You are on page 1of 108

National Highways of Infrastructure

Development Corporation Ltd


Consultancy Services for preparation of Detailed Project Report and providing
pre-construction activities for Construction of 2-laning with hard shoulder
configuration of Lunglei to Chhumkhum from Design Chainage Km 0.00 to Km
40.00 for Lunglei-Tlabung section of NH-302 in the State of Mizoram Under
‘Bharatmala Pariyojana’ on EPC Mode.

VOLUME – I: MAIN REPORT


Detailed Project Report (Annexure)
JULY- 2020

CM ENGINEERING & SOLUTION


Engineering, Planning and Project Management
House No. –1473A, Maruti Vihar, Gurgaon, Haryana – 122002, Tel – 0124 –4255138/9811406386
Construction of 2-laning with hard shoulder
Detailed
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Project Report

INVENTORY CUM CONDITION SURVEY

General
The proposed road consists of:
(i) Regrading portions; where existing route is utilized.
(ii) Realignment portions, which are new route stretches.
(iii) Inventory and Condition Survey of Existing Culverts.
(iv) Inventory and Condition Survey of Existing Bridges.
Inventorisation and Condition Survey relates to the existing road portions.
Road Inventory and Condition Survey
This section deals detailed data collection and survey of the project road to study and
understand the existing road condition. Road inventorization has been done with respect to
the project road sections. The data collected has been formatted at every 100 m for each km
of the road. The survey and investigations have been carried out in the months of Sept
2009. Major activities with respect to this have been as under.
• Road Inventory Survey
• Pavement Condition Survey
• Existing Culvert
• Existing Retaining Wall
• Existing Breast Wall
Road Inventory Survey

The inventory survey was undertaken by actual measurement, study, investigation and/or
visual assessment of various elements and features particularly with respect to roadway,
carriageway (type and width), shoulders (type and width), height of embankment,
drainage pattern, drainage structure, retaining structures, etc. The land environment
features such as topography, terrain, land use, soil, air environment, water bodies,
agriculture, etc. are based on actual survey, map studies and/or visual assessment.

Road Inventory Data Sheets are placed as Annexure-IIA.

The salient features of the Project Corridor are summarized as under.

Road Length

The Project Corridor is branched off from 405.00 Kmp (Old chainage 225/00 Kmp) on NH-
54 at Hrangchalkawn as NH-54A upto Km 6.65 at Sethlum village and Existing NH-302 is
takeoff from existing NH-54A at Km 5.65 near Sethlun village and Terminate at km 90.30at
Tlabung. Junction with MSRP-II Road.

Altitude

Altitude of alignment varies from 1220 m at take off point and 120 m at End point above

1
Construction of 2-laning with hard shoulder
Detailed
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Project Report

the MSL

Terrain

The project road is located in Mizoram, one of the most variegated hilly terrains in eastern
part of India. The hills are undulating and are separated by rivers, which flow either to the
north or south creating deep gorges between the hill ranges.

The classification of the terrain is normally done by means of cross slope to the country viz.
slope approximately perpendicular to the center line of the highway location.

Terrain Classification as per IRC: SP-48-1998

Sl no Terrain Classification % Cross slope of country


1 Plain 0 to 10
2 Rolling Greater than 10 upto 25
3 Hilly Greater than 25 upto 60
4 Steep Greater than 60
The road mostly is in the hilly to steep terrain.

Gradient

The existing gradients of the road between km 00.00 to km 98.0 are steep at many stretches.
As a result, the heavily loaded trucks and large sized vehicles find it difficult to pass
through these stretches safely and smoothly, especially during rainy season.

Towns and villages:

The project road passes through only a few scattered populations in the Lunglei district.
The list of the habitats along the project road is as follows:

Sr. Name of Existing Chainage


Name of Village Road
No. From To
1 Hrangchalkawn NH-54A 0 1975
2 Theiriat NH-54A 1975 4567
3 Sethlun NH-54A 4567 5650
4 Luangmual NH-302 0 1080
5 Hauruang NH-302 12780 14850
6 Pachang NH-302 25130 26830
7 Phairuang NH-302 35680 36610
8 Chhumkhum NH-302 42520 44830
9 Lungsen NH-302 52445 55140

2
Construction of 2-laning with hard shoulder
Detailed
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Project Report

Sr. Name of Existing Chainage


Name of Village Road
No. From To
10 Sihphir NH-302 60300 60570
11 Tuichwang NH-302 70170 73190
12 Tlabung NH-302 85180 90148
Land-use:

The regional land use plays an important role in the decision making process of any project.
The land use analysis is very essential requirement for the expansion/widening and
realignment of the road projects. The region is yet to be fully linked and connected with
wide network of roads. Hence the economic activities are also very less and the people in
the region still depend on primitive ways of livelihood. The region is scarcely populated
and the natural physical landscape beauty still enthrills the onlookers. The settlements are
all along the road. The forest have been cleared to give way for the cultivation of crops but
the percentage of land cover used for the agricultural purposes is still very small. The
clearing of the jungle and vegetation covers for settlements, agriculture, transport and
communication lines and consequent disappearance of the wild life have yet to take its toll
in the region.

Percentage Distribution of Land use


Sl No Land Use Percentage
1 Settlements 14.75 %
2 Agriculture 70.50 %
3 Forest 6.75%
4 Others 8.00 %
Thus we see that the forest and agriculture land covers the major area of the project sector.
Right Of-Way (ROW)
ROW of existing road is not define properly .As per reconnaissance survey the ROW
available is 8m to 10m in NH54A and 6m to 7m in NH302. But in habited areas it is even
less than this due to encroachments.
Formation
Cutting of the hill slopes mostly forms the road formations. The width of the formation
cutting is varying from 5.5m to 7.0 m.
Carriageway
The carriageway width varies from 3 m to 4.2 m.
Shoulders

Shoulders are more or less non-existent, and / or inadequate in width, depressed and non-
functional.

3
Construction of 2-laning with hard shoulder
Detailed
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Project Report

Pavement Condition Survey

The pavement condition of road sector from Km 0.00 to Km 8.25 of Existing NH-54-A and
from km 0.00 to km 90.30 of existing NH-302 has been carried out. The pavement
condition of the existing project road with respect to thickness, cracking, potholes, rutting
etc have been surveyed in detailed to access the condition. The reconnaissance survey of
the pavement reflects the following,
• Thickness of the existing pavement is inadequate.
• Sub grade has failed at some locations
• Pavement failure at many place is due to improper drainage system
• Cracking, raveling, potholes, ruts, etc. are of very high order.
The pavement condition survey of the project road was simultaneously carried out along
with the road inventory to assess existing pavement condition. Condition survey was
undertaken by visual assessment of pavement surface distress, potholes, cracks, patches,
raveling, condition of shoulders, etc.

The Pavement Condition Survey Data for the project road are presented in Annexure- II B

General condition of the road pavement is poor, especially in the portion, which has not
been reconstructed/rehabilitated in the past. The road has been resurfaced in some portion
but the surface has shown distress. The road requires regrading, widening and
strengthening for capacity augmentation as well as for improvement of the riding surface.

Pavement Visual Condition Survey was carried out over the road corridor by a team of
experienced highway engineers to assess different modes, regarding the following features:
• Type of Surface
• % Cracked area
• % Area covered by pot holes, raveling and patching
• Rutting
• Shoulder condition
• Embankment
The finding of the visual pavement condition survey has been tabulated and attached in
Annexure-II. Based on the visual survey findings, the percentage Cracks, Potholes,
Patching, Raveling and Edge drop over the entire road corridor are indicated in the
pavement condition survey sheets. The road surface is poor. Cracks, potholes, patching,
raveling and edge drops are very predominantly visible.
Analysis:
Analysis of data obtained consequent to the Condition Survey has revealed that the
pavement condition of the existing road is poor. The road has no well-defined camber,
super elevation and curve widening.
Culvert Inventory and Condition Survey of Culverts
The inventory survey was undertaken by actual survey, measurements and visual

4
Construction of 2-laning with hard shoulder
Detailed
configuration of NH-302 (From Lunglei to Tlabung)
under ‘Bharatmala Pariyojana’ in the state of Mizoram Project Report

inspection of various elements forming the Cross-Drainage structures viz. chainage, the
span arrangement, length, width, vertical clearance, details of superstructure, sub-structure
/ foundation and protection works, etc.
The survey has been conducted using the format given in Annexure – II C.
It has two parts:
• Culvert Inventory Data
• Condition Survey
The inventory survey was undertaken by actual study, site visit, measurements and visual
inspections. It was supplemented by survey and detailed investigations by the team.
Special attention was paid to the Condition Survey of various features of culverts / bridges
and adequacy or otherwise.
The condition of existing culverts is rated poor and recommended for replacement.
Inventory of Bridges
General
Inventory of all the Bridges falling on the project road has been prepared in terms of
guidelines provided in IRC: SP-35, 1990 so as to determine the number, category of
structures and also to attempt a scientific approach for their retention / repairs /
rehabilitation based on technical grounds. This inventory data for each structure consists
of location, construction data (wherever available), type of foundation, sub-structure and
super structure, overall length, details of spans, waterway, carriageway width, provision of
footpaths along with the past behavior of the structure from functional, hydraulic and
structural considerations.
The inventory survey was undertaken by actual measurement, study, investigation and
visual assessment of various elements and features particularly with respect to location,
span arrangement, structural details, roadway width, and condition of structures.
List of Existing Bailey Bridges on the NH-302 are tabulated below:
Location Span Name of Type Direction
No. in Km in m River
1 27.000 12 RCC bridge Right angle to the
direction of the river
2 33.510 85 Phairuang Bailey Right angle to the
River Bridge Bridge direction of the river
3 35.130 37 Chhawchhi Bailey Right angle to the
River Bridge Bridge direction of the river
4 67.015 110 Tuichang Bailey Right angle to the
River Bridge direction of the river
5 70.212 30 Thawrikau Bailey Right angle to the
River Bridge Bridge direction of the river

5
ROAD INVENTORY DATA SHEET Appendix II A

Road Name: Hrangchalkawn to Lunglei Sheet No. :

From: Hrangchalkawn To: Lunglei


Dt of Survey : 15.09.09 to 20.09.09
District (From) : Lunglei District (To) : Lunglei Weather : Fair
From (Km) To Terrain (Plain Rise & Land Use Name of Formation
(Km) Rolling/Hilly) Fall (Built Village/Town width (m) CARRIAGEWAY SHOULDER Submergence(in
Embank-ment Right
Up/Agri/Forest/ Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
Industrial/Barr type type (m) (BT/CC/G (m) / Stretch in m
en) R/ER)
0 0.100 Hilly Rise Built Up Hrangchalkawn 12.00 Flexible DBC 4.40 Soil 1.40 N/A N/A 13 poor and undulation
0.100 0.200 Hilly Rise Built Up Hrangchalkawn 9.00 Flexible DBC 3.70 Soil 1.80 N/A N/A 15 poor and undulation
0.200 0.400 Hilly Rise Built Up Hrangchalkawn 10.20 Flexible DBC 4.50 Soil 2.00 N/A N/A 15 poor and undulation
0.400 0.600 Hilly Rise Built Up Hrangchalkawn 9.70 Flexible DBC 5.70 Soil 1.40 N/A N/A 15 poor and undulation
0.600 0.800 Hilly Fall Built Up Hrangchalkawn 10.00 Flexible DBC 3.60 Soil 1.20 N/A N/A 15 poor and undulation
0.800 1.000 Hilly Fall Built Up Hrangchalkawn 7.50 Flexible DBC 3.50 Soil 1.30 N/A N/A 15 poor and undulation
1.000 1.200 Hilly Fall Built Up Hrangchalkawn 9.00 Flexible DBC 4.30 Soil 0.90 N/A N/A 15 poor and undulation
1.200 1.400 Hilly Fall Built Up Hrangchalkawn 9.00 Flexible DBC 4.50 Soil 1.00 N/A N/A 15 poor and undulation
1.400 1.600 Hilly Rise Built Up Hrangchalkawn 10.70 Flexible DBC 5.30 Soil 1.00 N/A N/A 15 poor and undulation
1.600 1.800 Hilly Rise Built Up Hrangchalkawn 12.50 Flexible DBC 4.50 Soil 2.00 N/A N/A 15 poor and undulation
1.800 2.000 Hilly Rise Built Up Theiriat 9.60 Flexible DBC 5.80 Soil 1.20 N/A N/A 15 poor and undulation
2.000 2.200 Hilly Rise Built Up Theiriat 10.00 Flexible DBC 5.00 Soil 1.30 N/A N/A 15 poor and undulation
2.200 2.400 Hilly Fall Built Up Theiriat 9.40 Flexible DBC 5.50 Soil 0.90 N/A N/A 15 poor and undulation
2.400 2.600 Hilly Fall Built Up Theiriat 10.10 Flexible DBC 5.00 Soil 1.10 N/A N/A 15 poor and undulation
2.600 2.800 Hilly Fall Built Up Theiriat 9.50 Flexible DBC 3.60 Soil 1.40 N/A N/A 15 poor and undulation
2.800 3.000 Hilly Fall Built Up Theiriat 10.00 Flexible DBC 4.00 Soil 1.60 N/A N/A 15 poor and undulation
3.000 3.200 Hilly Fall Built Up Sethlun 10.70 Flexible DBC 5.60 Soil 1.20 N/A N/A 15 poor and undulation
3.200 3.400 Hilly Fall Built Up Sethlun 9.50 Flexible DBC 5.60 Soil 1.30 N/A N/A 15 poor and undulation
3.400 3.600 Hilly Fall Built Up Sethlun 8.50 Flexible DBC 5.00 Soil 1.00 N/A N/A 15 poor and undulation
3.600 3.800 Hilly Fall Built Up Sethlun 10.30 Flexible DBC 5.60 Soil 1.20 N/A N/A 15 poor and undulation
3.800 4.000 Hilly Fall Built Up Sethlun 11.00 Flexible DBC 5.30 Soil 1.40 N/A N/A 15 poor and undulation
4.000 4.200 Hilly Fall Built Up Sethlun 8.60 Flexible DBC 5.00 Soil 1.30 N/A N/A 15 poor and undulation
4.200 4.400 Hilly Fall Built Up Sethlun 9.20 Flexible DBC 5.20 Soil 1.00 N/A N/A 12 poor and undulation
4.400 4.600 Hilly Fall Built Up Sethlun 9.80 Flexible DBC 5.40 Soil 1.50 N/A N/A 12 poor and undulation
4.600 4.800 Hilly Fall Built Up Sethlun 10.50 Flexible DBC 5.00 Soil 1.60 N/A N/A 12 poor and undulation
4.800 5.000 Hilly Rise Built Up Sethlun 8.90 Flexible DBC 5.10 Soil 1.30 N/A N/A 12 poor and undulation
5.000 5.200 Hilly Rise Built Up Sethlun 11.10 Flexible DBC 4.90 Soil 1.10 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 1 of 11


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: Hrangchalkawn to Lunglei Sheet No. :

From: Hrangchalkawn To: Lunglei


Dt of Survey : 15.09.09 to 20.09.09
District (From) : Lunglei District (To) : Lunglei Weather : Fair
From (Km) To Terrain (Plain Rise & Land Use Name of Formation
(Km) Rolling/Hilly) Fall (Built Village/Town width (m) CARRIAGEWAY SHOULDER Submergence(in
Embank-ment Right
Up/Agri/Forest/ Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
Industrial/Barr type type (m) (BT/CC/G (m) / Stretch in m
en) R/ER)
5.200 5.400 Hilly Rise Built Up Lunglawn 11.50 Flexible DBC 4.40 Soil 1.00 N/A N/A 12 poor and undulation
5.400 5.600 Hilly Fall Built Up Lunglawn 9.30 Flexible DBC 5.30 Soil 1.40 N/A N/A 12 poor and undulation
5.600 5.800 Hilly Fall Built Up Lunglawn 8.70 Flexible DBC 4.80 Soil 1.70 N/A N/A 12 poor and undulation
5.800 6.000 Hilly Fall Built Up Lunglawn 10.40 Flexible DBC 5.10 Soil 1.50 N/A N/A 12 poor and undulation
6.000 6.200 Hilly Fall Built Up Lunglei 12.10 Flexible DBC 5.80 BT 1.40 N/A N/A 12 poor and undulation
6.200 6.400 Hilly Rise Built Up Lunglei 11.60 Flexible DBC 5.90 BT 1.30 N/A N/A 12 poor and undulation
6.400 6.600 Hilly Rise Built Up Lunglei 11.80 Flexible DBC 5.60 BT 1.20 N/A N/A 12 poor and undulation
6.600 6.800 Hilly Rise Built Up Lunglei 10.90 Flexible DBC 5.80 BT 1.20 N/A N/A 12 poor and undulation
6.800 7.000 Hilly Fall Built Up Lunglei 9.70 Flexible DBC 5.70 BT 1.50 N/A N/A 12 poor and undulation
7.000 7.200 Hilly Fall Built Up Lunglei 10.80 Flexible DBC 5.90 BT 1.60 N/A N/A 12 poor and undulation
7.200 7.400 Hilly Fall Built Up Lunglei 9.40 Flexible DBC 5.70 BT 1.50 N/A N/A 12 poor and undulation
7.400 7.600 Hilly Fall Built Up Lunglei 11.90 Flexible DBC 5.90 BT 1.20 N/A N/A 12 poor and undulation
7.600 7.800 Hilly Fall Built Up Lunglei 10.70 Flexible DBC 5.80 BT 1.40 N/A N/A 12 poor and undulation
7.800 8.000 Hilly Fall Built Up Lunglei 11.20 Flexible DBC 5.80 BT 1.30 N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 2 of 11


PAVEMENT CONDITION SURVEY Appendix : II B

ROAD NAME : Hrangchalkawn to Lunglei Sheet No :

From (Km.) Hrangchalkawn TO : Lunglei Date of Survey : 15.09.09 to 20.09.09

District (from) :Lunglei District (To): Lunglei Weather : Fair

CHAINAGE Pavement Composition Shoulder Riding Quality Pavement Condition


Embankment
Pavement
Patching (No. Condition Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Edge drop Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) and % 100m) (Good/ Fair/ (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) (mm)
** poor)

Surface BM 25
Binder
Strengthening
0 1.000 Base WBM 150 Earthen Poor 20 Poor 52 78 Severe 30 N/A UnLine Drain
is required
Sub-base Gravel 125
Subgrade Soil
Surface BM 25
Binder
Strengthening
1.000 2.000 Base WBM 150 Earthen Poor 21 Poor 55 50 Severe 30 N/A UnLine Drain
is required
Sub-base Gravel 125
Subgrade Soil
Surface BM 25
Binder Patch repairing
and
2.000 3.000 Base WBM 150 Earthen Poor 22 Poor 50 64 Severe 30 N/A UnLine Drain
Strengthening
Sub-base Gravel 125 isrequired
Subgrade Soil
Surface BM 25
Binder Patch repairing
and
3.000 4.000 Base WBM 150 Earthen Poor 23 Poor 48 70 Severe 30 N/A UnLine Drain
Strengthening
Sub-base Gravel 125 isrequired
Subgrade Soil
Surface BM 25
Binder Patch repairing
and
4.000 5.000 Base WBM 150 Earthen Poor 24 Poor 45 75 Severe 30 N/A UnLine Drain
Strengthening
Sub-base Gravel 125 isrequired
Subgrade Soil
Surface BM 25
Binder Patch repairing
and
5.000 6.000 Base WBM 150 Earthen Poor 25 Poor 53 80 Severe 30 N/A UnLine Drain
Strengthening
Sub-base Gravel 125 isrequired
Subgrade Soil
Surface BM 25
Binder Patch repairing
Base WBM 150 and
6.000 7.000 Earthen Poor 26 Poor 49 40 Severe 30 N/A UnLine Drain
Strengthening
Sub-base Gravel 125
isrequired
Subgrade Soil

Surface BM 25

Binder Patch repairing


and
7.000 8.000 Base WBM 150 Earthen Poor 27 Poor 58 30 Severe 30 N/A UnLine Drain
Strengthening
Sub-base Gravel 125 isrequired

Subgrade Soil

Surveyed by Prepared by Checked by Sheet 3 of 11


Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :Hrangchalkawn to Lunglei Sheet No. :

Section : Date of Survey : 15.09.09 to 20.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

1 352 SLAB 0.2 1X1 4.3 7.0 N/A N/A P P P N/A N/A No Souring Sufficient h/w of v/s is damage other conditon is good

2 447 SLAB 0.2 1.2X1.5 4.4 6.0 N/A N/A P P P N/A N/A No Souring Sufficient h/w broken on both side rest good condition

3 633 SLAB 0.2 1.2X1.5 4.1 7.1 N/A N/A P P P N/A N/A No Souring Sufficient opening good walls need repair

4 683 SLAB 0.2 1X1.2 4.2 7.2 1.6X1.8 N/A N/A P P P N/A N/A No Souring Sufficient not exist

5 896 SLAB 0.2 1X1 3.6 6.4 N/A N/A P P P N/A N/A No Souring Sufficient not exist

6 992 SLAB 0.2 1X1 3.3 6.4 N/A N/A P P P N/A N/A No Souring Sufficient fully covered with landslide

7 1179 SLAB 0.2 1X1 5.0 8.4 N/A N/A P P P N/A N/A No Souring Sufficient h/w broken need relpace

8 1390 SLAB 0.2 1X1.2 3.3 5.1 N/A N/A P P P N/A N/A No Souring Sufficient h/w crack culvert condition is good

9 1755 SLAB 0.2 1X1 5.2 10.4 1.2X1.5 N/A N/A P P P N/A N/A No Souring Sufficient h/w slightly crack

10 2244 SLAB 0.2 1.2X1.5 6.0 10.0 1.2X1.6 N/A N/A P P P N/A N/A No Souring nalla its small bridge but good condition

11 2771 SLAB 0.2 1.2X1.5 5.5 11.0 N/A N/A P P P N/A N/A No Souring Sufficient condition is good

12 2911 PIPE 1X0.9 6.0 10.2 N/A N/A P P P N/A N/A No Souring Sufficient good condition but covered with weeds

13 3842 PIPE 1X0.9 5.7 9.9 N/A N/A F F P N/A N/A No Souring Sufficient good condition

14 4260 PIPE 1X0.9 4.4 7.6 N/A N/A P P P N/A N/A No Souring Sufficient opening is fill and no h/w

15 4507 PIPE 1X0.9 4.0 7.1 N/A N/A F F P N/A N/A No Souring Sufficient small pipe good condition
opening is fill and culvert condition is also need
16 4648 SLAB 0.2 1x1 3.8 5.9 N/A N/A P P P N/A N/A No Souring Sufficient
repair
17 4755 SLAB 0.2 1x1 4.3 8.8 N/A N/A F F P N/A N/A No Souring nalla good condition

18 5086 PIPE 1X0.9 5.4 11.0 1.5x1.5 N/A N/A P P P N/A N/A No Souring Sufficient slightly crack of wing/w

19 5169 PIPE 1X0.9 5.0 12.0 1.5x1.5 N/A N/A P P P N/A N/A No Souring Sufficient good condition
26.5right 17 leftv/s 1.2r/1.4left
20 5463 PIPE 1X0.9 4.0 6.9 N/A N/A F F P 17/10 h 3/2 v No Souring Sufficient no h/w need contruction
6right 4 left h/s 0.8r/0.6left
21 5909 SLAB 0.2 1x1 4.2 7.1 N/A N/A F F P N/A N/A No Souring Sufficient no h/w need contruction

22 6155 PIPE 1X0.9 4.0 8.1 N/A N/A P P P N/A N/A No Souring Sufficient wing/w is broken

23 6315 SLAB 0.2 1.2X1.5 4.1 7.7 1.2x1.2 N/A N/A F F P N/A N/A No Souring Nalla good condition

24 6478 SLAB 0.2 1.2X1.5 5.1 7.6 N/A N/A F F P N/A N/A No Souring Sufficient opening fill no h/w

25 7339 SLAB 0.2 1.2X1.5 5.2 7.4 N/A N/A P P P N/A N/A No Souring Sufficient opening fill wing/w crack

26 7551 SLAB 0.2 1.2X1.5 5.3 6.9 N/A N/A F F P N/A N/A No Souring Sufficient opening is fill but wing/w condition is good

27 7667 SLAB 0.2 1.2X1.5 5.0 7.0 1.6X1.8 N/A N/A P P P N/A N/A No Souring Sufficient good condition

28 7797 SLAB 0.2 1.2X1.5 4.5 6.7 N/A N/A P P P 7.5/7 N/A 2.1/2 No Souring Sufficient crack on the wing/w

Page 4
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : Hrangchalkawn to Lunglei Appendix-II D
Section : Dt of Survey :15.09.09 to 20.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
parapet walls crack at top
1 141 146 5.67 1 2
wall is good
parapet walls crack at top
2 219 234 15.75 2 NP
wall is good
parapet walls crack at top
3 548 556 8.16 3 6
wall is good
damage at some portion
4 572 577 5.66 2 4
need
repairing
old and damage need
5 594 598 4.07 6.8 3
repairing
most of the parapet are
6 602 620 18.5 5 10
crack
r/w is good
parapet wallsbut covered
crack at top
7 1180 1199 18.49 2 3
wall is good
good only parapet top need
8 1254 1282 27.12 3 9
repairing

9 1390 1399 9.14 2.5 5 crack on the wall

old and broken fully


10 1687 1696 9.36 2.5 5
covered with weeds
small portion is crack on the
11 1724 1734 10.08 3.5 3
wall
good only parapet top need
12 1886 1901 14.88 2 3
repairing

13 2139 2148 8.52 2 2 wall crack at some portion

good only parapet top need


14 3865 3875 10.42 4.6 5
repairing
good only parapet top need
15 3900 3910 9.16 4.7 5
repairing
174.98
INVENTORY & CONDITION SURVEY FOR BREAST WALL
Road Name : Hrangchalkawn to Lunglei Appendix-II E
Section : Dt of Survey :15.09.09 to 20.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Depression of the soil of breast wall
2 Crack in the wall 6 Erosion of the v/s toe at foundation
3 Part damage of the wall 7 Top portion of the breast wall damage
4 Growing of vegetation or weeds
Chainage in m Top
Structure Length in Height in
Sl. No Width in Remarks
FROM TO No. m m
m
1 503 526 22.79 2 0.6 1,3,4,5,7

2 2810 2855 44.89 2.2 0.6 1,2,4,7

3 3774 3869 94.7 2 0.6 1,3,4,5,7

4 5180 5187 7.18 1.8 0.6 1,2,4,7

5 7394 7405 10.54 1.6 0.6 1,2,4,7

6 7811 7867 55.66 2 0.6 1,2,4,7

7 7895 7926 31.42 2 0.6 1,2,4,7


DETAILS OF JUNCTION
Road Name : Hrangchalkawn to Lunglei Appendix - IIF
Section : Dt of Survey :15.09.09 to 20.09.09
Location Crossing
S.No Link Type Left/Right/Cross
in Km
1 Lawngtlai,Lunglei, Saiha, Polytecnic Road 0 Y - Junction Right
2 Polytecnic Road 1.52 Y - Junction Right
3 Theiriat Shortcut 3.09 Y - Junction Left
4 Theiriat Shortcut 4.89 Y - Junction Left
5 Way to Heliped 4.965 Y - Junction Left
6 Heliped,Demagri,Lunglei, Assam Rifle 5.66 X - Junction Left
7 Lunglei Radio Station Road 7.095 Y - Junction Left
8 7 Nos of link road with in the village portion
DETAILS OF VILLAGE & IMPORTANT LAND MARK

Road Name : Hrangchalkawn to Lunglei Appendix - IIG


Section : Dt of Survey :15.09.09 to 20.09.09

Sr.No From To Village Name


1.00 0.00 2.10 Hrangchalkawn
2.00 2.10 4.60 Theiriat
3.00 4.60 5.47 Sethlun
4.00 5.47 7.10 Lunglawn
5.00 7.10 8.36 Lunglei
Important Land Mark
1.00 0.00 1.47 Police Out Post
2.00 1.47 1.49 PowerHouse
3.00 3.07 3.09 Small Market
4.00 5.00 5.04 Church
5.00 5.24 5.25 Church
6.00 5.60 5.63 Assam Rifle
7.00 5.67 6.80 Assam Rifle
8.00 8.25 8.29 Petrol Pump
DETAILS OF UTILITY
Road Name : Hrangchalkawn to Lunglei Appendix - IH
Section : Dt of Survey :15.09.09 to 20.09.09
SL.No Chainage Chainage
Description Remaks SL.No. Description Remaks
. in m in m
1 27 Electric Pole Valley Side 95 3677 Telephone Pole Valley Side
2 59 Electric Pole Valley Side 96 3791 Electric Pole Valley Side
3 103 Electric Pole Valley Side 97 4013 Electric Pole Valley Side
3 141 Electric Pole Valley Side 98 4036 FENCING Valley Side
4 176 Electric Pole Valley Side 99 4639 Electric Pole Valley Side
5 219 Electric Pole Valley Side 100 4676 Electric Pole Valley Side
6 258 Electric Pole Valley Side 101 4719 Electric Pole Valley Side
7 338 Electric Pole Valley Side 102 4772 Electric Pole Valley Side
8 394 Electric Pole Valley Side 103 4806 Electric Pole Valley Side
9 447 Electric Pole Valley Side 104 4812 FENCING Valley Side
10 463 FENCING Valley Side 105 4891 Electric Pole Valley Side
11 1436 4Electric Pole Valley Side 106 4891 Telephone Pole Valley Side
12 1474 2Electric Pole Valley Side 107 4903 Telephone Pole Valley Side
13 1516 3Electric Pole Valley Side 108 4909 Electric Pole Valley Side
14 1565 Telephone Pole Valley Side 109 4921 Telephone Pole Valley Side
15 1597 Telephone Pole Valley Side 110 4921 Electric Pole Valley Side
16 1622 Telephone Pole Hill Side 111 4974 FENCING Valley Side
17 1680 Telephone Pole Valley Side 112 5000 Electric Pole Valley Side
18 1724 Telephone Pole Valley Side 113 5049 Electric Pole Valley Side
19 1774 Telephone Pole Valley Side 114 5138 Electric Pole Valley Side
20 1797 Telephone Pole Valley Side 115 5201 Electric Pole Hill Side
21 1814 Telephone Pole Valley Side 116 5230 FENCING Valley Side
22 1832 Telephone Pole Valley Side 117 5240 Electric Pole Valley Side
23 1860 Telephone Pole Valley Side 118 5300 Electric Pole Valley Side
24 1979 Telephone Pole Valley Side 119 5416 Electric Pole Valley Side
25 2018 Telephone Pole Valley Side 120 5461 Electric Pole Valley Side
26 2036 FFENCING Valley Side 121 5518 Electric Pole Valley Side
27 2068 Electric Pole Valley Side 122 5639 Electric Pole Valley Side
28 2068 Telephone Pole Valley Side 123 5639 Telephone Pole Valley Side
29 2113 Electric Pole Valley Side 124 5659 Telephone Pole Valley Side
30 2157 Electric Pole Valley Side 125 5688 Electric Pole Valley Side
31 2204 Electric Pole Valley Side 126 5715 Electric Pole Valley Side
32 2244 DRAIN Hill Side 127 5755 Electric Pole Valley Side
33 2248 Electric Pole Hill Side 128 5822 Electric Pole Hill Side
34 2248 Telephone Pole Valley Side 129 5844 Electric Pole Valley Side
35 2249 FENCING Valley Side 130 5856 Electric Pole Hill Side
36 2432 DRAIN Hill Side 131 5972 Electric Pole Valley Side
37 2448 Electric Pole Valley Side 132 6014 Electric Pole Valley Side
38 2467 DRAIN Hill Side 133 6058 Electric Pole Valley Side
39 2478 Electric Pole Valley Side 134 6120 Telephone Pole Valley Side
DETAILS OF UTILITY
Road Name : Hrangchalkawn to Lunglei Appendix - IH
Section : Dt of Survey :15.09.09 to 20.09.09
SL.No Chainage Chainage
Description Remaks SL.No. Description Remaks
. in m in m
40 2496 DRAIN Hill Side 135 6218 Electric Pole Valley Side
41 2519 Telephone Pole Valley Side 136 6255 Electric Pole Valley Side
42 2529 Electric Pole Valley Side 137 6266 Electric Pole Valley Side
43 2573 Electric Pole Valley Side 138 6315 Electric Pole Hill Side
44 2573 Telephone Pole Valley Side 139 6351 Electric Pole Valley Side
45 2612 Telephone Pole Valley Side 140 6379 Electric Pole Valley Side
46 2631 Electric Pole Valley Side 141 6558 Electric Pole Valley Side
47 2669 Electric Pole Valley Side 142 6541 Electric Pole Valley Side
48 2686 Telephone Pole Valley Side 143 6686 FENCING Valley Side
49 2709 Telephone Pole Valley Side 144 6723 Electric Pole Valley Side
50 2709 Electric Pole Valley Side 145 6761 Electric Pole Valley Side
51 2720 Telephone Pole Valley Side 146 6826 Electric Pole Valley Side
52 2754 Telephone Pole Valley Side 147 6910 Electric Pole Valley Side
53 2810 Electric Pole Valley Side 148 6951 Electric Pole Valley Side
54 2823 Telephone Pole Valley Side 149 6987 Electric Pole Valley Side
55 2837 Telephone Pole Valley Side 150 7030 Electric Pole Valley Side
56 2854 Electric Pole Valley Side 151 7060 Electric Pole Valley Side
57 2875 Electric Pole Valley Side 152 7106 Electric Pole Valley Side
58 2903 Electric Pole Valley Side 153 7151 Electric Pole Valley Side
59 2927 Telephone Pole Valley Side 154 7197 Electric Pole Hill Side
60 2945 Electric Pole Valley Side 155 7231 Electric Pole Valley Side
61 2945 Telephone Pole Valley Side 156 7260 Electric Pole Valley Side
62 2945 FENCING Valley Side 157 7295 Electric Pole Valley Side
63 2955 FENCING Valley Side 158 7336 Electric Pole Valley Side
64 2973 Telephone Pole Valley Side 159 7377 Electric Pole Valley Side
65 2973 Electric Pole Valley Side 160 7416 Electric Pole Valley Side
66 2990 Electric Pole Valley Side 161 7405 DRAIN Valley Side
67 3001 FENCING Valley Side 162 7427 FENCING Valley Side
68 3010 Electric Pole Valley Side 163 7450 Electric Pole Valley Side
69 3124 Telephone Pole Valley Side 164 7450 Telephone Pole Valley Side
70 3088 Telephone Pole Valley Side 165 7491 DRAIN Valley Side
71 3133 Electric Pole&T Valley Side 166 7530 Electric Pole Valley Side
72 3148 FENCING Valley Side 167 7607 DRAIN Valley Side
73 3174 Electric Pole Valley Side 168 7656 Electric Pole Valley Side
74 3147 DRAIN Valley Side 169 7656 Telephone Pole Valley Side
75 3221 Electric Pole Valley Side 170 7673 DRAIN Valley Side
76 3253 Telephone Pole Valley Side 171 7708 Telephone Pole Valley Side
77 3267 Electric Pole Valley Side 172 7775 Electric Pole Valley Side
78 3302 Telephone Pole Valley Side 173 7804 Electric Pole Hill Side
79 3309 Electric Pole Valley Side 174 7843 Electric Pole Valley Side
80 3336 Telephone Pole Valley Side 175 7859 Electric Pole Valley Side
81 3361 Telephone Pole Valley Side 176 7938 Electric Pole Valley Side
DETAILS OF UTILITY
Road Name : Hrangchalkawn to Lunglei Appendix - IH
Section : Dt of Survey :15.09.09 to 20.09.09
SL.No Chainage Chainage
Description Remaks SL.No. Description Remaks
. in m in m
82 3361 Electric Pole Valley Side 177 7972 Electric Pole Valley Side
83 3400 Telephone Pole Valley Side 178 8004 Electric Pole Valley Side
84 3409 Electric Pole Valley Side 179 8021 Electric Pole Hill Side
85 3425 Telephone Pole Valley Side 180 8063 Electric Pole Valley Side
86 3439 Electric Pole Valley Side 181 8085 Electric Pole Hill Side
87 3478 Telephone Pole Valley Side 182 8116 Electric Pole Valley Side
88 3482 Electric Pole Valley Side 183 8161 Electric Pole Hill Side
89 3504 Telephone Pole Valley Side 184 8191 Electric Pole Valley Side
90 3531 Telephone Pole Valley Side 185 8225 Electric Pole Hill Side
91 3545 Electric Pole Valley Side 186 8253 Electric Pole Valley Side
92 3573 Telephone Pole Valley Side 187 8287 2Telephone Pole Valley Side
93 3601 Electric Pole Valley Side 188 8304 Electric Pole Hill Side
94 3601 Telephone Pole Valley Side 189 8334 Electric Pole Hill Side
ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
0 0.100 Hilly Fall Built Up Lunglei 8.00 Flexible PC 4.70 Soil 0.50 N/A N/A 13 very poor condition
0.100 0.200 Hilly Fall Built Up Lunglei 10.50 Flexible PC 4.00 Soil 1.00 N/A N/A 15 very poor condition
0.200 0.400 Hilly Fall Built Up Lunglei 9.00 Flexible PC 4.30 Soil 0.70 N/A N/A 15 very poor condition
0.400 0.600 Hilly Fall Built Up Lunglei 8.00 Flexible PC 4.00 Soil 0.80 N/A N/A 15 very poor condition
0.600 0.800 Hilly Fall Built Up Lunglei 11.00 Flexible PC 4.50 Soil 0.90 N/A N/A 15 very poor condition
0.800 1.000 Hilly Fall Built Up Lunglei 9.80 Flexible PC 4.10 Soil 0.70 N/A N/A 15 very poor condition
1.000 1.200 Hilly Fall Built Up Lunglei 10.30 Flexible PC 4.30 Soil 0.90 N/A N/A 15 very poor condition
1.200 1.400 Hilly Fall Built Up Lunglei 10.80 Flexible PC 4.00 Soil 1.00 N/A N/A 15 very poor condition
1.400 1.600 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.00 Soil 3.00 N/A N/A 15 very poor condition
1.600 1.800 Hilly Fall Agri Lunglei 9.00 Flexible PC 3.00 Soil 1.00 N/A N/A 15 very poor condition
1.800 2.000 Hilly Fall Agri Lunglei 9.00 Flexible PC 3.50 Soil 1.20 N/A N/A 15 very poor condition
2.000 2.200 Hilly Fall Agri Lunglei 8.90 Flexible PC 3.40 Soil 1.10 N/A N/A 15 very poor condition
2.200 2.400 Hilly Fall Agri Lunglei 12.00 Flexible PC 4.40 Soil 1.30 N/A N/A 15 poor and undulation
2.400 2.600 Hilly Fall Agri Lunglei 13.00 Flexible PC 4.30 Soil 2.00 N/A N/A 15 poor and undulation
2.600 2.800 Hilly Fall Agri Lunglei 12.00 Flexible PC 3.30 Soil 2.10 N/A N/A 15 poor and undulation
2.800 3.000 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.50 Soil 2.30 N/A N/A 15 poor and undulation
3.000 3.200 Hilly Fall Agri Lunglei 13.00 Flexible PC 4.00 Soil 2.00 N/A N/A 15 poor and undulation
3.200 3.400 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.20 Soil 1.20 N/A N/A 15 poor and undulation
3.400 3.600 Hilly Fall Agri Lunglei 11.00 Flexible PC 3.30 Soil 2.00 N/A N/A 15 poor and undulation
3.600 3.800 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.30 Soil 2.50 N/A N/A 15 poor and undulation
3.800 4.000 Hilly Fall Agri Lunglei 9.50 Flexible PC 3.30 Soil 2.00 N/A N/A 15 poor and undulation
4.000 4.200 Hilly Fall Agri Lunglei 9.00 Flexible PC 3.20 Soil 2.10 N/A N/A 15 poor and undulation
4.200 4.400 Hilly Fall Agri Lunglei 8.00 Flexible PC 3.30 Soil 2.50 N/A N/A 12 very poor condition
4.400 4.600 Hilly Fall Agri Lunglei 8.20 Flexible PC 3.30 Soil 1.80 N/A N/A 12 very poor condition
4.600 4.800 Hilly Fall Agri Lunglei 10.10 Flexible PC 3.40 Soil 1.50 N/A N/A 12 very poor condition
4.800 5.000 Hilly Fall Agri Lunglei 9.80 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
5.000 5.200 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.50 Soil 2.00 N/A N/A 12 poor and undulation
5.200 5.400 Hilly Fall Agri Lunglei 9.00 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
5.400 5.600 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.30 Soil 2.10 N/A N/A 12 poor and undulation
5.600 5.800 Hilly Fall Agri Lunglei 10.20 Flexible PC 3.80 Soil 1.50 N/A N/A 12 poor and undulation
5.800 6.000 Hilly Fall Agri Lunglei 9.10 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
6.000 6.200 Hilly Fall Agri Lunglei 8.00 Flexible PC 3.70 Soil 1.50 N/A N/A 12 poor and undulation
6.200 6.400 Hilly Fall Agri Lunglei 11.00 Flexible PC 3.30 Soil 3.00 N/A N/A 12 poor and undulation
6.400 6.600 Hilly Fall Agri Lunglei 12.00 Flexible PC 4.40 Soil 1.80 N/A N/A 12 poor and undulation
6.600 6.800 Hilly Fall Agri Lunglei 8.50 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
6.800 7.000 Hilly Fall Agri Lunglei 7.30 Flexible PC 3.90 Soil 0.90 N/A N/A 12 poor and undulation
7.000 7.200 Hilly Fall Agri Lunglei 10.00 Flexible PC 3.60 Soil 1.40 N/A N/A 12 poor and undulation
7.200 7.400 Hilly Fall Agri Lunglei 7.50 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
7.400 7.600 Hilly Fall Agri Lunglei 9.00 Flexible PC 4.00 Soil 0.90 N/A N/A 12 poor

