Flooring complete as per drawing and Technical
15.8
specifications laid over cement concrete bedding.
A Rubble stone laid in cement mortar 1:3 cum 9074.00
Gabian Structure for Retaining Earth (Providing and construction of a gabain
structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m
each divided into 1.5 m compartments by cross netting, made from 4 mm galvanised
15.12 steel wire @ 32 kg per 10sqm having minimum tensile strength of 300 Mpa cum 3844.00
conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with boulders
with least dimension of 200 mm, all loose ends to be tied with 4 mm galvanised steel
wire

~~oOo~~

Chapter 15 - 24
CHAPTER-1
CARRIAGE OF MATERIALS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.1 Loading and Unloading of Stone Boulder/Stone cum
aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity 13 Min
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 1063.05 350.81 P&M-048
Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.330 2090.57 689.89 P&M-017

b) Overhead charges @ 10 % on (a) 104.07


c) Contractor's profit @ 10 % on (a+b) 114.48
Cost for 5.5 cum = a+b+c 1259.25
Rate per cum = (a+b+c)/ 5.5 228.95
Note Unloading will be by tipping. say 229.00
1.2 Loading and Unloading of Boulders by Manual Means

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 831.00 91.41 L-12
Mazdoor for loading and unloading day 0.750 554.00 415.50 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 1063.05 797.29 P&M-048
c) Overhead charges @ 10 % on (a+b) 130.42
d) Contractor's profit @ 10 % on (a+b+c) 143.46
Cost for5.5 cum = a+b+c+d 1578.08
Rate per cum = (a+b+c+d)/5.5 286.92
Note Unloading will be by tipping. say 287.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 831.00 66.48 L-12
Mazdoor for loading and unloading day 2.000 554.00 1108.00 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 1069.32 2138.64 P&M-057
c) Overhead charges @ 10 % on (a+b) 331.31
d) Contractor's profit @ 10 % on (a+b+c) 364.44
Cost for10 tonnes = a+b+c+d 4008.87
Rate per tonnes = (a+b+c+d)/10 400.89
say 401.00
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km

For Short Haul for a distance upto 100 km

(i) Surfaced Road


Speed with load : 17 km / hour.
Speed while Returning empty :30 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.650 1063.05 690.98 P&M-048
Time taken for empty return trip. hour 0.420 1063.05 446.48 P&M-048
b) Overhead charges @ 10 % on (a) 113.75
c) Contractor's profit @ 10 % on (a+b) 125.12
cost for 100 t km = a+b+c 1376.33
Rate per t.km = (a+b+c)/100 13.76

Chapter 1 - 1
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 13.80
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 15 km / hour
Speed for empty return trip :25 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.750 1063.05 797.29 P&M-048
Time taken for empty return trip hour 0.480 1063.05 510.26 P&M-048
b) Overhead charges @ 10 % on (a) 130.76
c) Contractor's profit @ 10 % on (a+b) 143.83
Cost for 100 t .km = a+b+c 1582.14
Rate per t.Km = (a+b+c)/100 15.82
say 15.80
1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and
Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 1063.05 1063.05 P&M-048
Time taken for empty return trip hour 0.670 1063.05 712.24 P&M-048
b) Overhead charges @ 10 % on (a) 177.53
c) Contractor's profit @ 10 % on (a+b) 195.28
Cost for 100 t .km = a+b+c 2148.10
Rate per t.Km = (a+b+c)/100 21.48
say 21.50
1.5 Loading and Unloading of Bitumen and Stacking the
unloaded bitumen properly in the stack yard by Manual
Means
Placing tipper at loading/unloading point, loading/unloading
with labours, etc
Unit = tonne
Taking output = 110 MT
a) Labour
Mate day 1.000 831.00 831.00 L-12
Mazdoor for loading and unloading day 21.500 554.00 11911.00 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 3.000 1063.05 3189.15 P&M-048
c) Overhead charges @ 10 % on (a+b) 1593.12
d) Contractor's profit @ 10 % on (a+b+c) 1752.43
Cost for 110 MT cum = a+b+c+d 19276.70
Rate per cum = (a+b+c+d)/110 175.24
Note Unloading will be by manual means. say 175.00
1.6 Loading and Unloading of NP2/NP3/NP4 Hume cum
Pipe of all diameter.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit = No
Taking output =3 No
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity 22 Min
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 29 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.480 1063.05 510.26 P&M-048
Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.480 2090.57 1003.47 P&M-017

b) Labour

Chapter 1 - 2
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor for loading and unloading day 0.400 554.00 221.60 L-13
c) Overhead charges @ 10 % on (a) 151.37
d) Contractor's profit @ 10 % on (a+b) 188.67
Cost for loading and unloading of 3 no hume pipe = a+b+c 2075.37
Rate per cum = (a+b+c)/ 3 691.79
Note Unloading will be by tipping. say 692.00
1.7 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
For Long Haul for a distance beyond 100 km

Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km

(i) Surfaced Road


Speed with load : 25 km / hour.
Speed while Returning empty :30 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.500 1063.05 531.53 P&M-048
Time taken for empty return trip. hour 0.420 1063.05 446.48 P&M-048
b) Overhead charges @ 10 % on (a) 97.80
c) Contractor's profit @ 10 % on (a+b) 107.58
cost for 100 t km = a+b+c 1183.39
Rate per t.km = (a+b+c)/100 11.83
say 11.80
1.7 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :25 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.600 1063.05 637.83 P&M-048
Time taken for empty return trip hour 0.480 1063.05 510.26 P&M-048
b) Overhead charges @ 10 % on (a) 114.81
c) Contractor's profit @ 10 % on (a+b) 126.29
Cost for 100 t .km = a+b+c 1389.19
Rate per t.Km = (a+b+c)/100 13.89
say 13.90
1.7 (iii) Katcha Track and Track in River Bed/Nallah Bed and
Choe Bed.
Speed with load :12 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 0.800 1063.05 850.44 P&M-048
Time taken for empty return trip hour 0.670 1063.05 712.24 P&M-048
b) Overhead charges @ 10 % on (a) 156.27
c) Contractor's profit @ 10 % on (a+b) 171.90
Cost for 100 t .km = a+b+c 1890.85
Rate per t.Km = (a+b+c)/100 18.91
say 18.90

Chapter 1 - 3
CHAPTER-2
SITE CLEARANCE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches
and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling in
the depression/pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 831.00 16.62 L-12
Mazdoors for cutting trees including cutting, refilling, day 0.600 554.00 332.40 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 811.14 81.11 P&M-053
c) Overhead charges @ 10 % on (a+b) 43.01
d) Contractor's profit @ 10 % on (a+b+c) 47.31
Rate for each tree = a+b+c+d 520.45
say 520.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 831.00 33.24 L-12
Mazdoors for cutting trees including cutting, refilling, day 0.900 554.00 498.60 L-13
compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 811.14 243.34 P&M-053
c) Overhead charges @ 10 % on (a+b) 77.52
d) Contractor's profit @ 10 % on (a+b+c) 85.27
Rate for each tree = a+b+c+d 937.97
say 938.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.150 831.00 124.65 L-12
Mazdoors for cutting trees including cutting, refilling, day 7.000 554.00 3878.00 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 811.14 324.46 P&M-053
c) Overhead charges @ 10 % on (a+b) 432.71
d) Contractor's profit @ 10 % on (a+b+c) 475.98
Rate for each tree = a+b+c+d 5235.80
say 5236.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.500 831.00 415.50 L-12
Mazdoors for cutting trees including cutting, refilling, day 14.000 554.00 7756.00 L-13
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 811.14 486.68 P&M-053
c) Overhead charges @ 10 % on (a+b) 865.82
d) Contractor's profit @ 10 % on (a+b+c) 952.40
Rate for each tree = a+b+c+d 10476.40
say 10476.00
2.2 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of 50
metres outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 831.00 1662.00 L-12
Mazdoor day 50.000 554.00 27700.00 L-13

Chapter 2 - 4
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Overhead charges @ 10 % on (a) 2936.20
c) Contractor's profit @ 10 % on (a+b) 3229.82
Rate per Hectare = a+b+c 35528.02
say 35528.00
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth up
to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.
Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 831.00 4986.00 L-12
Mazdoor day 150.000 554.00 83100.00 L-13
b) Machinery
Tractor-trolley hour 1.000 811.14 811.14 P&M-053
c) Overhead charges @ 10 % on (a+b) 8889.71
d) Contractor's profit @ 10 % on (a+b+c) 9778.69
Rate per Hectare = a+b+c+d 107565.54
say 107566.00
2.3 (i) B In area of thorny jungle
a) Labour
Mate day 8.000 831.00 6648.00 L-12
Mazdoor day 200.000 554.00 110800.00 L-13
b) Machinery
Tractor-trolley hour 2.000 811.14 1622.28 P&M-053
c) Overhead charges @ 10 % on (a+b) 11907.03
d) Contractor's profit @ 10 % on (a+b+c) 13097.73
Rate per Hectare = a+b+c+d 144075.04
say 144075.00
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 831.00 132.96 L-12
Mazdoor day 4.000 554.00 2216.00 L-13
b) Machinery
? Dozer D-50 with attachment for removal of trees & hour 7.500 3658.49 27438.68 P&M-015
stumps
Tractor-trolley hour 1.000 811.14 811.14 P&M-053
c) Overhead charges @ 10 % on (a+b) 3059.88
d) Contractor's profit @ 10 % on (a+b+c) 3365.87
Rate per Hectare = a+b+c+d 37024.53
say 37025.00
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 831.00 199.44 L-12
Mazdoor day 6.000 554.00 3324.00 L-13
b) Machinery
? Dozer D-50 with attachment for removal of trees & hour 9.000 3658.49 32926.41 P&M-015
stumps
Tractor-trolley hour 1.500 811.14 1216.71 P&M-053
c) Overhead charges @ 10 % on (a+b) 3766.66
d) Contractor's profit @ 10 % on (a+b+c) 4143.32
Rate per Hectare = a+b+c+d 45576.54
say 45577.00

Chapter 2 - 5
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.11 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
(i) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 831.00 265.92 L-12
Mazdoor day 8.000 554.00 4432.00 L-13
b) Overhead charges @ 10 % on (a) 469.79
c) Contractor's profit @ 10 % on (a+b) 516.77
Cost for 10 cum = a+b+c 5684.48
Rate per cum = (a+b+c)/10 568.45
say 568.00
Note Cost of dewatering may be added where required upto 10 per
cent of labour cost Assessment for dewatering shall be made
as per site conditions..
3.11 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 831.00 265.92 L-12
Mazdoor day 8.000 554.00 4432.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 3135.85 18815.10 P&M-026
c) Overhead charges @ 10 % on (a+b) 2351.30
d) Contractor's profit @ 10 % on (a+b+c) 2586.43
Cost for 300 cum = a+b+c+d 28450.75
Rate per cum = (a+b+c+d)/300 94.84
say 95.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.11 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 831.00 332.40 L-12
Mazdoor day 10.000 554.00 5540.00 L-13
b) Overhead charges @ 10 % on (a) 587.24
c) Contractor's profit @ 10 % on (a+b) 645.96
Cost for 10 cum = a+b+c 7105.60
Rate per cum = (a+b+c)/10 710.56
say 711.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.11 (ii) B Mechanical Means

Unit = cum
Taking output = 216 cum

Chapter 3 - 6
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.240 831.00 199.44 L-12
Mazdoor day 6.000 554.00 3324.00 L-13
b) Machinery
? Hydraulic excavator 1.0 cum bucket capacity hour 6.000 3135.85 18815.10 P&M-026
c) Overhead charges @ 10 % on (a+b) 2233.85
d) Contractor's profit @ 10 % on (a+b+c) 2457.24
Cost for 216 cum = a+b+c+d 27029.63
Rate per cum = (a+b+c+d)/216 125.14
say 125.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2.In case of rock, foundation beyond3 m is not dug and hence
not included.
3.11 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 831.00 440.43 L-12
ii) Driller day 0.840 609.40 511.90 L-06
iii) Blaster day 0.400 609.40 243.76 L-03
iv) Mazdoor day 12.000 554.00 6648.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.667 730.65 487.34 P&M-001
per hour
c) Material
Blasting Material kg 3.500 327.17 1145.10 M-104
Detonator electric each 14.000 38.57 539.98 M-094 /100

d) Overhead charges @ 10 % on (a+b+c) 1001.65


e) Contractor's profit @ 10 % on (a+b+c+d) 1101.82
Cost for 10 cum = a+b+c+d+e 12119.98
Rate per cum = (a+b+c+d+e)/10 1212.00
say 1212.00
Note Cost of dewatering @ 10 per cent of labour cost may be
added, where required Assessment for dewatering shall be
made as per site conditions.
3.11 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.200 831.00 166.20 L-12
Mazdoor day 5.000 554.00 2770.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 730.65 7306.50 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 10 % on (a+b) 1024.27
d) Contractor's profit @ 10 % on (a+b+c) 1126.70
Cost for 10 cum = a+b+c+d 12393.67
Rate per cum = (a+b+c+d)/10 1239.37
say 1239.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.

