Professional Documents
Culture Documents
Concrete Building
Master Thesis
Study Course Construction and Real Estate Management
Submitted on 15.09.2014
Haseeb Uz Zaman
541108
Study has been aimed to establish a structured solution for rehabilitation and
retrofitting of fire damaged concrete buildings. This study explains the rehab
process of fire damaged concrete buildings in three basic categories; condition
evaluation, decision making, rehabilitation & retrofitting. Evaluation method of
damaged building has been based upon understanding of material properties at
elevated temperatures, condition survey and condition assessment. Condition
survey includes visual inspection, hammering and chiselling techniques whereas
condition assessment includes both non-destructive and destructive tests that are
selected upon the basis of efficiency, economy, and performance. Feasibility
study is required to make right decisions for the rehab of fire damaged building.
Such a feasibility study should include all important aspects that will have an
impact in the future, therefore must be considered in decision making. A new
feasibility analysis model is developed as a part of research. It is expected to help
decision making process because of its sound conceptual foundation and
detailed structure. If feasibility study reveals rehabilitation and retrofitting
worthwhile then it can be effectively rehabilitated with the help of right techniques.
Rehabilitation of non-structural members/elements and retrofitting of structural
with the help of soda blasting, patch repair, FRP reinforcing, partial removal and
replacement, concrete jacketing, steel jacketing and few other retrofitting
techniques has been discussed. Respective pros and cons of these techniques
have been covered with special focus on sustainability, economy, efficiency and
limitations. These techniques can be used separately or in conjunction with other
techniques. As every locks has its own key similarly every case has its unique
solution therefore it can’t be said that which technique or set of technique is
universally superior to others. Generally speaking, partial removal and
replacement offers more advantages. It seems to have more ticks and less
crosses when compared to others.
1 Introduction ................................................................................................ 1
2.1.2 Steel...................................................................................................... 7
6.2.1Depreciation ......................................................................................... 90
9 List of Literature……………………………………………………………..118
I
Table of Figures
Figure 12: FRP Wraps on side faces and bottom side ...................................... 40
Figure 14: FRP sheet wrapped on the tension side of fire damaged slab ......... 41
Figure 23: Top view of damaged Valley- Ridge concrete roof ......................... 86
Figure 26: Burnt AC unit (left), Damages Electricity cables (right) .................. 100
II
List of Tabulation
Table 5: Visual Inspection Guide for fire damaged R.C.C elements ................. 16
List of Abbreviations
TR Technical Report
UPV Ultra Pulse Velocity
UTM Universal Testing Machine
1
1. Introduction
1.1. Background
Many books, journals and articles have been written over different aspects of fire
damage buildings e.g. evaluation of fire damaged buildings, NDTs for fire
damaged buildings, rehabilitation of fire damaged buildings, retrofitting of
structures subjected to high temperatures etc. Many Studies and researches
have been done on various aspects too. But still a crying need have been felt for
a structured study that takes care of matter right from the beginning (evaluation)
and encompass the whole process till the very end (rehabilitation and retrofitting
measures).
This study is inspired to take care of whole process. The process starts from
evaluation of fire damaged buildings. Various techniques for evaluation of
concrete structures are available and commonly practiced but not every
technique is suitable for evaluation of fire damaged building. It has been set as a
goal to explore different methodologies and discuss most suitable and most
practiced ones in the text. Then to explain their limitations and shortcomings to
work out that which technique or combination of techniques can provide with the
true assessment of the fire damaged concrete building.
on hand. This study is limited for concrete buildings with focus on research
questions only.
At first literature study has been done in which evaluation of fire damaged
buildings and rehabilitation & retrofitting were covered. The knowledge obtained
from literature study is then skimmed to include only targeted methodologies that
ticks certain criteria (as explained in section 1.2). Afterwards, development and
research work has started. In this phase, parametric mathematical model for
feasibility analysis had been developed based on technical and financial
feasibility. After it has been developed initially, then it has been tested.