Surveyed by Prepared by Checked by Page 1 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
7.600 7.800 Hilly Fall Agri Lunglei 8.70 Flexible PC 4.40 Soil 1.10 N/A N/A 12 poor
7.800 8.000 Hilly Fall Agri Lunglei 9.50 Flexible PC 3.80 Soil 1.30 N/A N/A 12 poor
8.000 8.200 Hilly Fall Agri Lunglei 10.00 Flexible PC 4.10 Soil 1.20 N/A N/A 12 poor
8.200 8.400 Hilly Fall Agri Lunglei 9.50 Flexible PC 3.80 Soil 2.00 N/A N/A 12 poor
8.400 8.600 Hilly Fall Agri Lunglei 6.50 Flexible PC 3.20 Soil 1.40 N/A N/A 12 poor
8.600 8.800 Hilly Fall Agri Lunglei 7.20 Flexible PC 4.00 Soil 2.50 N/A N/A 12 poor and undulation
8.800 9.000 Hilly Fall Agri Lunglei 8.20 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
9.000 9.200 Hilly Fall Agri Lunglei 6.90 Flexible PC 3.70 Soil 0.50 N/A N/A 12 poor and undulation
9.200 9.400 Hilly Fall Agri Lunglei 8.60 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
9.400 9.600 Hilly Fall Agri Lunglei 9.00 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
9.600 9.800 Hilly Fall Agri Lunglei 8.50 Flexible PC 3.90 Soil 1.20 N/A N/A 12 poor and undulation
9.800 10.000 Hilly Fall Agri Lunglei 7.70 Flexible PC 3.90 Soil 1.10 N/A N/A 12 poor and undulation
10.000 10.200 Hilly Fall Agri Lunglei 8.10 Flexible PC 3.70 Soil 0.90 N/A N/A 12 poor and undulation
10.200 10.400 Hilly Fall Agri Lunglei 8.20 Flexible PC 3.80 Soil 1.20 N/A N/A 12 poor
10.400 10.600 Hilly Fall Agri Lunglei 7.90 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor
10.600 10.800 Hilly Fall Agri Lunglei 8.00 Flexible PC 3.90 Soil 1.00 N/A N/A 12 poor
10.800 11.000 Hilly Fall Agri Lunglei 9.30 Flexible PC 4.50 Soil 1.20 N/A N/A 12 poor
11.000 11.200 Hilly Fall Agri Lunglei 9.10 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor
11.200 11.400 Hilly Fall Agri Lunglei 8.30 Flexible PC 4.10 Soil 0.60 N/A N/A 12 poor
11.400 11.600 Hilly Fall Agri Lunglei 7.80 Flexible PC 3.70 Soil 1.20 N/A N/A 12 poor
11.600 11.800 Hilly Fall Agri Lunglei 7.30 Flexible PC 3.20 Soil 1.30 N/A N/A 12 poor and undulation
11.800 12.000 Hilly Fall Agri Lunglei 7.90 Flexible PC 3.70 Soil 2.00 N/A N/A 12 poor and undulation
12.000 12.200 Hilly Fall Agri Lunglei 8.40 Flexible PC 3.60 Soil 1.80 N/A N/A 15 poor and undulation
12.200 12.400 Hilly Fall Agri Lunglei 8.50 Flexible PC 4.20 Soil 0.60 N/A N/A 15 poor and undulation
12.400 12.600 Hilly Fall Agri Lunglei 6.90 Flexible PC 4.10 Soil 0.90 N/A N/A 15 poor and undulation
12.600 12.800 Hilly Fall Agri Lunglei 8.60 Flexible PC 4.50 Soil 1.20 N/A N/A 15 poor and undulation
12.800 13.000 Hilly Fall Built Up Hauruang 8.50 Flexible PC 3.70 Soil 1.10 N/A N/A 15 poor and undulation
13.000 13.200 Hilly Fall Built Up Hauruang 8.90 Flexible PC 3.50 Soil 2.00 N/A N/A 15 poor and undulation
13.200 13.400 Hilly Fall Built Up Hauruang 8.90 Flexible PC 4.30 Soil 1.80 N/A N/A 15 poor and undulation
13.400 13.600 Hilly Fall Built Up Hauruang 8.00 Flexible PC 3.90 Soil 1.00 N/A N/A 15 poor and undulation
13.600 13.800 Hilly Fall Built Up Hauruang 8.50 Flexible PC 3.50 Soil 1.20 N/A N/A 15 poor and undulation
13.800 14.000 Hilly Fall Built Up Hauruang 7.70 Flexible PC 4.00 Soil 1.10 N/A N/A 15 poor and undulation
14.000 14.200 Hilly Fall Built Up Hauruang 6.00 Flexible PC 4.00 Soil 0.90 N/A N/A 15 poor and undulation
14.200 14.400 Hilly Fall Built Up Hauruang 8.00 Flexible PC 3.30 Soil 0.80 N/A N/A 15 poor and undulation
14.400 14.600 Hilly Fall Built Up Hauruang 6.60 Flexible PC 3.70 Soil 1.00 N/A N/A 15 poor and undulation
14.600 14.800 Hilly Fall Built Up Hauruang 8.50 Flexible PC 4.80 Soil 1.50 N/A N/A 15 poor and undulation
14.800 15.000 Hilly Fall Agri Hauruang 9.00 Flexible PC 3.70 Soil 1.20 N/A N/A 15 poor and undulation
15.000 15.200 Hilly Fall Agri Hauruang 8.50 Flexible PC 3.60 Soil 2.00 N/A N/A 15 poor and undulation
15.200 15.400 Hilly Fall Agri Hauruang 8.40 Flexible PC 4.40 Soil 1.00 N/A N/A 15 poor and undulation

Surveyed by Prepared by Checked by Page 2 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
15.400 15.600 Hilly Fall Agri Hauruang 9.00 Flexible PC 4.50 Soil 1.10 N/A N/A 15 poor and undulation
15.600 15.800 Hilly Fall Agri Hauruang 8.30 Flexible PC 4.20 Soil 1.80 N/A N/A 15 poor and undulation
15.800 16.000 Hilly Fall Agri Hauruang 8.20 Flexible PC 4.10 Soil 0.90 N/A N/A 15 poor and undulation
16.000 16.200 Hilly Fall Agri Hauruang 7.30 Flexible PC 4.00 Soil 0.50 N/A N/A 15 poor and undulation
16.200 16.400 Hilly Fall Agri Hauruang 7.90 Flexible PC 4.30 Soil 0.70 N/A N/A 15 poor and undulation
16.400 16.600 Hilly Fall Agri Hauruang 9.10 Flexible PC 4.60 Soil 1.20 N/A N/A 15 poor and undulation
16.600 16.800 Hilly Fall Agri Hauruang 10.00 Flexible PC 4.00 Soil 1.10 N/A N/A 15 poor and undulation
16.800 17.000 Hilly Fall Agri Hauruang 10.20 Flexible PC 4.10 Soil 1.80 N/A N/A 15 poor and undulation
17.000 17.200 Hilly Fall Agri Hauruang 8.50 Flexible PC 4.60 Soil 1.20 N/A N/A 15 poor and undulation
17.200 17.400 Hilly Fall Agri Hauruang 7.80 Flexible PC 3.90 Soil 0.90 N/A N/A 15 poor and undulation
17.400 17.600 Hilly Fall Agri Hauruang 11.00 Flexible PC 4.20 Soil 2.00 N/A N/A 15 poor and undulation
17.600 17.800 Hilly Fall Agri Hauruang 9.00 Flexible PC 4.30 Soil 1.30 N/A N/A 15 poor and undulation
17.800 18.000 Hilly Fall Agri Hauruang 7.50 Flexible PC 3.90 Soil 1.20 N/A N/A 15 poor and undulation
18.000 18.200 Hilly Fall Agri Hauruang 9.40 Flexible PC 4.20 Soil 1.30 N/A N/A 15 poor and undulation
18.200 18.400 Hilly Fall Agri Hauruang 9.20 Flexible PC 4.10 Soil 1.10 N/A N/A 15 poor and undulation
18.400 18.600 Hilly Fall Agri Hauruang 8.70 Flexible PC 4.20 Soil 1.80 N/A N/A 15 poor and undulation
18.600 18.800 Hilly Fall Agri Hauruang 7.90 Flexible PC 4.10 Soil 0.90 N/A N/A 15 poor and undulation
18.800 19.000 Hilly Fall Forest Hauruang 7.70 Flexible PC 4.00 Soil 0.50 N/A N/A 15 poor and undulation
19.000 19.200 Hilly Fall Forest Hauruang 10.80 Flexible PC 4.60 Soil 2.00 N/A N/A 15 poor and undulation
19.200 19.400 Hilly Fall Forest Hauruang 11.20 Flexible PC 4.30 Soil 1.80 N/A N/A 15 poor and undulation
19.400 19.600 Hilly Fall Forest Hauruang 8.20 Flexible PC 4.10 Soil 1.50 N/A N/A 15 poor and undulation
19.600 19.800 Hilly Fall Forest Hauruang 7.60 Flexible PC 4.20 Soil 1.20 N/A N/A 15 poor and undulation
19.800 20.000 Hilly Fall Forest Hauruang 11.10 Flexible PC 4.60 Soil 1.10 N/A N/A 15 poor and undulation
20.000 20.200 Hilly Fall Forest Hauruang 7.80 Flexible PC 4.10 Soil 1.00 N/A N/A 15 poor and undulation
20.200 20.400 Hilly Fall Forest Hauruang 11.80 Flexible PC 4.20 Soil 2.10 N/A N/A 15 poor and undulation
20.400 20.600 Hilly Fall Forest Hauruang 7.90 Flexible PC 3.90 Soil 0.90 N/A N/A 15 poor and undulation
20.600 20.800 Hilly Fall Forest Hauruang 8.70 Flexible PC 4.00 Soil 1.20 N/A N/A 15 poor and undulation
20.800 21.000 Hilly Fall Forest Hauruang 8.40 Flexible PC 4.10 Soil 1.20 N/A N/A 15 poor and undulation
21.000 21.200 Hilly Fall Forest Hauruang 8.20 Flexible PC 4.20 Soil 2.00 N/A N/A 12 poor and undulation
21.200 21.400 Hilly Fall Forest Hauruang 8.30 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
21.400 21.600 Hilly Fall Forest Hauruang 8.40 Flexible PC 3.80 Soil 1.60 N/A N/A 12 poor and undulation
21.600 21.800 Hilly Fall Forest Hauruang 7.90 Flexible PC 3.70 Soil 1.80 N/A N/A 12 poor and undulation
21.800 22.000 Hilly Fall Forest Hauruang 7.80 Flexible PC 4.00 Soil 1.00 N/A N/A 12 poor and undulation
22.000 22.200 Hilly Fall Forest Hauruang 8.80 Flexible PC 3.40 Soil 2.10 N/A N/A 12 poor and undulation
22.200 22.400 Hilly Fall Forest Hauruang 8.50 Flexible PC 4.00 Soil 0.90 N/A N/A 12 poor and undulation
22.400 22.600 Hilly Fall Forest Hauruang 8.30 Flexible PC 3.90 Soil 1.20 N/A N/A 12 poor and undulation
22.600 22.800 Hilly Fall Forest Hauruang 9.60 Flexible PC 4.00 Soil 0.90 N/A N/A 12 poor and undulation
22.800 23.000 Hilly Fall Forest Hauruang 9.40 Flexible PC 4.00 Soil 1.10 N/A N/A 12 poor and undulation
23.000 23.200 Hilly Fall Forest Hauruang 10.20 Flexible PC 4.10 Soil 1.50 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 3 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
23.200 23.400 Hilly Fall Forest Hauruang 7.80 Flexible PC 4.20 Soil 0.90 N/A N/A 12 poor and undulation
23.400 23.600 Hilly Fall Forest Hauruang 8.70 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
23.600 23.800 Hilly Fall Forest Hauruang 9.20 Flexible PC 3.80 Soil 1.00 N/A N/A 12 poor and undulation
23.800 24.000 Hilly Fall Forest Hauruang 10.20 Flexible PC 4.30 Soil 1.20 N/A N/A 12 poor and undulation
24.000 24.200 Hilly Fall Forest Hauruang 7.20 Flexible PC 3.80 Soil 1.00 N/A N/A 12 poor and undulation
24.200 24.400 Hilly Fall Forest Hauruang 8.50 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
24.400 24.600 Hilly Fall Forest Hauruang 7.90 Flexible PC 3.20 Soil 0.90 N/A N/A 12 poor and undulation
24.600 24.800 Hilly Fall Forest Hauruang 7.80 Flexible PC 4.00 Soil 0.90 N/A N/A 12 poor and undulation
24.800 25.000 Hilly Fall Built Up Pachang 9.10 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
25.000 25.200 Hilly Fall Built Up Pachang 8.20 Flexible PC 4.20 Soil 0.80 N/A N/A 12 poor and undulation
25.200 25.400 Hilly Fall Built Up Pachang 7.80 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
25.400 25.600 Hilly Fall Built Up Pachang 8.00 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
25.600 25.800 Hilly Fall Built Up Pachang 9.10 Flexible PC 4.10 Soil 1.30 N/A N/A 12 poor and undulation
25.800 26.000 Hilly Fall Built Up Pachang 10.50 Flexible PC 4.20 Soil 1.50 N/A N/A 12 poor and undulation
26.000 26.200 Hilly Fall Built Up Pachang 7.90 Flexible PC 3.90 Soil 0.90 N/A N/A 12 poor and undulation
26.200 26.400 Hilly Fall Built Up Pachang 11.20 Flexible PC 4.10 Soil 1.20 N/A N/A 12 poor and undulation
26.400 26.600 Hilly Fall Built Up Pachang 10.80 Flexible PC 4.30 Soil 1.00 N/A N/A 12 poor and undulation
26.600 26.800 Hilly Fall Built Up Pachang 11.50 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
26.800 27.000 Hilly Fall Agri Pachang 7.80 Flexible PC 4.00 Soil 0.90 N/A N/A 12 poor and undulation
27.000 27.200 Hilly Fall Agri Pachang 10.10 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
27.200 27.400 Hilly Fall Agri Pachang 10.50 Flexible PC 3.80 Soil 1.20 N/A N/A 12 poor and undulation
27.400 27.600 Hilly Fall Agri Pachang 8.10 Flexible PC 3.60 Soil 1.10 N/A N/A 12 poor and undulation
27.600 27.800 Hilly Fall Agri Pachang 7.90 Flexible PC 3.70 Soil 1.20 N/A N/A 12 poor and undulation
27.800 28.000 Hilly Fall Agri Pachang 7.80 Flexible PC 4.10 Soil 1.30 N/A N/A 12 poor and undulation
28.000 28.200 Hilly Fall Agri Pachang 7.10 Flexible PC 3.60 Soil 1.00 N/A N/A 12 poor and undulation
28.200 28.400 Hilly Fall Agri Pachang 10.50 Flexible PC 3.70 Soil 2.00 N/A N/A 12 poor and undulation
28.400 28.600 Hilly Fall Agri Pachang 8.90 Flexible PC 4.10 Soil 1.20 N/A N/A 12 poor and undulation
28.600 28.800 Hilly Fall Agri Pachang 7.90 Flexible PC 3.90 Soil 1.30 N/A N/A 12 poor and undulation
28.800 29.000 Hilly Fall Agri Pachang 9.20 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
29.000 29.200 Hilly Fall Agri Pachang 8.70 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
29.200 29.400 Hilly Fall Agri Pachang 10.80 Flexible PC 3.90 Soil 1.00 N/A N/A 12 poor and undulation
29.400 29.600 Hilly Fall Agri Pachang 11.40 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
29.600 29.800 Hilly Fall Agri Pachang 10.70 Flexible PC 4.20 Soil 1.30 N/A N/A 12 poor and undulation
29.800 30.000 Hilly Fall Agri Pachang 9.80 Flexible PC 3.60 Soil 1.30 N/A N/A 12 poor and undulation
30.000 30.200 Hilly Fall Agri Pachang 7.90 Flexible PC 4.10 Soil 1.00 N/A N/A 12 poor and undulation
30.200 30.400 Hilly Fall Forest Pachang 8.60 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
30.400 30.600 Hilly Fall Forest Pachang 9.00 Flexible PC 3.80 Soil 1.20 N/A N/A 12 poor and undulation
30.600 30.800 Hilly Fall Forest Pachang 11.20 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
30.800 31.000 Hilly Fall Forest Pachang 7.70 Flexible PC 3.40 Soil 1.10 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 4 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
31.000 31.200 Hilly Fall Forest Pachang 7.80 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
31.200 31.400 Hilly Fall Forest Pachang 6.80 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
31.400 31.600 Hilly Fall Forest Pachang 9.70 Flexible PC 4.10 Soil 1.30 N/A N/A 12 poor and undulation
31.600 31.800 Hilly Fall Forest Pachang 9.20 Flexible PC 4.20 Soil 2.00 N/A N/A 12 poor and undulation
31.800 32.000 Hilly Fall Forest Pachang 11.10 Flexible PC 4.00 Soil 2.10 N/A N/A 12 poor and undulation
32.000 32.200 Hilly Fall Forest Pachang 7.60 Flexible PC 3.60 Soil 1.30 N/A N/A 12 poor and undulation
32.200 32.400 Hilly Fall Forest Pachang 7.80 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
32.400 32.600 Hilly Fall Forest Pachang 7.90 Flexible PC 3.30 Soil 1.10 N/A N/A 12 poor and undulation
32.600 32.800 Hilly Fall Forest Pachang 8.20 Flexible PC 3.80 Soil 1.20 N/A N/A 12 poor and undulation
32.800 33.000 Hilly Fall Forest Pachang 7.90 Flexible PC 3.40 Soil 1.10 N/A N/A 12 poor and undulation
33.000 33.200 Hilly Fall Forest Pachang 8.30 Flexible PC 3.50 Soil 1.50 N/A N/A 12 poor and undulation
33.200 33.400 Hilly Fall Forest Pachang 11.10 Flexible PC 4.10 Soil 2.00 N/A N/A 12 poor and undulation
33.400 33.600 Hilly Fall Forest Pachang 7.50 Flexible PC 4.10 Soil 1.50 N/A N/A 12 poor and undulation
33.600 33.800 Hilly Fall Forest Pachang 8.10 Flexible PC 4.00 Soil 1.40 N/A N/A 12 poor and undulation
33.800 34.000 Hilly Fall Forest Pachang 9.20 Flexible PC 3.70 Soil 2.10 N/A N/A 12 poor and undulation
34.000 34.200 Hilly Fall Agri Pachang 8.10 Flexible PC 4.10 Soil 2.20 N/A N/A 12 poor and undulation
34.200 34.400 Hilly Fall Agri Pachang 7.90 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor and undulation
34.400 34.600 Hilly Fall Agri Pachang 9.50 Flexible PC 4.10 Soil 1.50 N/A N/A 12 poor and undulation
34.600 34.800 Hilly Fall Agri Pachang 10.20 Flexible PC 3.70 Soil 1.10 N/A N/A 12 poor and undulation
34.800 35.000 Hilly Fall Agri Pachang 10.60 Flexible PC 3.50 Soil 1.80 N/A N/A 12 poor and undulation
35.000 35.200 Hilly Fall Agri Pachang 7.90 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
35.200 35.400 Hilly Fall Agri Pachang 8.80 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
35.400 35.600 Hilly Fall Agri Phairuang 10.20 Flexible PC 3.50 Soil 1.70 N/A N/A 12 poor and undulation
35.600 35.800 Hilly Fall Built Up Phairuang 7.20 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
35.800 36.000 Hilly Fall Built Up Phairuang 8.20 Flexible PC 3.70 Soil 1.20 N/A N/A 12 poor and undulation
36.000 36.200 Hilly Fall Built Up Phairuang 8.40 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
36.200 36.400 Hilly Fall Built Up Phairuang 7.90 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
36.400 36.600 Hilly Fall Built Up Phairuang 8.10 Flexible PC 3.60 Soil 1.50 N/A N/A 12 poor and undulation
36.600 36.800 Hilly Fall Built Up Phairuang 9.20 Flexible PC 3.70 Soil 1.30 N/A N/A 12 poor and undulation
36.800 37.000 Hilly Fall Built Up Phairuang 8.70 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
37.000 37.200 Hilly Fall Agri Phairuang 8.50 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
37.200 37.400 Hilly Fall Agri Phairuang 8.90 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
37.400 37.600 Hilly Fall Agri Phairuang 7.70 Flexible PC 3.60 Soil 1.10 N/A N/A 12 poor and undulation
37.600 37.800 Hilly Fall Agri Phairuang 7.90 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
37.800 38.000 Hilly Fall Agri Phairuang 8.10 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
38.000 38.200 Hilly Fall Agri Phairuang 8.30 Flexible PC 3.30 Soil 1.10 N/A N/A 12 poor and undulation
38.200 38.400 Hilly Fall Agri Phairuang 7.40 Flexible PC 3.60 Soil 1.30 N/A N/A 12 poor and undulation
38.400 38.600 Hilly Fall Agri Phairuang 7.60 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
38.600 38.800 Hilly Fall Agri Phairuang 7.80 Flexible PC 3.70 Soil 1.00 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 5 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
38.800 39.000 Hilly Fall Agri Phairuang 9.20 Flexible PC 3.80 Soil 1.40 N/A N/A 12 poor and undulation
39.000 39.200 Hilly Fall Agri Phairuang 8.30 Flexible PC 3.50 Soil 2.00 N/A N/A 12 poor and undulation
39.200 39.400 Hilly Fall Agri Phairuang 7.50 Flexible PC 3.60 Soil 1.00 N/A N/A 12 poor and undulation
39.400 39.600 Hilly Fall Agri Phairuang 9.10 Flexible PC 4.10 Soil 1.20 N/A N/A 12 poor and undulation
39.600 39.800 Hilly Fall Agri Phairuang 8.20 Flexible PC 3.90 Soil 1.30 N/A N/A 12 poor and undulation
39.800 40.000 Hilly Fall Forest Phairuang 8.10 Flexible PC 3.50 Soil 1.50 N/A N/A 12 poor and undulation
40.000 40.200 Hilly Fall Forest Phairuang 8.40 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
40.200 40.400 Hilly Fall Forest Phairuang 7.90 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
40.400 40.600 Hilly Fall Forest Phairuang 7.80 Flexible PC 3.70 Soil 1.80 N/A N/A 12 poor and undulation
40.600 40.800 Hilly Fall Forest Phairuang 8.90 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
40.800 41.000 Hilly Fall Forest Phairuang 8.40 Flexible PC 3.40 Soil 2.00 N/A N/A 12 poor and undulation
41.000 41.200 Hilly Fall Forest Phairuang 8.20 Flexible PC 3.90 Soil 1.10 N/A N/A 12 poor and undulation
41.200 41.400 Hilly Fall Forest Phairuang 8.50 Flexible PC 3.40 Soil 2.00 N/A N/A 12 poor and undulation
41.400 41.600 Hilly Fall Forest Phairuang 7.90 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor and undulation
41.600 41.800 Hilly Fall Agri Phairuang 8.00 Flexible PC 3.70 Soil 0.90 N/A N/A 12 poor and undulation
41.800 42.000 Hilly Fall Agri Phairuang 7.80 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
42.000 42.200 Hilly Fall Agri Phairuang 8.60 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
42.200 42.400 Hilly Fall Agri Phairuang 8.20 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
42.400 42.600 Hilly Fall Agri Phairuang 8.40 Flexible PC 3.40 Soil 1.60 N/A N/A 12 poor and undulation
42.600 42.800 Hilly Fall Agri Phairuang 10.20 Flexible PC 3.30 Soil 2.00 N/A N/A 12 poor and undulation
42.800 43.000 Hilly Fall Agri Phairuang 8.50 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
43.000 43.200 Hilly Fall Agri Phairuang 7.50 Flexible PC 3.20 Soil 1.00 N/A N/A 12 poor and undulation
43.200 43.400 Hilly Fall Agri Phairuang 7.20 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
43.400 43.600 Hilly Fall Built Up Rotlang 7.60 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
43.600 43.800 Hilly Fall Built Up Rotlang 7.50 Flexible PC 3. 4 Soil 1.40 N/A N/A 12 poor and undulation
43.800 44.000 Hilly Fall Built Up Rotlang 7.80 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor and undulation
44.000 44.200 Hilly Fall Built Up Rotlang 8.10 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
44.200 44.400 Hilly Fall Built Up Rotlang 8.20 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
44.400 44.600 Hilly Fall Built Up Rotlang 7.50 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
44.600 44.800 Hilly Fall Built Up Rotlang 8.40 Flexible PC 3.30 Soil 1.40 N/A N/A 12 poor and undulation
44.800 45.000 Hilly Fall Built Up Rotlang 8.70 Flexible PC 3.20 Soil 0.90 N/A N/A 12 poor and undulation
45.000 45.200 Hilly Fall Agri Lungsen 8.50 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
45.200 45.400 Hilly Fall Agri Lungsen 7.60 Flexible PC 3.40 Soil 1.60 N/A N/A 12 poor and undulation
45.400 45.600 Hilly Fall Agri Lungsen 7.90 Flexible PC 3.50 Soil 1.50 N/A N/A 12 poor and undulation
45.600 45.800 Hilly Fall Agri Lungsen 7.40 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
45.800 46.000 Hilly Fall Agri Lungsen 8.20 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
46.000 46.200 Hilly Fall Agri Lungsen 7.40 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor and undulation
46.200 46.400 Hilly Fall Agri Lungsen 7.50 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
46.400 46.600 Hilly Fall Agri Lungsen 7.50 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 6 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
46.600 46.800 Hilly Fall Agri Lungsen 7.40 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
46.800 47.000 Hilly Fall Agri Lungsen 8.10 Flexible PC 3.70 Soil 2.00 N/A N/A 12 poor and undulation
47.000 47.200 Hilly Fall Agri Lungsen 7.50 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
47.200 47.400 Hilly Fall Agri Lungsen 7.80 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
47.400 47.600 Hilly Rise Agri Lungsen 8.10 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
47.600 47.800 Hilly Rise Agri Lungsen 8.30 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
47.800 48.000 Hilly Rise Agri Lungsen 7.80 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
48.000 48.200 Hilly Rise Agri Lungsen 8.20 Flexible PC 3.70 Soil 1.30 N/A N/A 12 poor and undulation
48.200 48.400 Hilly Rise Agri Lungsen 7.30 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
48.400 48.600 Hilly Rise Agri Lungsen 7.20 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
48.600 48.800 Hilly Rise Agri Lungsen 7.50 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
48.800 49.000 Hilly Rise Agri Lungsen 8.00 Flexible PC 3.50 Soil 2.00 N/A N/A 12 poor and undulation
49.000 49.200 Hilly Rise Agri Lungsen 7.80 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
49.200 49.400 Hilly Agri Lungsen 8.20 Flexible PC 3.60 Soil 1.40 N/A N/A 12 poor and undulation
49.400 49.600 Hilly Rise Agri Lungsen 7.60 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
49.600 49.800 Hilly Rise Agri Lungsen 8.10 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
49.800 50.000 Hilly Rise Agri Lungsen 6.90 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
50.000 50.200 Hilly Rise Agri Lungsen 6.80 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
50.200 50.400 Hilly Rise Agri Lungsen 7.90 Flexible PC 4.10 Soil 1.00 N/A N/A 12 poor and undulation
50.400 50.600 Hilly Rise Agri Lungsen 7.50 Flexible PC 4.20 Soil 1.20 N/A N/A 12 poor and undulation
50.600 50.800 Hilly Rise Agri Lungsen 7.80 Flexible PC 4.30 Soil 1.00 N/A N/A 12 poor and undulation
50.800 51.000 Hilly Rise Agri Lungsen 9.10 Flexible PC 3.50 Soil 2.20 N/A N/A 12 poor and undulation
51.000 51.200 Hilly Rise Agri Lungsen 8.70 Flexible PC 3.40 Soil 1.80 N/A N/A 12 poor and undulation
51.200 51.400 Hilly Rise Agri Lungsen 7.90 Flexible PC 4.00 Soil 1.30 N/A N/A 12 poor and undulation
51.400 51.600 Hilly Rise Agri Lungsen 8.90 Flexible PC 3.90 Soil 1.00 N/A N/A 12 poor and undulation
51.600 51.800 Hilly Rise Agri Lungsen 7.50 Flexible PC 4.20 Soil 1.20 N/A N/A 12 poor and undulation
51.800 52.000 Hilly Rise Agri Lungsen 8.20 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
52.000 52.200 Hilly Rise Agri Lungsen 8.00 Flexible PC 3.40 Soil 1.80 N/A N/A 12 poor and undulation
52.200 52.400 Hilly Rise Agri Lungsen 9.10 Flexible PC 3.50 Soil 1.50 N/A N/A 12 poor and undulation
52.400 52.600 Hilly Rise Agri Lungsen 7.90 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
52.600 52.800 Hilly Rise Agri Lungsen 10.20 Flexible PC 3.50 Soil 2.50 N/A N/A 12 poor and undulation
52.800 53.000 Hilly Rise Agri Lungsen 8.60 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
53.000 53.200 Hilly Rise Agri Lungsen 8.30 Flexible PC 3.60 Soil 1.30 N/A N/A 12 poor and undulation
53.200 53.400 Hilly Rise Agri Lungsen 8.60 Flexible PC 3.50 Soil 2.10 N/A N/A 12 poor and undulation
53.400 53.600 Hilly Rise Agri Lungsen 8.90 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
53.600 53.800 Hilly Rise Agri Lungsen 9.20 Flexible PC 4.10 Soil 1.30 N/A N/A 12 poor and undulation
53.800 54.000 Hilly Rise Agri Lungsen 9.80 Flexible PC 3.60 Soil 2.00 N/A N/A 12 poor and undulation
54.000 54.200 Hilly Rise Agri Lungsen 8.20 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
54.200 54.400 Hilly Rise Built Up Lungsen 6.90 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 7 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
54.400 54.600 Hilly Rise Built Up Lungsen 8.30 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
54.600 54.800 Hilly Rise Built Up Lungsen 8.90 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
54.800 55.000 Hilly Rise Built Up Lungsen 7.80 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
55.000 55.200 Hilly Rise Built Up Lungsen 8.20 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
55.200 55.400 Hilly Rise Built Up Lungsen 7.60 Flexible PC 4.00 Soil 1.00 N/A N/A 12 poor and undulation
55.400 55.600 Hilly Rise Built Up Lungsen 7.20 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
55.600 55.800 Hilly Rise Built Up Lungsen 7.90 Flexible PC 4.10 Soil 1.20 N/A N/A 12 poor and undulation
55.800 56.000 Hilly Rise Built Up Lungsen 7.60 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
56.000 56.200 Hilly Rise Built Up Lungsen 8.40 Flexible PC 3.70 Soil 1.50 N/A N/A 12 poor and undulation
56.200 56.400 Hilly Fall Built Up Lungsen 6.20 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
56.400 56.600 Hilly Fall Built Up Lungsen 7.10 Flexible PC 4.10 Soil 1.10 N/A N/A 12 poor and undulation
56.600 56.800 Hilly Fall Built Up Lungsen 7.20 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
56.800 57.000 Hilly Fall Built Up Lungsen 9.10 Flexible PC 3.70 Soil 1.20 N/A N/A 12 poor and undulation
57.000 57.200 Hilly Fall Built Up Lungsen 9.80 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
57.200 57.400 Hilly Fall Agri Lungsen 7.80 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
57.400 57.600 Hilly Fall Agri Lungsen 8.10 Flexible PC 3.70 Soil 0.90 N/A N/A 12 poor and undulation
57.600 57.800 Hilly Fall Agri Lungsen 10.20 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
57.800 58.000 Hilly Fall Agri Lungsen 8.60 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
58.000 58.200 Hilly Fall Agri Lungsen 8.20 Flexible PC 4.00 Soil 2.00 N/A N/A 12 poor and undulation
58.200 58.400 Hilly Fall Agri Lungsen 7.80 Flexible PC 3.40 Soil 1.80 N/A N/A 12 poor and undulation
58.400 58.600 Hilly Fall Agri Lungsen 7.90 Flexible PC 4.10 Soil 1.50 N/A N/A 12 poor and undulation
58.600 58.800 Hilly Fall Agri Lungsen 8.20 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
58.800 59.000 Hilly Fall Agri Lungsen 8.00 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
59.000 59.200 Hilly Fall Agri Lungsen 8.90 Flexible PC 3.40 Soil 2.00 N/A N/A 12 poor and undulation
59.200 59.400 Hilly Fall Agri Lungsen 7.20 Flexible PC 3.30 Soil 1.40 N/A N/A 12 poor and undulation
59.400 59.600 Hilly Fall Agri Lungsen 7.00 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
59.600 59.800 Hilly Fall Agri Lungsen 7.50 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
59.800 60.000 Hilly Fall Agri Lungsen 7.40 Flexible PC 3.20 Soil 1.20 N/A N/A 12 poor and undulation
60.000 60.200 Hilly Fall Agri Lungsen 8.60 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
60.200 60.400 Hilly Fall Built Up Sihphir 7.90 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
60.400 60.600 Hilly Fall Built Up Sihphir 8.20 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
60.600 60.800 Hilly Fall Built Up Sihphir 8.10 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
60.800 61.000 Hilly Fall Agri Tuichawng 7.80 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
61.000 61.200 Hilly Fall Agri Tuichawng 8.10 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
61.200 61.400 Hilly Fall Agri Tuichawng 8.90 Flexible PC 3.30 Soil 1.80 N/A N/A 12 poor and undulation
61.400 61.600 Hilly Fall Agri Tuichawng 7.60 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
61.600 61.800 Hilly Fall Agri Tuichawng 7.50 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
61.800 62.000 Hilly Fall Agri Tuichawng 7.80 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
62.000 62.200 Hilly Fall Agri Tuichawng 8.20 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 8 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
62.200 62.400 Hilly Fall Agri Tuichawng 7.40 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
62.400 62.600 Hilly Fall Agri Tuichawng 7.50 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
62.600 62.800 Hilly Fall Agri Tuichawng 7.80 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
62.800 63.000 Hilly Fall Agri Tuichawng 10.20 Flexible PC 3.30 Soil 2.00 N/A N/A 12 poor and undulation
63.000 63.200 Hilly Fall Agri Tuichawng 7.90 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
63.200 63.400 Hilly Rise Agri Tuichawng 7.40 Flexible PC 3.30 Soil 1.10 N/A N/A 12 poor and undulation
63.400 63.600 Hilly Rise Agri Tuichawng 8.10 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
63.600 63.800 Hilly Rise Agri Tuichawng 7.90 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
63.800 64.000 Hilly Rise Agri Tuichawng 6.50 Flexible PC 3.20 Soil 0.90 N/A N/A 12 poor and undulation
64.000 64.200 Hilly Rise Agri Tuichawng 8.10 Flexible PC 3.30 Soil 1.80 N/A N/A 12 poor and undulation
64.200 64.400 Hilly Rise Agri Tuichawng 7.80 Flexible PC 3.20 Soil 1.40 N/A N/A 12 poor and undulation
64.400 64.600 Hilly Rise Agri Tuichawng 10.20 Flexible PC 4.10 Soil 1.20 N/A N/A 12 poor and undulation
64.600 64.800 Hilly Rise Agri Tuichawng 7.90 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
64.800 65.000 Hilly Rise Agri Tuichawng 8.10 Flexible PC 3.20 Soil 1.30 N/A N/A 12 poor and undulation
65.000 65.200 Hilly Rise Agri Tuichawng 8.30 Flexible PC 3.30 Soil 1.40 N/A N/A 12 poor and undulation
65.200 65.400 Hilly Rise Agri Tuichawng 7.80 Flexible PC 3.20 Soil 1.10 N/A N/A 12 poor and undulation
65.400 65.600 Hilly Rise Agri Tuichawng 7.70 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
65.600 65.800 Hilly Rise Agri Tuichawng 7.60 Flexible PC 3.30 Soil 1.80 N/A N/A 12 poor and undulation
65.800 66.000 Hilly Rise Agri Tuichawng 8.50 Flexible PC 3.20 Soil 1.10 N/A N/A 12 poor and undulation
66.000 66.200 Hilly Rise Agri Tuichawng 8.40 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
66.200 66.400 Hilly Fall Forest Tuichawng 9.20 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
66.400 66.600 Hilly Fall Forest Tuichawng 7.20 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
66.600 66.800 Hilly Fall Forest Tuichawng 7.60 Flexible PC 3.20 Soil 1.00 N/A N/A 12 poor and undulation
66.800 67.000 Hilly Fall Forest Tuichawng 8.20 Flexible PC 3.80 Soil 1.40 N/A N/A 12 poor and undulation
67.000 67.200 Hilly Fall Forest Tuichawng 6.90 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
67.200 67.400 Hilly Fall Forest Tuichawng 8.10 Flexible PC 3.30 Soil 1.60 N/A N/A 12 poor and undulation
67.400 67.600 Hilly Fall Forest Tuichawng 6.80 Flexible PC 3.20 Soil 1.50 N/A N/A 12 poor and undulation
67.600 67.800 Hilly Fall Forest Tuichawng 6.90 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
67.800 68.000 Hilly Fall Forest Tuichawng 8.80 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
68.000 68.200 Hilly Fall Forest Tuichawng 7.60 Flexible PC 3.30 Soil 1.10 N/A N/A 12 poor and undulation
68.200 68.400 Hilly Fall Agri Tuichawng 7.90 Flexible PC 3.20 Soil 1.20 N/A N/A 12 poor and undulation
68.400 68.600 Hilly Fall Agri Tuichawng 8.20 Flexible PC 3.10 Soil 1.40 N/A N/A 12 poor and undulation
68.600 68.800 Hilly Fall Agri Tuichawng 7.70 Flexible PC 3.20 Soil 1.20 N/A N/A 12 poor and undulation
68.800 69.000 Hilly Fall Agri Tuichawng 7.60 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
69.000 69.200 Hilly Fall Agri Tuichawng 7.80 Flexible PC 3.20 Soil 1.60 N/A N/A 12 poor and undulation
69.200 69.400 Hilly Fall Agri Tuichawng 7.70 Flexible PC 3.30 Soil 1.50 N/A N/A 12 poor and undulation
69.400 69.600 Hilly Fall Agri Tuichawng 8.40 Flexible PC 3.20 Soil 2.00 N/A N/A 12 poor and undulation
69.600 69.800 Hilly Fall Agri Tuichawng 7.10 Flexible PC 3.10 Soil 1.30 N/A N/A 12 poor and undulation
69.800 70.000 Hilly Fall Agri Tuichawng 8.30 Flexible PC 3.30 Soil 1.80 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 9 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
70.000 70.200 Hilly Fall Agri Tuichawng 9.20 Flexible PC 3.50 Soil 2.00 N/A N/A 12 poor and undulation
70.200 70.400 Hilly Fall Agri Tuichawng 10.80 Flexible PC 3.40 Soil 2.10 N/A N/A 12 poor and undulation
70.400 70.600 Hilly Fall Agri Tuichawng 8.9 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
70.600 70.800 Hilly Fall Agri Tuichawng 8.50 Flexible PC 3.70 Soil 1.30 N/A N/A 12 poor and undulation
70.800 71.000 Hilly Fall Built up Tuichawng 7.90 Flexible PC 3.40 Soil 2.00 N/A N/A 12 poor and undulation
71.000 71.200 Hilly Fall Built up Tuichawng 9.30 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
71.200 71.400 Hilly Fall Built up Tuichawng 8.60 Flexible PC 3.60 Soil 1.60 N/A N/A 12 poor and undulation
71.400 71.600 Hilly Fall Built up Tuichawng 7.10 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
71.600 71.800 Hilly Fall Built up Tuichawng 7.00 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
71.800 72.000 Hilly Fall Built up Tuichawng 7.90 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
72.000 72.200 Hilly Fall Built up Tuichawng 8.10 Flexible PC 3.50 Soil 1.80 N/A N/A 12 poor and undulation
72.200 72.400 Hilly Fall Built up Tuichawng 8.20 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
72.400 72.600 Hilly Fall Built up Tuichawng 6.90 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
72.600 72.800 Hilly Fall Built up Tuichawng 7.40 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
72.800 73.000 Hilly Fall Built up Tuichawng 8.60 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
73.000 73.200 Hilly Rise Agri Tuichawng 7.80 Flexible PC 3.60 Soil 1.30 N/A N/A 12 poor and undulation
73.200 73.400 Hilly Rise Agri Tuichawng 7.60 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
73.400 73.600 Hilly Rise Agri Tuichawng 8.20 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
73.600 73.800 Hilly Rise Agri Tuichawng 9.10 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
73.800 74.000 Hilly Fall Agri Tuichawng 6.90 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
74.000 74.200 Hilly Fall Agri Tuichawng 6.80 Flexible PC 3.20 Soil 1.20 N/A N/A 12 poor and undulation
74.200 74.400 Hilly Fall Agri Tuichawng 6.40 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
74.400 74.600 Hilly Fall Agri Tuichawng 5.80 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
74.600 74.800 Hilly Fall Agri Tuichawng 6.80 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
74.800 75.000 Hilly Fall Agri Tuichawng 7.90 Flexible PC 3.60 Soil 1.40 N/A N/A 12 poor and undulation
75.000 75.200 Hilly Fall Agri Tuichawng 8.40 Flexible PC 4.20 Soil 1.30 N/A N/A 12 poor and undulation
75.200 75.400 Hilly Fall Agri Tuichawng 8.30 Flexible PC 4.10 Soil 0.90 N/A N/A 12 poor and undulation
75.400 75.600 Hilly Fall Agri Tuichawng 8.60 Flexible PC 4.20 Soil 1.20 N/A N/A 12 poor and undulation
75.600 75.800 Hilly Fall Agri Tuichawng 6.80 Flexible PC 3.50 Soil 1.10 N/A N/A 12 poor and undulation
75.800 76.000 Hilly Fall Forest Tuichawng 10.80 Flexible PC 3.70 Soil 1.80 N/A N/A 12 poor and undulation
76.000 76.200 Hilly Fall Forest Tuichawng 7.80 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
76.200 76.400 Hilly Fall Forest Tuichawng 8.50 Flexible PC 3.60 Soil 1.30 N/A N/A 12 poor and undulation
76.400 76.600 Hilly Fall Forest Tuichawng 7.90 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
76.600 76.800 Hilly Fall Forest Tuichawng 8.10 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
76.800 77.000 Hilly Fall Forest Tuichawng 7.90 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor and undulation
77.000 77.200 Hilly Fall Forest Tuichawng 6.80 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
77.200 77.400 Hilly Fall Forest Tuichawng 7.40 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
77.400 77.600 Hilly Fall Forest Tuichawng 7.10 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
77.600 77.800 Hilly Fall Forest Tuichawng 9.20 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 10 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
77.800 78.000 Hilly Fall Forest Tuichawng 8.30 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
78.000 78.200 Hilly Fall Forest Tuichawng 7.40 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
78.200 78.400 Hilly Fall Forest Tuichawng 6.80 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
78.400 78.600 Hilly Fall Forest Tuichawng 7.80 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
78.600 78.800 Hilly Fall Forest Tuichawng 9.20 Flexible PC 3.40 Soil 1.60 N/A N/A 12 poor and undulation
78.800 79.000 Hilly Fall Forest Tuichawng 7.10 Flexible PC 3.30 Soil 2.00 N/A N/A 12 poor and undulation
79.000 79.200 Hilly Fall Forest Tuichawng 6.10 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
79.200 79.400 Hilly Fall Forest Tuichawng 6.40 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
79.400 79.600 Hilly Fall Forest Tuichawng 7.90 Flexible PC 3.30 Soil 1.10 N/A N/A 12 poor and undulation
79.600 79.800 Hilly Rise Forest Tuichawng 7.30 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
79.800 80.000 Hilly Rise Forest Tuichawng 7.50 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
80.000 80.200 Hilly Rise Forest Tuichawng 6.10 Flexible PC 3.30 Soil 1.40 N/A N/A 12 poor and undulation
80.200 80.400 Hilly Rise Forest Demagri 6.20 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
80.400 80.600 Hilly Rise Forest Demagri 6.90 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
80.600 80.800 Hilly Rise Forest Demagri 7.10 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
80.800 81.000 Hilly Rise Forest Demagri 6.30 Flexible PC 3.20 Soil 1.30 N/A N/A 12 poor and undulation
81.000 81.200 Hilly Rise Forest Demagri 6.20 Flexible PC 3.30 Soil 1.10 N/A N/A 12 poor and undulation
81.200 81.400 Hilly Rise Forest Demagri 8.20 Flexible PC 3.40 Soil 1.80 N/A N/A 12 poor and undulation
81.400 81.600 Hilly Rise Forest Demagri 8.90 Flexible PC 3.50 Soil 1.50 N/A N/A 12 poor and undulation
81.600 81.800 Hilly Rise Forest Demagri 10.80 Flexible PC 3.40 Soil 1.60 N/A N/A 12 poor and undulation
81.800 82.000 Hilly Rise Agri Demagri 7.80 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
82.000 82.200 Hilly Rise Agri Demagri 7.20 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
82.200 82.400 Hilly Rise Agri Demagri 7.90 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
82.400 82.600 Hilly Rise Agri Demagri 8.40 Flexible PC 3.60 Soil 1.80 N/A N/A 12 poor and undulation
82.600 82.800 Hilly Rise Agri Demagri 7.40 Flexible PC 3.20 Soil 1.20 N/A N/A 12 poor and undulation
82.800 83.000 Hilly Rise Agri Demagri 7.10 Flexible PC 3.30 Soil 1.40 N/A N/A 12 poor and undulation
83.000 83.200 Hilly Rise Agri Demagri 6.80 Flexible PC 3.40 Soil 1.00 N/A N/A 12 poor and undulation
83.200 83.400 Hilly Rise Agri Demagri 8.20 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
83.400 83.600 Hilly Rise Agri Demagri 8.40 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation
83.600 83.800 Hilly Rise Agri Demagri 6.90 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
83.800 84.000 Hilly Rise Agri Demagri 7.40 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
84.000 84.200 Hilly Rise Agri Demagri 8.20 Flexible PC 3.20 Soil 1.40 N/A N/A 12 poor and undulation
84.200 84.400 Hilly Rise Agri Demagri 7.50 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
84.400 84.600 Hilly Rise Agri Demagri 6.80 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
84.600 84.800 Hilly Fall Agri Demagri 7.90 Flexible PC 3.40 Soil 1.80 N/A N/A 12 poor and undulation
84.800 85.000 Hilly Fall Agri Demagri 7.20 Flexible PC 3.50 Soil 1.60 N/A N/A 12 poor and undulation
85.000 85.200 Hilly Fall Built Up Demagri 8.30 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
85.200 85.400 Hilly Fall Built Up Demagri 7.40 Flexible PC 3.60 Soil 0.90 N/A N/A 12 poor and undulation
85.400 85.600 Hilly Fall Built Up Demagri 6.90 Flexible PC 3.40 Soil 1.20 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 11 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
85.600 85.800 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.30 Soil 0.90 N/A N/A 12 poor and undulation
85.800 86.000 Hilly Fall Built Up Demagri 8.20 Flexible PC 4.00 Soil 0.90 N/A N/A 12 poor and undulation
86.000 86.200 Hilly Fall Built Up Demagri 6.80 Flexible PC 3.50 Soil 0.80 N/A N/A 12 poor and undulation
86.200 86.400 Hilly Fall Built Up Demagri 10.90 Flexible PC 3.30 Soil 2.10 N/A N/A 12 poor and undulation
86.400 86.600 Hilly Fall Built Up Demagri 9.40 Flexible PC 3.30 Soil 2.00 N/A N/A 12 poor and undulation
86.600 86.800 Hilly Fall Built Up Demagri 6.50 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
86.800 87.000 Hilly Fall Built Up Demagri 8.10 Flexible PC 4.10 Soil 1.40 N/A N/A 12 poor and undulation
87.000 87.200 Hilly Fall Built Up Demagri 8.20 Flexible PC 4.00 Soil 1.30 N/A N/A 12 poor and undulation
87.200 87.400 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.90 Soil 1.00 N/A N/A 12 poor and undulation
87.400 87.600 Hilly Fall Built Up Demagri 7.60 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
87.600 87.800 Hilly Fall Built Up Demagri 8.60 Flexible PC 3.50 Soil 1.10 N/A N/A 12 poor and undulation
87.800 88.000 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.70 Soil 1.20 N/A N/A 12 poor and undulation
88.000 88.200 Hilly Fall Built Up Demagri 6.90 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
88.200 88.400 Hilly Fall Built Up Demagri 7.40 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
88.400 88.600 Hilly Fall Built Up Demagri 7.60 Flexible PC 3.50 Soil 1.10 N/A N/A 12 poor and undulation
88.600 88.800 Hilly Fall Built Up Demagri 6.20 Flexible PC 3.40 Soil 0.90 N/A N/A 12 poor and undulation
88.800 89.000 Hilly Fall Built Up Demagri 8.30 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
89.000 89.200 Hilly Fall Built Up Demagri 5.80 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
89.200 89.400 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.90 Soil 1.30 N/A N/A 12 poor and undulation
89.400 89.600 Hilly Fall Built Up Demagri 6.50 Flexible PC 3.60 Soil 1.10 N/A N/A 12 poor and undulation
89.600 89.800 Hilly Fall Built Up Demagri 7.40 Flexible PC 3.30 Soil 1.30 N/A N/A 12 poor and undulation
89.800 90.000 Hilly Fall Built Up Demagri 7.30 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
90.000 90.200 Hilly Fall Built Up Demagri 6.90 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
90.200 90.400 Hilly Fall Built Up Demagri 7.50 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
90.400 90.600 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.30 Soil 1.00 N/A N/A 12 poor and undulation
90.600 90.800 Hilly Fall Built Up Demagri 7.20 Flexible PC 3.50 Soil 1.00 N/A N/A 12 poor and undulation
90.800 91.000 Hilly Fall Built Up Demagri 7.50 Flexible PC 3.40 Soil 1.30 N/A N/A 12 poor and undulation
91.000 91.200 Hilly Fall Built Up Demagri 7.90 Flexible PC 3.50 Soil 1.40 N/A N/A 12 poor and undulation
91.200 91.400 Hilly Fall Built Up Demagri 8.60 Flexible PC 3.40 Soil 1.50 N/A N/A 12 poor and undulation
91.400 91.600 Hilly Fall Built Up Demagri 8.70 Flexible PC 3.30 Soil 1.20 N/A N/A 12 poor and undulation
91.600 91.800 Hilly Fall Built Up Demagri 8.10 Flexible PC 3.40 Soil 1.40 N/A N/A 12 poor and undulation
91.800 92.000 Hilly Fall Built Up Demagri 8.20 Flexible PC 3.50 Soil 1.20 N/A N/A 12 poor and undulation
92.000 92.200 Hilly Fall Built Up Demagri 7.90 Flexible PC 3.50 Soil 1.30 N/A N/A 12 poor and undulation
92.200 92.400 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
92.400 92.600 Hilly Fall Built Up Demagri 7.80 Flexible PC 3.60 Soil 1.50 N/A N/A 12 poor and undulation
92.600 92.800 Hilly Fall Built Up Demagri 6.50 Flexible PC 3.80 Soil 1.00 N/A N/A 12 poor and undulation
92.800 93.000 Hilly Fall Built Up Demagri 6.10 Flexible PC 3.40 Soil 1.10 N/A N/A 12 poor and undulation
93.000 93.200 Hilly Fall Built Up Demagri 6.30 Flexible PC 3.50 Soil 0.90 N/A N/A 12 poor and undulation
93.200 93.400 Hilly Fall Built Up Demagri 7.10 Flexible PC 3.80 Soil 1.00 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 12 of 62