Chapter 3 - 7
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.15 305 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 831.00 16.62 L-12
Mazdoor day 0.500 554.00 277.00 L-13
b) Machinery
Dozer D-80 for spreading @ 300 cum per hour hour 0.330 5958.11 1966.18 P&M-014
Motor grader for grading @ 200 cum per hour hour 0.500 4853.25 2426.63 P&M-032
Water tanker6 KL capacity hour 4.000 1042.15 4168.60 P&M-060
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 3082.54 3082.54 P&M-059
c) Material
Cost of water KL 24.000 337.63 8103.12 M-189
d) Overhead charges @ 10 % on (a+b+c) 2004.07
e) Contractor's profit @ 10 % on (a+b+c+d) 2204.48
Rate for 100 cum = a+b+c+d+e 24249.24
Rate per cum = (a+b+c+d+e)/100 242.49
say 242.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already provided
in the cost of excavation. However, if the earth is dumped by
tippers from roadway cutting, the input of dozer for spreading
is required to be provided.
3.16 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-2

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 831.00 33.24 L-12
Mazdoor day 1.000 554.00 554.00 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum per hour 1.670 3135.85 5236.87 P&M-026
hour
Tipper 10 tonne capacity tonne.km 175xL 12.54 10972.50 Lead =5 km
& P&M-058

Add 10 per cent of cost of carriage to cover cost of 1097.25


loading and unloading
Dozer D-80 for spreading @ 300 cum per hour hour 0.333 5958.11 1984.05 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 4853.25 9706.50 P&M-032
Water tanker with 6 km lead hour 4.000 1042.15 4168.60 P&M-060
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 1.670 3082.54 5147.84 P&M-059
c) Material
Cost of water KL 24.000 337.63 8103.12 M-189
Compensation for earth taken from private land cum 100.000 39.72 3972.00 M-092
d) Overhead charges @ 10 % on (a+b+c) 5097.60
e) Contractor's profit @ 10 % on (a+b+c+d) 5607.36
Cost for 100 cum = a+b+c+d+e 61680.93
Rate per cum = (a+b+c+d+e)/100 616.81
say 617.00
3.21 308 Seeding and Mulching

Chapter 3 - 8
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Preparation of seed bed on previously laid top soil, furnishing
and placing of seeds, fertilizer, mulching material, applying
bituminous emulsion at the rate of 0.23 litres per sqm and
laying and fixing jute netting, including watering for 3 months
all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 831.00 332.40 L-12
Mazdoor day 10.000 554.00 5540.00 L-13
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 14.000 1042.15 14590.10 P&M-060
months
Tractor-trolley hour 2.400 811.14 1946.74 P&M-053
c) Material
Seeds kg 3.600 35.54 127.94 M-162
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 348.08 149.67 M-167
Bitumen Emulsion litre 55.200 27.88 1538.98 M-077
Jute netting, open weave, 2.5 cm square opening sqm 264.000 31.36 8279.04 M-121
Cost of water for 3 months KL 84.000 337.63 28360.92 M-189
d) Overhead charges @ 10 % on (a+b+c) 6086.58
e) Contractor's profit @ 10 % on (a+b+c+d) 6695.24
Cost for 240 sqm = a+b+c+d+e 73647.61
Rate per sqm = (a+b+c+d+e)/240 306.87
say 307.00
EARTH WORK ON HILL ROAD
3.30' 301 Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means including
cutting and trimming of side slopes and disposing of
excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 831.00 199.44 L-12
Mazdoor for trimming slopes and helping in excavation day 6.000 554.00 3324.00 L-13
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 90 cum per hour hour 2.890 5958.11 17218.94 P&M-014
Front end loader hour 6.000 2090.57 12543.42 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 1063.05 12756.60 P&M-048
c) Overhead charges @ 10 % on (a+b) 4604.24
d) Contractor's profit @ 10 % on (a+b+c) 5064.66
Cost for 260 cum = a+b+c+d 55711.30
Rate per cum = (a+b+c+d)/260 214.27
say 214.00
Note In case the land on the valley side is barren and there is no Hence
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted as
excavated earth shall be disposed off on the valley side.

c) Overhead charges @ 10 % on (a+b) 2074.24


d) Contractor's profit @ 10 % on (a+b+c) 2281.66
Cost for 260 cum = a+b+c+d 25098.28
Rate per cum = (a+b+c+d)/260 96.53
say 97.00

3.31 301 Excavation in Hilly Area in Ordinary Rock by Mechanical


Means not Requiring Blasting.

Chapter 3 - 9
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of slopes
and disposal of cut material with all lift and lead upto 1000
metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 831.00 265.92 L-12
Mazdoor day 8.000 554.00 4432.00 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 54 cum per hour hour 3.150 5958.11 18768.05 P&M-014
Front end loader hour 7.000 2090.57 14633.99 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 1063.05 7441.35 P&M-048
c) Overhead charges @ 10 % on (a+b) 4554.13
d) Contractor's profit @ 10 % on (a+b+c) 5009.54
Cost for 170 cum = a+b+c+d 55104.98
Rate per cum = (a+b+c+d)/170 324.15
say 324.00
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted as
excavated earth can be disposed off on the valley side.

c) Overhead charges @ 10 % on (a+b) 2346.60


d) Contractor's profit @ 10 % on (a+b+c) 2581.26
Cost for 170 cum = a+b+c+d 28393.83
Rate per cum = (a+b+c+d)/170 167.02
say 167.00

3.32 301 Excavation in Hilly Areas in laminated rock (requiring


blasting) By Mechanical Means
Excavation for roadway in hilly areas in laminated rock
(requiring blasting) which are not suitable for construction of
masonry and pavement by drilling, blasting and breaking,
trimming of bottom and side slopes in accordance with
requirements of lines, grades and cross sections, loading and
disposal of cut road with in all lifts and leads upto 1000
metres
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 831.00 407.19 L-12
Mazdoor day 10.000 554.00 5540.00 L-13
Driller day 2.000 609.40 1218.80 L-06
Blaster day 0.250 609.40 152.35 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 4.200 5958.11 25024.06 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 cum hour 3.500 730.65 2557.28 P&M-001
per hour
Front end loader hour 4.900 2090.57 10243.79 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 4.900 1063.05 5208.95 P&M-048
c) Materials
Gelatine 80 per cent kg 21.000 327.17 6870.57 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks of each 84.000 38.57 3239.88 M-094 /100
125 gms each
d) Overhead charges @ 10 % on (a+b+c) 6046.29
e) Contractor's profit @ 10 % on (a+b+c+d) 6650.92
Cost for 170 cum = a+b+c+d+e 73160.08
Rate per cum = (a+b+c+d+e)/170 430.35
say 430.00

Chapter 3 - 10
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted as
excavated earth can be disposed off on the valley side.

d) Overhead charges @ 10 % on (a+b+c) 4501.01


e) Contractor's profit @ 10 % on (a+b+c+d) 4951.11
Cost for 170 cum = a+b+c+d+e 54462.25
Rate per cum = (a+b+c+d+e)/170 320.37
say 320.00

In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.

Chapter 3 - 11
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base (Table:- 400-1)
A Plant Mix Method
Construction of granular sub-base by providing the material,
mixing in a mechanical mix plant at OMC, carriage of mixed
Material to work site, spreading in uniform layers with motor
grader on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as per
clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 831.00 332.40 L-12
Mazdoor skilled day 2.000 609.40 1218.80 L-15
Mazdoor day 8.000 554.00 4432.00 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 2808.68 16852.08 P&M-093
Electric generator 125 KVA hour 6.000 1427.86 8567.16 P&M-018
Water tanker 6 KL capacity 5 km lead with one trip per hour hour 4.500 1042.15 4689.68 P&M-060

Front end loader 1 cum bucket capacity hour 9.000 2090.57 18815.13 P&M-017
Tipper 10 tonne tonne.km 450 x L 12.54 112860.00 Lead =20
km & P&M-
047
Add 10 per cent of cost of carriage to cover loading and 11286.00
unloading
Motor Grader 110 HP hour 6.000 4853.25 29119.50 P&M-032
Vibratory roller 8-10 t hour 6.000 3082.54 18495.24 P&M-059
c) Material
Granular sub-base Material as per table 400-1
For Grading-I Material
53 mm to 9.5 mm @ 50 per cent cum 144.000 1967.22 283279.68 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 1827.15 104147.55 M-017
2.36 mm below @ 30 per cent cum 86.400 1404.86 121379.90 M-020
Cost of water KL 27.000 337.63 9116.01 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 2294.40 231275.52 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 1827.15 131554.80 M-017
2.36 mm below @ 40 per cent cum 115.200 1404.86 161839.87 M-020
Cost of water KL 27.000 337.63 9116.01 M-189
OR
For Grading-III Material
53 mm to 26.5 mm @ 35 per cent cum 100.800 1967.22 198295.78 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 129.600 1782.21 230974.42 M-026
2.36 mm below @ 20 per cent (Coarse Sand) cum 57.600 1129.95 65085.12 M-022
Cost of water KL 18.000 337.63 6077.34 M-189
OR
For Grading-IV Material
26.5 mm to 4.75 mm @ 75 per cent cum 216.000 1782.21 384957.36 M-026
2.36 mm below @ 25 per cent cum 72.000 1129.95 81356.40 M-022
Cost of water KL 18.000 337.63 6077.34 M-189
OR
For Grading-V Material
53 mm to 9.5 mm @ 50 per cent cum 144.000 1967.22 283279.68 M-013
9.5 mm to 2.36 mm @ 15 per cent cum 43.200 1827.15 78932.88 M-017
2.36 mm below @ 35 per cent cum 100.800 1404.86 141609.89 M-020
Cost of water KL 27.000 337.63 9116.01 M-189
OR
For Grading-VI Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 2294.40 231275.52 M-015
9.5 mm to 2.36 mm @ 40 per cent cum 115.200 1827.15 210487.68 M-017
2.36 mm below @ 25 per cent cum 72.000 1404.86 101149.92 M-020
Cost of water KL 27.000 337.63 9116.01 M-189
4.1A (i) Rate per cum for Grading-I Material
d) Overhead charges @ 10 % on (a+b+c) 74459.11
e) Contractor's profit @ 10 % on (a+b+c+d) 81905.02
Cost for 225 cum = a+b+c+d+e 900955.26