Shortcomings have been identified and developed model is improved. This
becomes a loop of testing and improvement until satisfactory results are obtained.
After parametric mathematical model had been finally developed, it had been
tested on a real case (Beverly Centre Islamabad) to test its capacity and validity.
Literature
Internet sources
Interviews
Data collection
Case studies
Parametric mathematical modelling
Empirical testing
4
After the incident of fire, the buildings are in bad condition. The severity of the
damage depends upon the duration, magnitude and temperature attained by fire.
After fire is extinguished, building has to be immediately investigated to decide
that; is it safe to enter the building and can building withstand after the fire load,
without being progressively collapsed. After structure of the building is secured,
it is ready to be properly assessed. The condition assessment requirements,
techniques (field tests, laboratory testing etc.), methodology for data
management of collected data1 will be discussed in this chapter.
Buildings are consisting of construction materials that vary in nature from one
another. The very nature of each material is specific to its physical properties,
chemical properties and behaviour of material, when exposed to fire. The most
important materials found in the concrete buildings is obviously concrete and
structural steel but even in them, we have variations depending upon the
manufacturing process and ingredient mix.
Other materials like glass, aluminium, thermal insulations, wood, plastics etc. are
also part of building. Investigate of the damage occurred to the building, requires
the understanding of these materials especially those which are part of the
structural elements. Now, we will discuss the behaviour of basic structural
materials (concrete and steel).
2.1.1. Concrete
Concrete is a very stable material in nature. It is inert, solid, with high compressive
strength and excellent surface hardness. The melting point of concrete is around
1200 Celsius Centigrade (Concrete Society TR68, 2008). All these properties
makes it quite subtle when exposed to fire. EN 13501-12 classifies materials into
seven categories (A1, A2, B, C, D, E and F). A1 is considered as the best possible
material which is virtually inert to fire or fire resistant and concrete is assigned
under A1 category. Concrete doesn’t burn by itself because it is not a combustible
material hence doesn’t add up in the fire load. It doesn’t melts and doesn’t drips
materials at the temperature that normally occurs in fire. The inert property of
concrete is down to the ingredients in the concrete mix which gives it these inert
properties. Moreover concrete has poor thermal conductance and it transfers
heat at a very low rate.3
The rate of temperature increase through cross section is also slow. The
temperature of the material at the surface wouldn’t be that high after initial few
centimetres. According to a standard ISO 834/BS 476 fire test performed on a
concrete beam of cross section 160mm x 300mm showed that after exposure of
concrete from 3 sides for 1 hour, the surface temperature reached to 900 Celsius.
This decreases to only 600 Celsius after 16 mm and to 300 Celsius after 42mm.
So actually the temperature gradient decrease from 900 to 600 in depth of 16 mm
and from 600 to 300 in depth of 26mm.4
2European standard for building materials classification for the reaction to fire behaviour of
building products.
3 The Concrete centre. 2008. Concrete and fire safety. Page no 4.
4 The Concrete centre. 2008. Concrete and fire safety. Page no 4.
6
All these factors effects the strength of concrete after the event of fire. Upto the
temperature of 300 Celsius, concrete more or less retains is strength and this is
also considered as the benchmark of safe temperature of concrete. Upto the
temperature of 500 Celsius a significant loss of strength happens but still holds
sufficient residual strength. Above 600 Celsius serious damages occurs.
Concrete Society document TR68, 2008 explains the behaviours of concrete at
different temperatures and shown in Table 1.5
5Jeremy P Ingham. 2009. Forensic engineering of fire damaged concrete structures. Page no 2.
6Concrete Society. 2008. Technical Report No. 68 – “Assessment, Design and Repair of Fire-
damaged Concrete Structures”.
7
In event of fire, the structure should perform these following three limit state
functions.7
To avoid these two changes, following two factors have to be considered more
important than others in case of concrete.