ROAD INVENTORY DATA SHEET Appendix II A

Road Name: LUNGLEI TO TLABUNG (NH-302) Sheet No. :

From: LUNGLEI To: TLABUNG Dt of Survey : 10.09.09 to 22.09.09

District (From) : LUNGLEI District (To) : LUNGLEI Weather : Fair


From (Km) To Terrain (Plain Rise & Land Use (Built Name of Formation
CARRIAGEWAY SHOULDER Submergence(in
(Km) Rolling/Hilly) Fall Up/Agri/Forest/Indu Village/Tow width (m) Embank-ment Right
strial/Barren) n Pavement Surfacing Width Type Width cm) Remarks
Height (m) of Way
type type (m) (BT/CC/GR/ (m) / Stretch in m
ER)
93.400 93.600 Hilly Fall Built Up Demagri 5.80 Flexible PC 3.60 Soil 1.20 N/A N/A 12 poor and undulation
93.600 93.800 Hilly Fall Built Up Demagri 6.20 Flexible PC 4.20 Soil 0.80 N/A N/A 12 poor and undulation
93.800 94.000 Hilly Fall Built Up Demagri 6.30 Flexible PC 4.10 Soil 0.90 N/A N/A 12 poor and undulation
94.000 94.200 Hilly Fall Built Up Demagri 8.50 Flexible PC 5.20 Soil 1.00 N/A N/A 12 poor and undulation
94.200 94.400 Hilly Fall Built Up Demagri 7.20 Flexible PC 5.00 Soil 1.20 N/A N/A 12 poor and undulation

Surveyed by Prepared by Checked by Page 13 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder
Strengthenin
0 1.000 Base WBM 150 Soil Poor 25 Poor 22 55 8/5 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
1.000 2.000 Base WBM 150 Soil Poor 25 Poor 26 34 12.5/12 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
2.000 3.000 Base WBM 150 Soil Poor 25 Poor 30 10 .7/.3 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
3.000 4.000 Base WBM 150 Soil Poor 25 Poor 18 38 7/12 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
4.000 5.000 Base WBM 150 Soil Poor 25 Poor 23 24.5 - Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
5.000 6.000 Base WBM 150 Soil Poor 25 Poor 21 12.5 - Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder Patch
6.000 7.000 Base WBM 150 Soil Poor 25 Poor 16 10.5 1/.5 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
7.000 8.000 Base WBM 150 Soil Poor 25 Poor 18 43 9/22 Severe 20.00 N/A NE repairing is
requird
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 14 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder Patch
8.000 9.000 Base WBM 150 Soil Poor 25 Poor 20 67 20.5/36.5 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
9.000 10.000 Base WBM 150 Soil Poor 25 Poor 25 45 6/14.5 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
10.000 11.000 Base WBM 150 Soil Poor 25 Poor 28 54 5/7.5 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
11.000 12.000 Base WBM 150 Soil Poor 25 Poor 21 47.5 5/7.3 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder
Strengthenin
12.000 13.000 Base WBM 150 Soil Poor 25 Poor 30 48 7/10 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
13.000 14.000 Base WBM 150 Soil Poor 25 Poor 27 40.5 9/14 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
14.000 15.000 Base WBM 150 Soil Poor 25 Poor 36 25.5 2.5/3 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
15.000 16.000 Base WBM 150 Soil Poor 25 Poor 34 34.5 6.5/9.5 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 15 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder
Strengthenin
16.000 17.000 Base WBM 150 Soil Poor 25 Poor 35 44.5 6.1/5.2 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
17.000 18.000 Base WBM 150 Soil Poor 25 Poor 30 46 9.7/15 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
18.000 19.000 Base WBM 150 Soil Poor 25 Poor 29 34 1/1 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
19.000 20.000 Base WBM 150 Soil Poor 25 Poor 26 24 1.2/5 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
20.000 21.000 Base WBM 150 Soil Poor 25 Poor 27 47 4.5/9 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
21.000 22.000 Base WBM 150 Soil Poor 25 Poor 19 40.5 5/1.5 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
22.000 23.000 Base WBM 150 Soil Poor 25 Poor 16 5.5 6/1.2 Severe 20.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder Patch
23.000 24.000 Base WBM 150 Soil Poor 25 Poor 15 3 - Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 16 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder Patch
24.000 25.000 Base WBM 150 Soil Poor 25 Poor 12 1.5 0.5/1 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
25.000 26.000 Base WBM 150 Soil Poor 25 Poor 14 - .2/.1 Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
26.000 27.000 Base WBM 150 Soil Poor 25 Poor 18 4 - Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
27.000 28.000 Base WBM 150 Soil Poor 25 Poor 19 2.5 - Severe 20.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
28.000 29.000 Base WBM 150 Soil Poor 25 Poor 15 5 - Severe 30.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder Patch
29.000 30.000 Base WBM 150 Soil Poor 25 Poor 16 3.5 - Severe 30.00 N/A NE repairing is
Sub-base GSB 100 requird
Subgrade Soil
Surface PC 25
Binder
Strengthenin
30.000 31.000 Base WBM 150 Soil Poor 25 Poor 25 4.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
31.000 32.000 Base WBM 150 Soil Poor 25 Poor 32 5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 17 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder
Strengthenin
32.000 33.000 Base WBM 150 Soil Poor 25 Poor 38 1.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
33.000 34.000 Base WBM 150 Soil Poor 25 Poor 37 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
34.000 35.000 Base WBM 150 Soil Poor 25 Poor 29 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
35.000 36.000 Base WBM 150 Soil Poor 25 Poor 35 2.5 .5/.2 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
36.000 37.000 Base WBM 150 Soil Poor 25 Poor 40 3 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
37.000 38.000 Base WBM 150 Soil Poor 25 Poor 43 4.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
38.000 39.000 Base WBM 150 Soil Poor 25 Poor 41 3 .5/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
39.000 40.000 Base WBM 150 Soil Poor 25 Poor 39 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 18 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder
Strengthenin
40.000 41.000 Base WBM 150 Soil Poor 25 Poor 30 20.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 19 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder
Strengthenin
41.000 42.000 Base WBM 150 Soil Poor 25 Poor 40 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
42.000 43.000 Base WBM 150 Soil Poor 25 Poor 43 4 .5/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
43.000 44.000 Base WBM 150 Soil Poor 25 Poor 34 1.5 1/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
44.000 45.000 Base WBM 150 Soil Poor 25 Poor 30 40.5 5/1.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
45.000 46.000 Base WBM 150 Soil Poor 25 Poor 38 5.5 6/1.2 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
46.000 47.000 Base WBM 150 Soil Poor 25 Poor 42 3 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
47.000 48.000 Base WBM 150 Soil Poor 25 Poor 40 1.5 0.5/1 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
48.000 49.000 Base WBM 150 Soil Poor 25 Poor 36 - .2/.1 Severe 30.00 N/A NE
g is required

Surveyed by Prepared by Checked by Sheet 20 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)
Strengthenin
48.000 49.000 Soil Poor 25 Poor 36 - .2/.1 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
49.000 50.000 Base WBM 150 Soil Poor 25 Poor 36 4 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
50.000 51.000 Base WBM 150 Soil Poor 25 Poor 34 2.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
51.000 52.000 Base WBM 150 Soil Poor 25 Poor 40 5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
52.000 53.000 Base WBM 150 Soil Poor 25 Poor 47 3.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
53.000 54.000 Base WBM 150 Soil Poor 25 Poor 43 4.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
54.000 55.000 Base WBM 150 Soil Poor 25 Poor 32 5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
55.000 56.000 Base WBM 150 Soil Poor 25 Poor 30 1.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25

Strengthenin
56.000 57.000 Soil Poor 25 Poor 46 - - Severe 30.00 N/A NE
g is required
Surveyed by Prepared by Checked by Sheet 21 of 62
PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Binder
Strengthenin
56.000 57.000 Base WBM 150 Soil Poor 25 Poor 46 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
57.000 58.000 Base WBM 150 Soil Poor 25 Poor 41 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
58.000 59.000 Base WBM 150 Soil Poor 25 Poor 43 2.5 .5/.2 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
59.000 60.000 Base WBM 150 Soil Poor 25 Poor 40 3 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
60.000 61.000 Base WBM 150 Soil Poor 25 Poor 35 4.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
61.000 62.000 Base WBM 150 Soil Poor 25 Poor 36 3 .5/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
62.000 63.000 Base WBM 150 Soil Poor 25 Poor 32 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
63.000 64.000 Base WBM 150 Soil Poor 25 Poor 46 20.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100

Surveyed by Prepared by Checked by Sheet 22 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) *** Strengthenin
(mm) Fair/ poor)
63.000 64.000 (mm) Soil Poor
(Fair/Poor/Failed) 25
(Km/hr) Poor
(G/F/P/VP) 46 20.5 -
and % 100m) ** Severe
Moderate/Severe) and % 100m) ** 30.00 N/A NE
g is required

Subgrade Soil
Surface PC 25
Binder
Strengthenin
64.000 65.000 Base WBM 150 Soil Poor 25 Poor 48 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
65.000 66.000 Base WBM 150 Soil Poor 25 Poor 43 4 .5/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
66.000 67.000 Base WBM 150 Soil Poor 25 Poor 38 1.5 1/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
67.000 68.000 Base WBM 150 Soil Poor 25 Poor 39 40.5 5/1.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
68.000 69.000 Base WBM 150 Soil Poor 25 Poor 40 5.5 6/1.2 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
69.000 70.000 Base WBM 150 Soil Poor 25 Poor 45 3 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
70.000 71.000 Base WBM 150 Soil Poor 25 Poor 47 1.5 0.5/1 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
71.000 72.000 Soil Poor 25 Poor 49 - .2/.1 Severe 30.00 N/A NE
g is required

Surveyed by Prepared by Checked by Sheet 23 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Strengthenin
71.000 72.000 Base WBM 150 Soil Poor 25 Poor 49 - .2/.1 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
72.000 73.000 Base WBM 150 Soil Poor 25 Poor 38 4 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
73.000 74.000 Base WBM 150 Soil Poor 25 Poor 48 2.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
74.000 75.000 Base WBM 150 Soil Poor 25 Poor 45 5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
75.000 76.000 Base WBM 150 Soil Poor 25 Poor 41 3.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
76.000 77.000 Base WBM 150 Soil Poor 25 Poor 36 4.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
77.000 78.000 Base WBM 150 Soil Poor 25 Poor 42 5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
78.000 79.000 Base WBM 150 Soil Poor 25 Poor 40 1.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 24 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Surface PC 25
Binder
Strengthenin
79.000 80.000 Base WBM 150 Soil Poor 25 Poor 52 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
80.000 81.000 Base WBM 150 Soil Poor 25 Poor 51 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
81.000 82.000 Base WBM 150 Soil Poor 25 Poor 48 2.5 .5/.2 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
82.000 83.000 Base WBM 150 Soil Poor 25 Poor 57 3 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
83.000 84.000 Base WBM 150 Soil Poor 25 Poor 46 4.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
84.000 85.000 Base WBM 150 Soil Poor 25 Poor 48 3 .5/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
85.000 86.000 Base WBM 150 Soil Poor 25 Poor 53 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
86.000 87.000 Base WBM 150 Soil Poor 25 Poor 57 20.5 - Severe 30.00 N/A NE
g is required

Surveyed by Prepared by Checked by Sheet 25 of 62


PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)
Strengthenin
86.000 87.000 Soil Poor 25 Poor 57 20.5 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
87.000 88.000 Base WBM 150 Soil Poor 25 Poor 55 - - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
88.000 89.000 Base WBM 150 Soil Poor 25 Poor 50 4 .5/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
89.000 90.000 Base WBM 150 Soil Poor 25 Poor 47 1.5 1/.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
90.000 91.000 Base WBM 150 Soil Poor 25 Poor 52 40.5 5/1.5 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
91.000 92.000 Base WBM 150 Soil Poor 25 Poor 51 5.5 6/1.2 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
92.000 93.000 Base WBM 150 Soil Poor 25 Poor 49 3 - Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25
Binder
Strengthenin
93.000 94.000 Base WBM 150 Soil Poor 25 Poor 56 1.5 0.5/1 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil
Surface PC 25

Strengthenin
94.000 95.000 Soil Poor 25 Poor 59 - .2/.1 Severe 30.00 N/A NE
g is required
Surveyed by Prepared by Checked by Sheet 26 of 62
PAVEMENT CONDITION SURVEY Appendix : II B
ROAD NAME : LUNGLEI TO TLABUNG (NH-302) Sheet No :
From (Km.) LUNGLEI TO : TLABUNG Date of Survey : 10.09.09 to 25.09.09
District (from) :LUNGLEI District (To): LUNGLEI Weather : Fair
Chainage Pavement Composition Shoulder Riding Quality Pavement Condition