Chapter 4 - 12
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e)/225 4004.25
say 4004.00
4.1A (ii) Rate per cum for Grading-II Material
d) Overhead charges @ 10 % on (a+b+c) 76045.42
e) Contractor's profit @ 10 % on (a+b+c+d) 83649.96
Cost for 225 cum = a+b+c+d+e 920149.57
Rate per cum = (a+b+c+d+e)/225 4089.55
say 4090.00
4.1A (iii) Rate per cum for Grading-III Material
d) Overhead charges @ 10 % on (a+b+c) 72710.07
e) Contractor's profit @ 10 % on (a+b+c+d) 79981.07
Cost for 225 cum = a+b+c+d+e 892297.59
Rate per cum = (a+b+c+d+e)/225 3965.77
say 3966.00
4.1A (iv) Rate per cum for Grading-IV Material
d) Overhead charges @ 10 % on (a+b+c) 69905.91
e) Contractor's profit @ 10 % on (a+b+c+d) 76896.50
Cost for 225 cum = a+b+c+d+e 845861.50
Rate per cum = (a+b+c+d+e)/225 3759.38
say 3759.00
4.1A (v) Rate per cum for Grading-V Material
d) Overhead charges @ 10 % on (a+b+c) 73960.65
e) Contractor's profit @ 10 % on (a+b+c+d) 81356.71
Cost for 225 cum = a+b+c+d+e 894923.81
Rate per cum = (a+b+c+d+e)/225 3977.44
say 3977.00
4.1A (vi) Rate per cum for Grading-VI Material
d) Overhead charges @ 10 % on (a+b+c) 77869.71
e) Contractor's profit @ 10 % on (a+b+c+d) 85656.68
Cost for 225 cum = a+b+c+d+e 942223.51
Rate per cum = (a+b+c+d+e)/225 4187.66
say 4188.00
Note Any one of the grading for material may be adopted as per
design
4.5 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour
Mate day 0.480 831.00 398.88 L-12
Mazdoor skilled day 2.000 609.40 1218.80 L-15
Mazdoor day 10.000 554.00 5540.00 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 4853.25 29119.50 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 3082.54 18495.24 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 779.78 9357.36 P&M-054
Water tanker 6 KL capacity hour 10.000 1042.15 10421.50 P&M-060
c) Material
Cement at site @ 4 per cent by weight of crushed tonne 24.000 9174.00 220176.00 M-081
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 2220.18 468902.02 M-014
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 1959.91 150521.09 M-025
4.75 mm to 75 micron @ 25 per cent cum 96.000 1437.26 137976.96 M-023
Cost of water KL 60.000 337.63 20257.80 M-189
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 1967.22 245509.06 M-028
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 1959.91 37630.27 M-025
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 1827.15 438516.00 M-019

Chapter 4 - 13
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost of water KL 60.000 337.63 20257.80 M-189
4.5 (i) For Sub-Base course
d) Overhead charges @ 10 % on (a+b+c) 107238.52
e) Contractor's profit @ 10 % on (a+b+c+d) 117962.37
Cost for 300 cum = a+b+c+d+e 1297586.04
Rate per cum = (a+b+c+d+e)/300 4325.29
say 4325.00
4.5 (ii) For Base course
d) Overhead charges @ 10 % on (a+b+c) 103664.04
e) Contractor's profit @ 10 % on (a+b+c+d) 114030.45
Cost for 300 cum = a+b+c+d+e 1254334.90
Rate per cum = (a+b+c+d+e)/300 4181.12
say 4181.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.10 405.2 Penetration Coat Over Top Layer of Crushed Cement
Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at the
rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling
the surface as per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 831.00 465.36 L-12
Mazdoor skilled day 2.000 609.40 1218.80 L-15
Mazdoor day 12.000 554.00 6648.00 L-13
b) Machinery
Mechanical broom hydraulic @ 1250 sqm per hour hour 6.000 762.01 4572.06 P&M-031
Hydraulic self propelled chips spreader hour 6.000 5274.50 31647.00 P&M-025
Front end loader 1 cum bucket capacity hour 6.000 2090.57 12543.42 P&M-017
Tipper 10 tonne capacity hour 6.000 1063.05 6378.30 P&M-048
Vibratory roller 8 -10 tonnes @ 30 cum per hour hour 6.00x0.65* 3082.54 12021.91 P&M-059
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 2724.01 11658.76 P&M-004
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 2576.62 251220.45 M-051
Bitumen (60-70 grade) tonne 0.250 32164.00 8041.00 M-074
d) Overhead charges @ 10 % on (a+b+c) 34641.51
e) Contractor's profit @ 10 % on (a+b+c+d) 38105.66
Cost for 7500 sqm = a+b+c+d+e 419162.23
Rate per sqm = (a+b+c+d+e)/7500 55.89
say 56.00
Note Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours to
match with other machines. The usage rates of vibratory roller
may be multiplied with a factor of 0.65.
4.11 406 Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to achieve
the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 831.00 398.88 L-12
Mazdoor skilled day 2.000 609.40 1218.80 L-15
Mazdoor day 10.000 554.00 5540.00 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 2695.78 17792.15 P&M-094

Chapter 4 - 14
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Electric generator 125 KVA hour 6.000 1427.86 8567.16 P&M-018
Front end loader 1 cum capacity hour 6.000 2090.57 12543.42 P&M-017
Paver finisher hour 6.000 2001.72 12010.32 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 3082.54 12021.91 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 1042.15 3126.45 P&M-060
Tipper tonne.km 400 x L 12.54 100320.00 Lead =20
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of 10032.00
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 2220.18 197818.04 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 2019.49 239915.41 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 1580.47 140819.88 M-024
Cost of water KL 18.000 337.63 6077.34 M-189
d) Overhead charges @ 10 % on (a+b+c) 76820.18
e) Contractor's profit @ 10 % on (a+b+c+d) 84502.19
Cost for 225 cum = a+b+c+d+e 929524.13
Rate per cum = (a+b+c+d+e)/225 4131.22
say 4131.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours to
match with other machines. The usage rates of vibratory roller
may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..

Chapter 4 - 15
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.2 503 Tack Coat
Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom.

Unit = sqm
Taking output = 3500 sqm
i) Normal Bituminous Surface
a) Labour
Mate day 0.080 831.00 66.48 L-12
Mazdoor day 2.000 554.00 1108.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 762.01 2133.63 P&M-031
Air compressor 250 cfm hour 2.800 730.65 2045.82 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 2724.01 5448.02 P&M-004
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 0.875 27884.00 24398.50 M-077
d) Overhead charges @ 10 % on (a+b+c) 3520.05
e) Contractor's profit @ 10 % on (a+b+c+d) 3872.05
Cost for 3500 sqm = a+b+c+d+e 42592.55
Rate per sqm = (a+b+c+d+e)/3500 12.17
say 12.00
Note 1. Bitumen emulsion has been provided @ 0.25 kg per sqm as per
clause 503.8. Payment shall be made with adjustment, plus or minus,
for the variation between this quantity and actual quantity approved by
the Engineer after preliminary trials referred to in clause No. 503.4.3

2. An output of 3500 sqm has been considered in case of prime coat


and tack coat which can be covered by bituminous courses on the same
day.
ii) Dry and Hungry Bituminous Surface
a) Labour
Mate day 0.080 831.00 66.48 L-12
Mazdoor day 2.000 554.00 1108.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 762.01 2133.63 P&M-031
Air compressor 250 cfm hour 2.800 730.65 2045.82 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 2724.01 5448.02 P&M-004
c) Material
Bitumen emulsion @ 0.3 kg per sqm tonne 1.050 27884.00 29278.20 M-077
d) Overhead charges @ 10 % on (a+b+c) 4008.02
e) Contractor's profit @ 10 % on (a+b+c+d) 4408.82
Cost for 3500 sqm = a+b+c+d+e 48496.99
Rate per sqm = (a+b+c+d+e)/3500 13.86
say 14.00
1. Bitumen emulsion has been provided @ 0.30 kg per sqm as per
clause 503.8. Payment shall be made with adjustment, plus or minus,
for the variation between this quantity and actual quantity approved by
the Engineer after preliminary trials referred to in clause No. 503.4.3

2. An output of 3500 sqm has been considered in case of prime coat


and tack coat which can be covered by bituminous courses on the same
day.
iii) Granular Surface Treated with Primer
a) Labour
Mate day 0.080 831.00 66.48 L-12
Mazdoor day 2.000 554.00 1108.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 762.01 2133.63 P&M-031
Air compressor 250 cfm hour 2.800 730.65 2045.82 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 2724.01 5448.02 P&M-004
c) Material
Bitumen emulsion @ 0.35 kg per sqm tonne 1.225 27884.00 34157.90 M-077
d) Overhead charges @ 10 % on (a+b+c) 4495.99
e) Contractor's profit @ 10 % on (a+b+c+d) 4945.58
Cost for 3500 sqm = a+b+c+d+e 54401.42
Rate per sqm = (a+b+c+d+e)/3500 15.54
say 16.00

Chapter 5 - 16
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1. Bitumen emulsion has been provided @ 0.350 kg per sqm as per
clause 503.8. Payment shall be made with adjustment, plus or minus,
for the variation between this quantity and actual quantity approved by
the Engineer after preliminary trials referred to in clause No. 503.4.3

2. An output of 3500 sqm has been considered in case of prime coat


and tack coat which can be covered by bituminous courses on the same
day.
iv) Granular Surface Not Treated with Primer
a) Labour
Mate day 0.080 831.00 66.48 L-12
Mazdoor day 2.000 554.00 1108.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 762.01 2133.63 P&M-031
Air compressor 250 cfm hour 2.800 730.65 2045.82 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 2724.01 5448.02 P&M-004
c) Material
Bitumen emulsion @ 0.45 kg per sqm tonne 1.575 27884.00 43917.30 M-077
d) Overhead charges @ 10 % on (a+b+c) 5471.93
e) Contractor's profit @ 10 % on (a+b+c+d) 6019.12
Cost for 3500 sqm = a+b+c+d+e 66210.30
Rate per sqm = (a+b+c+d+e)/3500 18.92
say 19.00
1. Bitumen emulsion has been provided @ 0.45 kg per sqm as per
clause 503.8. Payment shall be made with adjustment, plus or minus,
for the variation between this quantity and actual quantity approved by
the Engineer after preliminary trials referred to in clause No. 503.4.3

2. An output of 3500 sqm has been considered in case of prime coat


and tack coat which can be covered by bituminous courses on the same
day.
v) Cement Concrete Base
a) Labour
Mate day 0.080 831.00 66.48 L-12
Mazdoor day 2.000 554.00 1108.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 762.01 2133.63 P&M-031
Air compressor 250 cfm hour 2.800 730.65 2045.82 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 2724.01 5448.02 P&M-004
c) Material
Bitumen emulsion @ 0.4 kg per sqm tonne 1.400 27884.00 39037.60 M-077
d) Overhead charges @ 10 % on (a+b+c) 4983.96
e) Contractor's profit @ 10 % on (a+b+c+d) 5482.35
Cost for 3500 sqm = a+b+c+d+e 60305.86
Rate per sqm = (a+b+c+d+e)/3500 17.23
say 17.00
1. Bitumen emulsion has been provided @ 0.40 kg per sqm as per
clause 503.8. Payment shall be made with adjustment, plus or minus,
for the variation between this quantity and actual quantity approved by
the Engineer after preliminary trials referred to in clause No. 503.4.3

2. An output of 3500 sqm has been considered in case of prime coat


and tack coat which can be covered by bituminous courses on the same
day.
5.4 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam with 100-120
TPH batch type HMP producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5 per cent by weight of total mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MoRTH specification clause No. 507
complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 831.00 698.04 L-12
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 554.00 8864.00 L-13
asphalt cutter and assistance for setting out lines, levels and layout
of construction
Skilled mazdoor for checking line & levels day 5.000 609.40 3047.00 L-15

Chapter 5 - 17
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 41618.99 249713.94 P&M-022
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 5763.69 34582.14 P&M-034

Generator 250 KVA hour 6.000 2833.76 17002.56 P&M-081


Front end loader 1 cum bucket capacity hour 6.000 2090.57 12543.42 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 12.54 112860.00 Lead =20
km & P&M-
047
Add 10 per cent of cost of carriage to cover cost of loading and 11286.00
unloading
smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 996.15 3884.99 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 3082.54 12021.91 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 2337.25 9115.28 P&M-045
c) Materials
Bitumen @ 4.25 per cent of weight of mix tonne 19.130 32164.00 615297.32 M-074
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 2167.92 136990.86 M-049
25 - 10 mm 13 per cent cum 37.340 2220.18 82901.52 M-046
10 -4.75 mm 19 per cent cum 54.580 2529.58 138064.48 M-040
4.75 mm and below 44 per cent cum 126.390 2232.72 282193.48 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 11280.69 97239.55 M-188
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 2220.18 191290.71 M-046
10 - 5 mm 28 per cent cum 80.430 2529.58 203454.12 M-040
5 mm and below 40 per cent cum 114.900 2232.72 256539.53 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 11280.69 97239.55 M-188
* Any one of the alternative may be adopted as per approved design

(i) For Grading I ( 40 mm nominal size )


d) Overhead charges @ 10 % on (a+b+c) 182830.65
e) Contractor's profit @ 10 % on (a+b+c+d) 201113.71
Cost for 205 cum = a+b+c+d+e 2212250.85
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 11344.88
say 11345.00
(ii) For GradingII(19 mm nominal size)
d) Overhead charges @ 10 % on (a+b+c) 183944.05
e) Contractor's profit @ 10 % on (a+b+c+d) 202338.46
Cost for 205 cum = a+b+c+d+e 2225723.02
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 11413.96
say 11414.00
Note *1. Although the roller are required only for 3 hours as per norms of
output, but the same have to be available at site for six hours as the hot
mix plant and paver will take six hours for mixing and paving the output
of 450 tonnes considered in this analysis. To cater for the idle period of
these rollers, their usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose. The actual
quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous
duties at site including sundries have been included in administrative
overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the same has
been included in the cost of tack coat.