2.1.2. Steel
for the spread of fire. The loss of strength in case of high temperature is generally
responsible for the extra deflections of R.C.C elements. Mostly after cooling
down, steel recovers its yield strength if it has experienced temperature less than
450 Celsius in case of cold rolled steel and 600 Celsius in case of hot rolled steel.
If the temperature is under these respective limits then steel can be re-used
comprehensively and structure can be retrofitted with various measures
available. But if temperature is exceeded in these respective kinds of reinforcing
steels then it will be a problem, as in that case replacement of reinforcement bars
or additional bars will be required (will be discussed in detail later). 9
Case for pre-stressed steel is more critical one than reinforcing steel as the nature
of the pre-stressed structure. Elongation of steel is done by hydraulic jack and
then concrete is casted over it. When steel has enough bonding with concrete
then steel wires are cut and released. They tends to squeeze inside but the
bonding with the concrete prohibits it, as a result of which the pre-stressing steel
inserts inwards/compression force on concrete. This compression force counter
acts the tensile load acting over it. If temperature will rise then pre-stressing steel
will lose the tensile force within itself which is causing the compression in
concrete and ultimately structure will lose its strength. From 200 to 400 Celsius,
reinforcements in pre stressing concrete structure lose considerable strength. At
400 Celsius, structure loses its 50% strength. In terms of re-use more important
factor is the tension available in pre stressed steel after the event of fire. If it still
has significant loss of tension then it may not carry its intended function.10
Other non-structural materials like glass, aluminium, wood and all such other
materials experience damages in event of fire and may contribute to the fire load
by themselves. These materials are not of much significant importance as they
can easily be replaced if damaged beyond repair. Materials may exhale harmful
fumes or gases or particles in air especially asbestos. If building has asbestos in
9 Jeremy P Ingham. 2009. Forensic engineering of fire damaged concrete structures. Page no 3.
10 Jeremy P Ingham. 2009. Forensic engineering of fire damaged concrete structures.Page no 3.
9
it and it caught fire then asbestos particles will be released in air although their
concentration will not be very high at least upto the level where it will be critically
dangerous but constant exposure to these particles will lead to serious health
risks. One of the prime responsibilities of the building disaster department is to
confirm or discard the presence of asbestos in the building. Once building is
regarded as asbestos free then experts and crew can enter the building for
examining it.
After the event of fire, building is in poor condition. When authorities are done
with preliminary survey to decide that building is safe enough to enter then
assessment team can start the assessment of building but before that a general
analysis of building is required to know following facts and figures about the case.
It is better to visit the site and conduct complete condition assessment but
preliminary report from fire and police department can be studied to have a
general idea about the damages building has incurred. This will make an initial
image and inform about the building’s damage at a crude level. Answer to basic
10
questions like how much area or stories have been damaged and how much got
indirectly effected can be obtained from the Fire department/Police report.
Duration, size and if possible then temperature of fire can also be determined
from the fire report and it will be a real assert for the upcoming stages of
assessment. Duration of fire is a very important factor in particular. Fire resistance
of the building is expressed in unit of time as it defines11
Hence duration of fire will give an idea what kind of damage building would have
undergone in the event. Interviews recorded from the inhabitants and witnesses
can give an idea about the fire path which also have impact on the damage
undergone and obviously on the duration of fire exposure.
Desk study before visiting the site and conducting general assessment is very
beneficial. It is always better to do homework before dealing with the case. It will
create an initial picture and equip the inspector with the valuable information
regarding structure, its properties and its materials.
the building during the event. Ideally they are assessed during visual inspection.
There is no need to conduct excessive testing on these parts or utilities of the
building. Visual inspection of the building with a team of crafts men can determine
the condition of the utilities or non-structural members.
Eye of an experienced engineer is more valuable than any other tool in the
condition assessment of non-structural members or utilities. A team consisting of
experts/craftsmen in respective field can conduct this task. Table 2 will give a
comprehensive insight about the important things to be inspected during visual
inspection
Windows
Doors
Detached Balconies
Roof Covering
(Shingles, Tiles etc.)