Pavement Embankment
Road Side Drain
Thickness Condition Speed Quality Potholing (No. Rut (None/ Patching (No. Edge drop Condition (Good/ Remarks
From (Km.) To (Km.) Composition Type * Composition Cracking (%) Raveling (%) (NE/PF/F) ***
(mm) (Fair/Poor/Failed) (Km/hr) (G/F/P/VP) and % 100m) ** Moderate/Severe) and % 100m) ** (mm) Fair/ poor)

Binder
Strengthenin
94.000 95.000 Base WBM 150 Soil Poor 25 Poor 59 - .2/.1 Severe 30.00 N/A NE
g is required
Sub-base GSB 100
Subgrade Soil

Surveyed by Prepared by Checked by Sheet 27 of 62


Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

1 120.863 SLAB 0.2 1X1 4.2 6.8 N/A N/A P P P 3.8/2.3 v N/A No Souring Sufficient h/w of v/s is damage other conditon is good

2 485.421 SLAB 0.2 1X2 4.0 7.5 N/A N/A P P P N/A No Souring Sufficient h/w broken on both side rest good condition

3 657.336 SLAB 0.2 1X1.50 4.0 6.4 N/A N/A P P P 9.86/2.6v N/A No Souring Sufficient opening good walls need repair

4 739.537 SLAB 0.2 1X1 4.0 6.1 N/A N/A P P P 4.1/10.4 N/A No Souring Sufficient not exist

5 816.627 SLAB 0.2 1.5X2.4 4.5 7.3 N/A N/A P P P 3.7/10 N/A No Souring Sufficient not exist

6 896.453 SLAB 0.2 1X1 4.3 8.2 N/A N/A P P P N/A No Souring Sufficient fully covered with landslide

7 1366.461 SLAB 0.2 1X0.75 3.5 6.0 N/A N/A P P P N/A No Souring Sufficient h/w broken need relpace

8 2383.441 SLAB 0.2 1X1 3.0 6.5 N/A N/A P P P N/A No Souring Sufficient h/w crack culvert condition is good

9 2594.470 SLAB 0.2 1X1.50 4.4 10.0 N/A N/A P P P N/A No Souring Sufficient h/w slightly crack

10 2801.262 SLAB 0.2 1X1.50 4.2 8.0 N/A N/A P P P N/A No Souring Sufficient its small bridge but good condition

11 2912.269 SLAB 0.2 1X1 3.3 6.0 N/A N/A P P P N/A No Souring Sufficient condition is good

12 3056.893 SLAB 0.2 1X1.50 3.5 7.2 N/A N/A P P P N/A Souring Nalla good condition but covered with weeds

13 3224.493 SLAB 0.2 1X1 4.0 7.4 N/A N/A F F P N/A No Souring Sufficient good condition

14 3409.064 SLAB 0.2 1X1 4.2 10.0 N/A N/A P P P N/A Souring Nalla opening is fill and no h/w

15 3508.788 SLAB 0.2 1X1 3.6 8.0 N/A N/A F F P N/A No Souring Sufficient small pipe good condition
opening is fill and culvert condition is also need
16 3559.070 SLAB 0.2 1X1 4.0 8.0 N/A N/A P P P N/A No Souring Sufficient
repair
17 3705.079 PIPE 1X0.9 4.1 8.3 N/A N/A F F P N/A No Souring Sufficient good condition

18 4041.325 SLAB 0.2 1X1.50 3.2 5.5 N/A N/A P P P N/A No Souring Sufficient slightly crack of wing/w

19 4130.000 SLAB 0.2 1X1.50 3.2 6.5 N/A N/A P P P N/A No Souring Sufficient good condition
1.2r/1.4left
20 4162.000 SLAB 0.2 1X1.50 3.4 6.7 N/A N/A F F P 17/10 h 3/2 v Souring Nalla no h/w need contruction
0.8r/0.6left
21 4406.327 SLAB 0.2 1X1.50 3.2 6.5 N/A N/A F F P N/A Souring Nalla no h/w need contruction

22 4553.289 PIPE 1X900mm 3.2 6.5 1x1 N/A N/A P P P N/A Souring Nalla wing/w is broken

23 4563.369 PIPE 1X900mm 3.3 6.7 N/A N/A F F P N/A Souring Nalla good condition

24 4779.675 SLAB 0.2 1x1 3.4 6.7 N/A N/A F F P N/A No Souring Sufficient opening fill no h/w

25 4928.923 PIPE 1x0.9 3.3 8.0 N/A N/A P P P 3/3.5 N/A No Souring Sufficient opening fill wing/w crack

26 5036.598 PIPE 1x0.9 3.2 6.0 1.5x2 N/A N/A F F P 1.6/2.3 N/A Souring Nalla opening is fill but wing/w condition is good

27 5170.569 SLAB 0.2 1x1 3.2 6.0 N/A N/A P P P N/A No Souring Sufficient good condition
3.2/0.8v
28 5641.809 SLAB 0.2 1X1.50 3.2 6.0 N/A N/A P P P N/A 2.1/2 No Souring Sufficient crack on the wing/w
3.9/1.6 h
29 5672.668 SLAB 0.2 1x1 3.3 6.5 N/A N/A F F P N/A 1.4/1.2 Souring Nalla parapet damage

30 6089.841 SLAB 0.2 1X1.50 3.3 6.0 N/A N/A P P P N/A Souring Nalla damage of parapet culvert condition is good

31 6230.172 SLAB 0.2 1X1.50 4.0 7.0 N/A N/A F F P N/A 2/1.6 No Souring Sufficient good condition

32 6270.544 SLAB 0.2 1X1.50 4.0 7.5 N/A N/A P P P N/A No Souring Sufficient good condition
Page 28
33 6709.165 SLAB 0.2 1X1.50 3.3 7.0 N/A N/A P P P N/A No Souring Sufficient crack on the parapet
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

34 6855.989 SLAB 0.2 1x1 3.5 7.1 N/A N/A P P P 2.8l N/A 1.1/1.2 No Souring Sufficient crack on the wing wall

35 6904.197 SLAB 0.2 1X1.50 3.2 5.4 N/A N/A P P P 1.4/1.2 N/A No Souring Sufficient good condition
culvert condition is good but wing/w is slightly
36 7099.124 SLAB 0.2 1X1.50 3.4 6.3 1.2x1.4 N/A N/A F F P N/A 1.1/1.3 No Souring Sufficient
crack
37 7218.017 SLAB 0.2 1.8x2.5 4.3 7.0 N/A N/A P P P N/A 1.2/1.4 No Souring Sufficient opening is fill and no parapet
culvert condition is good but wing/w is slightly
38 7337.726 SLAB 0.2 1X2. 3.6 6.6 N/A N/A F F P 2/3 1.8/1.6 No Souring Sufficient
crack
39 7426.836 SLAB 0.2 1X2.5 4.5 8.0 N/A N/A F F P 1.3/1.3 4/10 2.1/2 No Souring Sufficient wing/w is crack

40 7574.782 SLAB 0.2 1X2 3.6 6.1 1x1.2 N/A N/A P P P 2/3 1.6/1.8 No Souring Sufficient damage of wall and and opening is slightly fill

41 7695.943 SLAB 0.2 1X0.50 4.3 7.1 N/A N/A F F P 7/2 1.4/1.6 No Souring Sufficient opening is fill wall condition is good

42 7845.100 SLAB 0.2 1X1.50 3.4 6.1 N/A N/A F F P N/A No Souring Sufficient wall damage

43 8071.918 SLAB 0.2 1.2x1.8 3.9 6.8 N/A N/A P P P 5r 3 No Souring Sufficient wall damage

44 8174.000 SLAB 0.2 1X1.50 3.8 6.6 N/A N/A P P P 1.9/1.7 1 1.2 No Souring Sufficient cood condition

45 8282.820 SLAB 0.2 1X0.75 3.8 6.5 N/A N/A F F P N/A 1.4/1.6 No Souring Sufficient opening is fill and wing/w is crack

46 8349.703 SLAB 0.2 1X1.50 4.0 6.8 N/A N/A F F P N/A No Souring Sufficient fully covered with landslide

47 8461.865 SLAB 0.2 1X1 3.9 7.1 N/A N/A F F P N/A 4/4.2 No Souring Sufficient wall damage

48 8610.487 SLAB 0.2 1X1 3.5 6.5 N/A N/A F F P 5.2/2.2 N/A 1.6/2 Souring Nalla wing/w is crack
all parapet damage culvert is good but walls
49 9009.331 SLAB 0.2 1X1 4.2 7.1 N/A N/A F F P N/A 0.6/1 No Souring Sufficient
need repair and no headwall
50 9161.356 SLAB 0.2 1X1 3.7 6.7 N/A N/A F F P 2/2 1.2/1.4 No Souring Sufficient all parapet damage culvert is good no headwall
1.2
51 9340.962 SLAB 0.2 1X1 3.9 6.4 N/A N/A F F P 3/2 No Souring Sufficient good condition
1.2
52 9506.246 PIPE 1X900 4.0 7.1 N/A N/A F F P 2/2 1/1.2 No Souring Sufficient good condition

53 10088.829 SLAB 0.2 1X0.50 3.4 7.3 N/A N/A F F P 2/2 1.2/2 No Souring Sufficient good condition

54 10272.376 SLAB 0.2 1X1 3.7 6.8 N/A N/A F F P N/A 1.6/1.4 No Souring Sufficient parapet damage rest are in good condition

55 10461.935 SLAB 0.2 1X2 3.5 6.8 N/A N/A F F P 1/2 2.1/1.8 No Souring Sufficient no headwall walls slightly damage

56 10653.470 SLAB 0.2 1X1 3.4 6.2 N/A N/A F F P 3/4 0.8/0.6 No Souring Sufficient can be considered good

57 10747.332 SLAB 0.2 1X2 3.7 6.7 N/A N/A F F P 3.7/5.9 N/A 2.1/2.2 No Souring Sufficient parapet damage walls slightly crack

58 10906.878 SLAB 0.2 1X1 4.1 6.6 N/A N/A F F P 1/2 1.2/1.4 No Souring Sufficient parapet damage culvert condition is good

59 11139.676 SLAB 0.2 1X1.50 3.7 6.0 N/A N/A F F P 3.2® 2/2 1.6/1.2 No Souring Sufficient good condition

60 11271.667 SLAB 0.2 1X1.50 3.3 5.6 N/A N/A F F P 2/2 2.1/1.6 No Souring Sufficient crack at top of parapet rest portion is good

61 11529.736 SLAB 0.2 1X1 3.6 6.6 N/A N/A F F P 2/2 1/1 No Souring Sufficient opening is fill and wing/w is crack

62 11590.995 SLAB 0.2 1X1.50 4.2 6.8 N/A N/A F F P 1.1/2.7 3/2 1.2/1.1 No Souring Sufficient wall damage

63 12192.163 SLAB 0.2 1X1.50 4.3 6.5 N/A N/A F F P 5.4/7.2 2/2 1/1.1 No Souring Sufficient opening is fill and wing/w is crack

64 12601.742 SLAB 0.2 1X1 4.2 7.0 N/A N/A F F P 1/2 1.2/1 No Souring Sufficient good condition

65 13085.228 SLAB 0.2 1X1 4.5 7.5 N/A N/A F F P 2/2 2.2/1.8 No Souring Sufficient opening is fill walls are in good condition
Page 29
66 13290.507 SLAB 0.2 1X1 4.2 7.0 N/A N/A F F P 2.5/6.8 N/A 1.2/1.6 No Souring Sufficient opening is good but no h/w
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

67 14948.278 SLAB 0.2 1X1.50 3.5 5.2 N/A N/A F F P 2/2 1.2/1.6 No Souring Sufficient opening is good but no h/w

68 15099.319 SLAB 0.2 1X1 4.9 9.5 N/A N/A F F P N/A No Souring Sufficient no h/w but in good condition

69 15204.555 SLAB 0.2 1X1 4.0 6.5 1.5x1.2 N/A N/A F F P 2/2 1/1.2 No Souring Sufficient good condition

70 15308.544 SLAB 0.2 1X1.50 3.0 7.4 N/A N/A F F P 2/3 1.2/1.2 No Souring Sufficient opening fill walls good

71 15413.868 SLAB 0.2 1X1 3.7 7.3 N/A N/A F F P 3/2 0.8/0.6 No Souring Sufficient opening fill parapet crack at top

72 15518.504 SLAB 0.2 1X1 3.8 7.3 N/A N/A F F P 2/3 1.2/1.2 No Souring Sufficient good condition

73 15581.615 SLAB 0.2 1X0.75 4.4 7.0 N/A N/A F F P 5/4 1.8/2 No Souring Sufficient good condition

74 15711.424 SLAB 0.2 1X1 4.2 6.4 N/A N/A F F P 5/4 1.2/1.4 No Souring Sufficient parapet crack at top rest are in good condition

75 15877.860 SLAB 0.2 1X1.50 4.3 6.8 N/A N/A F F P N/A No Souring Sufficient opening is fill crack wall

76 15998.585 SLAB 0.2 1X1 3.8 7.1 N/A N/A F F P N/A No Souring Sufficient no headwall

77 16142.182 SLAB 0.2 1X1.50 4.4 6.9 N/A N/A F F P N/A No Souring Sufficient opening fill no headwall

78 16200.517 SLAB 0.2 1X1 4.5 7.3 N/A N/A F F P 3/21 2/8 No Souring Sufficient good condition

79 16283.619 SLAB 0.2 1X1 3.4 4.9 N/A N/A F F P N/A No Souring Sufficient fully covered with landslide

80 16498.662 SLAB 0.2 1X1 4.2 6.7 N/A N/A F F P N/A No Souring Sufficient fully covered broken wall

81 16732.819 SLAB 0.2 1X1 4.2 7.1 N/A N/A F F P 2/2 0.8/1 No Souring Sufficient no headwall

82 17093.885 SLAB 0.2 1X1 3.6 7.2 N/A N/A F F P 2/2 1/1.2 No Souring Sufficient culvert condition is good but wall slightly crack

83 17254.256 SLAB 0.2 1X1 3.9 6.9 N/A N/A F F P 4.6/2.4 2/2 2/2 No Souring Sufficient opening fill r/s parapet is damage

84 17355.660 SLAB 0.2 1X1 3.9 7.1 N/A N/A F F P 2/3 1.8/1.6 No Souring Sufficient good condition
6.5/1.6 h R/Wslightly crack opening
85 17460.748 SLAB 0.2 1X1 4.0 6.9 N/A N/A F F P NA No Souring Sufficient
1.7 v good
86 17767.936 SLAB 0.2 1X1 3.7 6.7 N/A N/A F F P 1/2 1.1/1.2 No Souring Sufficient good condition

87 18012.395 SLAB 0.2 1X1.50 3.7 7.1 N/A N/A F F P 6.4/1.3 2/4 1/1.2 Souring Nalla good condition

88 18112.496 SLAB 0.2 1X1 4.5 6.3 N/A N/A F F P 6.7/1.4 2/1 2.2/1.8 No Souring Sufficient no headwall parapet damage

89 18281.268 SLAB 0.2 1X1.50 4.7 8.0 N/A N/A F F P 5.7/1.6 3/1 2.1/1.8 No Souring Sufficient parapet damage wall condition good

90 18487.883 SLAB 0.2 1x1.2 3.5 7.8 N/A N/A F F P 1.7/1.7 3/2 1.2/1.8 No Souring Sufficient wing/w condition is bad

91 18596.808 SLAB 0.2 1X1 3.7 6.7 N/A N/A F F P 7.7/5.5 2/3 1.2/1.4 No Souring Sufficient culvert condition is poor

92 18937.703 SLAB 0.2 1X1 3.4 6.4 N/A N/A F F P 3/5 1.2/0.8 Souring Nalla parapet damage opening good

93 19043.598 SLAB 0.2 1X1 3.4 6.3 N/A N/A F F P 6.3/7.7 3/3 3.5/2.8 No Souring Sufficient new

94 19097.097 SLAB 0.2 1X1.50 3.7 6.7 N/A N/A F F P 16.4/7.1 3/3 3.5/2.8 Souring Nalla new

95 19225.718 SLAB 0.2 1.5x2 3.7 6.7 N/A N/A F F P 6.9/6.8 2/2 3.6/3.2 No Souring Sufficient good condition only parapet crack at top
1.5/10.4 v
96 19482.309 SLAB 0.2 1X1 4.0 7.8 N/A N/A P P P 5/6 3.5/3.3 No Souring Sufficient good condition only parapet crack at top
9.5/0.8
97 19482.423 SLAB 0.2 1X1 3.3 6.2 N/A N/A F F P 3/1 1.3/1 No Souring Sufficient new

98 19687.220 SLAB 0.2 1X1 3.2 6.3 N/A N/A F F P 3/4 2.6/2 No Souring Sufficient new
Page 30
99 19901.506 SLAB 0.2 1X1 3.3 6.8 N/A N/A F F P 3/1 2.3/1.8 No Souring Sufficient good conditon
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

100 20001.199 SLAB 0.2 1x1.2 3.6 6.4 N/A N/A F F P N/A No Souring Sufficient fully covered wiyh landslide

101 20161.790 SLAB 0.2 1x1 3.7 7.0 N/A N/A F F P N/A 0.8/0.5 No Souring Sufficient no headwall and parapet bad condition

102 20532.293 SLAB 0.2 1X1.50 3.5 7.3 N/A N/A F F P 1L 2.3 No Souring Sufficient good condition

103 20808.745 SLAB 0.2 1x1 4.5 7.0 N/A N/A F F P 2/2 2.1/1.8 No Souring Sufficient damage

104 20997.624 SLAB 0.2 1x1 3.8 6.4 N/A N/A F F P 2/1 1.8/0.8 No Souring Sufficient crack on the wall opening is good
1.6/2.7 v
105 21385.084 SLAB 0.2 1x0.8 4.4 9.1 N/A N/A F F P 2/3 3.6/3.4 No Souring Sufficient only parapet crack
2.5 h
3/2.8v
106 21649.027 PIPE 1x0.9 4.4 7.4 1.2x1.4 N/A N/A P P P 3/2V 3/1H No Souring Sufficient walls condition is poor
1.8/1.8h
107 21677.309 SLAB 0.2 1x0.8 3.5 6.2 1.4x1.6 N/A N/A F F P 2/1 2.2/2.1 No Souring Sufficient crack on the wall

108 21795.424 SLAB 0.2 1X1.50 3.7 7.2 N/A N/A F F P 4/2 2.2/2.1 No Souring Sufficient no headwall and parapet bad condition

109 21925.661 SLAB 0.2 1x1.50 4.0 7.0 N/A N/A F F P 2/3 4/3.8 No Souring Sufficient good condition

110 22202.167 SLAB 0.2 1x1.50 4.0 7.1 N/A N/A F F P 2/2 3/2.8 No Souring Sufficient poor condition

111 22268.360 SLAB 0.2 1x0.8 4.2 7.1 N/A N/A F F P 4/3 2.8/1.8 No Souring Sufficient crack parapet covered with weeds
1.2/1.1 h
112 22773.111 SLAB 0.2 1x0.8 3.6 7.0 1.6x2.0 N/A N/A F F P 4/5 1.2/2.2 No Souring Sufficient crack parapet covered with weeds
2.4/0.7 v
113 22971.947 SLAB 0.2 1x1 3.2 6.8 N/A N/A F F P 2/1 0.8/0.6 No Souring Sufficient condition is good
6.8(l) v
114 23059.146 SLAB 0.2 1x0.8 3.5 6.7 N/A N/A F F P 1/1 2.5/2.3 No Souring Sufficient walls crack
2/1.4 h
115 23230.576 SLAB 0.2 1x1.50 3.6 8.1 N/A N/A F F P 2/1 1.2/0.8 No Souring Sufficient crack wall opening is good

116 23344.518 SLAB 0.2 1x0.8 3.2 7.6 N/A N/A F F P 6/5 4/3.8 No Souring Sufficient good condition

117 23387.710 SLAB 0.2 1x1.50 3.1 7.2 1.5x1.2 N/A N/A F F P 1/1 6.8/0.6 No Souring Sufficient opening is fill and culvert condition is bad

118 23481.360 SLAB 0.2 1x2.0 3.2 6.8 1.4x1.6 N/A N/A P P P 1/1 No Souring Sufficient small bridge and good condition
1.6/2.5 v
119 23557.020 SLAB 0.2 1x0.2 3.4 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
2.3/1.2 h
120 24119.843 SLAB 0.2 1x0.8 3.6 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

121 24266.467 PIPE 1x0.9 4.0 7.3 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

122 24658.471 SLAB 0.2 1x0.8 3.8 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

123 24796.686 SLAB 0.2 1x1.0 4.0 7.2 N/A N/A P P P 4.7(l) No Souring Sufficient Wooden logs are used Inspite of RCC slab

124 24916.765 SLAB 0.2 1x1.0 4.2 7.5 1.2x1.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
2.8/2.2 v
125 25069.444 SLAB 0.2 1x0.8 3.9 7.0 N/A N/A P P P Souring Nalla Wooden logs are used Inspite of RCC slab

126 25280.555 SLAB 0.2 1x0.8 4.0 7.2 N/A N/A P P P 1.8/1.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab

127 25406.936 SLAB 0.2 1x0.8 3.3 6.3 1.2x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

128 25560.710 SLAB 0.2 1x1 4.3 7.2 1.4x1.6 N/A N/A P P P 2.3(l) No Souring Sufficient Wooden logs are used Inspite of RCC slab

129 25878.228 SLAB 0.2 1X1.50 4.7 7.6 N/A N/A P P P 1.5/7.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

130 26067.615 SLAB 0.2 1x1 3.6 7.0 N/A N/A P P P 8/2.3 No Souring Sufficient Wooden logs are used Inspite of RCC slab

131 26238.939 PIPE 1x1 3.8 7.1 1.8x2.0 N/A N/A P P P 5.7(l) N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie
Page 31
132 26509.698 SLAB 0.2 1x1.50 3.6 7.2 1.4x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

133 26892.306 SLAB 0.2 1x1.51 3.8 7.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
1.4/2.4 h
134 27183.189 SLAB 0.2 1x1.52 3.6 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
4.1/8.5 v
8.3/4.2 v
135 27491.766 SLAB 0.2 1x1.53 3.8 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
1.9/1.8 h
136 27620.508 SLAB 0.2 1x1.50 4.2 7.4 N/A N/A P P P 3.6/5.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab

137 27677.064 SLAB 0.2 1x0.8 4.0 7.2 N/A N/A P P P 2.7/2.7 No Souring Sufficient Wooden logs are used Inspite of RCC slab

138 27857.752 SLAB 0.2 1x1.50 3.8 7.0 N/A N/A P P P 5.3® No Souring Sufficient Wooden logs are used Inspite of RCC slab

139 28030.074 SLAB 0.2 1x1.5 3.6 6.8 N/A N/A P P P 2.8/2.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab

140 28233.162 SLAB 0.2 1x1.5 3.6 6.8 1.6x1.8 N/A N/A P P P 4/3.1 No Souring Sufficient Wooden logs are used Inspite of RCC slab

141 28269.439 SLAB 0.2 1.5x2 3.4 6.7 1.2x1.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

142 28233.162 SLAB 0.2 1x1.5 3.6 7.0 N/A N/A P P P 1.333333333 No Souring Sufficient Wooden logs are used Inspite of RCC slab

143 28342.640 SLAB 0.2 1x1.5 3.8 7.2 1.2x1.2 N/A N/A P P P 9.3/5.9V 1.2/1H No Souring Sufficient Wooden logs are used Inspite of RCC slab

144 28501.142 SLAB 0.2 1x1 3.6 7.1 N/A N/A P P P 1/1.2V 10.7/2H No Souring Sufficient Wooden logs are used Inspite of RCC slab

145 28531.495 SLAB 0.2 1x1 3.7 7.1 N/A N/A P P P 2.4/7V 1.9/1.3H No Souring Sufficient Wooden logs are used Inspite of RCC slab

146 28605.257 SLAB 0.2 1x1 3.6 7.0 N/A N/A P P P 8.1/1.1V 2.2/1.6 No Souring Sufficient Wooden logs are used Inspite of RCC slab

147 28676.473 SLAB 0.2 1x1 3.4 6.8 N/A N/A P P P 3.3/6.6V 1.3/1.6 No Souring Sufficient Wooden logs are used Inspite of RCC slab

148 28775.983 SLAB 0.2 1x1 3.4 6.8 N/A N/A P P P 3.6/3.3V1.1/1.8H No Souring Sufficient Wooden logs are used Inspite of RCC slab

149 29064.079 SLAB 0.2 1x1.2 3.6 7.1 1.5x1.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

150 29117.969 SLAB 0.2 1x1.50 3.8 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

151 29282.760 SLAB 0.2 1x1 4.2 7.4 1.4x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

152 29454.855 SLAB 0.2 1x0.8 3.8 7.6 1.2x1.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

153 29694.520 SLAB 0.2 1x0.8 3.8 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

154 29694.520 SLAB 0.2 1x0.9 4.0 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

155 29752.000 PIPE 1x1.0 4.2 7.1 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

156 30192.186 SLAB 0.2 1x0.9 4.4 7.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

157 30303.827 PIPE 1x0.9 4.0 7.1 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

158 30496.229 PIPE 1x0.9 4.1 6.9 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

159 30549.270 SLAB 0.2 1x1.2 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

160 30890.092 SLAB 0.2 1x1.2 4.2 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

161 30967.796 SLAB 0.2 1x1 3.4 6.7 1.2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

162 30995.617 SLAB 0.2 1x1 3.4 6.8 1.6x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

163 31026.141 SLAB 0.2 1x1.2 3.6 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

164 31111.712 SLAB 0.2 1x1 3.6 6.5 1.5x2.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 32
165 31402.190 SLAB 0.2 1x1.2 3.4 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

166 31601.705 SLAB 0.2 1x1.2 3.4 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

167 31709.949 SLAB 0.2 1x1 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

168 31603.536 SLAB 0.2 1x1.2 3.2 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

169 31709.949 SLAB 0.2 1x1 4.0 7.0 1x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

170 31870.763 SLAB 0.2 1x1.2 4.2 7.1 1.2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

171 31907.106 SLAB 1.5x2 3.8 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

172 32134.449 SLAB 1x1 3.9 6.6 N/A N/A P P P 2/0.7 Souring Nalla Wooden logs are used Inspite of RCC slab

173 32164.891 PIPE 1x0.9 3.6 6.2 N/A N/A P P P N/A Souring Nalla GI sheets are used inplaca of RCC pipie

174 32524.725 SLAB 1x1.2 3.8 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

175 32706.110 SLAB 1x1 3.9 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

176 32842.215 SLAB 1x1 4.1 7.0 N/A N/A P P P 6.7LV Souring Nalla Wooden logs are used Inspite of RCC slab

177 33002.035 SLAB 1x1.5 4.0 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

178 33075.735 PIPE 1x1 3.9 7.0 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

179 33340.020 SLAB 1x1.5 4.0 7.1 1.2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

180 33414.278 SLAB 1x1.2 4.2 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

181 33474.280 SLAB 1x1.2 3.8 7.2 1.2x1.5 N/A N/A P P P 2.5/0.8V 0.8/1H No Souring Sufficient Wooden logs are used Inspite of RCC slab

182 33538.671 SLAB 1x1 3.6 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

183 33634.851 SLAB 1x1 3.6 6.8 N/A N/A P P P 3.2/5.1 No Souring Sufficient Wooden logs are used Inspite of RCC slab

184 33730.048 SLAB 1x1.5 4.0 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

185 33840.789 SLAB 1x1.5 4.0 6.8 N/A N/A P P P 1.6/0.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

186 33928.312 SLAB 1x1.5 4.2 7.1 1.2x1.4 N/A N/A P P P 4.1/1.5V 1.5/1.2H No Souring Sufficient Wooden logs are used Inspite of RCC slab

187 33959.288 PIPE 1x0.9 4.3 7.1 N/A N/A P P P 4.9/3.2V N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

188 34036.390 SLAB 1x1.2 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

189 34128.636 PIPE 1x0.9 3.6 6.8 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

190 34180.305 SLAB 1x1.2 3.8 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

191 34227.647 PIPE 1x1.2 4.2 7.1 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

192 34281.765 SLAB 1x1.2 4.4 7.2 1.2x1.5 N/A N/A P P P 11.2/5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

193 34668.039 SLAB 1x1.2 4.3 6.8 1.4x1.6 N/A N/A P P P 5.3/3.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

194 34845.365 SLAB 1x1 3.8 6.7 1.2x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

195 34979.014 SLAB 1x1.2 3.4 6.3 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

196 35031.606 SLAB 1x1.50 3.6 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

197 35142.932 SLAB 1x1 3.7 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 33
198 35267.065 SLAB 1x1.5 3.7 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

199 35391.378 SLAB 1x1 4.0 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

200 35715.545 SLAB 1x1. 4.1 6.8 N/A N/A P P P 2.5/3.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

201 36501.915 SLAB 1x1 3.1 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

202 36804.829 SLAB 1x1.2 3.2 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

203 36997.462 SLAB 1x1.5 3.4 7.1 1.2x1.4 N/A N/A P P P 8.1/8.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

204 37154.329 SLAB 1x1.5 3.2 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

205 37262.530 SLAB 1x1 3.1 6.7 N/A N/A P P P 6.6LV No Souring Sufficient Wooden logs are used Inspite of RCC slab

206 37548.713 SLAB 1x1 3.2 6.8 N/A N/A P P P 1.7/2.3V 6.3/4.7H No Souring Sufficient Wooden logs are used Inspite of RCC slab

207 37800.918 SLAB 1x0.8 3.4 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

208 37922.654 SLAB 1x1 3.2 6.4 N/A N/A P P P 2.8/6V 1.5/1.6H No Souring Sufficient Wooden logs are used Inspite of RCC slab

209 38057.300 PIPE 1x1 3.3 7.2 1.2x1.4 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

210 38134.578 SLAB 1x1 3.4 7.4 N/A N/A P P P 9.8/3.6V 1.1/1.0H Souring Nalla Wooden logs are used Inspite of RCC slab

211 38144.052 PIPE 1X9000mm 4.9 10.0 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

212 38239.199 SLAB 1x1.5 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

213 38334.011 SLAB 1x1.5 4.1 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

214 38576.510 SLAB 1x1 3.5 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

215 38738.717 SLAB 2.2x2.5 3.6 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

216 38820.191 SLAB 1.5x2 3.4 6.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

217 39094.166 SLAB 1x1 4.9 10.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

218 39334.628 SLAB 1x1 4.2 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

219 39457.084 SLAB 1X1 3.4 7.0 1x1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

220 39617.002 SLAB 1x1.5 4.0 9.0 1.8x2.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

221 39870.814 SLAB 1X1 3.5 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

222 39982.686 SLAB 1.2x1.5 3.6 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

223 40039.493 SLAB 1X1 3.7 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

224 40222.608 SLAB 1X1 3.2 6.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

225 40374.654 SLAB 1X1.5 3.9 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

226 40522.269 SLAB 1X4 4.4 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

227 41378.004 SLAB 1X1.5 3.5 5.9 1.8x2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

228 41565.419 SLAB 1X1 3.6 7.0 N/A N/A P P P 2.2/1.4 No Souring Sufficient Wooden logs are used Inspite of RCC slab

229 41684.912 PIPE 1x0.9 3.8 6.5 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

230 41888.625 SLAB 1X900 3.9 7.3 N/A N/A P P P 2.5/2.3 No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 34
231 42012.741 PIPE 1X1 3.8 7.1 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

232 42152.324 SLAB 1X1.5 4.0 7.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

233 42469.580 SLAB 1X1 3.8 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

234 42565.209 SLAB 1X1 3.2 5.6 2X2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

235 42705.157 SLAB 1X1.5 3.4 7.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

236 42814.272 SLAB 2x2.5 4.3 7.3 1.8x2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

237 42873.457 SLAB 1X1 4.0 7.3 1.7X1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

238 43053.302 SLAB 1x1.5 4.3 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

239 43212.293 SLAB 1X1 4.2 7.1 1.2X1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

240 43351.000 SLAB 1X1.5 4.1 7.2 N/A N/A P P P 5.1/6.3V 1.8/1.9H No Souring Sufficient Wooden logs are used Inspite of RCC slab

241 49175.829 SLAB 1X1 3.2 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

242 50226.539 SLAB 1X1.5 3.6 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

243 50449.706 PIPE 1X1 3.8 7.1 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

244 51342.268 PIPE 1X1 4.0 7.0 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

245 51873.980 PIPE 1X1 3.2 8.2 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

246 53895.735 SLAB 1X1 3.7 7.2 N/A N/A P P P 6.9/5.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

247 54220.461 SLAB 1X1.5 4.0 7.4 2X1.8 N/A N/A P P P 3.9/6.4 No Souring Sufficient Wooden logs are used Inspite of RCC slab

248 54560.211 PIPE 2X0.9 4.0 7.6 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

249 54640.814 PIPE 1X0.9 4.5 7.6 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

250 54830.038 SLAB 1X1.5 3.7 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

251 54932.665 PIPE 1X0.9 3.9 7.2 1.2X1.6 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

252 54987.490 SLAB 1X1.5 3.5 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

253 55256.863 SLAB 1.2X1.5 3.3 6.3 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

254 55468.153 SLAB 1X1.5 2.8 4.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

255 55624.844 SLAB 1X1 3.2 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

256 55693.442 PIPE 1X900 3.6 6.7 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

257 55899.266 SLAB 1X1 4.7 6.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

258 56274.652 SLAB 1X1.5 4.2 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

259 56579.028 SLAB 1X1.5 3.5 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

260 56724.894 SLAB 1X1 3.4 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

261 56765.108 SLAB 1.2X1.5 4.3 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

262 56902.015 PIPE 1X0.9 4.0 7.2 N/A N/A P P P 5.5/5.6V 1.9/1.3 N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

263 57228.422 PIPE 1X0.9 3.9 7.2 1.2X1.5 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie
Page 35
264 57261.361 SLAB 1X1.5 4.0 7.1 N/A N/A P P P 4.1/3V 1.6/0.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

265 57566.894 PIPE 1X0.9 4.2 7.0 N/A N/A P P P 14.2/2.1V 1.5/1.2 N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

266 57992.993 SLAB 1X1.5 3.8 7.1 N/A N/A P P P 8.7/6.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

267 58224.567 SLAB 1X1.5 4.3 7.3 N/A N/A P P P 4.3/3.3 No Souring Sufficient Wooden logs are used Inspite of RCC slab

268 58438.911 SLAB 1X2.0 4.0 7.3 N/A N/A P P P 3.4/5.2 No Souring Sufficient Wooden logs are used Inspite of RCC slab

269 58614.175 SLAB 1x1 4.0 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

270 58851.760 SLAB 1X1 4.0 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

271 59592.448 SLAB 1X1 3.7 7.0 N/A N/A P P P 5.5/4 No Souring Sufficient Wooden logs are used Inspite of RCC slab

272 59732.577 SLAB 1X1 3.6 7.0 1.5x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

273 59832.716 SLAB 1X1.50 4.0 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

274 59946.671 SLAB 1X1.5 3.5 6.8 1.5x1.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

275 60106.230 SLAB 1X1.5 3.5 6.8 N/A N/A P P P 3.6/2.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