Chapter 5 - 18
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5. The individual density for each size of aggregates to be used for
construction I.e. 37.5-25 mm, 25-10 mm etc. should be found in the
laboratory and accordingly the quantities should be ammended for use
in field. The average density of 1.5 tonne/cum is only a reference
density in this Data Book.
6. The individual percentage of aggregates should be calculated from
the total weight of dry aggregates i.e.. excluding the weight of bitumen.
The weight of filler will also be 2 per cent by weight of dry aggregates.

5.5 509 Bituminous Concrete


Providing and laying bituminous concrete with 100-120 TPH batch type
hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous
binder @ 5.4 to 5.6 per cent of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 509 complete in all respects

Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 831.00 698.04 L-12
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 554.00 8864.00 L-13
asphalt cutter and assistance for setting out lines, levels and layout
of construction
Skilled mazdoor for checking line & levels day 5.000 609.40 3047.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 41618.99 249713.94 P&M-022
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 5763.69 34582.14 P&M-034

Generator 250 KVA hour 6.000 2833.76 17002.56 P&M-081


Front end loader 1 cum bucket capacity hour 6.000 2090.57 12543.42 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 12.54 112860.00 Lead =20
km & P&M-
047
Add 10 per cent of cost of carriage to cover cost of loading and 11286.00
unloading
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 996.15 3884.99 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 3082.54 12021.91 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 2337.25 9115.28 P&M-045
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 32164.00 723690.00 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 27.0 tonnes
Weight of aggregate = 450 -27 = 423 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 2220.18 221462.96 M-045
10 - 5 mm 23 per cent cum 65.550 2529.58 165813.97 M-040
5 mm and below 40 per cent cum 114.000 2232.72 254530.08 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 11280.69 97239.55 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 2355.02 201354.21 M-044
10 - 5 mm 25 per cent cum 71.250 2529.58 180232.58 M-040
5 mm and below43 per cent cum 122.550 2232.72 273619.84 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 11280.69 97239.55 M-188
*Any one of the alternative may be adopted as per approved
design
(i) for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10 % on (a+b+c) 193835.58

Chapter 5 - 19
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 10 % on (a+b+c+d) 213219.14
Cost for 205 cum = a+b+c+d+e 2345410.56
Rate per cum = (a+b+c+d+e)/191 12279.64
say 12280.00
5.5 (ii) for Grading-II(10 mm nominal size)
d) Overhead charges @ 10 % on (a+b+c) 195175.55
e) Contractor's profit @ 10 % on (a+b+c+d) 214693.10
Cost for 205 cum = a+b+c+d+e 2361624.11
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 12364.52
say 12365.00

Using Modified Bitumen


Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 831.00 698.04 L-12
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 554.00 8864.00 L-13
asphalt cutter and assistance for setting out lines, levels and layout
of construction
Skilled mazdoor for checking line & levels day 5.000 609.40 3047.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 41618.99 249713.94 P&M-022
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 5763.69 34582.14 P&M-034

Generator 250 KVA hour 6.000 2833.76 17002.56 P&M-081


Front end loader 1 cum bucket capacity hour 6.000 2090.57 12543.42 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 12.54 112860.00 Lead =20
km & P&M-
047
Add 10 per cent of cost of carriage to cover cost of loading and 11286.00
unloading
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 996.15 3884.99 P&M-044

Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 3082.54 12021.91 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem roller. hour 6.00x0.65* 2337.25 9115.28 P&M-045
c) Material
i) Bitumen@ 5 per cent of weight of mix tonne 22.500 91067.15 2049010.88 M-078
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 27.0 tonnes
Weight of aggregate = 450 -27 = 423 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 2220.18 221462.96 M-045
10 - 5 mm 23 per cent cum 65.550 2529.58 165813.97 M-040
5 mm and below 40 per cent cum 114.000 2232.72 254530.08 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 11280.69 97239.55 M-188
or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 2355.02 201354.21 M-044
10 - 5 mm 25 per cent cum 71.250 2529.58 180232.58 M-040
5 mm and below43 per cent cum 122.550 2232.72 273619.84 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 11280.69 97239.55 M-188
*Any one of the alternative may be adopted as per approved
design
(i) for Grading-I ( 13 mm nominal size )
d) Overhead charges @ 10 % on (a+b+c) 326367.67
e) Contractor's profit @ 10 % on (a+b+c+d) 359004.44
Cost for 205 cum = a+b+c+d+e 3949048.83
Rate per cum = (a+b+c+d+e)/191 20675.65
say 20676.00

Chapter 5 - 20
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(ii) for Grading-II(10 mm nominal size)
d) Overhead charges @ 10 % on (a+b+c) 327707.63
e) Contractor's profit @ 10 % on (a+b+c+d) 360478.40
Cost for 205 cum = a+b+c+d+e 3965262.37
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 20760.54
say 20761.00

Note *1. Although the rollers are required only for 3 hours as per norms of
output, but the same have to be available at site for six hours as the hot
mix plant and paver will take six hours for mixing and paving the output
of 450 tonnes considered in this analysis. To cater for the idle period of
these rollers, their usage rates have been multiplied by a factor of 0.65

2.Quantity of Bitumen has been taken for analysis purpose. The actual
quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous
duties at site including sundries have been included in administrative
overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of mechanical
broom and 2 mazdoors shall be deleted as the same has been included
in the cost of tack coat.
5. The individual density for each size of aggregates to be used for
construction i.e. 37.5-25 mm, 25-10 mm etc. should be found in the
laboratory and accordingly the quantities should be ammended for use
in field. The average density of 1.5 tonne/cum is only a reference
density in this Data Book.
6. The individual percentage of aggregates should be calculated from
the total weight of dry aggregates i.e.. excluding the weight of bitumen.
The weight of filler will also be 2 per cent by weight of dry aggregates.

5.16 522 Crack Prevention Courses


5.16 (ii) Stress absorbing membrane (SAM) with crack width 6 mm to 9 mm

Providing and laying of a stress absorbing membrane over a cracked


road surface, with crack width 6 to 9 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to
conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 831.00 199.44 L-12
Mazdoor day 6.000 554.00 3324.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 762.01 4572.06 P&M-031
Air compressor 250 cfm capacity hour 6.000 730.65 4383.90 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 2724.01 16344.06 P&M-004
Hydraulic Chip spreader hour 6.000 5274.50 31647.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 996.15 5976.90 P&M-044
c) Material
Modified binder tonne 11.550 91067.15 1051825.58 M-078
Crushed stone chipping 11.2 mm size cum 105.000 2576.62 270545.10 M-051
d) Overhead charges @ 10 % on (a+b+c) 138881.80
e) Contractor's profit @ 10 % on (a+b+c+d) 152769.98
Cost for 10500 sqm = a+b+c+d+e 1680469.82
Rate per sqm = (a+b+c+d+e)/10500 160.04
say 160.00

Chapter 5 - 21
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
8.4 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing
Unit = Each
Taking output = one traffic sign
568.00 122.69 Item No.
i) Excavation for foundation cum 0.216
3.13
9683.00 1161.96 Item 12.8
ii) Cement concrete M15 grade cum 0.120
(A)
iii) Painting angle iron post two coats sqm 0.430 113.00 48.59 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 831.00 8.31 L-12
Mazdoor day 0.250 554.00 138.50 L-13
b) Material
94.96 1804.24 M-179
Mild steel angle iron 75 x 75 x 6 mm kg 19.000
/1000
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 21290.32 7451.61 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 21290.32 3321.29 M-061
or
( iii ) 60 cm circular sqm 0.283 21290.32 6025.16 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 21290.32 10219.35 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 21290.32 5748.39 M-061
or
(vi ) 60 cm x 60 cm square sqm 0.360 21290.32 7664.52 M-061
or
( vii ) 90 cm high octagon sqm 0.672 21290.32 14307.10 M-061
c) Machinery
Tractor-trolley hour 0.010 811.14 8.11 P&M-053
(i) 90 cm equilateral triangle
d) Overhead charges @ 10 % on (a+b+c) 941.08
e) Contractor's profit @ 10 % on (a+b+c+d) 1035.19
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 12720.28
say 12720.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 10 % on (a+b+c) 528.05
e) Contractor's profit @ 10 % on (a+b+c+d) 580.85
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 7722.59
say 7723.00
( iii ) 60 cm circular
d) Overhead charges @ 10 % on (a+b+c) 798.43
e) Contractor's profit @ 10 % on (a+b+c+d) 878.28
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 10994.27
say 10994.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 10 % on (a+b+c) 1217.85
e) Contractor's profit @ 10 % on (a+b+c+d) 1339.64
Chapter 8 - 22
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 16069.24
say 16069.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 10 % on (a+b+c) 770.76
e) Contractor's profit @ 10 % on (a+b+c+d) 847.83
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 10659.38
say 10659.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 10 % on (a+b+c) 962.37
e) Contractor's profit @ 10 % on (a+b+c+d) 1058.61
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 12977.90
say 12978.00
( vii ) 90 cm high octagon
d) Overhead charges @ 10 % on (a+b+c) 1626.63
e) Contractor's profit @ 10 % on (a+b+c+d) 1789.29
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 21015.42
say 21015.00
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete in
the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas. This
is applicable to all road signs and directions boards.
Direction and Place Identification Signs upto 0.9 sqm Size
8.5 801
Board.
Providing and erecting direction and place identification retro-
reflectorised sign as per IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area not exceeding 0.9 sqm supported on a
mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to
the ground by means of properly designed foundation with
M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below
ground level as per approved drawing
Unit = sqm
Taking output = 0.9 sqm
568.00 122.69 Item No.
i) Excavation for foundation cum 0.216
3.13
9683.00 1161.96 Item 12.8
ii) Cement concrete M15 grade cum 0.120
(A)
iii) Painting angle iron post two coats sqm 0.430 113.00 48.59 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 831.00 8.31 L-12
Mazdoor day 0.200 554.00 110.80 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 94.96 1804.24 M-179
kg 19.000
metres long /1000
Aluminium sheeting fixed with encapsulated lens type 21290.32 19161.29 M-061
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 811.14 16.22 P&M-053
d) Overhead charges @ 10 % on (a+b+c) 2110.09
e) Contractor's profit @ 10 % on (a+b+c+d) 2321.10
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 26865.29
Rate per sqm (for sign having area upto 0.9 sqm) =
29850.32
(I+ii+iii+a+b+c+d+e)/0.90
say 29850.00

Chapter 8 - 23
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Road Marking with Hot Applied Thermoplastic Compound
8.13 803
with Reflectorising Glass Beads on Bituminous Surface

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to be
level, uniform and free from streaks and holes.
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 831.00 24.93 L-12
Mazdoor day 0.750 554.00 415.50 L-13
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 348.08 3480.80 P&M-043
Tractor-trolley hour 0.500 811.14 405.57 P&M-053
c) Material
Hot applied thermoplastic compound Litre 1500.000 487.10 730650.00 M-118
Reflectorising glass beads kg 150.000 209.06 31359.00 M-152
d) Overhead charges @ 10 % on (a+b+c) 76633.58
e) Contractor's profit @ 10 % on (a+b+c+d) 84296.94
Cost for 600 sqm = a+b+c+d+e 927266.32
Rate per sqm = a+b+c+d+e)/600 1545.44
say 1545.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position including
painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
9683.00 22755.05 Item 12.8
a) M-15 grade of concrete cum 2.350
(A)
85.42 1886.07 Item 13.6
b) Steel reinforcement @ 5 kg per sqm kg 22.080
/1000
568.00 954.24 Item No.
c) Excavation in soil for foundation cum 1.680
3.13
d) Painting two coats on concrete surface sqm 9.850 258.00 2541.30 Item 8.8
e) Lettering on km post (average 30 letters of 10 per cm per 1.00 1800.00 Item 8.3
1800.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.260 831.00 216.06 L-12
Mason day 0.600 831.00 498.60 L-11
Mazdoor including loading/unloading day 6.000 554.00 3324.00 L-13
g) Machinery
Tractor-trolley hour 6.000 811.14 4866.84 P&M-053
h) Overhead charges @ 10 % on (f+g) 890.55
i) Contractor's profit @ 10 % on (f+g+h) 979.61
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 40712.32

Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i ) /6 6785.39

Chapter 8 - 24
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 6785.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
9683.00 36504.91 Item 12.8
a) M-15 grade of concrete cum 3.770
(A)
85.42 2248.25 Item 13.6
b) Steel reinforcement @ 5 kg per sqm kg 26.320
/1000
568.00 1573.36 Item No.
c) Excavation in soil for foundation cum 2.770
3.13
d) Painting two coats on concrete surface sqm 11.410 258.00 2943.78 Item 8.8
e) Lettering on km post ( average 12 letters of 10 per cm per 1.00 1680.00 Item 8.3
1680.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 831.00 265.92 L-12
Mason day 1.000 831.00 831.00 L-11
Mazdoor day 7.000 554.00 3878.00 L-13
g) Machinery
Tractor-trolley hour 6.000 811.14 4866.84 P&M-053
h) Overhead charges @ 10 % on (f+g) 984.18
i) Contractor's profit @ 10 % on (f+g+h) 1082.59

Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i) 56858.83


Rate for each ordinary km stone = (a+b+ c +d+e+f+g+h+j)
4061.35
/14
say 4061.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
9683.00 15299.14 Item 12.8
a) M-15 grade of concrete cum 1.580
(A)
85.42 5637.72 Item 13.6
b) Steel reinforcement @ 5 kg per sqm kg 66.000
/1000
568.00 789.52 Item No.
c) Excavation in soil for foundation cum 1.390
3.13
d) Painting two coats on concrete surface sqm 6.270 258.00 1617.66 Item 8.8
e) Lettering on km post (average 1 letter of 10 cm per cm per 1.00 330.00 Item 8.3
330.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 831.00 282.54 L-12
Mason day 1.500 831.00 1246.50 L-11
Mazdoor day 7.000 554.00 3878.00 L-13
g) Machinery
Tractor-trolley hour 6.000 811.14 4866.84 P&M-053
h) Overhead charges @ 10 % on (f+g) 1027.39
i) Contractor's profit @ 10 % on (f+g+h) 1130.13

Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+ g+h+i) 36105.44


Rate for each Hectometer stone = (a+b +c +d+e+f+ g+h+i)
1094.10
33
say 1094.00

The rate for excavation, cement concrete, steel reinforcement,


Note
painting and lettering may be taken from respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above
ground level, painted black and white in 15 cm wide strips,
fitted with 80 x 100 mm rectangular or 75 mm dia circular
reflectorised panels at the top, buried or pressed into the
ground and conforming toIRC-79 and the drawings.
Unit = Each
Chapter 8 - 25
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output= 30 Nos.
a) Labour
Mate day 0.040 831.00 33.24 L-12
Mazdoor for fixing day 1.000 554.00 554.00 L-13
b) Material
Cost of approved type of delineators from ISI certified 4244.89 127346.70 M-091
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 12734.67
c) Overhead charges @ 10 % on (a+b) 14066.86
d) Contractor's profit @ 10 % on (a+b+c) 15473.55
Cost for 30 Nos. delineators = (a+b+ c+d) 170209.02
Rate per delineators = (a+b+c+d) /30 5673.63
say 5674.00
In case of soft ground, a proper foundation may be provided
as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete are
required to be measured and paid separately.
8.16 806 Boundary pillar
Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each
Taking output = 57 Nos.
9683.00 12103.75 Item 12.8
a) M-15 grade of the boundary stone cum 1.250
(A)
85.42 6816.52 Item 13.6
b) Steel reinforcement kg 79.800
/1000
568.00 6088.96 Item No.
c) Excavation in soil cum 10.720
3.13
1.00 2280.00 Item 8.3
per letter
d) Lettering, each 10 cm high 2280.000
per cm high
Transportation and fixing
e) Labour
Mate day 0.570 831.00 473.67 L-12
Mazdoor day 14.250 554.00 7894.50 L-13
f) Machinery
Tractor-trolley hour 6.000 811.14 4866.84 P&M-053
g) Material
Stone spall cum 11.970 1310.76 15689.80 M-008
h) Overhead charges @ 10 % on (e+f+g) 2892.48
i) Contractor's profit @ 10 % on (e+f+g+h) 3181.73

Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i ) 62288.25

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 1092.78


say 1093.00
In case of soft ground, a proper foundation may be provided
as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete are
required to be measured and paid separately.
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series channel
vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre,
1.8 m high, 1.1 m below ground/road level, all steel parts and
fitments to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to be fixed
on the vertical post with a spacer of channel section 150 x 75
x 5 mm, 330 mm long complete as per clause 810

Chapter 8 - 26
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 831.00 49.86 L-12
Blacksmith day 0.500 831.00 415.50 L-02
Mazdoor day 1.000 554.00 554.00 L-13
b) Machinery
Tractor-trolley hour 0.100 811.14 81.11 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section 94.96 3913.30 M-179
kg 41.210
railing,4.5 m in length /1000
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 94.96 8409.66 M-179
kg 88.560
kg per metre /1000
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 94.96 1542.15 M-179
kg 16.240
16.4 kg per metre /1000
Nuts and bolts kg 20.000 307.31 6146.20 M-130
Add 25 per cent of the cost of material for fabrication, nuts,
5002.83
bolts and washers etc.)
d) Overhead charges @ 10 % on (a+b+c) 2611.46
e) Contractor's profit @ 10 % on (a+b+c+d) 2872.61
Cost for 4.5 metre = a+b+c+d+e 31598.68
Rate per metre = (a+b+c+d+e)/4.5 7021.93
say 7022.00

Chapter 8 - 27
CHAPTER-12
FOUNDATIONS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.32 831.00 265.92 L-12
Mazdoor day 8.00 554.00 4432.00 L-13
b) Overhead charges @ 25 % on (a) 1174.48
c) Contractor's profit @ 10 % on (a+b) 587.24
Cost for 10 cum = a+b+c 6459.64
Rate per cum = (a+b+c)/10 645.96
say 646.00
Note 1. Cost of dewatering may be added where required upto, 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for marshy
soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) A (ii) Depth 3 m to 6 m
a) Labour
Mate/Supervisor day 0.40 831.00 332.40 L-12
Mazdoor day 10.00 554.00 5540.00 L-13
b) Overhead charges @ 25 % on (a) 1468.10
c) Contractor's profit @ 10 % on (a+b) 734.05
Cost for 10 cum = a+b+c 8074.55
Rate per cum = (a+b+c)/10 807.46
say 807.00
Note Cost of dewatering may be added where required upto 15 per
cent of labour cost. Assessment for dewatering shall be done
as per actual ground conditions.
12.1 (I) A (iii) Depth above 6 m
a) Labour
Mate/Supervisor day 0.55 831.00 457.05 L-12
Mazdoor day 13.70 554.00 7589.80 L-13
b) Overhead charges @ 25 % on (a) 2011.71
c) Contractor's profit @ 10 % on (a+b) 1005.86
Cost for 10 cum = a+b+c 11064.42
Rate per cum = (a+b+c)/10 1106.44
say 1106.00
Note 1. Cost of dewatering may be added where required upto 20
per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.70 831.00 581.70 L-12
Mazdoor day 18.00 554.00 9972.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 4.00 3135.85 12543.40 P&M-026
c) Overhead charges @ 25 % on (a+b) 5774.28
d) Contractor's profit @ 10 % on (a+b+c) 2887.14
Cost for 240 cum = a+b+c+d 31758.52
Rate per cum = (a+b+c+d)/240 132.33
say 132.00

Chapter 12 - 28
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions..
12.1 (I) B (ii) Depth 3 m to 6 m

Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.70 831.00 581.70 L-12
Mazdoor day 18.00 554.00 9972.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 4.00 3135.85 12543.40 P&M-026
c) Overhead charges @ 25 % on (a+b) 5774.28
d) Contractor's profit @ 10 % on (a+b+c) 2887.14
Cost for 210 cum = a+b+c+d 31758.52
Rate per cum = (a+b+c+d)/210 151.23
say 151.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B (iii) Depth above 6m

Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.90 831.00 747.90 L-12
Mazdoor day 23.00 554.00 12742.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 4.00 3135.85 12543.40 P&M-026
c) Overhead charges @ 25 % on (a+b) 6508.33
d) Contractor's profit @ 10 % on (a+b+c) 3254.16
Cost for 180 cum = a+b+c+d 35795.79
Rate per cum = (a+b+c+d)/180 198.87
say 199.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.

12.1 II Ordinary Rock (not requiring blasting)


A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.45 831.00 373.95 L-12
Mazdoor day 11.40 554.00 6315.60 L-13
b) Overhead charges @ 25 % on (a) 1672.39
c) Contractor's profit @ 10 % on (a+b) 836.19
Cost for 10 cum = a+b+c 9198.13
Rate per cum = (a+b+c)/10 919.81
say 920.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 831.00 199.44 L-12
Mazdoor day 6.00 554.00 3324.00 L-13

Chapter 12 - 29
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 4.00 3135.85 12543.40 P&M-026
c) Overhead charges @ 25 % on (a+b) 4016.71
d) Contractor's profit @ 10 % on (a+b+c) 2008.36
Cost for 180 cum = a+b+c+d 22091.91
Rate per cum = (a+b+c+d)/180 122.73
say 123.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and hence
not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.80 831.00 664.80 L-12
Driller day 1.10 609.40 670.34 L-06
Blaster day 0.55 609.40 335.17 L-03
Mazdoor day 18.00 554.00 9972.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. hour 1.00 730.65 730.65 P&M-001

c) Material
Blasting Material kg 3.50 327.17 1145.10 M-104
Detonator electric each 14.00 38.57 539.98 M-094/100
d) Overhead charges @ 25 % on (a+b+c) 3514.51
e) Contractor's profit @ 10 % on (a+b+c+d) 1757.26
Cost for 10 cum = a+b+c+d+e 19329.81
Rate per cum = (a+b+c+d+e)/10 1932.98
say 1933.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering shall be
made as per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.45 831.00 373.95 L-12
Mazdoor day 11.40 554.00 6315.60 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 730.65 4383.90 P&M-001
breaker
c) Overhead charges @ 25 % on (a+b) 2768.36
d) Contractor's profit @ 10 % on (a+b+c) 1384.18
Cost for 10 cum = a+b+c+d 15225.99
Rate per cum = (a+b+c+d)/10 1522.60
say 1523.00
Note 1. Cost of dewatering upto10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and hence
not included.
12.1 V Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour

Chapter 12 - 30
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate/Supervisor day 0.90 831.00 747.90 L-12
Mazdoor day 22.00 554.00 12188.00 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 811.14 2165.74 P&M-053
c) Overhead charges @ 25 % on (a+b) 3775.41
d) Contractor's profit @ 10 % on (a+b+c) 1887.71
Cost for 10 cum = a+b+c+d 20764.76
Rate per cum = ( a+b+c+d)/ 10 2076.48
say 2076.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1 (i) to (iv) for ordinary soil
12.1 (V) B Mechanical Means
a) Labour
Mate day 0.18 831.00 149.58 L-12
Mazdoor for dressing sides, bottom and backfilling day 4.50 554.00 2493.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum hour 0.17 3135.85 533.09 P&M-026
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 1063.05 478.37 P&M-048
c) Overhead charges @ 25 % on (a+b) 913.51
d) Contractor's profit @ 10 % on (a+b+c) 456.76
Cost for 10 cum = a+b+c+d 5024.31
Rate per cum = (a+b+c+d)/10 502.43
say 502.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1 (i) to (iv) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.27 831.00 224.37 L-12
Mazdoor for dressing sides, bottom and backfilling day 6.84 554.00 3789.36 L-13
b) Machinery
Tractor-trolley for transportation hour 2.00 811.14 1622.28 P&M-053
c) Overhead charges @ 25 % on (a+b) 1409.00
d) Contractor's profit @ 10 % on (a+b+c) 704.50
Cost for 6 cum = a+b+c+d 7749.51
Rate per cum = (a+b+c+d)/6 1291.59
say 1292.00
12.2 304 Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken
as per item 12.4.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 831.00 8.31 L-12