Partition Walls
Façade Elements
HVAC
Plumbing
Electrical wirings
Railings
Flooring material
Dropped ceiling
Light Fixtures
Alarm System
Mechanical equipment
Table 2: Non-structural members’ and utilities’ visual inspection report
12 FD= fire damage, SD= Smoke damage, WD= Water damage, ID= Internal damage, BW= Bio
waste like blood, carcases etc.
13 1= needs cleaning, 2= needs surface treatment (polishing shinning etc.), 3= needs minor repair,
While assessing the condition of utilities and non-structural part of the building
nature of damage has to be determined to realise that what was the cause of
damage. Either it was because of fire or because of water or fire extinguishing
foam that fire brigade have used or damage has been done due to smoke etc.
Once cause of damage is recognised then extent of damage is assessed and
probably be given rating from 5 to 1. Five is the worst case scenario where only
replacement is the option. While giving utilities the damage rating then eye should
be kept upon the price factor.
Visual inspection is a very powerful tool and one of the most common and oldest
available non-destructive testing techniques available. Visual inspection gives a
wealth of information about the structure and its condition but has certain
requirements and limitations. Visual inspection can only be governed by a
technically sound professional who has knowledge about structure, material
science and construction methodologies. Visual inspection only gives impression
of visible issues and hidden issues remain unnoticed. It also doesn’t give us any
quantitative information about the properties of the material. Due to these
13
Tapping with a hammer and chisel is also one of the oldest methods to inspect
the strength of concrete. This is not an exact methodology to estimate concrete
14 http://www.engineeringcivil.com/visual-inspection-of-concrete-structure.html accessed
10.07.2014.
15 http://www.structuremag.org/?p=4102 accessed 10.07.2014.
16 http://www.structuremag.org/?p=4102 accessed 10.07.2014.
14
Chisel and metallic pencils are also used for the evaluation of concrete’s strength
and the depth of damage that has occurred. In this case hammer is placed at the
right angle to the surface and then stroked form behind with the hammer. The
results of the practice gives the idea about the concrete’s strength and also shows
that upto which depth concrete has endured damage. Usually the damaged
concrete that already has plane of failure spalled away and exposes the
reinforcements. Chisel can also be used to scratch the surface and resultantly
can emit some light over the condition of the concrete. Table 4 gives us the criteria
for Concrete strength.19
17 http://www.engineeringcivil.com/visual-inspection-of-concrete-structure.html accessed
10.07.2014.
18 http://www.engineeringcivil.com/visual-inspection-of-concrete-structure.html accessed
10.07.2014.
19 http://www.engineeringcivil.com/visual-inspection-of-concrete-structure.html accessed
10.07.2014.
15
10.0 to 20.0 Thin scales split off round the Visible scratches no deeper
mark than 1 mm
Degree of Observations
Damage
Colour Finishes Spalling Cracks Deflections Reinfor-
cement
20http://www.engineeringcivil.com/visual-inspection-of-concrete-structure.html accessed
10.07.14.
16
Visual inspection can give some idea about the structure and its residual strength
and has to be supplemented by other NDT and partially destructive tests to create
a clear picture of the situation. The results obtained by one
team/engineer/craftsman can differentiate from the other as these testing
techniques are highly subjective and depends upon personal competence.
21Modified from (Concrete Society. 2008. Technical Report No. 68 – Assessment, Design and
Repair of Fire-damaged).