276 60405.240 SLAB 1X1.5 3.3 6.6 N/A N/A P P P 1.8/1.6V1.2/1.5H No Souring Sufficient Wooden logs are used Inspite of RCC slab

277 60794.566 SLAB 1X1.5 3.7 6.5 N/A N/A P P P 1.5/3.8V0.8/0.9H No Souring Sufficient Wooden logs are used Inspite of RCC slab

278 60894.702 SLAB 1X1 3.6 6.6 N/A N/A P P P 1.2/3.9V 1.4/1H No Souring Sufficient Wooden logs are used Inspite of RCC slab

279 61002.869 SLAB 1X1 3.7 6.7 1.5x2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

280 61218.647 SLAB 1X1.5 3.2 6.7 N/A N/A P P P 7/2.2V 1.6LH No Souring Sufficient Wooden logs are used Inspite of RCC slab

281 61531.337 SLAB 1X2.0 3.2 6.0 N/A N/A P P P 1.8/3.4V 1.6/2.2H No Souring Sufficient Wooden logs are used Inspite of RCC slab

282 61705.410 SLAB 1X1 3.5 8.0 N/A N/A P P P 5.6RV1.4/0.9H No Souring Sufficient Wooden logs are used Inspite of RCC slab

283 61821.147 SLAB 1X1 3.7 7.2 1.5x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

284 62076.850 SLAB 1X1 3.5 7.0 1.5x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

285 62272.063 SLAB 1x1 3.4 7.0 1.5x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

286 62418.636 SLAB 1X1.50 3.5 7.0 N/A N/A P P P 11.3/0.8V0.8/0.9H No Souring Sufficient Wooden logs are used Inspite of RCC slab

287 62566.219 SLAB 1X1 3.6 6.8 N/A N/A P P P 4.7/0.8V1.3/0.8H No Souring Sufficient Wooden logs are used Inspite of RCC slab

288 62799.527 SLAB 1X1.5 3.4 7.1 N/A N/A P P P 1.9/2.7V 0.7/0.6 No Souring Sufficient Wooden logs are used Inspite of RCC slab

289 62893.804 SLAB 1X1 3.2 6.8 N/A N/A P P P 1.2/4.0V 1.2/1.4 No Souring Sufficient Wooden logs are used Inspite of RCC slab

290 62979.474 SLAB 1X2.0 3.4 7.1 N/A N/A P P P 3.5/4.4V 2/1.3H No Souring Sufficient Wooden logs are used Inspite of RCC slab

291 63253.409 SLAB 1X1 3.6 7.2 N/A N/A P P P 1.6/3.5V 1.1/0.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

292 63469.484 SLAB 1X2.0 3.4 7.0 1.5x1.4 N/A N/A P P P 4.8/2V 1.1/1.4 No Souring Sufficient Wooden logs are used Inspite of RCC slab

293 63658.453 SLAB 1X1.5 3.6 6.6 N/A N/A P P P 10.9V1.1/2H No Souring Sufficient Wooden logs are used Inspite of RCC slab

294 63834.469 SLAB 1X1 3.2 5.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

295 63918.778 SLAB 1X2.0 3.2 5.7 N/A N/A P P P 5.7/1.6V 0.5/0.6H No Souring Sufficient Wooden logs are used Inspite of RCC slab

296 64027.446 SLAB 1X1.5 3.4 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 36
297 64073.040 SLAB 1X1.5 3.6 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

298 64187.937 SLAB 1X1.5 4.0 7.1 1.5x2 N/A N/A P P P 1.8/5.8V 1.1/1.5H No Souring Sufficient Wooden logs are used Inspite of RCC slab

299 64230.274 SLAB 1X1.5 3.0 6.5 N/A N/A P P P 3.8/4.8V 0.6/0.8H No Souring Sufficient Wooden logs are used Inspite of RCC slab

300 64313.757 SLAB 1X2.0 4.0 6.5 N/A N/A P P P 1.2/1.1V 0.8/0.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab

301 64626.246 SLAB 1X1 3.5 6.7 N/A N/A P P P 2.5/1.1V 1.6/1.7H No Souring Sufficient Wooden logs are used Inspite of RCC slab

302 64716.270 SLAB 1X1.5 3.9 7.0 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

303 64792.052 SLAB 1X1.5 3.4 7.0 N/A N/A P P P 3.5/3.5V 1.2/0.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

304 64988.123 SLAB 1X1.5 3.5 6.9 N/A N/A P P P 9.6/2.3V No Souring Sufficient Wooden logs are used Inspite of RCC slab

305 65197.383 SLAB 1X1.5 3.5 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

306 65347.434 PIPE 1X900 3.4 7.0 N/A N/A P P P 3.8/8.4V 1.6/1.6H N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

307 65461.987 SLAB 1X1.5 3.7 7.4 N/A N/A P P P 5/5.6V No Souring Sufficient Wooden logs are used Inspite of RCC slab

308 65758.858 SLAB 1x1.5 3.6 7.2 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

309 65862.511 SLAB 1X1.5 3.5 7.0 N/A N/A P P P 5.4/6.1 No Souring Sufficient Wooden logs are used Inspite of RCC slab

310 65937.515 SLAB 1X1.5 3.3 7.0 N/A N/A P P P 15.3/1.7 No Souring Sufficient Wooden logs are used Inspite of RCC slab

311 65976.209 SLAB 1X1 3.3 7.0 N/A N/A P P P 5.9/6.2V0.9/0.6 No Souring Sufficient Wooden logs are used Inspite of RCC slab

312 66289.551 SLAB 1X1 3.6 7.0 N/A N/A P P P 26RV No Souring Sufficient Wooden logs are used Inspite of RCC slab

313 66433.018 SLAB 1X1.5 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

314 66.555.458 SLAB 1X1 3.0 5.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

315 66725.578 SLAB 1x1 3.6 6.5 1.5x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

316 66930.845 SLAB 1X1 3.1 6.2 N/A N/A P P P 5.2/3.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

317 67044.562 SLAB 1X1 3.7 7.0 1.5x2 N/A N/A P P P 3.6/4.4 No Souring Sufficient Wooden logs are used Inspite of RCC slab

318 67132.713 SLAB 1X1.5 3.7 7.0 1.5x1.2 N/A N/A P P P 1.9/4.6 No Souring Sufficient Wooden logs are used Inspite of RCC slab

319 67257.709 SLAB 1X1 3.3 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

320 67400.092 SLAB 1X1 3.3 6.5 1x1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

321 67551.531 SLAB 1XX1.5 3.3 7.0 2x1.5 N/A N/A P P P 5.7/1.5V No Souring Sufficient Wooden logs are used Inspite of RCC slab

322 67693.695 SLAB 1X1.5 3.5 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

323 68723.744 SLAB 1X1 3.7 7.0 1.5x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

324 67909.779 SLAB 1X1 3.6 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

325 67992.384 SLAB 1X1 3.5 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

326 68180.389 SLAB 1X1 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

327 68245.953 SLAB 1X1 3.8 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

328 68399.972 SLAB 1x1 3.5 7.3 N/A N/A P P P 1.7/14.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab

329 68822.315 SLAB 1X1.5 3.0 6.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 37
330 68915.207 SLAB 1X1 3.5 7.1 1.5x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

331 69058.858 SLAB 1X1.5 3.3 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

332 69322.691 SLAB 1X1 4.0 7.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

333 69405.551 SLAB 1X1 3.8 7.0 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

334 69526.905 SLAB 1X1.5 3.6 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

335 69665.098 SLAB 1X1.5 4.5 7.0 1.5x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

336 69725.660 SLAB 1X1.5 4.2 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

337 69963.082 SLAB 1X1.5 4.0 7.4 2x1.5 N/A N/A P P P 10.5/11.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

338 70059.898 SLAB 1X1.5 4.2 7.4 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

339 70166.928 SLAB 1X1.5 4.2 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

340 70332.621 SLAB 1.2x1.5 3.6 7.0 1.2x1.5 N/A N/A P P P 6.4/2.9 No Souring Sufficient Wooden logs are used Inspite of RCC slab

341 70386.016 SLAB 1X1 3.7 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

342 70475.059 SLAB 1.5x1.8 4.0 7.3 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

343 70617.944 SLAB 1X1.5 3.6 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

344 70711.470 SLAB 1X1.5 4.0 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

345 71002.852 SLAB 1X1.5 4.2 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

346 71089.396 SLAB 1X1.5 3.4 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

347 71256.779 SLAB 1X1.5 3.3 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

348 71373.314 SLAB 1X1 3.2 5.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

349 71634.526 SLAB 1X1.5 3.6 6.6 N/A N/A P P P 1/7.3V 1.3/1.4H No Souring Sufficient Wooden logs are used Inspite of RCC slab

350 71719.039 SLAB 1X1.5 3.7 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

351 71867.183 SLAB 1X1.5 3.6 6.4 1.6x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

352 71932.201 SLAB 1X1.5 3.8 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

353 72301.289 SLAB 2.5x3 4.5 8.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

354 72433.635 SLAB 1X1 3.4 6.3 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

355 72543.204 SLAB 1X1 3.6 6.8 N/A N/A P P P 8.1/9.3 No Souring Sufficient Wooden logs are used Inspite of RCC slab

356 72625.203 SLAB 1X1.5 3.6 7.0 N/A N/A P P P 7.2/4.8 No Souring Sufficient Wooden logs are used Inspite of RCC slab

357 72778.806 SLAB 1X1.5 3.4 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

358 BRIDGE 72854.95 TO 72973.402(118.80) No Souring Sufficient

359 73101.959 SLAB 1X1 3.3 6.5 1.2x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

360 73216.624 SLAB 1X1 3.8 6.9 1.2x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

361 73391.570 SLAB 1X1 4.1 7.0 1.2x1.0 N/A N/A P P P 5.7/4.5 No Souring Sufficient Wooden logs are used Inspite of RCC slab

362 73637.464 SLAB 1X1 4.2 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 38
363 73842.425 SLAB 1X1 3.7 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

364 73902.822 SLAB 1X1 3.6 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

365 74141.838 SLAB 1X1.5 3.7 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

366 74258.552 SLAB 1X1 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

367 74574.814 SLAB 1X1.5 3.8 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

368 74690.249 SLAB 1X1 4.0 7.1 1.0x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

369 75148.168 SLAB 1X1 3.7 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

370 75272.329 SLAB 2x2.5 3.7 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

371 75385.748 SLAB 1X1.5 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

372 75635.062 SLAB 1X1 3.7 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

373 75767.544 SLAB 1X1 3.8 6.9 1.2x1.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

374 75831.737 SLAB 2x2.5 4.2 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

375 76096.576 SLAB 1.5x2.5 3.8 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

376 76239.100 SLAB 5.5x4.5 4.6 7.4 N/A N/A P P P 8.8/7.6 No Souring Sufficient Wooden logs are used Inspite of RCC slab

377 76369.289 SLAB 2.5x3 4.2 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

378 76399.529 SLAB 2.5x3 4.0 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

379 76512.729 SLAB 1X1.6 3.6 7.1 1.2x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

380 76651.720 SLAB HW-17.51M 4.0 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

381 76680.517 SLAB 1x1.5 3.8 6.6 1.2x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

382 76698.726 SLAB 1X1.5 3.9 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

383 76834.486 TO7686.082


BRIDGE 3.4 6.0 No Souring Sufficient

384 76932.399 SLAB 1X1.5 3.8 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

385 76978.759 SLAB 1X1.5 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

386 77052.068 SLAB 2x2.5 3.8 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

387 77115.543 SLAB 1X1.5 4.1 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

388 77237.040 SLAB 1X1 4.0 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

389 77356.078 SLAB 1X1.5 3.9 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

390 77442.374 SLAB 1X1.5 4.1 7.0 1.2X1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

391 77588.999 SLAB 1x1.5 3.8 6.9 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

392 77662.692 SLAB 1X1 4.6 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

393 77790.491 SLAB 4x3.8 4.5 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

394 77902.145 SLAB 1X1.5 4.1 7.2 1.4X1.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

395 78093.546 SLAB 1x1.5 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 39
396 78135.316 SLAB 1X1.5 3.4 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

397 78178.796 SLAB 1X1.5 3.3 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

398 78301.349 SLAB 1X1.5 3.6 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

399 78429.061 SLAB 1X1.5 3.4 6.2 1.2X1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

400 78523.569 SLAB 1X1 3.4 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

401 78616.671 SLAB 1X1 3.4 7.0 1.2X1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

402 78672.677 SLAB 1X1 3.6 6.8 1x1.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

403 78803.986 SLAB 1X1 3.5 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

404 79067.886 SLAB 1X1.5 3.5 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

405 79326.374 SLAB 1X1.5 3.5 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

406 79652.794 SLAB 1X1.5 3.7 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

407 79847.044 SLAB 1X0.75 3.6 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

408 79953.449 SLAB 1X1.5 3.0 6.0 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

409 80366.784 SLAB 1X1 3.4 6.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

410 80570.288 SLAB 1X1.5 3.5 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

411 80872.642 SLAB 1X1.5 3.2 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

412 80937.349 SLAB 1X3 3.1 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

413 81028.664 SLAB 1X2 3.5 6.0 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

414 81625.934 SLAB 1X1 3.6 6.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

415 81661.326 SLAB 1X1.5 3.5 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

416 81997.577 SLAB 1X0.75 4.0 7.0 1.5X1.2 N/A N/A P P P 6.4/7.2V 1.4/0.7 No Souring Sufficient Wooden logs are used Inspite of RCC slab

417 82141.562 SLAB 1X1.5 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

418 82262.034 SLAB 1X1.5 3.0 6.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

419 82493.351 SLAB 1X1.5 3.2 6.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

420 82575.103 SLAB 1X1.5 3.4 6.3 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

421 82735.643 SLAB 1X1.5 3.8 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

422 82823.021 SLAB 1.2x1.8 3.6 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

423 82988.153 SLAB 1X1.5 4.0 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

424 83081.779 SLAB 1X1 3.3 6.4 N/A N/A P P P 6.4LV No Souring Sufficient Wooden logs are used Inspite of RCC slab

425 83192.804 SLAB 1X6 3.4 6.2 1.5x1.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

426 83507.518 SLAB 1X1.5 3.5 6.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

427 83574.939 SLAB 1X2 3.3 6.6 N/A N/A P P P Souring Nalla Wooden logs are used Inspite of RCC slab

428 83701.046 SLAB 1X1 3.4 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Page 40
429 83905.387 SLAB 1X1 4.0 7.0 2x1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab
Appendix-II C
INVENTORY & CONDITION SURVEY FOR CULVERTS
Road Name :LUNGLEI TO TLABUNG (NH-302) Sheet No. :

Section : Date of Survey : 10.09.09 to 25.09.09

REFERENCE FOR REMARKS G = Good F = Fair P = Poor VP = Very Poor NA = Not Avoidable N/A = Not Available

1 Opening of the masonry joints 2 Damage of the headwall 3 Bulging of headwall 4 Crack in the wall 5 Part damage of the wall

6 Completely choked 7 Growing of vegetation 8 Crack in the parapet 9 No parapet,all damage 10 Partial choked

Span Details of Protection Works Condition of various features of Culvert


Type of
Arrangement
Sl. Location structure Thickness of Carriageway Width of Height of Presence of Adequacy of
and Total Remarks
No. (m) (Pipe,Slab,Box slab (m) Width(m) Culvert (m) Slab/ Pipe/ Head Wing Parapet/ wing wall Sour Water-way
Ventway[No.xL Catch Pit Apron Type Condition Return Wall
,Arch) Box/ Arch Wall Wall Handrail
enght(m)]

430 84008.195 SLAB 1x1.5 4.1 7.3 N/A N/A P P P 7/8.5V 3/2.3H No Souring Sufficient Wooden logs are used Inspite of RCC slab

431 84106.816 SLAB 3x2.5 4.2 7.0 N/A N/A P P P 6.6/5.2V 0.8/2.1H No Souring Sufficient Wooden logs are used Inspite of RCC slab

432 84276.534 SLAB 1x1 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

433 84717.175 SLAB 1X1 3.9 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

434 84924.866 SLAB 1X1 4.0 7.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

435 85082.167 SLAB 21x1.2 4.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

436 85201.312 SLAB 1X1 3.6 7.1 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

437 85228.617 SLAB 1X1 3.7 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

438 85335.510 SLAB 1X1.5 3.8 7.0 1.8x2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

439 85649.813 SLAB 1X1.5 3.9 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

440 85850.045 SLAB 1X1 3.0 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

441 85907.220 SLAB 1X1 4.0 6.6 1.2x1.4 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

442 86006.704 SLAB 1x1.2 3.8 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

443 86160.489 SLAB 1X1 3.6 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

444 86422.624 SLAB 1.2x1.5 4.0 6.9 1.2X1.6 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

445 86560.335 SLAB 1X1 3.8 7.0 1.5X1.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

446 86703.025 SLAB 1X1 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

447 86776.117 SLAB 1.2x1.5 3.9 7.2 N/A N/A P P P 3.9/3.9V 0.5/1.0H No Souring Sufficient Wooden logs are used Inspite of RCC slab

448 87262.960 SLAB 1.2x1.5 4.0 7.2 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

449 87299.707 SLAB 2.5x1.6 3.5 6.7 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

450 87479.364 SLAB 1x1.2 3.7 6.5 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

451 87550.064 SLAB 1x1.5 3.6 6.8 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

452 88676.853 SLAB 1.2x1.5 4.4 6.9 2X1.5 N/A N/A P P P 1.8RV No Souring Sufficient Wooden logs are used Inspite of RCC slab

453 89195.229 SLAB 1x1.2 3.7 7.0 N/A N/A P P P No Souring Sufficient Wooden logs are used Inspite of RCC slab

454 89345.823 SLAB 1x1 3.4 5.6 N/A N/A P P P 4.7/4.5V 1.2/1.3H No Souring Sufficient Wooden logs are used Inspite of RCC slab

455 89386.945 PIPE 1x0.9 3.8 7.2 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

456 89589.647 PIPE 1x0.9 4.2 7.2 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

457 90871.673 PIPE 1x0.9 3.4 6.0 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

458 91012.102 PIPE 1x0.9 2.6 4.9 N/A N/A P P P N/A No Souring Sufficient GI sheets are used inplaca of RCC pipie

Page 41
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
1 284 290 12 1.5 8 1,2,3,6,7
2 643 625 9.78 1.2 4 1,2,3,6,7
3 818 829 11 4.3 8 1,2,3,6,7
4 1008 1016 8.16 5.4 4 1,2,3,6,7
5 1320 1335 14.82 1.5 NP 1,2,3,5,6,7
6 1448 1450 2.1 2 NP 1,2,3,5,6,7
7 1570 1577 7.48 2 NP 1,2,3,5,6,7
8 1998 2036 37.69 3 3 1,2,3,6,7
9 2115 2125 9.2 2.2 NP 1,2,3,5,6,7
10 2152 2177 25.54 2.4 NP 1,2,3,5,6,7
11 2391 2422 31.48 2.5 2 1,2,3,6,7
12 2455 2493 37.79 3 2 1,2,3,6,7
13 2818 2853 34.99 1.5 NP 1,2,3,5,6,7
14 2956 2984 28.28 2.1 13 1,2,3,6,7
15 3059 3060 1.11 0.5 NP 1,2,3,5,6,7
16 3168 3205 37.09 4.2 6 1,2,3,6,7
17 3235 3346 110.98 5.5 81 1,2,3,6,7
18 3469 3487 17.93 1.5 NP 1,2,3,5,6,7
19 3628 3636 8.15 1.5 NP 1,2,3,5,6,7
20 3762 3776 13.97 1.2 2 1,2,3,6,7
21 3870 3878 7.24 0.8 4 1,2,3,6,7
22 3928 4004 75.22 3.4 18 1,2,3,6,7
23 4071 4106 34.71 5.2 16 1,2,3,6,7
24 4168 4174 6.1 1 2 1,2,3,6,7
25 4263 4452 189.09 2.6 NP 1,2,3,5,6,7
26 4463 4541 77.7 2.2 33 1,2,3,6,7
27 4680 4775 95.08 5.3 29 1,2,3,6,7
28 4785 4787 1.58 0.6 NP 1,2,3,5,6,7
29 4841 4854 12.09 1.2 4 1,2,3,6,7
30 4898 4906 8.54 1.4 3 1,2,3,6,7
31 5133 5208 75.07 3.2 36 1,2,3,6,7
32 5505 5509 4.33 1.1 2 1,2,3,6,7
33 5714 5807 92.69 1.5 14 1,2,3,6,7
34 5855 5881 26.19 1 7 1,2,3,6,7
35 5875 5881 6.28 1.2 7 1,2,3,6,7
36 5928 6087 158.67 1.2 5 1,2,3,6,7
37 6152 6158 6.32 1.5 8 1,2,3,6,7
38 6186 6212 25.61 1.5 10 1,2,3,6,7
39 6429 6443 13.95 1.2 6 1,2,3,6,7
40 6500 6564 64.47 1.2 23 1,2,3,6,7
41 6601..603 6705 103.07 3 17 1,2,3,6,7
42 6915 6936 20.39 0.8 11 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
43 6999 7011 11.47 2.5 6 1,2,3,6,7
44 7041 7065 23.95 1.8 2 1,2,3,6,7
45 7067 7091 23.63 1.2 16 1,2,3,6,7
46 7118 7136 17.24 1 9 1,2,3,6,7
47 7181 7206 25.24 1.2 7 1,2,3,6,7
48 7272 7328 55.88 1 6 1,2,3,6,7
49 7490 7508 18.02 2 10 1,2,3,6,7
50 7673 7680 7.03 0.8 8 1,2,3,6,7
51 7699 7707 8.23 1.5 3 1,2,3,6,7
52 7890 7894 4.72 1.5 3 1,2,3,6,7
53 7928 7935 7.18 1.3 6 1,2,3,6,7
54 5059 8070 11.22 1.3 3 1,2,3,6,7
55 8075 8080 4.2 2 6 1,2,3,6,7
56 8179 8191 12.58 2 2 1,2,3,6,7
57 8281 8303 21.89 2.5 2 1,2,3,6,7
58 8410 8422 11.72 1.5 6 1,2,3,6,7
59 8560 8579 19.61 2 5 1,2,3,6,7
60 8751 8759 8.08 1.8 8 1,2,3,6,7
61 9749 9762 12.99 1.1 5 1,2,3,6,7
62 9803 9812 8.47 2.5 4 1,2,3,6,7
63 9898 9910 12.32 2 4 1,2,3,6,7
64 10034 10039 4.45 1.5 3 1,2,3,6,7
65 10113 10136 22.65 2 3 1,2,3,6,7
66 10187 10196 9.42 1.5 1 1,2,3,6,7
67 10322 10333 11.53 1.2 1 1,2,3,6,7
68 10391 10399 8.12 2 7 1,2,3,6,7
69 10445 10454 16.72 1.5 3 1,2,3,6,7
70 10492 10509 16.73 1.3 2 1,2,3,6,7
71 10541 10553 12.9 1 NP 1,2,3,5,6,7
72 10580 10591 11.02 1.5 12 1,2,3,6,7
73 10676 10684 8.28 2 4 1,2,3,6,7
74 10818 10824 5.83 2.5 5 1,2,3,6,7
75 10849 10873 23.84 2.5 4 1,2,3,6,7
76 10915 10927 12.06 1.5 1.1 1,2,3,6,7
77 11001 11012 11.45 3 4 1,2,3,6,7
78 11610 11629 19.53 2 5 1,2,3,6,7
79 11653 11676 23.41 3 3 1,2,3,6,7
80 11721 11751 29.98 1.2 NP 1,2,3,5,6,7
81 11844 11883 39.87 1.2 NP 1,2,3,5,6,7
82 11943 11950 6.45 2 9 1,2,3,6,7
83 11982 11992 9.83 2 NP 1,2,3,5,6,7
84 12296 12314 17.17 3 1 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
85 12362 12405 43.13 2 7 1,2,3,6,7
86 12392 12419 27.63 1.5 3 1,2,3,6,7
87 12419 12437 18.16 1.5 3 1,2,3,6,7
88 12783 12786 3.83 1.5 3 1,2,3,6,7
89 12838 12843 4.81 2 NP 1,2,3,5,6,7
90 13717 13721 4.55 1.5 NP 1,2,3,5,6,7
91 13861 138883 28.32 2.5 7 1,2,3,6,7
92 13879 13891 12.36 4.5 9 1,2,3,6,7
93 14663 14670 6.63 2 2 1,2,3,6,7
94 14819 14835 15.67 1.5 5 1,2,3,6,7
95 15118 15123 4.91 1.8 5 1,2,3,6,7
96 15246 15258 12.32 2 2 1,2,3,6,7
97 15419 15425 5.8 1.5 NP 1,2,3,5,6,7
98 15985 15992 7.47 1.5 NP 1,2,3,5,6,7
99 16029 16041 12.31 2 2 1,2,3,6,7
100 16363 16371 7.59 2 NP 1,2,3,5,6,7
101 16416 16426 9.94 1.2 NP 1,2,3,5,6,7
102 17057 17071 14.06 3 5 1,2,3,6,7
103 17572 17578 5.77 1.5 3 1,2,3,6,7
104 17994 18007 36 4 4 1,2,3,6,7
105 18056 18069 13 1.8 10 1,2,3,6,7
106 18316 18436 120 2 4 1,2,3,6,7
107 18450 18486 36.47 2 NP 1,2,3,5,6,7
108 18558 18565 7.09 1.5 NP 1,2,3,5,6,7
109 18613 18625 12.49 1 5 1,2,3,6,7
110 18668 18688 20.44 1.2 NP 1,2,3,5,6,7
111 18721 18764 43.21 2.5 NP 1,2,3,5,6,7
112 18863 18877 13.81 1.2 NP 1,2,3,5,6,7
113 19343 19358 15.11 1.4 6 1,2,3,6,7
114 19566 19572 5.26 1 8 1,2,3,6,7
115 19692 19722 29.66 2.8 3 1,2,3,6,7
116 20001 20092 90.74 5.2 NP 1,2,3,5,6,7
117 20277 20353 75.76 3.5 8 1,2,3,6,7
118 20365 20488 123.08 3.5 9 1,2,3,6,7
119 20619 20699 79 2.5 7 1,2,3,6,7
120 20954 20999 45.31 1.3 6 1,2,3,6,7
121 21032 21097 65.75 1.2 6 1,2,3,6,7
122 21092 21232 140.2 1.2 4 1,2,3,6,7
123 21208 21346 137.84 1 2 1,2,3,6,7
124 21456 21494 37.9 1.5 7 1,2,3,6,7
125 21509 21523 13.76 1.5 1 1,2,3,6,7
126 21553 21624 71.38 1.5 NP 1,2,3,5,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
127 21722 21758 36.06 4 6 1,2,3,6,7
128 21781 21795 13.99 4 11 1,2,3,6,7
129 21869 21910 40.83 3.5 8 1,2,3,6,7
130 21931 22047 115.65 1.5 8 1,2,3,6,7
131 22191 22198 7.29 1.5 5 1,2,3,6,7
132 22234 22245 10.49 1.5 5 1,2,3,6,7
133 22291 22299 7.86 2 4 1,2,3,6,7
134 22342 22354 11.88 1.2 6 1,2,3,6,7
135 22406 22430 23.97 1.9 16 1,2,3,6,7
136 22753 22752 19.34 1.7 10 1,2,3,6,7
137 23905 23918 12.77 1.5 9 1,2,3,6,7
138 23948 23962 13.86 1.2 5 1,2,3,6,7
139 24142 24159 17.06 2 5 1,2,3,6,7
140 24426 24441 14.73 1 NP 1,2,3,5,6,7
141 24500 24509 9.65 1.8 NP 1,2,3,5,6,7
142 24637 24686 48.85 2 9 1,2,3,6,7
143 27238 27248 9.32 0.8 6 1,2,3,6,7
144 27908 27922 14.26 2 5 1,2,3,6,7
145 28835 28856 20.16 2 4 1,2,3,6,7
146 29169 29198 28.3 2.2 4 1,2,3,6,7
147 29283 29295 11.83 1.8 3 1,2,3,6,7
148 29792 29802 10.08 1 3 1,2,3,6,7
149 29909 29922 12.97 1.4 4 1,2,3,6,7
150 30066 30072 6.11 1.1 NP 1,2,3,5,6,7
151 30859 30865 6.08 1 2 1,2,3,6,7
152 31231 31241 9.98 1.2 3 1,2,3,6,7
153 31499 31515 16.32 2.1 4 1,2,3,6,7
154 31576 31589 13.09 1.8 2 1,2,3,6,7
155 32034 32055 20.32 2 4 1,2,3,6,7
156 32083 32140 56.86 3.5 22 1,2,3,6,7
157 32222 32254 31.52 2.6 NP 1,2,3,5,6,7
158 32316 32336 19.89 1.8 NP 1,2,3,5,6,7
159 32407 32424 16.24 1.5 NP 1,2,3,5,6,7
160 32482 32495 12.68 1.2 4 1,2,3,6,7
161 32615 32717 101.78 4.2 51 1,2,3,6,7
162 32836 32868 32.428 1.6 4 1,2,3,6,7
163 33165 33214 48.6 2.5 NP 1,2,3,5,6,7
164 33604 33645 41.07 3.5 NP 1,2,3,5,6,7
165 34005 34043 38.57 4.2 NP 1,2,3,5,6,7
166 34342 34353 11.56 1.2 5 1,2,3,6,7
167 34545 34558 12.46 1.2 4 1,2,3,6,7
168 34605 34615 9.34 1 6 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
169 34734 34748 14.27 2 NP 1,2,3,5,6,7
170 34820 34845 25.55 2.2 12 1,2,3,6,7
171 35208 35214 6.39 1.8 2 1,2,3,6,7
172 35245 35263 17.95 1.5 4 1,2,3,6,7
173 35380 35385 4.95 0.8 4 1,2,3,6,7
174 36108 36123 14.52 2 7 1,2,3,6,7
175 36408 36416 7.58 1.2 3 1,2,3,6,7
176 36442 36455 13.42 1.6 7 1,2,3,6,7
177 62503 36509 5.938 0.8 NP 1,2,3,5,6,7
178 36535 36562 26.56 2.1 18 1,2,3,6,7
179 36275 36742 17.57 1.8 NP 1,2,3,5,6,7
180 37071 37073 1.48 0.8 NP 1,2,3,5,6,7
181 37131 37146 15.14 1.2 10 1,2,3,6,7
182 37245 37253 7.95 1.2 3 1,2,3,6,7
183 37275 37339 63.63 2.2 22 1,2,3,6,7
184 37371 37411 40.26 2.4 NP 1,2,3,5,6,7
185 37447 37463 16.434 1.8 10 1,2,3,6,7
186 37489 37516 26.93 2.2 NP 1,2,3,5,6,7
187 37729 37740 10.92 1.2 7 1,2,3,6,7
188 37778 37796 17.68 2.5 NP 1,2,3,5,6,7
189 37809 37816 7.737 1.8 5 1,2,3,6,7
190 37849 37859 10.69 1.5 7 1,2,3,6,7
191 38242 38251 9.45 1.5 6 1,2,3,6,7
192 38318 38328 9.65 1.2 3 1,2,3,6,7
193 38332 38368 35.75 2.8 NP 1,2,3,5,6,7
194 38419 38425 5.58 1 2 1,2,3,6,7
195 38577 38611 34.05 2.8 8 1,2,3,6,7
196 38732 38734 2.052 1 2 1,2,3,6,7
197 38739 38741 2.7 0.8 NP 1,2,3,5,6,7
198 38778 38793 14.96 2.2 NP 1,2,3,5,6,7
199 38825 38859 34.37 2.4 14 1,2,3,6,7
200 38943 38965 22.78 3.4 6 1,2,3,6,7
201 39202 39216 14.43 3 NP 1,2,3,5,6,7
202 39453 39456 3.08 1 3 1,2,3,6,7
203 39459 39460 1.62 0.8 1 1,2,3,6,7
204 39585 39596..041 11.15 1.2 8 1,2,3,6,7
205 39617 39622 4.9 1.6 2 1,2,3,6,7
206 39863 39873 10.8 2.2 7 1,2,3,6,7
207 40029 40038 8.8 1.8 4 1,2,3,6,7
208 40041 40057 16.02 2 10 1,2,3,6,7
209 40179 40186 7.67 2 1 1,2,3,6,7
210 40378 40385 6.62 2.4 3 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
211 40420 40426 5.91 2 NP 1,2,3,5,6,7
212 40514 40519 5.52 2 NP 1,2,3,5,6,7
213 40567 40571 4.15 1.8 NP 1,2,3,5,6,7
214 40657 40670 12.89 2 NP 1,2,3,5,6,7
215 40835 40851 16.25 2.1 NP 1,2,3,5,6,7
216 40922 40988 65.84 3.2 NP 1,2,3,5,6,7
217 41030 41053 22.75 2.5 4 1,2,3,6,7
218 41058 41081 23.49 3.1 6 1,2,3,6,7
219 41164 41208 44 4.8 13 1,2,3,6,7
220 41282 41293 10.39 1.2 4 1,2,3,6,7
221 41339 41351 11.81 2 1 1,2,3,6,7
222 41530 41547 17.65 3.5 4 1,2,3,6,7
223 41776 41783 6.52 2 NP 1,2,3,5,6,7
224 41842 41851 8.9 3.5 1 1,2,3,6,7
225 41967 41984 16.42 2 4 1,2,3,6,7
226 42234 42246 12.19 1.5 4 1,2,3,6,7
227 42386 42396 9.73 2 7 1,2,3,6,7
228 42951 42962 10.86 1.5 3 1,2,3,6,7
229 43477 43489 11.31 2.1 4 1,2,3,6,7
230 44986 45007 14.18 1.2 4 1,2,3,6,7
231 45127 45246 119 5.2 36 1,2,3,6,7
232 45311 45332 20.64 3.2 16 1,2,3,6,7
233 45744 45756 12.01 1.8 7 1,2,3,6,7
234 45795 45811 16.5 2 NP 1,2,3,5,6,7
235 46119 46133 14.5 2.4 NP 1,2,3,5,6,7
236 46163 46193 29.94 3.8 19 1,2,3,6,7
237 46238 46308 69.58 4.5 13 1,2,3,6,7
238 46343 46350 6.29 1.2 2 1,2,3,6,7
239 46594 46639 44.25 4.2 10 1,2,3,6,7
240 46674 46739 65.43 3.5 14 1,2,3,6,7
241 46810 46818 8.52 1.2 5 1,2,3,6,7
242 46929 46971 42.08 3.8 24 1,2,3,6,7
243 47024 47034 10.23 1.2 NP 1,2,3,5,6,7
244 47183 47189 6.52 0.8 NP 1,2,3,5,6,7
245 47278 47296 18.41 1.8 6 1,2,3,6,7
246 47357 47376 19.07 2 4 1,2,3,6,7
247 47452 47483 31.49 2.5 17 1,2,3,6,7
248 47751 47767 16.09 2.1 NP 1,2,3,5,6,7
249 47842 47853 11.22 0.8 6 1,2,3,6,7
250 47937 47955 18.19 1.8 8 1,2,3,6,7
251 48004 48032 28.26 2 14 1,2,3,6,7
252 48107 48164 56.69 3.9 37 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
253 48222 48262 40.06 4.8 23 1,2,3,6,7
254 48283 48324 41.11 5.2 24 1,2,3,6,7
255 48634 48718 83.97 4.7 3 1,2,3,6,7
256 48761 48823 62.38 3.8 4 1,2,3,6,7
257 49452 49469 17.27 2.8 2 1,2,3,6,7
258 49514 49524 9.87 1.4 NP 1,2,3,5,6,7
259 49635 49640 4.74 0.8 NP 1,2,3,5,6,7
260 49707 49732 24.49 1.4 13 1,2,3,6,7
261 50044 50065 21.18 2.2 13 1,2,3,6,7
262 50144 50170 26.33 4 5 1,2,3,6,7
263 50241 50251 10.04 1.2 2 1,2,3,6,7
264 50533 50545 12.04 1.4 4 1,2,3,6,7
265 50596 50616 20.36 1.5 12 1,2,3,6,7
266 50763 50763 3.08 0.8 1 1,2,3,6,7
267 50765 50769 3.86 1.8 NP 1,2,3,5,6,7
268 50810 50841 30.14 4 21 1,2,3,6,7
269 50888 50913 24.97 3.2 16 1,2,3,6,7
270 50951 50971 19.84 3 8 1,2,3,6,7
271 51187 51208 21.74 3.8 13 1,2,3,6,7
272 52088 52100 11.67 2.8 8 1,2,3,6,7
273 52577 52598 20.15 3.2 15 1,2,3,6,7
274 52695 52698 3.53 2.3 2 1,2,3,6,7
275 53378 53384 5.98 1.5 NP 1,2,3,5,6,7
276 53444 53457 13.66 2.1 NP 1,2,3,5,6,7
277 54067 54081 13.61 3.5 2 1,2,3,6,7
278 54125 54136 10.9 1.5 NP 1,2,3,5,6,7
279 54825 54837 12.15 4.6 NP 1,2,3,5,6,7
280 55083 55114 30.82 2.3 NP 1,2,3,5,6,7
281 55171 55187 15.69 2.3 NP 1,2,3,5,6,7
282 55368 55379 11.09 1.5 NP 1,2,3,5,6,7
283 55462 55468 6.3 1.5 10 1,2,3,6,7
284 55470 55476 5.82 1.5 7 1,2,3,6,7
285 55831 55840 9.25 3.3 NP 1,2,3,5,6,7
286 55890 55898 7.47 2.8 NP 1,2,3,5,6,7
287 55901 55907 5.69 1.6 8 1,2,3,6,7
288 56041 56051 10.44 1.7 9 1,2,3,6,7
289 56349 56389 40.03 2.5 1 1,2,3,6,7
290 56491 56502 11.05 1.7 NP 1,2,3,5,6,7
291 56573 56577 3.85 1.5 3 1,2,3,6,7
292 56579 56584 4.74 2 3 1,2,3,6,7
293 56612 56622 9.16 2 NP 1,2,3,5,6,7
294 56663 56668 5.19 1.5 8 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
295 56895 56901 5.78 1.5 4 1,2,3,6,7
296 56902 56908 5.97 1.5 6 1,2,3,6,7
297 57011 57024 12.92 1.8 NP 1,2,3,5,6,7
298 57054 57065 10.6 2.1 4 1,2,3,6,7
299 57152 57178 26.13 2.2 13 1,2,3,6,7
300 57381 57389 7.26 1.4 4 1,2,3,6,7
301 57651 57695 43.78 1.5 NP 1,2,3,5,6,7
302 57763 57770 6.78 1.2 4 1,2,3,6,7
303 57886 57935 49.16 1.6 5 1,2,3,6,7
304 58067 58073 6.54 1.2 5 1,2,3,6,7
305 58399 58435 35.36 2.5 24 1,2,3,6,7
306 58616 58626 10.14 3 3 1,2,3,6,7
307 58691 58739 48.66 3 12 1,2,3,6,7
308 58867 58867 6.05 2.2 NP 1,2,3,5,6,7
309 58938 58953 14.87 16 6 1,2,3,6,7
310 59314 59346 32.44 2 27 1,2,3,6,7
311 59403 59414 11.6 1.2 4 1,2,3,6,7
312 59457 59486 28.85 1.5 NP 1,2,3,5,6,7
313 59823 59845 22.18 2.2 NP 1,2,3,5,6,7
314 59938 59953 14.71 2 5 1,2,3,6,7
315 60059 60063 4.34 2 NP 1,2,3,5,6,7
316 60649 60721 73.13 3 28 1,2,3,6,7
317 61249 61269 20.33 2 5 1,2,3,6,7
318 61301 61313 12 3.2 NP 1,2,3,5,6,7
319 61334 61343 9.8 3.2 NP 1,2,3,5,6,7
320 61550 61572 22.97 2.1 NP 1,2,3,5,6,7
321 61954 61977 22.43 2 NP 1,2,3,5,6,7
322 62043 62057 13.71 4 11 1,2,3,6,7
323 62120 62161 40.45 2.2 NP 1,2,3,5,6,7
324 63044 63067 22.81 2 9 1,2,3,6,7
325 63201 63209 8.9 3 4 1,2,3,6,7
326 63417 63431 13.62 2.5 NP 1,2,3,5,6,7
327 64076 64092 15.51 3 9 1,2,3,6,7
328 64136 64144 7.56 2.5 3 1,2,3,6,7
329 64211 64219 7.45 3.5 NP 1,2,3,5,6,7
330 64519 64534 15.14 4 NP 1,2,3,5,6,7
331 64562 64574 12.04 2 NP 1,2,3,5,6,7
332 64740 64749 9.16 5.5 NP 1,2,3,5,6,7
333 64860 64868 7.46 2.5 6 1,2,3,6,7
334 64928 64937 9.27 2.1 5 1,2,3,6,7
335 65176 65188 11.75 2.5 7 1,2,3,6,7
336 65506 65511 5.4 2.5 7 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
337 65547 65556 9.19 5 NP 1,2,3,5,6,7
338 65983 66010 26.5 3.5 NP 1,2,3,5,6,7
339 66194 66220 26.09 2.8 7 1,2,3,6,7
340 66364 66372 7.92 2.2 NP 1,2,3,5,6,7
341 66792 66808 15.87 4 12 1,2,3,6,7
342 66924 66934 5.37 2.6 NP 1,2,3,5,6,7
343 67063 67072 8.42 2.2 6 1,2,3,6,7
344 67132 67136 4.66 2.5 NP 1,2,3,5,6,7
345 67463 67484 16.12 2.1 2 1,2,3,6,7
346 67544 67550 5.7 3 2 1,2,3,6,7
347 67586 67587 18.99 1.2 NP 1,2,3,5,6,7
348 67948 67962 14.29 1.8 6 1,2,3,6,7
349 67992 67997 5.28 1.2 4 1,2,3,6,7
350 68957 69009 52.1 1.8 1.4 1,2,3,6,7
351 69091 69138 47.45 2.5 11 1,2,3,6,7
352 69210 69221 10.53 1.5 NP 1,2,3,5,6,7
353 69251 69276 24.77 2 9 1,2,3,6,7
354 69618 69625 7.62 1.6 3 1,2,3,6,7
355 69702 69714 11.6 1.8 2 1,2,3,6,7
356 69776 69833 56.82 2.2 NP 1,2,3,5,6,7
357 69878 69885 7.83 1.5 2 1,2,3,6,7
358 70589 70595 6.08 2 NP 1,2,3,5,6,7
359 70995 71001 6.77 1.8 3 1,2,3,6,7
360 71568 71587 18.76 2.8 NP 1,2,3,5,6,7
361 71665 71672 6.75 4 4 1,2,3,6,7
362 71950 71969 19.03 2.5 9 1,2,3,6,7
363 72715 71969 19.03 2.5 9 1,2,3,6,7
364 73174 73182 8.03 3 3 1,2,3,6,7
365 73296 73324 28.07 4 9 1,2,3,6,7
366 73534 73581 46.9 2.2 11 1,2,3,6,7
367 74058 74070 11.78 2.1 NP 1,2,3,5,6,7
368 74104 74133 28.94 2 6 1,2,3,6,7
369 74715 74727 12.59 2 4 1,2,3,6,7
370 75080 75093 12.95 1.8 7 1,2,3,6,7
371 75319 75351 31.94 2 21 1,2,3,6,7
372 75403 75412 9.18 2 4 1,2,3,6,7
373 75854 75856 1.65 0.8 NP 1,2,3,5,6,7
374 76264 76275 10.82 2 3 1,2,3,6,7
375 76264 76307 12.12 2 NP 1,2,3,5,6,7
376 76437 76453 15.29 3 4 1,2,3,6,7
377 76499 76506 7.37 2 NP 1,2,3,5,6,7
378 76559 76581 21.85 3 6 1,2,3,6,7
INVENTORY & CONDITION SURVEY FOR RETAINING WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II D
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Parapet wall fully broken
2 Crack in the wall 6 Growing of vegetation or weeds
3 Part damage of the wall 7 Depression of the soil of retaining wall
4 Crack in the parapet wall 8 Erosion of the v/s toe at foundation
Chainage in m Structure Length in Height in Parapet
Sl. No Remarks
FROM TO No. m m Wall No.
379 77422 77432 9.49 2.5 3 1,2,3,6,7
380 77726 77745 18.83 3 NP 1,2,3,5,6,7
381 78024 78032 7.86 1.5 2 1,2,3,6,7
382 78280 78294 7.77 2.2 3 1,2,3,6,7
383 78428 78439 11.81 1.5 NP 1,2,3,5,6,7
384 78820 78856 32.39 3.2 5 1,2,3,6,7
385 79298 79306 7.6 2 2 1,2,3,6,7
386 79341 79349 8.24 3 1 1,2,3,6,7
387 79520 79532 12.23 2.5 NP 1,2,3,5,6,7
388 79713 79720 6.59 2 NP 1,2,3,5,6,7
389 80008 80063 54.65 2.5 2 1,2,3,6,7
390 80178 80187 9.02 3 4 1,2,3,6,7
391 80213 80224 11.38 2 2 1,2,3,6,7
392 80483 80491 7.76 2 2 1,2,3,6,7
393 80695 80705 1047 2 3 1,2,3,6,7
394 81215 81224 8.91 2 3 1,2,3,6,7
395 81333 81345 11.92 1.8 NP 1,2,3,5,6,7
396 81540 81621 81.03 2.5 11 1,2,3,6,7
397 81671 81708 36.51 2 11 1,2,3,6,7
398 81734 81757 22.67 2.2 11 1,2,3,6,7
399 81720 81814 22.36 1.8 6 1,2,3,6,7
400 81844 81859 15.08 2.8 6 1,2,3,6,7
401 81905 81912 7.93 2 4 1,2,3,6,7
402 81929 81943 14.62 1.5 4 1,2,3,6,7
403 83860 83877 16.99 1.5 5 1,2,3,6,7
404 84044 84063 18.85 2.6 5 1,2,3,6,7
405 84702 84709 7.34 1.8 NP 1,2,3,5,6,7
406 84734 85017 23.34 3 3 1,2,3,6,7
407 84994 85017 23.34 3 3 1,2,3,6,7
408 85375 85386 10.76 1.5 NP 1,2,3,5,6,7
409 85573 85581 8.72 1.8 3 1,2,3,6,7
410 85608 85615 6.87 2.8 NP 1,2,3,5,6,7
411 85640 85642 3.17 1.6 3 1,2,3,6,7
412 85657 85663 5.86 1 2 1,2,3,6,7
413 85891 85896 5.76 2 5 1,2,3,6,7
414 86468 86476 7.44 2.2 4 1,2,3,6,7
415 86989 86999 9.78 1.5 NP 1,2,3,5,6,7
416 87434 87442 7.87 2 3 1,2,3,6,7
417 88530 88540 9.35 1.8 NP 1,2,3,5,6,7
418 88558 88563 5.08 2 NP 1,2,3,5,6,7
419 89509 89523 14.69 1.5 NP 1,2,3,5,6,7
420 89757 89772 14.27 4 NP 1,2,3,5,6,7
INVENTORY & CONDITION SURVEY FOR BREAST WALL
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix-II E
Section : Dt of Survey :10.09.09 to 26.09.09
REFERENCE FOR REMARKS
1 Bulging of retaining wall 5 Depression of the soil of breast wall
2 Crack in the wall 6 Erosion of the v/s toe at foundation
3 Part damage of the wall 7 Top portion of the breast wall damage
4 Growing of vegetation or weeds
Chainage in m Top
Structure Length in Height in
Sl. No Width in Remarks
FROM TO No. m m
m
1 50 79 30 5.5 0.6 1,3,4,5,7
2 843 866 23 3.2 0.6 1,3,4,5,7
3 2971 2989 18 2.5 0.6 1,3,4,5,7
4 5596 5624 28 2.1 0.6 1,3,4,5,7
5 6762 6772 10 1.5 0.6 1,3,4,5,7
6 7417 7447 30 1.5 0.6 1,3,4,5,7
7 8150 8187 37 3 0.6 1,3,4,5,7
8 10318 10340 22 3 0.6 1,3,4,5,7
9 11250 11266 16 2.2 0.6 1,3,4,5,7
10 12292 12304 12 2.5 0.6 1,3,4,5,7
11 12679 12694 16 2.6 0.6 1,3,4,5,7
12 13782 13823 41 2 0.6 1,3,4,5,7
13 19072 19093 22 2.5 0.6 1,3,4,5,7
14 19844 19869 25 1.8 0.6 1,3,4,5,7
15 22223 22234 11 1.5 0.6 1,3,4,5,7
16 24427 24466 39 2.5 0.6 1,3,4,5,7
17 25253 25280 27 2.6 0.6 1,3,4,5,7
18 25666 25790 124 3 0.6 1,3,4,5,7
19 26432 26465 33 2.5 0.6 1,3,4,5,7
20 35062 35078 16 2.1 0.6 1,3,4,5,7
21 36833 36863 30 2 0.6 1,3,4,5,7
22 41313 41334 22 2.5 0.6 1,3,4,5,7
23 42269 42291 22 2 0.6 1,3,4,5,7
24 42325 42352 27 2.1 0.6 1,3,4,5,7
25 45018 45037 19 3 0.6 1,3,4,5,7
26 59118 59165 47 2.5 0.6 1,3,4,5,7
27 59276 59301 26 2.2 0.6 1,3,4,5,7
28 61169 61201 32 2 0.6 1,3,4,5,7
29 62761 62777 16 2 0.6 1,3,4,5,7
30 63250 63265 16 2 0.6 1,3,4,5,7
31 63551 63563 12 2.7 0.6 1,3,4,5,7
32 63808 63816 8 2.5 0.6 1,3,4,5,7
33 66763 66786 23 2.2 0.6 1,3,4,5,7
34 70248 70299 52 1.5 0.6 1,3,4,5,7
35 70772 70788 16 2.3 0.6 1,3,4,5,7
36 70833 70864 31 2.5 0.6 1,3,4,5,7
976 2.39
DETAILS OF JUNCTION
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIF
Section : Dt of Survey :10.09.09 to 26.09.09
Crossing
S.No Link Location Type Left/Right/Cross
Aizawl Road, Lunglei Road,Demagri
1 0 Y - Junction Right
Shortcut,Assam Rifle
2 FCI Complex 1.06 Y - Junction Left
3 Lunglei Shortcut 5.865 Y - Junction Right
4 Zehtet,Zawlpui Road 35.831 Y - Junction Left
5 Chawngte Road 43.859 Y - Junction Left
6 BDO Office 53.839 Y - Junction Right
7 Matisora Road 71.159 Y - Junction Left
8 Rest House 86.369 Y - Junction Left
9 Borapansury Road 88.439 Y - Junction Right
10 Short Cut Road 90.239 Y - Junction Left
11 Borapansury Road 90.359 Y - Junction Left
12 Short Cut Road, PWD Rest House 90.409 Y - Junction Right
13 Short Cut Road 91.104 Y - Junction Left
DETAILS OF VILLAGE & IMPORTANT LAND MARK
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIG

Section : Dt of Survey :10.09.09 to 26.09.09

S.No From To Village Name


1.00 0.00 2.90 Lunglei
2.00 12.90 25.43 Hauruang
3.00 25.43 35.45 Pachang
4.00 35.45 43.53 Phairuang
5.00 43.53 44.34 Rotlang
6.00 44.34 60.43 Lungsen
7.00 60.43 60.62 Sihphir
8.00 60.62 80.25 Tuichawng
9.00 80.25 94.40 Tlabung
Important Land Mark
1.00 0.00 0.16 Assam Rifle
2.00 0.84 0.86 FCI Godown
3.00 3.84 3.85 HT Tower
4.00 5.47 5.49 HT Tower
5.00 5.86 5.87 Lunglei Short Cut
6.00 6.13 HT Tower
7.00 6.22 6.22 HT Tower
8.00 6.39 6.41 HT Tower Sub Station
9.00 8.15 8.19 Grave Yard
10.00 25.68 25.81 BRTF Complex
11.00 27.42 HT Tower
12.00 35.97 Bridge
13.00 36.29 36.31 Waiting Shed
14.00 46.86 46.88 Pond
15.00 52.92 52.92 Police Station
16.00 54.37 54.38 Bank
17.00 54.64 54.65 Workshop
18.00 54.87 54.88 HT Tower
19.00 63.14 63.15 Rest House
20.00 71.16 71.17 Matisora Road
21.00 71.99 72.00 HT Tower
22.00 72.94 72.96 Bridge
23.00 76.89 76.89 Bridge
24.00 85.14 85.17 LPG Godown
25.00 85.25 85.25 Rest Shed
26.00 86.35 86.36 Rest House
27.00 86.39 86.40 Rest House
28.00 90.35 90.37 Borapansury Road
29.00 90.39 90.41 School
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
Electric Pole &
1 0 Valley Side 277 60659 Electric Pole Valley Side
Telephone Pole
2 20 Telephone Pole Valley Side 278 60859 2Electric Pole Valley Side
3 50 Electric Pole Valley Side 279 61069 Electric Pole Valley Side
4 85 Telephone Pole Hill Side 280 61219 2Electric Pole Valley Side
5 108 Telephone Pole Hill Side 281 61309 Electric Pole Valley Side
6 110 Telephone Pole Hill Side 282 61315 2Electric Pole Valley Side
7 160 Electric Pole Valley Side 283 61399 2Electric Pole Valley Side
8 210 Electric Pole Valley Side 284 61534 2Electric Pole Valley Side
9 230 Electric Pole Valley Side 285 61540 2Electric Pole Valley Side
10 370 Electric Pole Valley Side 286 61609 Electric Pole Valley Side
11 395 Electric Pole Valley Side 287 61695 2Electric Pole Valley Side
12 430 Electric Pole Valley Side 288 61814 4Electric Pole Valley Side
13 630 Telephone Pole Hill Side 289 61895 2Electric Pole Valley Side
14 660 Electric Pole Valley Side 290 62125 2Electric Pole Valley Side
15 700 Electric Pole Valley Side 291 62240 Electric Pole Valley Side
16 730 Electric Pole Valley Side 292 62259 Electric Pole Valley Side
17 760 Electric Pole Valley Side 293 62335 Electric Pole Valley Side
18 790 Electric Pole Valley Side 294 62345 2Electric Pole Valley Side
19 840 Telephone Pole Valley Side 295 62709 2Electric Pole Valley Side
20 890 Electric Pole Valley Side 296 62714 2Electric Pole Valley Side
21 910 Telephone Pole Valley Side 297 62965 Electric Pole Valley Side
22 930 Electric Pole Valley Side 298 63065 Electric Pole Valley Side
23 970 Electric Pole & Valley Side 299 64009 2Electric Pole Valley Side
24 1000 Telephone Pole
Electric Pole Valley Side 300 65279 2Electric Pole Valley Side
25 1020 Telephone Pole Valley Side 301 65625 2Electric Pole Valley Side
26 1030 Electric Pole Valley Side 302 65699 4Electric Pole Valley Side
27 1050 Telephone Pole Valley Side 303 65759 Electric Pole Valley Side
28 1070 Electric Pole Valley Side 304 65805 2Electric Pole Valley Side
29 1690 2Electric Pole Valley Side 305 65929 2Electric Pole Valley Side
30 1860 2Electric Pole Valley Side 306 65085 2Electric Pole Valley Side
31 2140 2Electric Pole Valley Side 307 66219 2Electric Pole Valley Side
32 2850 2Electric Pole Valley Side 308 66349 2Electric Pole Valley Side
33 2990 2Electric Pole Valley Side 309 67205 2Electric Pole Valley Side
34 3210 2Electric Pole Valley Side 310 67345 2Electric Pole Valley Side
35 3320 Electric Pole Valley Side 311 67539 2Electric Pole Valley Side
36 3460 Electric Pole Valley Side 312 68535 2Electric Pole Valley Side
37 3640 Electric Pole Valley Side 313 68585 2Electric Pole Valley Side
38 3740 Electric Pole Valley Side 314 68625 2Electric Pole Valley Side
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
39 5850 2Electric Pole Valley Side 315 68919 Electric Pole Valley Side
40 6170 Electric Pole Valley Side 316 69009 2Electric Pole Valley Side
41 6360 Electric Pole Hill Side 317 69195 Electric Pole Valley Side
42 12100 Electric Pole Hill Side 318 69269 2Electric Pole Valley Side
43 12170 Electric Pole Hill Side 319 69479 Electric Pole Valley Side
44 12230 Electric Pole Valley Side 320 69609 2Electric Pole Valley Side
45 12290 Electric Pole Valley Side 321 70189 2Electric Pole Valley Side
46 12350 Electric Pole Valley Side 322 70439 2Electric Pole Hill Side
47 12450 Electric Pole Valley Side 323 71169 Electric Pole Valley Side
48 12570 2Electric Pole Hill Side 324 71199 Electric Pole Valley Side
49 12600 Electric Pole Valley Side 325 71209 Electric Pole Valley Side
50 12670 Electric Pole Valley Side 326 71265 Electric Pole Valley Side
51 12750 Electric Pole Valley Side 327 71309 Electric Pole Valley Side
52 12810 Electric Pole Valley Side 328 71339 Electric Pole Valley Side
53 12890 Electric Pole Valley Side 329 71425 Electric Pole Valley Side
54 12970 Electric Pole Valley Side 330 71499 Electric Pole Valley Side
55 13020 Electric Pole Valley Side 331 71575 2Electric Pole Valley Side
56 13070 Electric Pole Valley Side 332 71649 Electric Pole Valley Side
57 13130 Electric Pole Valley Side 333 71715 Electric Pole Valley Side
58 13180 Electric Pole Valley Side 334 71819 Electric Pole Valley Side
59 13190 Telephone Pole Valley Side 335 71849 Electric Pole Valley Side
60 13235 Electric Pole Valley Side 336 71889 Electric Pole Valley Side
61 13260 Electric Pole Valley Side 337 71935 Electric Pole Valley Side
62 13285 Electric Pole Valley Side 338 72025 Electric Pole Valley Side
63 13340 Electric Pole Valley Side 339 72065 Electric Pole Valley Side
64 13380 Electric Pole Valley Side 340 72129 Electric Pole Hill Side
65 13420 Telephone Pole Valley Side 341 72255 Electric Pole Valley Side
66 13420 Electric Pole Valley Side 342 72305 Electric Pole Valley Side
67 13530 Electric Pole Valley Side 343 72369 Electric Pole Hill Side
68 13550 Telephone Pole Valley Side 344 72419 Electric Pole Hill Side
69 13590 2Electric Pole Valley Side 345 72479 Electric Pole Valley Side
70 13660 Electric Pole Valley Side 346 72539 Electric Pole Valley Side
71 13680 Electric Pole Valley Side 347 72604 Electric Pole Valley Side
72 13730 Electric Pole Valley Side 348 72685 Electric Pole Valley Side
73 13800 Electric Pole Valley Side 349 77429 Electric Pole Valley Side
74 13850 Electric Pole Valley Side 350 80379 2Electric Pole Valley Side
75 13900 Electric Pole Hill Side 351 81099 Electric Pole Valley Side
76 13920 Electric Pole Hill Side 352 81909 2Electric Pole Valley Side
77 13940 Electric Pole Hill Side 353 81919 2Electric Pole Valley Side
78 13960 Electric Pole Hill Side 354 85559 2Electric Pole Valley Side
79 14000 4Electric Pole Hill Side 355 85739 Electric Pole Valley Side
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
80 14020 Electric Pole Hill Side 356 85799 Electric Pole Valley Side
81 14060 Electric Pole Valley Side 357 85854 Electric Pole Valley Side
82 14080 Electric Pole Hill Side 358 85909 Electric Pole Valley Side
83 14120 Electric Pole Valley Side 359 85969 Electric Pole Valley Side
84 14150 Electric Pole Hill Side 360 86009 Electric Pole Valley Side
85 14170 Electric Pole Valley Side 361 86079 Electric Pole Valley Side
86 14220 Electric Pole Valley Side 362 86135 Electric Pole Valley Side
87 14230 Electric Pole Valley Side 363 86185 Electric Pole Valley Side
88 14280 Electric Pole Valley Side 364 86239 Electric Pole Valley Side
89 14300 Telephone Pole Valley Side 365 86285 2Electric Pole Valley Side
90 14330 Electric Pole Valley Side 366 86329 Electric Pole Valley Side
91 14360 Telephone Pole Hill Side 367 86375 Telephone Pole Valley Side
92 14370 Telephone Pole Valley Side 368 86395 Electric Pole Valley Side
93 14380 Electric Pole Valley Side 369 86399 Telephone Pole Valley Side
94 14440 Electric Pole Valley Side 370 86439 Telephone Pole Valley Side
95 14460 Electric Pole Valley Side 371 86469 Telephone Pole Valley Side
96 14500 Electric Pole Valley Side 372 86475 Electric Pole Valley Side
97 14520 Telephone Pole Valley Side 373 86479 Telephone Pole Valley Side
98 14560 Electric Pole Valley Side 374 86499 Telephone Pole Valley Side
99 14600 Electric Pole Valley Side 375 86525 Electric Pole Valley Side
Electric Pole &
100 14650 Electric Pole Hill Side 376 86545 Valley Side
Telephone Pole
101 14710 Electric Pole Valley Side 377 86625 Telephone Pole Valley Side
Electric Pole &
102 14780 Electric Pole Valley Side 378 86649 Valley Side
Telephone Pole
103 16410 2Electric Pole Valley Side 379 86669 Telephone Pole Valley Side
Electric Pole &
104 19830 2Electric Pole Valley Side 380 86699 Valley Side
Telephone Pole
105 20681 2Electric Pole Valley Side 381 86729 Telephone Pole Valley Side
Electric Pole &
106 25375 Electric Pole Valley Side 382 86759 Valley Side
Telephone Pole
107 25431 Electric Pole Valley Side 383 86859 Telephone Pole Valley Side
108 25481 Electric Pole Valley Side 384 86879 Telephone Pole Valley Side
109 25521 Electric Pole Valley Side 385 86889 Electric Pole Valley Side
110 25631 Electric Pole Valley Side 386 86899 Telephone Pole Valley Side
111 25681 Electric Pole Valley Side 387 86915 Electric Pole Valley Side
112 26021 Electric Pole Valley Side 388 86925 Telephone Pole Valley Side
Electric Pole &
113 26101 Electric Pole Valley Side 389 86954 Valley Side
Telephone Pole
Electric Pole &
114 26151 Electric Pole Valley Side 390 87039 Valley Side
Telephone Pole
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
Electric Pole &
115 26241 Electric Pole Valley Side 391 87079 Valley Side
Telephone Pole
116 26271 Electric Pole Valley Side 392 87159 Electric Pole Valley Side
117 26411 Electric Pole Valley Side 393 87179 Telephone Pole Valley Side
118 27281 2Electric Pole Valley Side 394 87194 3Electric Pole Valley Side
119 28171 2Electric Pole Hill Side 395 87204 Telephone Pole Valley Side
Electric Pole &
120 28445 2Electric Pole Valley Side 396 87239 Valley Side
Telephone Pole
121 28601 2Electric Pole Valley Side 397 87379 Electric Pole Valley Side
122 32011 Electric Pole Valley Side 398 87389 Telephone Pole Valley Side
123 32411 2Electric Pole Valley Side 399 87415 Telephone Pole Valley Side
Electric Pole &
124 33251 2Electric Pole Valley Side 400 87449 Valley Side
Telephone Pole
125 35701 Electric Pole Valley Side 401 87469 Telephone Pole Valley Side
126 35861 Electric Pole Valley Side 402 87489 Telephone Pole Valley Side
127 35911 Electric Pole Hill Side 403 87499 Electric Pole Valley Side
128 36021 Electric Pole Valley Side 404 87509 Telephone Pole Hill Side
129 36121 Electric Pole Valley Side 405 87529 Telephone Pole Valley Side
130 36175 Electric Pole Valley Side 406 87539 Telephone Pole Valley Side
131 36221 Electric Pole Valley Side 407 87549 Electric Pole Valley Side
132 36281 Electric Pole Valley Side 408 87565 Telephone Pole Valley Side
133 36401 Electric Pole Valley Side 409 87579 Telephone Pole Valley Side
134 36451 Electric Pole Valley Side 410 87599 Telephone Pole Valley Side
135 36495 Electric Pole Valley Side 411 87615 Telephone Pole Valley Side
136 36531 Electric Pole Valley Side 412 87619 Electric Pole Valley Side
137 36581 Electric Pole Valley Side 413 87629 Telephone Pole Valley Side
138 38021 2Electric Pole Valley Side 414 87645 Telephone Pole Valley Side
139 38101 Electric Pole Valley Side 415 87665 Telephone Pole Valley Side
140 38319 2Electric Pole Valley Side 416 87669 Electric Pole Valley Side
141 38429 Electric Pole Valley Side 417 87685 Telephone Pole Valley Side
142 38525 2Electric Pole Valley Side 418 87709 Telephone Pole Valley Side
143 39014 2Electric Pole Valley Side 419 87719 Electric Pole Valley Side
144 39209 Electric Pole Valley Side 420 87729 Telephone Pole Valley Side
145 39599 Electric Pole Valley Side 421 87739 2Electric Pole Valley Side
146 39720 2Electric Pole Valley Side 422 87759 Electric Pole Valley Side
147 42249 2Electric Pole Valley Side 423 87769 Telephone Pole Valley Side
Electric Pole &
148 42529 Electric Pole Valley Side 424 87799 Valley Side
Telephone Pole
149 42570 2Electric Pole Valley Side 425 87809 Telephone Pole Valley Side
150 43704 Electric Pole Valley Side 426 87829 Telephone Pole Valley Side
151 43739 Electric Pole Valley Side 427 87845 Telephone Pole Valley Side
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
152 43849 Electric Pole Valley Side 428 87855 Telephone Pole Valley Side
153 43739 Electric Pole Valley Side 429 87875 Telephone Pole Valley Side
154 43849 Electric Pole Valley Side 430 87889 Telephone Pole Valley Side
155 43894 Electric Pole Valley Side 431 87915 Telephone Pole Valley Side
156 43994 Electric Pole Valley Side 432 87929 Electric Pole Valley Side
157 44045 Electric Pole Valley Side 433 87945 Telephone Pole Valley Side
158 44099 Electric Pole Valley Side 434 87989 Electric Pole Valley Side
159 44149 Electric Pole Valley Side 435 87999 Telephone Pole Valley Side
160 44325 Electric Pole Valley Side 436 88019 Electric Pole Valley Side
161 44459 Electric Pole Valley Side 437 88035 Telephone Pole Valley Side
162 44639 Electric Pole Hill Side 438 88079 Electric Pole Valley Side
163 44699 Electric Pole Hill Side 439 88119 Electric Pole Valley Side
164 45749 2Electric Pole Hill Side 440 88169 Electric Pole Valley Side
165 45819 Electric Pole Hill Side 441 88199 Electric Pole Valley Side
166 46929 2Electric Pole Hill Side 442 88255 Electric Pole Valley Side
167 47959 2Electric Pole Hill Side 443 88319 Electric Pole Valley Side
168 49539 2Electric Pole Hill Side 444 88369 Electric Pole Valley Side
169 49589 Electric Pole Hill Side 445 88399 Electric Pole Valley Side
170 49639 2Electric Pole Hill Side 446 88459 Electric Pole Valley Side
171 50339 2Electric Pole Hill Side 447 88519 Electric Pole Valley Side
172 50529 2Electric Pole Hill Side 448 88549 2Electric Pole Valley Side
173 50719 2Electric Pole Hill Side 449 88585 Electric Pole Valley Side
174 50819 2Electric Pole Hill Side 450 88619 Telephone Pole Valley Side
175 50889 Electric Pole Hill Side 451 88729 Electric Pole Valley Side
176 50959 2Electric Pole Hill Side 452 88769 Electric Pole Valley Side
177 51419 Electric Pole Hill Side 453 88805 Electric Pole Valley Side
178 51449 Electric Pole Hill Side 454 88849 Electric Pole Valley Side
179 51589 2Electric Pole Hill Side 455 88979 Electric Pole Valley Side
180 51599 2Electric Pole Valley Side 456 89039 Electric Pole Valley Side
181 51729 2Electric Pole Valley Side 457 89109 Electric Pole Valley Side
182 51789 Electric Pole Valley Side 458 89259 Telephone Pole Valley Side
183 51899 2Electric Pole Valley Side 459 89275 Telephone Pole Valley Side
184 51949 Electric Pole Hill Side 460 89289 Telephone Pole Valley Side
185 52309 Electric Pole Hill Side 461 89295 2Electric Pole Valley Side
186 52899 2Electric Pole Valley Side 462 89309 Electric Pole Valley Side
187 52929 Telephone Pole Valley Side 463 89315 Telephone Pole Valley Side
188 52959 Telephone Pole Valley Side 464 89335 Telephone Pole Valley Side
Electric Pole &
189 53019 Electric Pole Valley Side 465 89349 Valley Side
Telephone Pole
190 53029 Telephone Pole Valley Side 466 89435 Telephone Pole Valley Side
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
Electric Pole &
191 53060 Valley Side 467 89464 Electric Pole Valley Side
Telephone Pole
192 53099 Telephone Pole Valley Side 468 89479 Telephone Pole Valley Side
Electric Pole &
193 53129 Valley Side 469 89509 Telephone Pole Valley Side
Telephone Pole
Electric Pole &
194 53149 Telephone Pole Valley Side 470 89529 Valley Side
Telephone Pole
195 53179 Telephone Pole Valley Side 471 89539 Telephone Pole Valley Side
196 53189 Electric Pole Valley Side 472 89559 Telephone Pole Valley Side
197 53219 Telephone Pole Valley Side 473 89569 Telephone Pole Valley Side
198 53239 Electric Pole Valley Side 474 89589 Telephone Pole Valley Side
Electric Pole & Electric Pole &
199 53269 Valley Side 475 89599 Valley Side
Telephone Pole Telephone Pole
Electric Pole &
200 53309 Valley Side 476 89695 Electric Pole Valley Side
Telephone Pole
201 53339 Telephone Pole Valley Side 477 89739 Telephone Pole Valley Side
2Electric Pole &
202 53379 Electric Pole Valley Side 478 89809 Valley Side
Telephone Pole
203 53409 Electric Pole Valley Side 479 89829 Telephone Pole Valley Side
Electric Pole & Electric Pole &
204 53429 Valley Side 480 89849 Valley Side
Telephone Pole Telephone Pole
205 53459 Telephone Pole Valley Side 481 89879 Telephone Pole Valley Side
206 53469 Electric Pole Valley Side 482 89889 3Telephone Pole Valley Side
207 53485 Telephone Pole Valley Side 483 89899 Telephone Pole Valley Side
Electric Pole &
208 53499 Telephone Pole Valley Side 484 89919 Valley Side
Telephone Pole
209 53509 Telephone Pole Valley Side 485 89929 Telephone Pole Valley Side
210 53535 Telephone Pole Hill Side 486 89925 Telephone Pole Valley Side
211 53549 Electric Pole Valley Side 487 89959 Telephone Pole Valley Side
212 53565 Telephone Pole Hill Side 488 89969 Telephone Pole Valley Side
Electric Pole &
213 53599 Telephone Pole Hill Side 489 89989 Valley Side
Telephone Pole
214 53609 Electric Pole Valley Side 490 90005 Telephone Pole Valley Side
215 53629 Telephone Pole Hill Side 491 90025 Telephone Pole Valley Side
216 53659 Electric Pole Valley Side 492 90059 Electric Pole Valley Side
217 53665 Telephone Pole Valley Side 493 90069 Telephone Pole Valley Side
218 53705 Telephone Pole Hill Side 494 90089 Telephone Pole Valley Side
Electric Pole & Electric Pole &
219 53729 Valley Side 495 90109 Valley Side
Telephone Pole Telephone Pole
220 53749 Telephone Pole Hill Side 496 90225 Telephone Pole Valley Side
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
Electric Pole &
221 53779 Hill Side 497 90139 Telephone Pole Valley Side
Telephone Pole
222 53809 Telephone Pole Valley Side 498 90149 Electric Pole Valley Side
Electric Pole &
223 53839 Hill Side 499 90159 Telephone Pole Valley Side
Telephone Pole
224 53889 Electric Pole Hill Side 500 90169 Telephone Pole Valley Side
Electric Pole &
225 53939 Electric Pole Valley Side 501 90179 Valley Side
Telephone Pole
226 53979 Telephone Pole Valley Side 502 90205 Telephone Pole Valley Side
Electric Pole &
227 53999 Electric Pole Valley Side 503 90219 Valley Side
Telephone Pole
228 54045 Electric Pole Valley Side 504 90239 Telephone Pole Valley Side
229 54099 Electric Pole Hill Side 505 90259 Electric Pole Valley Side
230 54155 Electric Pole Valley Side 506 90295 Telephone Pole Valley Side
231 54205 Telephone Pole Valley Side 507 90305 Telephone Pole Valley Side
232 54229 Telephone Pole Valley Side 508 90329 Telephone Pole Valley Side
233 54269 Electric Pole Valley Side 509 90345 Telephone Pole Valley Side
Electric Pole &
234 54285 Telephone Pole Valley Side 510 90365 Valley Side
Telephone Pole
Electric Pole &
235 54335 Electric Pole Valley Side 511 90385 Valley Side
Telephone Pole
236 54345 Electric Pole Valley Side 512 90399 Electric Pole Valley Side
237 54435 Telephone Pole Valley Side 513 90419 Electric Pole Valley Side
238 54509 Telephone Pole Valley Side 514 90469 Electric Pole Valley Side
239 54559 Electric Pole Valley Side 515 90579 Electric Pole Valley Side
240 54569 Telephone Pole Hill Side 516 90609 Electric Pole Valley Side
241 54589 Electric Pole Valley Side 517 90655 Electric Pole Valley Side
242 54609 Telephone Pole Valley Side 518 90699 Electric Pole Valley Side
243 54629 Electric Pole Valley Side 519 90739 Electric Pole Valley Side
244 54669 Electric Pole Hill Side 520 90779 Electric Pole Valley Side
245 54709 Electric Pole Valley Side 521 90809 Electric Pole Valley Side
246 54749 Electric Pole Valley Side 522 90849 Electric Pole Valley Side
247 54799 Electric Pole Valley Side 523 90889 Electric Pole Valley Side
248 54839 Electric Pole Valley Side 524 90999 Electric Pole Valley Side
249 54905 Electric Pole Valley Side 525 91039 Electric Pole Valley Side
250 54949 Electric Pole Valley Side 526 91099 Electric Pole Valley Side
251 55009 Electric Pole Valley Side 527 91119 Telephone Pole Valley Side
252 55049 Electric Pole Valley Side 528 91135 Telephone Pole Valley Side
Electric Pole &
253 55095 Electric Pole Valley Side 529 91149 Valley Side
Telephone Pole
254 55455 2Electric Pole Valley Side 530 91165 Telephone Pole Valley Side
DETAILS OF UTILITY
Road Name : LUNGLEI TO TLABUNG (NH-302) Appendix - IIH
Section : Dt of Survey :10.09.09 to 26.09.09
SL. Chainage Description Remaks SL.N Chainage Description Remaks
No. o.
255 55549 2Electric Pole Valley Side 531 91179 Telephone Pole Valley Side
256 55579 Electric Pole Valley Side 532 91189 Electric Pole Valley Side
257 55765 Electric Pole Valley Side 533 91205 Telephone Pole Valley Side
258 55815 2Electric Pole Valley Side 534 91305 Electric Pole Valley Side
259 57455 2Electric Pole Valley Side 535 91235 Electric Pole Valley Side
260 57765 2Electric Pole Valley Side 536 91239 Telephone Pole Valley Side
261 58599 2Electric Pole Valley Side 537 91259 Telephone Pole Valley Side
262 58659 Electric Pole Valley Side 538 91269 Telephone Pole Valley Side
263 58709 2Electric Pole Valley Side 539 91305 Telephone Pole Valley Side
264 58785 2Electric Pole Valley Side 540 91315 Telephone Pole Valley Side
265 58809 Electric Pole Valley Side 541 91335 Telephone Pole Valley Side
266 59139 Electric Pole Valley Side 542 91340 Telephone Pole Valley Side
Electric Pole &
267 59165 2Electric Pole Valley Side 543 91349 Valley Side
Telephone Pole
Electric Pole &
268 59235 2Electric Pole Valley Side 544 91379 Valley Side
Telephone Pole
269 59409 2Electric Pole Valley Side 545 91405 2Electric Pole Valley Side
270 60379 3Electric Pole Valley Side 546 91425 Telephone Pole Valley Side
271 60409 Electric Pole Valley Side 547 91499 Electric Pole Valley Side
272 60469 Electric Pole Valley Side 548 91489 Telephone Pole Valley Side
273 60519 Electric Pole Valley Side 549 91499 Telephone Pole Valley Side
Electric Pole &
274 60555 Electric Pole Hill Side 550 91509 Valley Side
Telephone Pole
275 60559 Electric Pole Hill Side 551 91519 2Electric Pole Valley Side
276 60599 2Electric Pole Hill Side 552 91529 Telephone Pole Valley Side
ECONOMIC AND FINANCIAL ANALYSIS
GENERAL
The project cost and benefits have been estimated for the project analysis period
of 30 years, including 2.5 years construction period. At the terminal year of the
analysis period a salvage value of 10% has been considered. The social discount
rate for the purpose of working out net present value (NPV) is taken at 12%.
This is the rate considered for similar kinds of projects in developing countries,
and also reflecting the premium on 'decision to invest today' vis-a-vis 'saving it
for future consumption'.
Constant base year (Yr. 2019) prices are used for economic evaluation. Since the
project costs such as capital, vehicle, consumables, etc., are based on the market
prices, these costs have been converted into economic costs by applying
appropriate factors established for resource costs. For this, all the costs items
(under 'with' and 'without' project cases) estimated at base year prices are
adjusted for transfer of payments such as taxes, duties and subsidies on
materials and equipments. Standard conversion factor (SCF) of 0.80 for road
construction and for road maintenance has been used for converting the cost
estimates at market prices to economic prices. The project capital cost comprises
the costs relating to physical works implemented under the project.
Approach
The economic evaluation has been carried out within the broad framework of
social cost-benefit analysis. The kernel of the concept of economic feasibility
obviously is maximising the returns on investment. This objective is
accomplished by determining the appropriate improvement proposal that leads
to the minimum total transport costs, defined as comprising two basic
components shown below.
Total Transport Costs