Chapter 12 - 31
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 0.30 554.00 166.20 L-13
b) Material
Sand (assuming 20 per cent voids) cum 1.20 1320.74 1584.89 M-006
c) Overhead charges @ 25 % on (a+b) 439.85
d) Contractor's profit @ 10 % on (a+b+c) 219.93
Rate per cum = a+b+c+d 2419.18
say 2419.00
12.4 2100 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 831.00 531.84 L-12
Mason day 1.00 831.00 831.00 L-11
Mazdoor day 15.00 554.00 8310.00 L-13
b) Material
40 mm Aggregate cum 13.50 2355.02 31792.77 M-055
coarse Sand cum 6.75 1489.15 10051.76 M-005
cement tonne 3.45 9174.00 31650.30 M-081
Cost of water KL 18.00 337.63 6077.34 M-189
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Water tanker 6 KL capacity hour 2.00 1042.15 2084.30 P&M-060
d) Overhead charges @ 25 % on (a+b+c) 24671.51
e) Contractor's profit @ 10 % on (a+b+c+d) 12335.75
Cost for 15 cum = a+b+c+d+e 135693.29
Rate per cum = (a+b+c+d+e)/15 9046.22
say 9046.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
12.5 1300 Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 12.54 31350.00 M-079
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.20 6774.00 8128.80 Item 12.6
(A)
b) Labour
Mate day 0.48 831.00 398.88 L-12
Mason day 4.00 831.00 3324.00 L-11
Mazdoor day 8.00 554.00 4432.00 L-13
c) Overhead charges @ 25 % on (a+b) 11908.42
d) Contractor's profit @ 10 % on (a+b+c) 5954.21
Cost for 5 cum = a+b+c+d 65496.31
Rate per cum (a+b+c+d)/5 13099.26
say 13099.00
12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)
analysis

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 9174.00 4678.74 M-081

Chapter 12 - 32
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sand cum 1.05 1489.15 1563.61 M-005
b) Labour
Mate day 0.04 831.00 33.24 L-12
Mazdoor day 0.90 554.00 498.60 L-13
Total Material and Labour = (a+b) say 6774.00
Sub- (B) Cement Mortar1:2 (1cement :2 sand)
analysis
(Addl.)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 9174.00 6146.58 M-081
Sand cum 0.93 1489.15 1384.91 M-005
b) Labour
Mate day 0.04 831.00 33.24 L-12
Mazdoor day 0.90 554.00 498.60 L-13
Total Material and Labour = (a+b) say 8063.00
Sub- (C) Cement Mortar1:4 (1cement :4 sand)
analysis
(Addl.)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 9174.00 3669.60 M-081
Sand cum 1.12 1489.15 1667.85 M-005
b) Labour
Mate day 0.04 831.00 33.24 L-12
Mazdoor day 0.90 554.00 498.60 L-13
Total Material and Labour = (a+b) say 5869.00
Sub- (D) Cement Mortar1:6 (1cement :6 sand)
analysis
(Addl.)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 9174.00 2660.46 M-081
Sand cum 1.34 1489.15 1995.46 M-005
b) Labour
Mate day 0.04 831.00 33.24 L-12
Mazdoor day 0.90 554.00 498.60 L-13
Total Material and Labour = (a+b) say 5188.00
12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in Foundation
complete as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 874.90 4811.95 M-169
Through and bond stone each 35.00 61.67 2158.45 M-182

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.50 6774.00 10161.00 Item 12.6
(A)
b) Labour
Mate day 0.60 831.00 498.60 L-12
Mason day 7.50 831.00 6232.50 L-11
Mazdoor day 7.50 554.00 4155.00 L-13

Chapter 12 - 33
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add for scaffolding @ 5 per cent of cost of a) Material 1400.88
and b) Labour
c) Overhead charges @ 25 % on (a+b) 7354.60
d) Contractor's profit @ 10 % on (a+b+c) 3677.30
Cost for 5 cum = a+b+c+d 40450.28
Rate per cum (a+b+c+d)/5 8090.06
say 8090.00
1405.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.00 874.90 4374.50 M-148
Through and bond stone each 35.00 61.67 2158.45 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.65 6774.00 11177.10 Item 12.6
(A)
b) Labour
Mate day 0.50 831.00 415.50 L-12
Mason day 6.00 831.00 4986.00 L-11
Mazdoor day 6.00 554.00 3324.00 L-13
Add for scaffolding @ 5 per cent of cost of a) Material 1321.78
and b) Labour
c) Overhead charges @ 25 % on (a+b) 6939.33
d) Contractor's profit @ 10 % on (a+b+c) 3469.67
Cost for 5 cum = a+b+c+d 38166.33
Rate per cum (a+b+c+d)/5 7633.27
say 7633.00
1400 Stone Masonry Work in Cement Mortar 1:4 in Foundation
complete as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
1405.4 (C) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 874.90 4811.95 M-169
Through and bond stone each 35.00 61.67 2158.45 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:4 (Rate as in Item 12.6 A sub-analysis) cum 1.50 5869.00 8803.50 Item 12.6
(A)
b) Labour
Mate day 0.60 831.00 498.60 L-12
Mason day 7.50 831.00 6232.50 L-11
Mazdoor day 7.50 554.00 4155.00 L-13
Add for scaffolding @ 5 per cent of cost of a) Material 1333.00
and b) Labour
c) Overhead charges @ 25 % on (a+b) 6998.25
d) Contractor's profit @ 10 % on (a+b+c) 3499.13
Cost for 5 cum = a+b+c+d 38490.38
Rate per cum (a+b+c+d)/5 7698.08
say 7698.00
1405.3 (D) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.00 874.90 4374.50 M-148
Through and bond stone each 35.00 61.67 2158.45 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)

Chapter 12 - 34
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement mortar 1:4 (Rate as in Item 12.6 A sub-analysis) cum 1.65 5869.00 9683.85 Item 12.6
(A)
b) Labour
Mate day 0.50 831.00 415.50 L-12
Mason day 6.00 831.00 4986.00 L-11
Mazdoor day 6.00 554.00 3324.00 L-13
Add for scaffolding @ 5 per cent of cost of a) Material 1247.12
and b) Labour
c) Overhead charges @ 25 % on (a+b) 6547.36
d) Contractor's profit @ 10 % on (a+b+c) 3273.68
Cost for 5 cum = a+b+c+d 36010.46
Rate per cum (a+b+c+d)/5 7202.09
say 7202.00
1400 Stone Masonry Work in Cement Mortar 1:6 in Foundation
complete as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
1405.4 (E) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 874.90 4811.95 M-169
Through and bond stone each 35.00 61.67 2158.45 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:6 (Rate as in Item 12.6 A sub-analysis) cum 1.50 5188.00 7782.00 Item 12.6
(A)
b) Labour
Mate day 0.60 831.00 498.60 L-12
Mason day 7.50 831.00 6232.50 L-11
Mazdoor day 7.50 554.00 4155.00 L-13
Add for scaffolding @ 5 per cent of cost of a) Material 1281.93
and b) Labour
c) Overhead charges @ 25 % on (a+b) 6730.11
d) Contractor's profit @ 10 % on (a+b+c) 3365.05
Cost for 5 cum = a+b+c+d 37015.59
Rate per cum (a+b+c+d)/5 7403.12
say 7403.00
1405.3 (F) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.00 874.90 4374.50 M-148
Through and bond stone each 35.00 61.67 2158.45 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:6 (Rate as in Item 12.6 A sub-analysis) cum 1.65 5188.00 8560.20 Item 12.6
(A)
b) Labour
Mate day 0.50 831.00 415.50 L-12
Mason day 6.00 831.00 4986.00 L-11
Mazdoor day 6.00 554.00 3324.00 L-13
Add for scaffolding @ 5 per cent of cost of a) Material 1190.93
and b) Labour
c) Overhead charges @ 25 % on (a+b) 6252.40
d) Contractor's profit @ 10 % on (a+b+c) 3126.20
Cost for 5 cum = a+b+c+d 34388.18
Rate per cum (a+b+c+d)/5 6877.64
say 6878.00
Note The labour already considered in cement mortar has been
taken into account while proposing labour for masonry works.

Chapter 12 - 35
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.8 1500, Plain/Reinforced Cement Concrete in Open Foundation
1700 & complete as per Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 9174.00 37888.62 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
40 mm Aggregate cum 8.10 2355.02 19075.66 M-055
20 mm Aggregate cum 4.05 2576.62 10435.31 M-053
10 mm Aggregate cum 1.35 2576.62 3478.44 M-051
b) Labour
Mate day 0.86 831.00 714.66 L-12
Mason day 1.50 831.00 1246.50 L-11
Mazdoor day 20.00 554.00 11080.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 63 KVA hour 6.00 875.95 5255.70 P&M-019
Per Cum Basic Cost of Labour, Material & Machinery 6772.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 4062.89
material, labour and machinery

e) Overhead charges @ 25 % on (a+b+c+d) 26408.80


f) Contractor's profit @ 10 % on (a+b+c+d+e) 13204.40
Cost for 15 cum = a+b+c+d+e+f 145248.38
Rate per cum = (a+b+c+d+e+f)/15 9683.23
say 9683.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 9174.00 47337.84 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
40 mm Aggregate cum 5.40 2355.02 12717.11 M-055
20 mm Aggregate cum 5.40 2576.62 13913.75 M-053
10 mm Aggregate cum 2.70 2576.62 6956.87 M-051
b) Labour
Mate day 0.86 831.00 714.66 L-12
Mason day 1.50 831.00 1246.50 L-11
Mazdoor day 20.00 554.00 11080.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 7426.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 4455.01
material, labour and machinery
e) Overhead charges @ 25 % on (a+b+c+d) 28957.56
f) Contractor's profit @ 10 % on (a+b+c+d+e) 14478.78
Cost for 15 cum = a+b+c+d+e+f 159266.56
Rate per cum = (a+b+c+d+e+f)/15 10617.77
say 10618.00
12.8 C RCC Grade M20
Case I Using Concrete Mixer
Unit = cum

Chapter 12 - 36
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 15 cum
a) Material
Cement tonne 5.21 9174.00 47796.54 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
20 mm Aggregate cum 8.10 2576.62 20870.62 M-053
10 mm Aggregate cum 5.40 2576.62 13913.75 M-051
b) Labour
Mate day 0.86 831.00 714.66 L-12
Mason day 1.50 831.00 1246.50 L-11
Mazdoor day 20.00 554.00 11080.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 7536.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 4521.22
e) Overhead charges @ 25 % on (a+b+c+d) 29387.94
f) Contractor's profit @ 10 % on (a+b+c+d+e) 14693.97
Cost for 15 cum = a+b+c+d+e+f 161633.68
Rate per cum = ( a+b+c+d+e+f )/15 10775.58
say 10776.00
12.8 E RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 9174.00 55502.70 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
20 mm Aggregate cum 8.10 2576.62 20870.62 M-053
10 mm Aggregate cum 5.40 2576.62 13913.75 M-051
b) Labour
Mate day 0.86 831.00 714.66 L-12
Mason day 1.50 831.00 1246.50 L-11
Mazdoor day 20.00 554.00 11080.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 8050.00
(a+b+c)
d) Formwork @ 3.75 per cent of a+b+c. 4527.63
e) Overhead charges @ 25 % on (a+b+c+d) 31316.09
f) Contractor's profit @ 10 % on (a+b+c+d+e) 15658.04
cost of 15 cum = a+b+c+d+e+f 172238.47
Rate per cum (a+b+c+d+e+f )/15 11482.56
say 11483.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 9174.00 55961.40 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
20 mm Aggregate cum 8.10 2576.62 20870.62 M-053
10 mm Aggregate cum 5.40 2576.62 13913.75 M-051
b) Labour
Mate day 0.86 831.00 714.66 L-12
Mason day 1.50 831.00 1246.50 L-11
Mazdoor day 20.00 554.00 11080.00 L-13

Chapter 12 - 37
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 8080.00
(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost 4241.84
of material, labour and machinery
e) Overhead charges @ 25 % on (a+b+c+d) 31359.31
f) Contractor's profit @ 10 % on (a+b+c+d+e) 15679.66
cost of 15 cum = a+b+c+d+e+f 172476.22
Rate per cum = (a+b+c+d+e+f)/15 11498.41
say 11498.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 53223.00 55884.15 M-082

Binding wire Kg 6.00 114.98 689.88 M-072


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 831.00 332.40 L-12
Blacksmith day 2.00 831.00 1662.00 L-02
Mazdoor day 6.00 554.00 3324.00 L-13
15473.11
7736.55
85102.09
say 85102.00

Chapter 12 - 38
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and Technical
1700 Specification
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 9174.00 55961.40 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
20 mm Aggregate cum 8.10 2576.62 20870.62 M-053
10 mm Aggregate cum 5.40 2576.62 13913.75 M-051
b) Labour
Mate day 0.90 831.00 747.90 L-12
Mason day 1.50 831.00 1246.50 L-11
Mazdoor day 21.00 554.00 11634.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 121783.00
for 15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 121783.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 24356.60
e) Overhead charges @ 25 % on (a+b+c+d) 36534.90
f) Contractor's profit @ 10 % on (a+b+c+d+e) 18267.45
Cost for 15 cum = a+b+c+d+e+f 200941.95
Rate per cum = (a+b+c+d+e+f)/15 13396.13
say 13396.00
14.1C (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 121783.00


cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 30445.75
e) Overhead charges @ 25 % on (a+b+c+d) 38057.19
f) Contractor's profit @ 10 % on (a+b+c+d+e) 19028.59
Cost for 15 cum = a+b+c+d+e+f 209314.53
Rate per cum = (a+b+c+d+e+f)/15 13954.30
say 13954.00
14.1C (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 121783.00


cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 36534.90
e) Overhead charges @ 25 % on (a+b+c+d) 39579.48
f) Contractor's profit @ 10 % on (a+b+c+d+e) 19789.74
Cost for 15 cum = a+b+c+d+e+f 217687.12
Rate per cum = (a+b+c+d+e+f)/15 14512.47
say 14512.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 121783.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 30445.75

Chapter 14 - 39
e) Overhead charges @ 25 % on (a+b+c+d) 38057.19
f) Contractor's profit @ 10 % on (a+b+c+d+e) 19028.59
Cost for 15 cum = a+b+c+d+e+f 209314.53
Rate per cum = (a+b+c+d+e+f)/15 13954.30
say 13954.00
14.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 121783.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 36534.90
e) Overhead charges @ 25 % on (a+b+c+d) 39579.48
f) Contractor's profit @ 10 % on (a+b+c+d+e) 19789.74
Cost for 15 cum = a+b+c+d+e+f 217687.12
Rate per cum = (a+b+c+d+e+f)/15 14512.47
say 14512.00
14.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 121783.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 42624.05
e) Overhead charges @ 25 % on (a+b+c+d) 41101.76
f) Contractor's profit @ 10 % on (a+b+c+d+e) 20550.88
Cost for 15 cum = a+b+c+d+e+f 226059.69
Rate per cum = (a+b+c+d+e+f)/15 15070.65
say 15071.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 9174.00 59172.30 M-081
Coarse sand cum 6.75 1489.15 10051.76 M-005
20 mm Aggregate cum 8.10 2576.62 20870.62 M-053
10 mm Aggregate cum 5.40 2576.62 13913.75 M-051
Admixture @ 0.4 per cent of cement kg 25.80 310.45 8009.61 M-180
b) Labour
Mate day 0.96 831.00 797.76 L-12
Mason day 2.00 831.00 1662.00 L-11
Mazdoor day 22.00 554.00 12188.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 390.94 2345.64 P&M-009
Generator 33 KVA hour 6.00 835.18 5011.08 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) 134023.00
for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 134023.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 26804.60
e) Overhead charges @ 25 % on (a+b+c+d) 40206.90
f) Contractor's profit @ 10 % on (a+b+c+d+e) 20103.45
Cost for 15 cum = a+b+c+d+e+f 221137.95
Rate per cum = (a+b+c+d+e+f)/15 14742.53
say 14743.00
14.1E (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 134023.00


cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 33505.75
e) Overhead charges @ 25 % on (a+b+c+d) 41882.19

Chapter 14 - 40
f) Contractor's profit @ 10 % on (a+b+c+d+e) 20941.09
Cost for 15 cum = a+b+c+d+e+f 230352.03
Rate per cum = (a+b+c+d+e+f)/15 15356.80
say 15357.00
14.1E (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 15 134023.00


cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 40206.90
e) Overhead charges @ 25 % on (a+b+c+d) 43557.48
f) Contractor's profit @ 10 % on (a+b+c+d+e) 21778.74
Cost for 15 cum = a+b+c+d+e+f 239566.12
Rate per cum = (a+b+c+d+e+f)/15 15971.07
say 15971.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 134023.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 33505.75
e) Overhead charges @ 25 % on (a+b+c+d) 41882.19
f) Contractor's profit @ 10 % on (a+b+c+d+e) 20941.09
Cost for 15 cum = a+b+c+d+e+f 230352.03
Rate per cum = (a+b+c+d+e+f)/15 15356.80
say 15357.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 134023.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 40206.90
e) Overhead charges @ 25 % on (a+b+c+d) 43557.48
f) Contractor's profit @ 10 % on (a+b+c+d+e) 21778.74
Cost for 15 cum = a+b+c+d+e+f 239566.12
Rate per cum = (a+b+c+d+e+f)/15 15971.07
say 15971.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 134023.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 46908.05
e) Overhead charges @ 25 % on (a+b+c+d) 45232.76
f) Contractor's profit @ 10 % on (a+b+c+d+e) 22616.38
Cost for 15 cum = a+b+c+d+e+f 248780.19
Rate per cum = (a+b+c+d+e+f)/15 16585.35
say 16585.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 9174.00 511909.20 M-081
Coarse sand cum 54.00 1489.15 80414.10 M-004
20 mm Aggregate cum 64.80 2576.62 166964.98 M-053
10 mm Aggregate cum 43.20 2576.62 111309.98 M-051
Admixture @ 0.4 per cent of cement kg 223.20 310.45 69292.44 M-180
b) Labour
Mate day 0.94 831.00 781.14 L-12
Mason day 3.50 831.00 2908.50 L-11
Mazdoor day 20.00 554.00 11080.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 4600.29 27601.74 P&M-002
Generator 100 KVA hour 6.00 1541.79 9250.74 P&M-080

Chapter 14 - 41
Loader hour 6.00 2090.57 12543.42 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 1762.35 26435.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 64.81 388860.00 Lead =20
km & P&M-
050
Concrete Pump hour 6.00 448.43 2690.58 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) 1422043.00
for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-26 per cent
of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 16 per cent of (a+b+c) 16.00 227526.88
e) Overhead charges @ 25 % on (a+b+c+d) 412392.47
f) Contractor's profit @ 10 % on (a+b+c+d+e) 206196.24
Cost for 120 cum = a+b+c+d+e+f 2268158.59
Rate per cum = (a+b+c+d+e+f)/120 18901.32
say 18901.00
14.1F (i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00


120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 298629.03
e) Overhead charges @ 25 % on (a+b+c+d) 430168.01
f) Contractor's profit @ 10 % on (a+b+c+d+e) 215084.00
Cost for 120 cum = a+b+c+d+e+f 2365924.04
Rate per cum = (a+b+c+d+e+f)/120 19716.03
say 19716.00
14.1F (i) v (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00


120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 369731.18
e) Overhead charges @ 25 % on (a+b+c+d) 447943.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 223971.77
Cost for 120 cum = a+b+c+d+e+f 2463689.50
Rate per cum = (a+b+c+d+e+f)/120 20530.75
say 20531.00
14.1F (ii) For T-beam & slab including launching of precast girders
by launching truss upto 40 m span, 21-31 per cent of
cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 298629.03
e) Overhead charges @ 25 % on (a+b+c+d) 430168.01
f) Contractor's profit @ 10 % on (a+b+c+d+e) 215084.00
Cost for 120 cum = a+b+c+d+e+f 2365924.04
Rate per cum = (a+b+c+d+e+f)/120 19716.03
say 19716.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 369731.18
e) Overhead charges @ 25 % on (a+b+c+d) 447943.55
f) Contractor's profit @ 10 % on (a+b+c+d+e) 223971.77
Cost for 120 cum = a+b+c+d+e+f 2463689.50
Rate per cum = (a+b+c+d+e+f)/120 20530.75
say 20531.00
14.1F (r) Height above 10m
(ii)

Chapter 14 - 42
Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 440833.33
e) Overhead charges @ 25 % on (a+b+c+d) 465719.08
f) Contractor's profit @ 10 % on (a+b+c+d+e) 232859.54
Cost for 120 cum = a+b+c+d+e+f 2561454.95
Rate per cum = (a+b+c+d+e+f)/120 21345.46
say 21345.00
14.1F (iii) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 36 per cent of (a+b+c) 36.00 511935.48
e) Overhead charges @ 25 % on (a+b+c+d) 483494.62
f) Contractor's profit @ 10 % on (a+b+c+d+e) 241747.31
Cost for 120 cum = a+b+c+d+e+f 2659220.41
Rate per cum = (a+b+c+d+e+f)/120 22160.17
say 22160.00
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 46 per cent of (a+b+c) 46.00 654139.78
e) Overhead charges @ 25 % on (a+b+c+d) 519045.70
f) Contractor's profit @ 10 % on (a+b+c+d+e) 259522.85
Cost for 120 cum = a+b+c+d+e+f 2854751.33
Rate per cum = (a+b+c+d+e+f)/120 23789.59
say 23790.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 1422043.00
120 cum
d) Formwork and staging 56 per cent of (a+b+c) 56.00 796344.08
e) Overhead charges @ 25 % on (a+b+c+d) 554596.77
f) Contractor's profit @ 10 % on (a+b+c+d+e) 277298.39
Cost for 120 cum = a+b+c+d+e+f 3050282.24
Rate per cum = (a+b+c+d+e+f)/120 25419.02
say 25419.00
14.2 1600 Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and wastage tonne 1.05 53223.00 55884.15 M-082

Binding wire Kg 8.00 114.98 919.84 M-072


b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 831.00 365.64 L-12
Blacksmith day 3.00 831.00 2493.00 L-02
Mazdoor day 8.00 554.00 4432.00 L-13
Basic Cost of Labour & Material (a+b) 64095.00
c) Overhead charges @ 25 % on (a+b) 16023.66
d) Contractor's profit @ 10 % on (a+b+c) 8011.83
Rate per MT = a+b+c+d 88130.12
say 88130.00
14.3 1800 High tensile steel wires/strands including all accessories
for stressing, stressing operations and grouting complete
as per drawing and Technical Specifications

Unit = 1 MT
Taking output = 0.377 MT

Chapter 14 - 43
Details of cost for 12T13 strand 40 m long cable (weight =
0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for tonne 0.39 106446.00 41513.94 M-119
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra metre 42.00 260.28 10931.76 M-165
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each 2.00 4973.46 9946.92 M-187
permanent wedges etc
Cement for grouting including 3 per cent wastage @ tonne 0.125 9174.00 1146.75 M-081
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

Add 0.50 per cent cost of material for Spacers, 3176.97


Insulation tape and miscellaneous items
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 831.00 132.96 L-12
Blacksmith day 1.00 831.00 831.00 L-02
Mazdoor day 3.00 554.00 1662.00 L-13
ii) For prestressing
Mate/Supervisor day 0.05 831.00 41.55 L-12
Prestressing operator / Fitter day 0.25 609.40 152.35 L-08
Mazdoor day 1.00 554.00 554.00 L-13
iii) For grouting
Mate/Supervisor day 0.05 831.00 41.55 L-12
Mason day 0.25 831.00 207.75 L-11
Mazdoor day 1.00 554.00 554.00 L-13
c) Machinery
Stressing jack with pump hour 2.50 218.46 546.15 P&M-040
Grouting pump with agitator hour 1.00 487.10 487.10 M-111
Generator 33 KVA. hour 3.50 835.18 2923.13 P&M-079
d) Overhead charges @ 25 % on (a+b+c) 2033.39
e) Contractor's profit @ 10 % on (a+b+c+d) 1016.69
Cost for 0.377 MT (a+b+c+d+e) 77899.96
Rate per MT = (a+b+c+d+e)/0.377 206631.19
say 206631.00
Note Cost of HT steel has been taken for delivery at site. Hence
carriage has not been considered.
14.5 515 & Mastic Asphalt
2702
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with
paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface,
including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm
nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm to 4
mm over mastic surface, all complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 831.00 407.19 L-12
Mazdoor day 11.00 554.00 6094.00 L-13
Mazdoor (Skilled) day 1.25 609.40 761.75 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 762.01 45.72 P&M-031
Air compressor 250 cfm hour 0.06 730.65 43.84 P&M-001
Mastic cooker 1 tonne capacity hour 6.00 139.02 834.12 P&M-030
Bitumen boiler 1500 litres capacity hour 6.00 976.29 5857.74 P&M-005