Road Costs Road User Costs

Construction Vehicle Operating Costs (VOC)


Maintenance Other User Costs (like travel time costs)

The economic analysis has been based on incremental costs and incremental
benefits, i.e. comparing the total transport costs “with the Project” and “without
the Project”, which is the base case or the “do minimum” case. All costs and
benefits considered in the study have been valued in monetary terms and
expressed in economic prices for avoiding distortion in the input prices of
labour, materials, equipment’s, equipment and foreign exchange due to market
imperfections.
Comparisons between the total transport costs for the project road, section wise
for “with the Project” and “without the Project” situations have been worked
out on yearly basis for the entire analysis period. The concept behind the
approach is that if the Project is implemented, the benefits will be the decreased
costs when compared to the costs of the alternative foregone, i.e. the base case
or without Project situation. The results have been expressed in terms of
Economic Internal Rate of Return (EIRR) and Net Present Value (NPV).
The economic analysis has been carried out using the World Bank developed
“Highway Design and Maintenance Standards Model” (HDM) – its latest
version HDM-4. The HDM Model has been used for analysing flexible
pavement by generating economic cost streams and computing the EIRR and
NPV for economic evaluation.
HDM Model Input Data
The main inputs for HDM relate to road and pavement characteristics, traffic
volume and its composition, traffic growth rate, vehicle characteristics,
pavement construction and maintenance policies. In addition, economic prices
for vehicles, tyres and tubes, fuel, maintenance crew labour, passenger time and
cargo time have been considered. Fuel prices, particularly diesel and petrol, are
“border” prices. For other items these are net of taxes and duties.
VEHICLE FLEET DATA INPUTS
Vehicle fleet data is used for estimating the operating cost of the vehicles. The
inputs relate to vehicle cost, cost of tire, fuel prices, maintenance labor cost, and
crew cost, etc., details on vehicle specification and performance. These input
costs are given in Table 10.2-1. All the cost items are at economic cost, estimated
on the basis of the method described earlier in this chapter.
Table 10.2-1 Unit Economic Cost and Vehicle Fleet Data

Tractor
Wheel

Wheel

2-Axle
Truck
Three

Multi
Mini

Axle

LCV
Two

Bus

Bus
Car

Item

Vehicle Price
420.0 54.0 139.0 924.0 651.0 1008.0 1117.0 680.0 454.0
(Rs. 000)
No. of Wheels 4.0 2.0 3.0 6.0 4.0 6.0 10.0 4.0 4.0
No. of Axles 2.0 2.0 1.0 2.0 2.0 2.0 3.0 2.0 2.0
Passengers 4.0 1.0 3.0 30.0 15.0 - - - -
Tire(Rs.000) 3.3 0.8 1.0 9.2 9.2 9.2 9.2 5.9 9.2
Fuel Per/Lt. (Rs.) 38.6 38.6 38.6 39.8 39.8 39.8 39.8 39.8 39.8
Maint. Labor
105.0 63.0 105.0 189.0 157.5 189.0 210.0 157.5 210.0
(Rs. per hr.)
Crew Wages
16.8 0.0 14.7 67.2 41.0 37.8 43.1 28.4 0.0
(Rs. per hr)
Annual Overhead
21.0 0.0 10.5 42.0 31.5 31.5 42.0 31.5 10.5
(Rs 000)
Interest Rate (%) 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0 12.0
Pass. Time Value*
80.1 64.0 64.0 53.7 53.7 0.0 0.0 0.0 0.0
(Rs. per/hr.)
PCSE 1.0 0.5 1.0 1.8 1.5 1.8 2.4 1.5 2.4
Working Hours 850.0 240.0 950.0 2200.0 1400.0 2600.0 2800.0 1400.0 650.0
Annual km (000) 40.0 12.0 25.0 75.0 55.0 85.0 85.0 50.0 10.0
Tractor
Wheel

Wheel

2-Axle
Truck
Three

Multi
Mini

Axle

LCV
Two

Bus

Bus
Car
Item

Avg. life (Yrs) 8.0 8.0 8.0 8.0 8.0 10.0 10.0 8.0 8.0
Source: Market Survey & Previous Studies in India
PROJECT COST
The cost estimates for the NH-302 were prepared by consultant. It may be noted
that the proposed construction works is only applicable for construction of
Widening existing Road ('with' the project cases), and are not applicable for the
base case alternative ('without' the project case).
The first year of construction period is considered as Yr. 2020; with the
construction period lasting for 2.5 years (i.e. up to Yr.2024).The opening year of
traffic operations is expected to be Yr. 2022. The construction is expected to be
completed in a phased manner as indicated as follows.
Table 9.3-1 Investment Schedule for Construction

Construction Year Percentage Investment


2020 – 21 15%
2021 - 22 45%
2022 - 23 80%
2023 - 24 100%

MAINTENANCE STANDARDS AND CAPITAL COSTS


The maintenance (annual and periodic) cost has been taken separately for the
base case alternative (do-nothing\ do-minimum) and the project alternatives.
While the maintenance cost for 'base case' alternative is based on the existing
practices being followed by the road agency.
The capital costs (market prices) for the 6 package are presented in Table 10.4-
1.
SOR-2016 with WPI Dec-19 in Rs Cr
Road Name
2020 2021 2022 2023
NH-302 216.80 650.41 1156.29 1445.36

The salvage value of 15% of capital cost at the end of the analysis period has
been considered.
Routine and Periodic Maintenance Costs
The pavement maintenance costs for flexible pavement have been generated by
the HDM Model. Periodic pavement maintenance has been suggested after 10th
year Other annual routine maintenance costs have been taken @ Rs. 319800 per
km for two-lane highway. Both routine and periodic maintenance costs have
been converted into economic costs by applying the standard conversion factor.
Project Benefits
The direct benefits of road improvement considered in the study include VOC
savings for vehicular traffic using the project road and time savings for
passengers and goods (carried) in transit. The benefit streams have been
computed annually over the analysis period.
 VOC Savings
The unit VOC by vehicle type and VOC savings “with” and “without” the
project, section wise, have been computed by the Model. The VOC computation
takes into account pavement characteristics, roughness, traffic characteristics,
geometric conditions and vehicle characteristics. For flexible pavement, the
roughness progression have been estimated by the Model. The unit VOC saving
have been taken in full for building up annual streams of VOC savings for the
projected volume of traffic.
 Time Value of Passengers and Goods in Transit
The HDM Model has generated average speeds in km/hr by vehicle type, in the
existing (without Project) and the improved (with Project) road conditions. The
time savings for passengers and goods vehicles have been derived using an
average occupancy by vehicle type (for vehicle group weighted by their
number), such as Car – 3.5 persons, Bus - 40 persons, LCV – 2.1 tonnes, HCV –
6.4 tonnes and MAV -10.68 tonnes.
The value of time for passengers and goods considered in this analysis has been
based on earlier studies carried out in recent years. For the average car
passenger, time value has been taken as Rs. 40 per hour, and for the average bus
passenger as Rs. 15 per hour. The value placed on time is rather on the
conservative side. For goods in transit, time value has been worked out using
the inventory cost method with a 12% interest rate, considered as an
opportunity cost of capital. It worked out to Rs. 15 per tonne per hour.
ECONOMIC EVALUATION
The economic analysis based on the method elaborated above, allowed the
Study Team to obtain the economic indicators for each of the by-passes. The
economic indicators such as economic internal rate of return (EIRR) are
important for judging the economic feasibility of projects. The annual cost and
benefit streams are used to derive the net cash flow for the project. The EIRR is
determined using the discounted cash-flow technique for with and without time
savings. The results of economic analysis are set out in Table 10.8-1.
Table 10.8-1 Results of Economic Analysis of N

NH 302 EIRR (%) Cost benefit ratio


NH - 302 12.11% 1.18

The rate of return considered desirable for transport infrastructure projects in India is
12 percent. As EIRR of all the sections and total project road is above 12 percent cut-
off rate, the project sections as well as total project road are economically viable.
COST ESTIMATE FOR PERIODICAL RENEWAL PER KM PER YEAR AS PER SOR NH-2016
DETAILED ESTIMATE
Sl. No./ Area Depth Rate Amount
Description of item 2 Quantity Unit
SOR No (m ) (m) in ` in `
1 2 3 4 5 7 6 8 9
1/3.12 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means
(Scarifying the existing granular road surface to a depth of 50 mm and
disposal of scarified material within all lifts and leads upto 1000 metres. ) 1 7700.00 - 7700.00 Sqm 52.00 400,400.00
2/4.8 Water Bound Macadam (Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with vibratory roller 8-
10 tonnes in stages to proper grade and camber, applying and brooming
requisite type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required density.)
A) By Manual Means
ii) Grading- II
b) Using Screening Type-B (11.2mm Agg.) 1 7700.00 0.075 577.50 Cum
Adding 10% for profile correction : 57.75 Cum
Total 635.25 Cum 4755.00 3,020,614.00
3/5.1 Prime Coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
spraying primer at the rate shown in 500-1 using mechanical means.)
i) Low Porosity 1 7700.00 - 7700.00 Sqm 25.00 192,500.00
4/5.2 Tack coat (Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom)
iii) Granular Surface Treated with Primer 1 7700.00 - 7700.00 Sqm 16.00 123,200.00
5/5.2 Tack coat (Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom)
ii) Dry and Hungry Bituminous Surface 1 7700.00 - 7700.00 Sqm 14.00 107,800.00
Sl. No./ Area Depth Rate Amount
Description of item 2 Quantity Unit
SOR No (m ) (m) in ` in `
6/5.6 Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 507 complete in all
respects.) 1 7700.00 0.04 308.00 Cum 11442.00 3,524,136.00
7/5.5 Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to
work site, laying with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction as per MORTH
specification clause No. 509 complete in all respects)
Case I : Using Bitumen 60/70 grade
ii) For Grading-II (10mm nominal size) 1 7700.00 0.03 231.00 Cum 12393.00 2,862,783.00
7/3.16 Construction of Subgrade and Earthen Shoulders (Construction of subgrade
and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required slope
and compacted to meet requirement of table No. 300-2) 1 4400.00 0.03 132.00 Cum 619.00 81,708.00
8/3.22 Surface Drains in Soil (Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions
to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of 50 metres (average lead 25 metres))
A) Mechanical means 1 1000.00 1000.00 m 56.00 56,000.00
Construction cost = 10,369,141.00
Sl. No./ Area Depth Rate Amount
Description of item 2 Quantity Unit
SOR No (m ) (m) in ` in `
Crushed Total requirement from estimate
Ref Item Bitumen Aggregate
Description Requirement for Sand Total requirement Bitumen Aggregate Sand
no 3
ton m m
3
from estimate ton m
3
m
3

3 3
2/4.12 WBM 360 m 522.00 635.25 m 921.11
2 2
3/5.1 Primer coat 3500 m 2.100 7700.00 m 4.62
2 2
4/5.2 Tack coat 3500 m 1.050 15400.00 m 4.62
3 3
5/5.6 DBM 195.00 m 19.13 281.50 5.750 308.00 m 30.22 444.63 9.08
2 2
6/5.8 BC 191.00 m 22.50 279.300 5.750 231.00 m 27.21 337.79 6.95
Total requirement for the whole length of the road = 66.67 1703.53 16.04
Ton/Unit quantity 1 1.74 1.84
Total weight 67.00 2964.00 30.00
ton ton ton
9/1.1 Loading and unloading of stone boulder/stone aggregates 2964.00 Cum 230.00 681,720.00
10/1.3 Loading and unloading of sand/ kanker/moorum. 30.00 Tonne 230.00 6,900.00
11/1.4 Loading and Unloading of Bitumen by Manual Means 67.00 Tonne 176.00 11,792.00
12/1.6 & Cost of Haulage Excluding Loading and Unloading
1.7
Total Lead for Agggregate = 100 + 38 = 138 Km
Total Lead for Stone Screening = 100 + 38 = 138 Km
Total Lead for Bitumen/ Cement = 209+38= 247 Km
(i) Surfaced Road Lead (Km)
a) Aggregates : 138.00 x 2964.00 T.Km 11.90 4,867,481.00
b) Stone Screening : 138.00 x 30.00 T.Km 11.90 49,266.00
c) Bitumen : 247.00 x 67.00 T.Km 11.90 196,933.00
Carriage cost :Rs. 5,814,092.00
Say : Rs. 16,183,233.00
COST ESTIMATE FOR STRENGTHING OF PAVEMENT PER KM PER YEAR AS PER SOR NH-2016
DETAILED ESTIMATE
Sl. No./ Area Depth Rate Amount
Description of item 2 Quantity Unit
SOR No (m ) (m) in ` in `
1 2 3 4 5 7 6 8 9
1/3.12 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means
(Scarifying the existing granular road surface to a depth of 50 mm and
disposal of scarified material within all lifts and leads upto 1000 metres. ) 1 7700.00 - 7700.00 Sqm 52.00 400,400.00
2/4.1 Construction of granular sub-base by providing close graded Material,
mixing in a mechanical mix plant at OMC, carriage of mixed Material to work
site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density,
complete as per clause 401 1 12000.00 0.15 1800.00 Cum 3061.00 5,509,800.00
3/4.8 Water Bound Macadam (Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with vibratory roller 8-
10 tonnes in stages to proper grade and camber, applying and brooming
requisite type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required density.)
A) By Manual Means
ii) Grading- II
b) Using Screening Type-B (11.2mm Agg.) 1 7700.00 0.075 577.50 Cum
Adding 10% for profile correction : 57.75 Cum
Total 635.25 Cum 4755.00 3,020,614.00
4/5.1 Prime Coat (Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface and
spraying primer at the rate shown in 500-1 using mechanical means.)
i) Low Porosity 1 7700.00 - 7700.00 Sqm 25.00 192,500.00
5/5.2 Tack coat (Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom)
iii) Granular Surface Treated with Primer 1 7700.00 - 7700.00 Sqm 16.00 123,200.00
6/5.2 Tack coat (Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom)
ii) Dry and Hungry Bituminous Surface 1 7700.00 - 7700.00 Sqm 14.00 107,800.00
Sl. No./ Area Depth Rate Amount
Description of item 2 Quantity Unit
SOR No (m ) (m) in ` in `
7/5.6 Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 507 complete in all
respects.) 1 7700.00 0.04 308.00 Cum 11442.00 3,524,136.00
8/5.5 Bituminous Concrete (Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix to
work site, laying with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction as per MORTH
specification clause No. 509 complete in all respects)
Case I : Using Bitumen 60/70 grade
ii) For Grading-II (10mm nominal size) 1 7700.00 0.03 231.00 Cum 12393.00 2,862,783.00
9/3.16 Construction of Subgrade and Earthen Shoulders (Construction of subgrade
and earthen shoulders with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading, grading to required slope
and compacted to meet requirement of table No. 300-2) 1 4400.00 0.03 132.00 Cum 619.00 81,708.00
10/3.22 Surface Drains in Soil (Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions
to the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of 50 metres (average lead 25 metres))
A) Mechanical means 1 1000.00 1000.00 m 56.00 56,000.00
Construction cost = 15,878,941.00
Sl. No./ Area Depth Rate Amount
Description of item 2 Quantity Unit
SOR No (m ) (m) in ` in `
Crushed Total requirement from estimate
Bitumen Aggregate
Ref Item no Description Requirement for Sand Total requirement Bitumen Aggregate Sand
3
ton m m
3
from estimate ton m
3
m
3

3 3
GSB (Drainage layer) 225 m 201.00 86.40 1800.00 m 1608.00 691.20
3 3
2/4.12 WBM 360 m 522.00 635.25 m 921.11
2 2
3/5.1 Primer coat 3500 m 2.100 7700.00 m 4.62
2 2
4/5.2 Tack coat 3500 m 1.050 15400.00 m 4.62
3 3
5/5.6 DBM 195.00 m 19.13 281.50 5.750 308.00 m 30.22 444.63 9.08
2 2
6/5.8 BC 191.00 m 22.50 279.300 5.750 231.00 m 27.21 337.79 6.95
Total requirement for the whole length of the road = 66.67 3311.53 707.24
Ton/Unit quantity 1 1.74 1.84
Total weight 67.00 5762.00 1301.00
ton ton ton
11/1.1 Loading and unloading of stone boulder/stone aggregates 5762.00 Cum 230.00 1,325,260.00
12/1.3 Loading and unloading of sand/ kanker/moorum. 1301.00 Tonne 230.00 299,230.00
13/1.4 Loading and Unloading of Bitumen by Manual Means 67.00 Tonne 176.00 11,792.00
14/1.6 & 1.7 Cost of Haulage Excluding Loading and Unloading

Total Lead for Agggregate = 100 + 38 = 138 Km


Total Lead for Stone Screening = 100 + 38 = 138 Km
Total Lead for Bitumen/ Cement = 209+38= 247 Km
(i) Surfaced Road Lead (Km)
a) Aggregates : 138.00 x 5762.00 T.Km 11.90 9,462,356.00
b) Stone Screening : 138.00 x 1301.00 T.Km 11.90 2,136,502.00
c) Bitumen : 247.00 x 67.00 T.Km 11.90 196,933.00
Carriage cost :Rs. 13,432,073.00
Say : Rs. 29,311,014.00
ESTIMATE FOR MAINTENANCE OF NATIONAL HIGHWAY PER KILOMETRE UP TO THE THIRD YEAR (SOR 2016)
Length = 1000.00 m
Width = 7.00 m
2
Total Area = 7000.00 m
Sl.No Item Unit Rate (Rs.) Length (m) Width (m) Thickness(m) Quantity Amount(Rs.)

1/10.2 Maintenance of earthen shoulder


2
Valley side m 116.00 1000.00 2.50 2500.00

Hill side 1000.00 1.90 1900.00

Sub total 4400.00 510400.00


2
2/10.4 Filling pot holes and patch repair with OGPMC m 375.00 7000.00 2625000.00
2
3/10.8D Surface Dressing by 19mm nominal chipping size m 128.00 7000.00 896000.00

Sub total (A) 4031400.00


Clearing and Grubbing Road land ( average height
4/2.3 Ha 107954.00 1000.00 4.00 0.40 43181.60
upto 4m)
5/10.11 Hill side drain clearance Rm 75.00 1000.00 75000.00

Sub total (B) 118181.60

Grant Total 4149581.60

Cost of Maintenance of Flexible pavement per kilometre upto third year

Sl.No Description Cost / Km (Rs.) Remark

1 First year ( 5% of sub-Total A plus sub-Total B) 319800.00


Rate Escalation @ 10% per
2 Second year ( 15% of sub-Total A plus sub-Total B) 795200.00
annum is assumed)
3 Third year ( 25% of sub-Total A plus sub-Total B) 1351200.00
LIFE CYCLE COST ANALYSIS
MAINTENANCE COST NATIONAL HIGHWAY PER KILOMETRE PER YEAR
Maintenance cost/km/year (Rs.)
Sl.No Description Remark
Flexible Pavement
1 Year 1 0
Construction period
2 Year 2 0
3 Year 3 0
4 Year 4(Normal Maintenance) 0 Maintenance period by
5 Year 5 (Normal Maintenance) 0 contractor under the contract
6 Year 6 (Normal Maintenance) 0
7 Year 7 (Normal Maintenance) 319,800.00 Same escalation @ 10% per
8 Year 8 (Normal Maintenance) 795,200.00 annum is assumed for both
Flexible and Rigid pavements
9 Year 9 (Normal Maintenance) 1,351,200.00
for the sake of comparision.
10 Year 10 (Periodic Renewal) 16,183,233.00
11 Year 11 (Normal Maintenance) 479,700.00 Normal maintenance for year 5
12 Year 12 (Normal Maintenance) 1,272,320.00 is from year 1, year 6 is from
13 Year 13 (Normal Maintenance) 2,297,040.00 year 2 and year 7 is from year 3.
14 Year 14 (Periodic Renewal) 22,656,526.20 Similarly,
15 Year 15 (Normal Maintenance) 719,550.00 The year 8 PR is from year 4.
The pattern is repeated through
16 Year 16 (Normal Maintenance) 2,035,712.00
out the life cycle of flexible
17 Year 17 (Normal Maintenance) 3,904,968.00
pavement
Total of Maintenance cost/km 52,015,249.20
For total length (80.64 km) 4,194,509,695.49
LIFE CYCLE COST COMPARISION OF FLEXIBLE AND RIGID PAVEMENT
Sl.No Type of Pavement Construction cost (Rs.) Total Life cycle cost (Rs.)

1 Construction cost 2,857,702,336.76


2 Maintenance cost 4,194,509,695.49
3 Life cycle cost difference 7,052,212,032.25
EQUIVALENT ANNUAL COST ANALYSIS A-IV
(This analysis is done to compare projects with different Economic lives)
a) Discount rate (%) = 12 ( as per para 7.8 of IRC : SP-30:2001
(1+i)= 1.12
b) Salvage value = Zero in both the proposals
Proposal-I : Flexible Pavement Proposal-I : Rigid Pavement
1 Design Life 15 yrs 1 30 yrs
2 Investment (`) 28577.02 lakh 2 #REF! lakh
Present Value (PV)
PVcost = PVinvestment + PVmaintenance
0
(Pvinvestment) 28577.02 Conclusion
Flexible
Year PVmaintenance From the Equivalent Annual Cost analysis,
1 0.00 it is evident that, the Capital recovery
2 0.00 factor (CRF), which is apportioning the
present value investment amount into an
3 0.00
annuity, it is far advantageous with Rigid
4 0.00
pavement over Flexible pavement. For the
5 0.00 same purpose the two proposals are
6 0.00 intended to serve, present value
Rs
7 0.58 investment in annuity is lower with the
lakh/km/
8 1.45 Rigid pavement than that of Flexible
year
9 2.47 pavement.
10 29.57
11 0.88
12 2.32
13 4.20
14 41.39
15 1.31
Sub-Total 84.18
PV cost 28661.20
15
I Equivalent Annual Cost of Flexible = PV cost/(PV) 12%

Rs. 5236.29 lakh per year


30
II Equivalent Annual Cost of Rigid = PV cost/(PV) 12%
Rs. lakh per year

0
INTERNAL RATE OF RETURN (IRR) ANALYSIS
1 TRAFFIC IN 2015 A-III
Type of Vehicle ADT % ADT Balance on
(existing) Bypassable (Bypass) existing
Car (New Technology) 996 40 398 598
LCV 159 80 100 59
HCV 170 95 170 0
Bus 74 92 70 4
MAV 8 95 8 0
Two Wheelers 327 45 150 177
2 Traffic Growth Rate = 7.50%
3 BREAKUP OF CONSTRUCTION COST
Total cost ` 1391.11 Cr (Flexible) 1265.83 Cr (Rigid)
2020-2021 20% 278.222 253.166
2021-2022 80% 1112.888 1012.664
4 Maintenance cost of Existing Flexible pavement for 15 yrs (in lakh)= Rs. 5236.29 perkm/ year
5 Assuming 5% reduction after bypass constrcution = Rs. 4974.48 perkm/ year
6 Assuming 95% reduction for new bypass maintenance=Rs. 261.81 perkm/ year
7 Length of Existing road 76.598 km
8 Length of proposed by-pass 4.04 km
9 The Road is through hilly terrain.
10 Traffic volume in terms of PCUs per day
Balance on
Existing Bypass (Case-
Type of Vehicle Equivalency Factor existing
(Case-1) 3)
(Case-2)
Car (New Technology) 1 996 597.6 398.4
LCV 1.5 239 89 150
HCV 3 510 0 510
Bus 3 222 12 210
MAV 4.5 36 0 36
Two Wheelers 0.5 163.5 88.5 75
Total 2166 787 1379.4
10 Assuming 10% of total daily traffic to represent the peak hourly traffic
PCU/hr Case-1 217
PCU/hr Case-2 79
PCU/hr Case-3 138
11 Maximum Capacity of 2-lane road in Hilly terrain 1400 (Both dir)
12 NTC= New Technology Cars
LCV = Light Commercial Vehicles
HCV = Heavy Commercial Vehicles (2-Axle)
MAV = Multi-Axial Vehicles
TW= Two Wheelers
VCR = Volume / Capacity Ration
(PCU/hr) / Maximum Capacity but not more than 1
n
13 Traffic Growth Rate = P(1+r)
r= 0.1
n= No of years
TRAFFIC DATA ON EXISTING ROAD " FOR DO NOTHING" (CASE-1)
Year n NTC LCV HCV BUS MAV TW PCU/hr VCR
2020 0 996 159 170 74 8 327 217 0.15
2021 1 1096 175 187 81 9 360 238 0.17
2022 2 1205 192 206 90 10 396 262 0.19
2023 3 1326 212 226 98 11 435 288 0.21
2024 4 1458 233 249 108 12 479 317 0.23
2025 5 1604 256 274 119 13 527 349 0.25
2026 6 1764 282 301 131 14 579 384 0.27
2027 7 1941 310 331 144 16 637 422 0.30
2028 8 2135 341 364 159 17 701 464 0.33
2029 9 2349 375 401 174 19 771 511 0.36
2030 10 2583 412 441 192 21 848 562 0.40
2031 11 2842 454 485 211 23 933 618 0.44
2032 12 3126 499 534 232 25 1026 680 0.49
2033 13 3438 549 587 255 28 1129 748 0.53
2034 14 3782 604 646 281 30 1242 823 0.59
2035 15 4161 664 710 309 33 1366 905 0.65
2036 16 4577 731 781 340 37 1503 995 0.71
2037 17 5034 804 859 374 40 1653 1095 0.78
2038 18 5538 884 945 411 44 1818 1204 0.86
2039 19 6091 972 1040 453 49 2000 1325 0.95
2040 20 6701 1070 1144 498 54 2200 1457 1.00
2041 21 7371 1177 1258 548 59 2420 1603 1.00

TRAFFIC DATA ON BALANCE TRAFFIC USING EXISTING ROAD ROAD AFTER CONSTRUCTION (CASE-2)
Year n NTC LCV HCV BUS MAV TW PCU/hr VCR
2020 0 996 159 170 74 8 327 217 0.15
2021 1 1096 175 187 81 9 360 238 0.17
2022 2 1205 192 206 90 10 396 262 0.19
2023 3 795 79 0 5 0 236 105 0.07
2024 4 875 86 0 6 0 259 115 0.08
2025 5 962 95 0 6 0 285 127 0.09
2026 6 1059 105 0 7 0 314 139 0.10
2027 7 1165 115 0 8 0 345 153 0.11
2028 8 1281 126 0 9 0 379 169 0.12
2029 9 1409 139 0 9 0 417 185 0.13
2030 10 1550 153 0 10 0 459 204 0.15
2031 11 1705 168 0 11 0 505 224 0.16
2032 12 1876 185 0 13 0 556 247 0.18
2033 13 2063 204 0 14 0 611 272 0.19
2034 14 2269 224 0 15 0 672 299 0.21
2035 15 2496 246 0 17 0 739 329 0.23
2036 16 2746 271 0 18 0 813 361 0.26
2037 17 3021 298 0 20 0 895 398 0.28
2038 18 3323 328 0 22 0 984 437 0.31
2039 19 3655 361 0 24 0 1083 481 0.34
2040 20 4020 397 0 27 0 1191 529 0.38
2041 21 4422 437 0 30 0 1310 582 0.42
TRAFFIC DATA ON BYPASS ROAD AFTER CONSTRUCTION (CASE-3)
Year n NTC LCV HCV BUS MAV TW PCU/hr VCR
2020 0 0 0 0 0 0 0 0 0.00
2021 1 0 0 0 0 0 0 0 0.00
2022 2 0 0 0 0 0 0 0 0.00
2023 3 0 0 0 0 0 0 0 0.00
2024 4 0 0 0 0 0 0 0 0.00
2025 5 0 0 0 0 0 0 0 0.00
2026 6 706 177 301 124 14 266 244 0.17
2027 7 776 195 331 136 16 292 269 0.19
2028 8 854 214 364 150 17 322 296 0.21
2029 9 939 236 401 165 19 354 325 0.23
2030 10 1033 259 441 182 21 389 358 0.26
2031 11 1137 285 485 200 23 428 394 0.28
2032 12 1250 314 534 220 25 471 433 0.31
2033 13 1375 345 587 242 28 518 476 0.34
2034 14 1513 380 646 266 30 570 524 0.37
2035 15 1664 418 710 292 33 627 576 0.41
2036 16 1831 459 781 322 37 689 634 0.45
2037 17 2014 505 859 354 40 758 697 0.50
2038 18 2215 556 945 389 44 834 767 0.55
2039 19 2437 612 1040 428 49 917 844 0.60
2040 20 2680 673 1144 471 54 1009 928 0.66
2041 21 2948 740 1258 518 59 1110 1021 0.73
CALCULATION OF CONGESTION FACTORS (CF)
Congestion factor Minimum value is 1 and Maximum Value is 2
Congestion factor for the Peak hour Traffic = 0.8
1. Distance related congestion factor
i) NTC CF= 1.0 + 0.10 VCR
ii) LCV CF= 0.9 + 0.35 VCR
iii) HCV CF= 0.9 + 0.35 VCR
iv) BUS CF= 0.9 + 0.35 VCR
v) MAV CF= 0.9 + 0.45 VCR
Case-1
Year NTC LCV HCV BUS MAV TW
2020 1.00 1.00 1.00 1.00 1.00 1.00
2021 1.00 1.00 1.00 1.00 1.00 1.00
2022 1.00 1.00 1.00 1.00 1.00 1.00
2023 1.00 1.00 1.00 1.00 1.00 1.00
2024 1.00 1.00 1.00 1.00 1.00 1.00
2025 1.00 1.00 1.00 1.00 1.00 1.00
2026 1.00 1.00 1.00 1.00 1.00 1.00
2027 1.00 1.00 1.00 1.00 1.00 1.00
2028 1.00 1.00 1.00 1.00 1.00 1.00
2029 1.00 1.00 1.00 1.00 1.00 1.00
2030 1.00 1.00 1.00 1.00 1.00 1.00
2031 1.00 1.00 1.00 1.00 1.00 1.00
2032 1.00 1.00 1.00 1.00 1.00 1.00
2033 1.00 1.00 1.00 1.00 1.00 1.00
2034 1.00 1.00 1.00 1.00 1.00 1.00
2035 1.00 1.00 1.00 1.00 1.00 1.00
2036 1.00 1.00 1.00 1.00 1.00 1.00
2037 1.00 1.00 1.00 1.00 1.25 1.00
2038 1.00 1.00 1.00 1.00 1.29 1.00
2039 1.00 1.00 1.00 1.00 1.33 1.00
2040 1.00 1.00 1.00 1.00 1.35 1.00
2041 1.00 1.00 1.00 1.00 1.35 1.00
Case-2
Year NTC LCV HCV BUS MAV TW
2020 1.00 1.00 1.00 1.00 1.00 1.00
2021 1.00 1.00 1.00 1.00 1.00 1.00
2022 1.00 1.00 1.00 1.00 1.00 1.00
2023 1.00 1.00 1.00 1.00 1.00 1.00
2024 1.00 1.00 1.00 1.00 1.00 1.00
2025 1.00 1.00 1.00 1.00 1.00 1.00
2026 1.00 1.00 1.00 1.00 1.00 1.00
2027 1.00 1.00 1.00 1.00 1.00 1.00
2028 1.00 1.00 1.00 1.00 1.00 1.00
2029 1.00 1.00 1.00 1.00 1.00 1.00
2030 1.00 1.00 1.00 1.00 1.00 1.00
2031 1.00 1.00 1.00 1.00 1.00 1.00
2032 1.00 1.00 1.00 1.00 1.00 1.00
2033 1.00 1.00 1.00 1.00 1.00 1.00
2034 1.00 1.00 1.00 1.00 1.00 1.00
2035 1.00 1.00 1.00 1.00 1.00 1.00
2036 1.00 1.00 1.00 1.00 1.00 1.00
2037 1.00 1.00 1.00 1.00 1.00 1.00
2038 1.00 1.00 1.00 1.00 1.00 1.00
2039 1.00 1.00 1.00 1.00 1.00 1.00
2040 1.00 1.00 1.00 1.00 1.00 1.00
2041 1.00 1.00 1.00 1.00 1.00 1.00
Case-3
Year NTC LCV HCV BUS MAV TW
2020 1.00 1.00 1.00 1.00 1.00 1.00
2021 1.00 1.00 1.00 1.00 1.00 1.00
2022 1.00 1.00 1.00 1.00 1.00 1.00
2023 1.00 1.00 1.00 1.00 1.00 1.00
2024 1.00 1.00 1.00 1.00 1.00 1.00
2025 1.00 1.00 1.00 1.00 1.00 1.00
2026 1.00 1.00 1.00 1.00 1.00 1.00
2027 1.00 1.00 1.00 1.00 1.00 1.00
2028 1.00 1.00 1.00 1.00 1.00 1.00
2029 1.00 1.00 1.00 1.00 1.00 1.00
2030 1.00 1.00 1.00 1.00 1.00 1.00
2031 1.00 1.00 1.00 1.00 1.00 1.00
2032 1.00 1.00 1.00 1.00 1.00 1.00
2033 1.00 1.00 1.00 1.00 1.00 1.00
2034 1.00 1.00 1.00 1.00 1.00 1.00
2035 1.00 1.00 1.00 1.00 1.00 1.00
2036 1.00 1.00 1.00 1.00 1.00 1.00
2037 1.00 1.00 1.00 1.00 1.00 1.00
2038 1.00 1.00 1.00 1.00 1.00 1.00
2039 1.00 1.00 1.00 1.00 1.00 1.00
2040 1.00 1.00 1.00 1.00 1.00 1.00
2041 1.00 1.00 1.00 1.00 1.00 1.00
2 Time related congestion factor
i) VCN = 72.63 - 0.017 Q
ii) VLCV = 56.07 - 0.013 Q
iii) VT = 46.58 - 0.008 Q
iv) VMAV = 35.40 - 0.006 Q
v) VB = 52.76 - 0.013 Q
vi) VTW = 40.75 - 0.007 Q
Where Q=PCU/hr
CF= Intercept of the above equation/Speed (Calculated from the equation)
Calculation of Speed
Case-1
year VCN VLCV VT VMAV VB VTW
2020 68.95 53.25 44.85 34.10 49.94 39.23
2021 68.58 52.97 44.67 33.97 49.66 39.08
2022 68.17 52.66 44.48 33.83 49.35 38.92
2023 67.73 52.32 44.27 33.67 49.01 38.73
2024 67.24 51.95 44.04 33.50 48.64 38.53
2025 66.70 51.54 43.79 33.31 48.23 38.31
2026 66.11 51.08 43.51 33.10 47.77 38.06
2027 65.45 50.58 43.20 32.87 47.27 37.80
2028 64.74 50.03 42.87 32.61 46.72 37.50
2029 63.95 49.43 42.49 32.34 46.12 37.17
2030 63.08 48.77 42.09 32.03 45.46 36.82
2031 62.12 48.04 41.64 31.69 44.73 36.42
2032 61.07 47.23 41.14 31.32 43.92 35.99
2033 59.92 46.35 40.60 30.91 43.04 35.52
2034 58.65 45.38 40.00 30.46 42.07 34.99
2035 57.25 44.31 39.34 29.97 41.00 34.42
2036 55.71 43.13 38.62 29.43 39.82 33.78
2037 54.02 41.84 37.82 28.83 38.53 33.09
2038 52.16 40.41 36.95 28.17 37.10 32.32
2039 50.11 38.85 35.98 27.45 35.54 31.48
2040 47.86 37.13 34.92 26.66 33.82 30.55
2041 45.38 35.23 33.76 25.78 31.92 29.53
Case-2
year VCN VLCV VT VMAV VB VTW
2020 68.95 53.25 44.85 34.10 49.94 39.23
2021 68.58 52.97 44.67 33.97 49.66 39.08
2022 68.17 52.66 44.48 33.83 49.35 38.92
2023 70.85 54.71 45.74 34.77 51.40 40.02
2024 70.67 54.57 45.66 34.71 51.26 39.94
2025 70.48 54.42 45.57 34.64 51.11 39.86
2026 70.26 54.26 45.47 34.56 50.95 39.77
2027 70.02 54.08 45.35 34.48 50.77 39.68
2028 69.76 53.88 45.23 34.39 50.57 39.57
2029 69.48 53.66 45.10 34.29 50.35 39.45
2030 69.16 53.42 44.95 34.18 50.11 39.32
2031 68.81 53.15 44.78 34.05 49.84 39.18
2032 68.43 52.86 44.61 33.92 49.55 39.02
2033 68.01 52.54 44.41 33.77 49.23 38.85
2034 67.55 52.19 44.19 33.61 48.88 38.66
2035 67.04 51.80 43.95 33.43 48.49 38.45
2036 66.49 51.37 43.69 33.23 48.06 38.22
2037 65.87 50.90 43.40 33.01 47.59 37.97
2038 65.20 50.38 43.08 32.78 47.07 37.69
2039 64.45 49.82 42.73 32.51 46.51 37.38
2040 63.63 49.19 42.35 32.22 45.88 37.05
2041 62.73 48.50 41.92 31.91 45.19 36.68
Case-3
year VCN VLCV VT VMAV VB VTW
2020 72.63 56.07 46.58 35.40 52.76 40.75
2021 72.63 56.07 46.58 35.40 52.76 40.75
2022 72.63 56.07 46.58 35.40 52.76 40.75
2023 72.63 56.07 46.58 35.40 52.76 40.75
2024 72.63 56.07 46.58 35.40 52.76 40.75
2025 72.63 56.07 46.58 35.40 52.76 40.75
2026 68.48 52.89 44.63 33.93 49.58 39.04
2027 68.06 52.58 44.43 33.79 49.27 38.87
2028 67.60 52.23 44.21 33.63 48.92 38.68
2029 67.10 51.84 43.98 33.45 48.53 38.47
2030 66.55 51.42 43.72 33.25 48.11 38.25
2031 65.94 50.95 43.43 33.04 47.64 38.00
2032 65.27 50.44 43.12 32.80 47.13 37.72
2033 64.53 49.88 42.77 32.54 46.57 37.42
2034 63.72 49.26 42.39 32.26 45.95 37.08
2035 62.83 48.58 41.97 31.94 45.27 36.72
2036 61.85 47.83 41.51 31.60 44.52 36.31
2037 60.78 47.01 41.00 31.22 43.70 35.87
2038 59.59 46.10 40.44 30.80 42.79 35.38
2039 58.29 45.10 39.83 30.34 41.79 34.84
2040 56.85 44.01 39.16 29.83 40.70 34.25
2041 55.28 42.80 38.41 29.28 39.49 33.60
Time related Congestion factor
Case-1
Year NTC LCV HCV BUS MAV TW
2020 1.00 1.00 1.00 1.00 1.00 1.00
2021 1.00 1.00 1.00 1.00 1.00 1.00
2022 1.00 1.00 1.00 1.00 1.00 1.00
2023 1.00 1.00 1.00 1.00 1.00 1.00
2024 1.00 1.00 1.00 1.00 1.00 1.00
2025 1.00 1.00 1.00 1.00 1.00 1.00
2026 1.00 1.00 1.00 1.00 1.00 1.00
2027 1.00 1.00 1.00 1.00 1.00 1.00
2028 1.00 1.00 1.00 1.00 1.00 1.00
2029 1.00 1.00 1.00 1.00 1.00 1.00
2030 1.00 1.00 1.00 1.00 1.00 1.00
2031 1.00 1.00 1.00 1.00 1.00 1.00
2032 1.00 1.00 1.00 1.00 1.00 1.00
2033 1.00 1.00 1.00 1.00 1.00 1.00
2034 1.00 1.00 1.00 1.91 1.00 1.00
2035 1.01 1.31 1.00 1.94 1.00 1.00
2036 1.04 1.35 1.00 1.97 1.00 1.00
2037 1.08 1.39 1.00 2.00 1.00 1.00
2038 1.11 1.44 1.57 2.00 1.57 1.80
2039 1.16 1.50 1.61 2.00 1.63 1.85
2040 1.21 1.57 1.66 2.00 1.72 1.90
2041 1.28 1.65 1.72 2.00 1.82 1.97

Case-2
Year NTC LCV HCV BUS MAV TW
2020 1.00 1.00 1.00 1.00 1.00 1.00
2021 1.00 1.00 1.00 1.00 1.00 1.00
2022 1.00 1.00 1.00 1.00 1.00 1.00
2023 1.00 1.00 1.00 1.00 1.00 1.00
2024 1.00 1.00 1.00 1.00 1.00 1.00
2025 1.00 1.00 1.00 1.00 1.00 1.00
2026 1.00 1.00 1.00 1.00 1.00 1.00
2027 1.00 1.00 1.00 1.00 1.00 1.00
2028 1.00 1.00 1.00 1.00 1.00 1.00
2029 1.00 1.00 1.00 1.00 1.00 1.00
2030 1.00 1.00 1.00 1.00 1.00 1.00
2031 1.00 1.00 1.00 1.00 1.00 1.00
2032 1.00 1.00 1.00 1.00 1.00 1.00
2033 1.00 1.00 1.00 1.00 1.00 1.00
2034 1.00 1.00 1.00 1.00 1.00 1.00
2035 1.00 1.00 1.00 1.00 1.00 1.00
2036 1.00 1.00 1.00 1.00 1.00 1.00
2037 1.00 1.00 1.00 1.00 1.00 1.00
2038 1.00 1.00 1.00 1.00 1.00 1.00
2039 1.00 1.00 1.00 1.00 1.00 1.00
2040 1.00 1.00 1.00 1.00 1.00 1.00
2041 1.00 1.00 1.00 1.00 1.00 1.00
Case-3
Year NTC LCV HCV BUS MAV TW
2020 1.00 1.00 1.00 1.00 1.00 1.00
2021 1.00 1.00 1.00 1.00 1.00 1.00
2022 1.00 1.00 1.00 1.00 1.00 1.00
2023 1.00 1.00 1.00 1.00 1.00 1.00
2024 1.00 1.00 1.00 1.00 1.00 1.00
2025 1.00 1.00 1.00 1.00 1.00 1.00
2026 1.00 1.00 1.00 1.00 1.00 1.00
2027 1.00 1.00 1.00 1.00 1.00 1.00
2028 1.00 1.00 1.00 1.00 1.00 1.00
2029 1.00 1.00 1.00 1.00 1.00 1.00
2030 1.00 1.00 1.00 1.00 1.00 1.00
2031 1.00 1.00 1.00 1.00 1.00 1.00
2032 1.00 1.00 1.00 1.00 1.00 1.00
2033 1.00 1.00 1.00 1.00 1.00 1.00
2034 1.00 1.00 1.00 1.00 1.00 1.00
2035 1.00 1.00 1.00 1.00 1.00 1.00
2036 1.00 1.00 1.00 1.00 1.00 1.00
2037 1.00 1.00 1.00 1.00 1.00 1.00
2038 1.00 1.00 1.00 1.00 1.00 1.00
2039 1.00 1.00 1.00 1.01 1.00 1.00
2040 1.00 1.08 1.00 1.04 1.00 1.00
2041 1.00 1.10 1.00 1.07 1.00 1.00
VEHICLE OPERATING COST (Flexible)
VOC = VOC for uncongested condition X Congestion factor
RF factor for hilly terrain (30-50) = 40.00
Roughness = 4000mm/km
Length of existing Road 76.598 Km Length of bypass 4.04 Km
1 Distance related economic costs (Rs/km)
NTC LCV HCV BUS MAV TW
i) Fuel 0.71 0.68 0.78 0.72 1.89 0.22
ii) Tyre 0.06 0.43 1.09 1.07 1.81 0.01
iii) Lubricants 0.03 0.01 0.02 0.01 0.02 0.03
iv) Spares 0.16 0.19 0.22 0.34 0.38 0.06
v) Maintenance 0.14 0.08 0.11 0.19 0.22 0.04
Total 1.1 1.39 2.22 2.33 4.32 0.36
2 Time related economic cost (Rs/km)
NTC LCV HCV BUS MAV TW
i) Fixed cost 0.8 3.13 2.16 1.29 3.47 0.31
ii) Depreciation 0.08 0.19 0.33 0.27 0.7 0.04
Total 0.88 3.32 2.49 1.56 4.17 0.35
3 Distance related VOC (Rs/km)
Case-1
Year NTC LCV HCV BUS MAV TW
2020 1.1 1.39 2.22 2.33 4.32 0.36
2021 1.1 1.39 2.22 2.33 4.32 0.36
2022 1.1 1.39 2.22 2.33 4.32 0.36
2023 1.1 1.39 2.22 2.33 4.32 0.36
2024 1.1 1.39 2.22 2.33 4.32 0.36
2025 1.1 1.39 2.22 2.33 4.32 0.36
2026 1.1 1.39 2.22 2.33 4.32 0.36
2027 1.1 1.39 2.22 2.33 4.32 0.36
2028 1.1 1.39 2.22 2.33 4.32 0.36
2029 1.1 1.39 2.22 2.33 4.32 0.36
2030 1.1 1.39 2.22 2.33 4.32 0.36
2031 1.1 1.39 2.22 2.33 4.32 0.36
2032 1.1 1.39 2.22 2.33 4.32 0.36
2033 1.1 1.39 2.22 2.33 4.32 0.36
2034 1.1 1.39 2.22 2.33 4.32 0.36
2035 1.1 1.39 2.22 2.33 4.32 0.36
2036 1.1 1.39 2.22 2.33 4.32 0.36
2037 1.1 1.39 2.22 2.33 5.41 0.36
2038 1.1 1.39 2.22 2.33 5.56 0.36
2039 1.1 1.39 2.22 2.33 5.73 0.36
2040 1.1 1.39 2.22 2.33 5.83 0.36
2041 1.1 1.39 2.22 2.33 5.83 0.36
Case-2
Year NTC LCV HCV BUS MAV TW
2020 1.1 1.39 2.22 2.33 4.32 0.36
2021 1.1 1.39 2.22 2.33 4.32 0.36
2022 1.1 1.39 2.22 2.33 4.32 0.36
2023 1.1 1.39 2.22 2.33 4.32 0.36
2024 1.1 1.39 2.22 2.33 4.32 0.36
2025 1.1 1.39 2.22 2.33 4.32 0.36
2026 1.1 1.39 2.22 2.33 4.32 0.36
2027 1.1 1.39 2.22 2.33 4.32 0.36
2028 1.1 1.39 2.22 2.33 4.32 0.36
2029 1.1 1.39 2.22 2.33 4.32 0.36
2030 1.1 1.39 2.22 2.33 4.32 0.36
2031 1.1 1.39 2.22 2.33 4.32 0.36
2032 1.1 1.39 2.22 2.33 4.32 0.36
2033 1.1 1.39 2.22 2.33 4.32 0.36
2034 1.1 1.39 2.22 2.33 4.32 0.36
2035 1.1 1.39 2.22 2.33 4.32 0.36
2036 1.1 1.39 2.22 2.33 4.32 0.36
2037 1.1 1.39 2.22 2.33 4.32 0.36
2038 1.1 1.39 2.22 2.33 4.32 0.36
2039 1.1 1.39 2.22 2.33 4.32 0.36
2040 1.1 1.39 2.22 2.33 4.32 0.36
2041 1.1 1.39 2.22 2.33 4.32 0.36

Case-3
Year NTC LCV HCV BUS MAV TW
2020 1.1 1.39 2.22 2.33 4.32 0.36
2021 1.1 1.39 2.22 2.33 4.32 0.36
2022 1.1 1.39 2.22 2.33 4.32 0.36
2023 1.1 1.39 2.22 2.33 4.32 0.36
2024 1.1 1.39 2.22 2.33 4.32 0.36
2025 1.1 1.39 2.22 2.33 4.32 0.36
2026 1.1 1.39 2.22 2.33 4.32 0.36
2027 1.1 1.39 2.22 2.33 4.32 0.36
2028 1.1 1.39 2.22 2.33 4.32 0.36
2029 1.1 1.39 2.22 2.33 4.32 0.36
2030 1.1 1.39 2.22 2.33 4.32 0.36
2031 1.1 1.39 2.22 2.33 4.32 0.36
2032 1.1 1.39 2.22 2.33 4.32 0.36
2033 1.1 1.39 2.22 2.33 4.32 0.36
2034 1.1 1.39 2.22 2.33 4.32 0.36
2035 1.1 1.39 2.22 2.33 4.32 0.36
2036 1.1 1.39 2.22 2.33 4.32 0.36
2037 1.1 1.39 2.22 2.33 4.32 0.36
2038 1.1 1.39 2.22 2.33 4.32 0.36
2039 1.1 1.39 2.22 2.33 4.32 0.36
2040 1.1 1.39 2.22 2.33 4.32 0.36
2041 1.10 1.39 2.22 2.33 4.32 0.36
4 Time related VOC (Rs/km)
Case-1
Year NTC LCV HCV BUS MAV TW
2020 0.88 3.32 2.49 1.56 4.17 0.35
2021 0.88 3.32 2.49 1.56 4.17 0.35
2022 0.88 3.32 2.49 1.56 4.17 0.35
2023 0.88 3.32 2.49 1.56 4.17 0.35
2024 0.88 3.32 2.49 1.56 4.17 0.35
2025 0.88 3.32 2.49 1.56 4.17 0.35
2026 0.88 3.32 2.49 1.56 4.17 0.35
2027 0.88 3.32 2.49 1.56 4.17 0.35
2028 0.88 3.32 2.49 1.56 4.17 0.35
2029 0.88 3.32 2.49 1.56 4.17 0.35
2030 0.88 3.32 2.49 1.56 4.17 0.35
2031 0.88 3.32 2.49 1.56 4.17 0.35
2032 0.88 3.32 2.49 1.56 4.17 0.35
2033 0.88 3.32 2.49 1.56 4.17 0.35
2034 0.88 3.32 2.49 2.98 4.17 0.35
2035 0.89 4.35 2.49 3.02 4.17 0.35
2036 0.92 4.47 2.49 3.08 4.17 0.35
2037 0.95 4.61 2.49 3.12 4.17 0.35
2038 0.98 4.77 3.92 3.12 6.53 0.63
2039 1.02 4.97 4.02 3.12 6.82 0.65
2040 1.07 5.20 4.14 3.12 7.16 0.67
2041 1.13 5.48 4.29 3.12 7.59 0.69

Case-2
Year NTC LCV HCV BUS MAV TW
2020 0.88 3.32 2.49 1.56 4.17 0.35
2021 0.88 3.32 2.49 1.56 4.17 0.35
2022 0.88 3.32 2.49 1.56 4.17 0.35
2023 0.88 3.32 2.49 1.56 4.17 0.35
2024 0.88 3.32 2.49 1.56 4.17 0.35
2025 0.88 3.32 2.49 1.56 4.17 0.35
2026 0.88 3.32 2.49 1.56 4.17 0.35
2027 0.88 3.32 2.49 1.56 4.17 0.35
2028 0.88 3.32 2.49 1.56 4.17 0.35
2029 0.88 3.32 2.49 1.56 4.17 0.35
2030 0.88 3.32 2.49 1.56 4.17 0.35
2031 0.88 3.32 2.49 1.56 4.17 0.35
2032 0.88 3.32 2.49 1.56 4.17 0.35
2033 0.88 3.32 2.49 1.56 4.17 0.35
2034 0.88 3.32 2.49 1.56 4.17 0.35
2035 0.88 3.32 2.49 1.56 4.17 0.35
2036 0.88 3.32 2.49 1.56 4.17 0.35
2037 0.88 3.32 2.49 1.56 4.17 0.35
2038 0.88 3.32 2.49 1.56 4.17 0.35
2039 0.88 3.32 2.49 1.56 4.17 0.35
2040 0.88 3.32 2.49 1.56 4.17 0.35
2041 0.88 3.32 2.49 1.56 4.17 0.35
Case-3
Year NTC LCV HCV BUS MAV TW
2020 0.88 3.32 2.49 1.56 4.17 0.35
2021 0.88 3.32 2.49 1.56 4.17 0.35
2022 0.88 3.32 2.49 1.56 4.17 0.35
2023 0.88 3.32 2.49 1.56 4.17 0.35
2024 0.88 3.32 2.49 1.56 4.17 0.35
2025 0.88 3.32 2.49 1.56 4.17 0.35
2026 0.88 3.32 2.49 1.56 4.17 0.35
2027 0.88 3.32 2.49 1.56 4.17 0.35
2028 0.88 3.32 2.49 1.56 4.17 0.35
2029 0.88 3.32 2.49 1.56 4.17 0.35
2030 0.88 3.32 2.49 1.56 4.17 0.35
2031 0.88 3.32 2.49 1.56 4.17 0.35
2032 0.88 3.32 2.49 1.56 4.17 0.35
2033 0.88 3.32 2.49 1.56 4.17 0.35
2034 0.88 3.32 2.49 1.56 4.17 0.35
2035 0.88 3.32 2.49 1.56 4.17 0.35
2036 0.88 3.32 2.49 1.56 4.17 0.35
2037 0.88 3.32 2.49 1.56 4.17 0.35
2038 0.88 3.32 2.49 1.56 4.17 0.35
2039 0.88 3.32 2.49 1.58 4.17 0.35
2040 0.88 3.58 2.49 1.62 4.17 0.35
2041 0.88 3.65 2.49 1.67 4.17 0.35

5 TOTAL VOC (DISTANCE AND TIME RELATED ) (Rs/km)


Case-1
Year NTC LCV HCV BUS MAV TW
2020 1.98 4.71 4.71 3.89 8.49 0.71
2021 1.98 4.71 4.71 3.89 8.49 0.71
2022 1.98 4.71 4.71 3.89 8.49 0.71
2023 1.98 4.71 4.71 3.89 8.49 0.71
2024 1.98 4.71 4.71 3.89 8.49 0.71
2025 1.98 4.71 4.71 3.89 8.49 0.71
2026 1.98 4.71 4.71 3.89 8.49 0.71
2027 1.98 4.71 4.71 3.89 8.49 0.71
2028 1.98 4.71 4.71 3.89 8.49 0.71
2029 1.98 4.71 4.71 3.89 8.49 0.71
2030 1.98 4.71 4.71 3.89 8.49 0.71
2031 1.98 4.71 4.71 3.89 8.49 0.71
2032 1.98 4.71 4.71 3.89 8.49 0.71
2033 1.98 4.71 4.71 3.89 8.49 0.71
2034 1.98 4.71 4.71 5.31 8.49 0.71
2035 1.99 5.74 4.71 5.35 8.49 0.71
2036 2.02 5.86 4.71 5.41 8.49 0.71
2037 2.05 6.00 4.71 5.45 9.58 0.71
2038 2.08 6.16 6.14 5.45 12.09 0.99
2039 2.12 6.36 6.24 5.45 12.55 1.01
2040 2.17 6.59 6.36 5.45 13.00 1.03
2041 2.23 6.87 6.51 5.45 13.42 1.05
Case-2
Year NTC LCV HCV BUS MAV TW
2020 1.98 4.71 4.71 3.89 8.49 0.71
2021 1.98 4.71 4.71 3.89 8.49 0.71
2022 1.98 4.71 4.71 3.89 8.49 0.71
2023 1.98 4.71 4.71 3.89 8.49 0.71
2024 1.98 4.71 4.71 3.89 8.49 0.71
2025 1.98 4.71 4.71 3.89 8.49 0.71
2026 1.98 4.71 4.71 3.89 8.49 0.71
2027 1.98 4.71 4.71 3.89 8.49 0.71
2028 1.98 4.71 4.71 3.89 8.49 0.71
2029 1.98 4.71 4.71 3.89 8.49 0.71
2030 1.98 4.71 4.71 3.89 8.49 0.71
2031 1.98 4.71 4.71 3.89 8.49 0.71
2032 1.98 4.71 4.71 3.89 8.49 0.71
2033 1.98 4.71 4.71 3.89 8.49 0.71
2034 1.98 4.71 4.71 3.89 8.49 0.71
2035 1.98 4.71 4.71 3.89 8.49 0.71
2036 1.98 4.71 4.71 3.89 8.49 0.71
2037 1.98 4.71 4.71 3.89 8.49 0.71
2038 1.98 4.71 4.71 3.89 8.49 0.71
2039 1.98 4.71 4.71 3.89 8.49 0.71
2040 1.98 4.71 4.71 3.89 8.49 0.71
2041 1.98 4.71 4.71 3.89 8.49 0.71
Case-3
Year NTC LCV HCV BUS MAV TW
2020 1.98 4.71 4.71 3.89 8.49 0.71
2021 1.98 4.71 4.71 3.89 8.49 0.71
2022 1.98 4.71 4.71 3.89 8.49 0.71
2023 1.98 4.71 4.71 3.89 8.49 0.71
2024 1.98 4.71 4.71 3.89 8.49 0.71
2025 1.98 4.71 4.71 3.89 8.49 0.71
2026 1.98 4.71 4.71 3.89 8.49 0.71
2027 1.98 4.71 4.71 3.89 8.49 0.71
2028 1.98 4.71 4.71 3.89 8.49 0.71
2029 1.98 4.71 4.71 3.89 8.49 0.71
2030 1.98 4.71 4.71 3.89 8.49 0.71
2031 1.98 4.71 4.71 3.89 8.49 0.71
2032 1.98 4.71 4.71 3.89 8.49 0.71
2033 1.98 4.71 4.71 3.89 8.49 0.71
2034 1.98 4.71 4.71 3.89 8.49 0.71
2035 1.98 4.71 4.71 3.89 8.49 0.71
2036 1.98 4.71 4.71 3.89 8.49 0.71
2037 1.98 4.71 4.71 3.89 8.49 0.71
2038 1.98 4.71 4.71 3.89 8.49 0.71
2039 1.98 4.71 4.71 3.91 8.49 0.71
2040 1.98 4.97 4.71 3.95 8.49 0.71
2041 1.98 5.04 4.71 4.00 8.49 0.71
6 Vehicle operation cost for one year
Data on Vehicular Traffic on Alternative Proposals
vehicle type Case-1 Case-2 Case-3
NTC 996 597.6 398.4
LCV 159 59 100
HCV 170 0 170
BUS 74 4 70
MAV 8 0 8
TW 327 177 150
Increase in Price rate factor from base year 1990 = 6.50
Number of days = 365
Number of days during constrcution & Maintenance = 0
Case-1
Length of road = 76.598 km
Year NTC LCV HCV BUS MAV TW Total
2020 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2021 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2022 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2023 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2024 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2025 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2026 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2027 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2028 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2029 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2030 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2031 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2032 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2033 358383643 136094847.3 145510214.1 52312439 12343017 42191965 746836126.1
2034 358383643 136094847.3 145510214.1 71345471 12343017 42191965 765869157.8
2035 360763784 165965319.8 145510214.1 72004327 12343017 42191965 798778626.9
2036 365227214 169396025.1 145510214.1 72754593 12343017 42191965 807423027.8
2037 370430574 173392603.6 145510214.1 73291207 13925083 42191965 818741646.6
2038 376544186 178084402.3 189564316.9 73291207 17577214 58784654 893845980.5
2039 383793687 183642436.2 192803536.5 73291207 18238540 59786046 911555453.3
2040 392484515 190297671.7 196573103.1 73291207 18895299 60951408 932493204.5
2041 403040678 198369874.2 200992996.6 73291207 19513436 62317841 957526032.8
Case-2
Length of road = 76.598 km
Year NTC LCV HCV BUS MAV TW Total
2020 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2021 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2022 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2023 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2024 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2025 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2026 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2027 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2028 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2029 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2030 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2031 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2032 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2033 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2034 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2035 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2036 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2037 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2038 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2039 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2040 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7
2041 215030186 50500603.73 0 2827699.4 0 22837853 291196341.7

Case-3
Length of road = 4.04 km
Year NTC LCV HCV BUS MAV TW Total
2020 0 0 0 0 0 0 0
2021 0 0 0 0 0 0 0
2022 0 0 0 0 0 0 0
2023 0 0 0 0 0 0 0
2024 0 0 0 0 0 0 0
2025 0 0 0 0 0 0 0
2026 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2027 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2028 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2029 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2030 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2031 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2032 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2033 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2034 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2035 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2036 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2037 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2038 7560875.84 4514487.9 7674629.43 2609968.3 651006.41 1020791.9 24031759.69
2039 7560875.84 4514487.9 7674629.43 2620365.9 651006.41 1020791.9 24042157.34
2040 7560875.84 4762516.211 7674629.43 2648852.8 651006.41 1020791.9 24318672.53
2041 7560875.84 4828809.474 7674629.43 2682015.9 651006.41 1020791.9 24418128.9
COST BENEFIT ANALYSIS
t
IRR Sum Co=(Bt-Ct)/(1+i) Length of Existing Road = 76.598 km
1. Do Nothing and Flexible Pavement Length of Bypass Road = 4.04 km
Case-1 = Do Nothing Construction cost of Bypass (Rs.) = 13911100000
Case-2 = Existing Road after Bypass is constructed The Internal Rate of Return (IRR) (%) = 12.00
Case-3 = Bypass Road (with flexible pavement) Rs in Lakhs
Maintenance cost +
Year (t) t Road User Cost/VOC Cost Benefit Discounted Costs and
construction cost
(6-7-8) (3-4-5) Benefits
Case-1 Case-2 Case-3 Case-1 Case-2 Case-3
1 2 3 4 5 6 7 8 9 10 11 12
2020 0 7468.36 2911.96 0.00 401089.65 401089.65 1041.00 -1041.00 0.00 -1041.00
2021 1 7468.36 2911.96 0.00 401089.65 401089.65 3037.00 -3037.00 0.00 -2711.61
2022 2 7468.36 2911.96 0.00 381035.17 381035.17 3810.35 -3810.35 4556.40 6669.92
2023 3 7468.36 2911.96 0.00 381035.17 381035.17 3810.35 -3810.35 4556.40 5955.29
2024 4 7468.36 2911.96 0.00 381035.17 381035.17 3810.35 -3810.35 4556.40 5317.22
2025 5 7468.36 2911.96 0.00 381035.17 381035.17 3810.35 -3810.35 4556.40 4747.52
2026 6 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 4117.10
2027 7 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 3675.99
2028 8 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 3282.13
2029 9 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 2930.47
2030 10 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 2616.49
2031 11 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 2336.15
2032 12 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 2085.85
2033 13 7468.36 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4316.08 1862.37
2034 14 7658.69 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4506.41 1701.77
2035 15 7987.79 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4835.51 1579.57
2036 16 8074.23 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 4921.95 1424.43
2037 17 8187.42 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 5035.14 1288.30
2038 18 8938.46 2911.96 240.32 381035.17 381035.17 3810.35 -3810.35 5786.18 1247.93
2039 19 9115.55 2911.96 240.42 381035.17 381035.17 3810.35 -3810.35 5963.17 1134.77
2040 20 9324.93 2911.96 243.19 381035.17 381035.17 3810.35 -3810.35 6169.78 1034.61
-76474.68 89972.36 -3752.61 55007.88
B/C = 1.18

You might also like