Chapter 14 - 44
Tractor for towing and positioning of mastic cooker and hour 1.00 811.14 811.14 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent by tonne 0.204 32164.00 6561.46 M-074
weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix cum 0.39 1116.36 435.38 M-021
= 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39

iii) Lime stone dust filler with calcium carbonate content tonne 0.36 11280.69 4061.05 M-188
not less than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cum 0.55 2576.62 1417.14 M-051
cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456
= 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid cum 0.036 2778.36 100.02 M-142
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight kg 1.05 32.16 33.77 M-074/1000
= 0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg

d) Overhead charges @ 25 % on (a+b+c) 6866.08


e) Contractor's profit @ 10 % on (a+b+c+d) 3433.04
Cost for 72.46 sqm = a+b+c+d+e 37763.44
Rate per sqm = (a+b+c+d+e)/72.46 521.16
say 521.00
Note 1.The rates for 6 mm or any other thickness may be worked
out on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and paid
separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic
asphalt blocks without aggregates and falls within the
standards laid down by MoRTH Specifications.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 9312.00 9312.00 Item 12.8
formworks (A)
Rate per cum say 9312.00
14.11 1500,160 Reinforced cement concrete approach slab including
0,1700 & reinforcement and formwork complete as per drawing
2704 and Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 10725.00 10725.00 Item 12.8
concrete in item 12.8(G)by using batching plant, (G)
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G) 214.50
except that form work may be added at the rate of 2 per
cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 64095.00 3204.75 Item 14.2 A
14.2(Excluding OH & CP)
b) Overhead charges @ 25 % on (a) 3536.06
c) Contractor's profit @ 10 % on(a+b) 1768.03
Rate per cum (a+b+c) 19448.34

Chapter 14 - 45
say 19448.00
Note The grade of reinforced cement concrete may be adopted as
M30 for severe conditions and M25 for moderate conditions.

14.18 2605 Filler joint


14.18 (iii) Providing and fixing in position 20 mm thick premoulded
joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.01 831.00 8.31 L-12
Mazdoor day 0.20 554.00 110.80 L-13
Mazdoor (Skilled) day 0.10 609.40 60.94 L-15
b) Material
Premoulded joint filler 12 m long,20 mm thick and 300 sqm 3.60 719.15 2588.94 M-141
mm deep.
c) Overhead charges @ 25 % on (a+b) 692.25
d) Contractor's profit @ 10 % on (a+b+c) 346.12
Cost for 12 m = (a+b+c+d) 3807.36
Rate per m = (a+b+c+d)/12 317.28
say 317.00
14.22 2607 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions
for installation.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.05 831.00 41.55 L-12
Mazdoor day 1.00 554.00 554.00 L-13
Mazdoor (Skilled) day 0.25 609.40 152.35 L-15
b) Material
Supply of complete assembly of strip seal expansion joint metre 12.00 13994.25 167931.00 M-178
comprising of edge beams, anchorage, strip seal element
and complete accessories as per approved specifications
and drawings.
Add 5 per cent of cost of material for anchorage 8433.95
reinforcement, welding and other incidentals.
c) Overhead charges @ 25 % on (a+b) 44278.21
d) Contractor's profit @ 10 % on (a+b+c) 22139.11
Cost for 12 m = (a+b+c+d) 243530.17
Rate per m = (a+b+c+d)/12 20294.18
say 20294.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.

Chapter 14 - 46
CHAPTER-13
SUB-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work in sub-
2200 structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 6774.00 975.46 Item 12.6
(A)
b) Labour
Mate day 0.04 831.00 33.24 L-12
Mason day 0.50 831.00 415.50 L-11
Mazdoor day 0.50 554.00 277.00 L-13
c) Overhead charges @ 25 % on (a+b) 425.30
d) Contractor's profit @ 10 % on (a+b+c) 212.65
Rate per 10 sqm (a+b+c+d) 2339.15
say 2339.00
Note 1.Scaffolding is already included in item no. 13.1
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 6772.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 677.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 25 % on (a+b+c+d) 1862.30
f) Contractor's profit @ 10 % on (a+b+c+d+e) 931.15
Rate perm (a+b+c+d+e+f) 10242.65
say 10243.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 7426.00 Item 12.8 (B) PCC
(a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 742.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 25 % on (a+b+c+d) 2042.15
f) Contractor's profit @ 10 % on (a+b+c+d+e) 1021.08
Rate perm (a+b+c+d+e+f) 11231.83
say 11232.00
13.5 F RCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 8050.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork

Chapter 13 - 47
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 10 per cent of cost of material, labour and 10.00 805.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 25 % on (a+b+c+d) 2213.75
f) Contractor's profit @ 10 % on (a+b+c+d+e) 1106.88
Rate perm (a+b+c+d+e+f) 12175.63
say 12176.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 8080.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 808.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 25 % on (a+b+c+d) 2222.00
f) Contractor's profit @ 10 % on (a+b+c+d+e) 1111.00
Rate perm (a+b+c+d+e+f) 12221.00
say 12221.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 8080.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 929.20
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 129.28
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 25 % on (a+b+c+d) 2284.62
f) Contractor's profit @ 10 % on (a+b+c+d+e) 1142.31
Rate perm (a+b+c+d+e+f) 12565.41
say 12565.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 8080.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 1131.20
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 282.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 25 % on (a+b+c+d) 2373.50
f) Contractor's profit @ 10 % on (a+b+c+d+e) 1186.75
Rate perm (a+b+c+d+e+f) 13054.25
say 13054.00
13.6 Section Supplying, fitting and placing HYSD bar reinforcement in
1600 & sub-structure complete as per drawing and Technical
2200 Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 53223.00 55884.15 M-082

Binding wire kg 6.00 114.98 689.88 M-072

Chapter 13 - 48
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 831.00 282.54 L-12
Blacksmith day 2.00 831.00 1662.00 L-02
Mazdoor day 6.50 554.00 3601.00 L-13
c) Overhead charges @ 25 % on (a+b) 15529.89
d) Contractor's profit @ 10 % on (a+b+c) 7764.95
Rate for per MT (a+b+c+d) 85414.41
say 85414.00
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm
dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce.
Complete as per drawing and Technical Specifications

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 1097.55 34572.83 M-056

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp each. 30.00 98.26 2947.80 M-123
collar for AC pipe (average) taking 10% of above pipe each. 10.00 109.76 1097.60 M-056/10
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 6774.00 338.70 Item 12.6
(A)
b) Labour
Mate day 0.03 831.00 24.93 L-12
Mason day 0.50 831.00 415.50 L-11
Mazdoor day 0.25 554.00 138.50 L-13
c) Overhead charges @ 25 % on (a+b) 9883.97
d) Contractor's profit @ 10 % on (a+b+c) 4941.98
Cost for 30 m = a+b+c+d 54361.81
Rate per m (a+b+c+d)/30 1812.06
say 1812.00
Note 1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work and
shall not be paid separately.
13.9 710.1.4.o Back filling behind abutment, wing wall and return wall
f IRC:78 complete as per drawing and Technical Specification
& 2200

Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 831.00 232.68 L-12
Mazdoor day 7.00 554.00 3878.00 L-13
b) Material
Granular material cum 12.00 1310.76 15729.12 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 372.12 930.30 P&M-086
Water Tanker hour 0.05 1042.15 52.11 P&M-060
d) Overhead charges @ 25 % on (a+b+c) 5205.55
e) Contractor's profit @ 10 % on (a+b+c+d) 2602.78
Cost for 10 cum of granular backfill = a+b+c+d+e 28630.54
Rate per cum = (a+b+c+d+e)/10 2863.05
say 2863.00

Chapter 13 - 49
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.9 B Sandy material
a) Labour
Mate day 0.28 831.00 232.68 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 554.00 3878.00 L-13
b) Material
Sand cum 12.00 1320.74 15848.88 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 372.12 930.30 P&M-086
Water Tanker hour 0.06 1042.15 62.53 P&M-060
d) Overhead charges @ 25 % on (a+b+c) 5238.10
e) Contractor's profit @ 10 % on (a+b+c+d) 2619.05
Cost for 10 cum of sandy backfill = a+b+c+d+e 28809.54
Rate per cum = (a+b+c+d+e)/10 2880.95
say 2881.00
13.10 710.1.4.o Providing and laying of Filter media with granular
f IRC:78 materials/stone crushed aggregates satisfying the
and 2200 requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size towards
the wall and provided over the entire surface behind
abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing
and Technical Specification.

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 831.00 265.92 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 554.00 3878.00 L-13
Mazdoor (Skilled) day 1.00 609.40 609.40 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 1310.76 15729.12 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 1042.15 62.53 P&M-060
d) Overhead charges @ 25 % on (a+b+c) 5136.24
e) Contractor's profit @ 10 % on (a+b+c+d) 2568.12
cost for 10 cum of Fiter Media = a+b+c+d+e 28249.33
Rate per cum = (a+b+c+d+e)/10 2824.93
say 2825.00

Chapter 13 - 50
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.8 2505 Providing and laying Flooring complete as per drawing
and Technical specifications laid over cement concert
bedding.
A Rubble stone laid in cement mortar 1:3
Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis) cum 0.33 6774.00 2235.42 Item 12.6
excluding OH & CP (A)
b) Add for cement concrete bedding (M15 Nominal cum 0.33 6772.00 2234.76 Item 12.8
mix) vide Item 12.8 (A) excluding OH & CP . Quantity shall (A)
be adopted as per design ( Assume Rubble stone
Flooring thickness 300mm and cement concrete bedding
thickness 100mm)
Add 1 per cent of cost to account for excavation for 44.70
preparation of bed.
c) Material
Stone cum 1.00 1131.27 1131.27 M-003
Stone Spalls cum 0.20 1310.76 262.15 M-008
d) Labour
Mate day 0.08 831.00 66.48 L-12
Mason day 0.50 831.00 415.50 L-11
Mazdoor (for laying stones, filling of quarry spalls) day 1.50 554.00 831.00 L-13
e) Overhead charges @ 25 % on (a+c+d) 1235.46
f) Contractor's profit @ 10 % on (a+c+d+e) 617.73
Rate per cum = (a+b+c+d+e+f) 9074.47
say 9074.00
* Includes cement mortar for laying and filling of joints.
15.12 2503.3 Gabian Structure for Retaining Earth
Providing and construction of a gabian structure for retaining
earth with segments of wire crates of size 7 m x 3 m x 0.6 m
each divided into 1.5 m compartments by cross netting, made
from 4 mm galvanised steel wire @ 32 kg per 10 sqm having
minimum tensile strength of 300 Mpa conforming to IS:280
and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 x 100
mm, filled with boulders with least dimension of 200 mm, all
loose ends to be tied with 4 mm galvanised steel wire

Unit = cum
Taking output = 6 x 2.0 x 1.0 x 1.0 = 12.00 cum
a) Labour
Mate day 0.27 831.00 224.37 L-12
Mazdoor day 4.76 554.00 2637.04 L-13
Mazdoor (Skilled) day 1.90 609.40 1157.86 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x 100 sqm 60.00 348.08 20884.80 M-102
mm woven with 3mm dia. GI wire in rolls of required size.

Stone boulders with least dimension of 200 mm cum 12.00 600.00 7200.00 M-003
Stone spalls of minimum size 25 mm cum 2.40 600.00 1440.00 M-008
c) Overhead charges @ 25 % on (a+b) 8386.02
d) Contractor's profit @ 10 % on (a+b+c) 4193.01
Cost for 12.0 cum (a+b+c+d) 46123.10
Rate per cum (a+b+c+d)/12.60 3843.59
say 3844.00
Note Readymade woven wire crate rolls have been considered in
the rate analysis. In case readymade rolls are not available,
GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for
weaving the wire crates.

Chapter 15 - 51

You might also like