17
The Schmidt rebound hammer works on the principle that the rebound of an
elastic mass depends upon the hardness of the surface against which the mass
strikes. When the plunger of the rebound hammer is pressed against the surface
of the concrete, it will hit the concrete at a defined energy and the spring-
controlled mass rebounds. The extent of such a rebound depends upon the
surface hardness of the concrete. The surface hardness, and therefore the
rebound, is taken to be related to the compressive strength of the concrete. The
rebound value is read from a graduated scale and is designated as the rebound
number or rebound index. By reference to the conversion chart, the rebound
value can be used to determine the compressive strength. There is little apparent
theoretical relationship between the strength of concrete and the rebound number
of the hammer. However, within limits, empirical correlations have been
established between strength properties and the rebound number.24
22 Haseeb Uz Zaman, Tahir Saleem, Azhar Shehzad, Mohsin Ashfaq & Muhammad Bilal. 2011.
Comparison of compressive strength of concrete calculated by destructive and non-destructive
testing. Chapter 6.
23 http://www.theconcreteportal.com/nde.html accessed 11.07.2014.
24 Haseeb Uz Zaman, Tahir Saleem, Azhar Shehzad, Mohsin Ashfaq & Muhammad Bilal. 2011.
Schmidt hammer is really a useful handy technique but can’t be really relied upon.
It is a test which requires personal competence. The values of the test are quite
variable even when same test is performed on the same element at two different
places. Reason for that is the nature of the test. As described earlier that rebound
hammer calculates the surface hardness of the concrete which then we relate to
the compressive strength with empirical charts/graphs. So if there will be an
aggregate just beneath the surface of the test point then it will give high value
and if there is a plane of weakness (cement paste in the fire damaged concrete
is the weaker plane) then it will show less values. Moreover, the nature of the test
and its requirement to interpret hammer value to the compressive strength
summed up to deviation of 15% to 30%. Conditions of smooth surface and
repeated number of tests at the same points and no of points required for
successful testing make it very difficult to test the fire damaged concrete
structures where concrete spalling and disintegration is often the case.25
This is a commonly used non-destructive test. It is done to assess the quality and
compressive strength of concrete by ultrasonic pulse velocity method. The
method consists of measuring the time of travel of an ultrasonic pulse passing
through the concrete being tested. Comparatively higher velocity is obtained
when concrete quality is good in terms of density, uniformity and homogeneity
etc. To evaluate the compressive strength of concrete we use graphical
relationship between pulse velocity and compressive strength of concrete.26
Ultrasonic pulse velocity is a good technique for examining concrete but it has its
limitations as other non-destructive testing methods. This testing technique
measures the propagation time of waves through the concrete in reality and there
is no direct relation of wave propagation timing and concrete’s strength but some
indirect relations are used to get concrete’s strength. Hence, possibility of error
and deviation from result is there due to the conversions involved28. Moreover, it
indicates the level of cracking in the structure with the fluctuation of the
propagation time of wave within set distance not the concrete’s strength. Although
concrete’s strength is then calculated by indirect relations.29
Moreover specific care has to be taken while conducting ultrasonic pulse velocity
tests. Experienced testing staff are required as this test depends upon the
competence of the inspector’s technical skills of getting the results and then the
conversion of data to compressive strength. Several factors have their say in the
end results for example
Temperature of concrete
Moisture level
27 Haseeb Uz Zaman, Tahir Saleem, Azhar Shehzad, Mohsin Ashfaq & Muhammad Bilal. 2011.
Comparison of compressive strength of concrete calculated by destructive and non-destructive
testing. Chapter 7.
28 From pulse velocity to strength through graphs and formulas.
29 Haseeb Uz Zaman, Tahir Saleem, Azhar Shehzad, Mohsin Ashfaq & Muhammad Bilal. 2011.
If moisture level of concrete is more than usual then it will also cause deviation in
readings as waves propagates through water filled pockets in concrete faster than
the dry air filled concrete. Therefore, structure, that is not dried after it became
wet due to the water sprayed over it due to firefighting, cannot be accurately
assessed. Usually, there is a difference of 2% is there which can be adjusted.
Surface of testing
Surface on which transducers are placed must be smooth and if it is not then it
must be prepared by grinding and then by applying wax to tightly put transducers
against the surface of concrete. As in case of fire damaged building where
excessive spalling is experienced, there this methodology can’t give the right
impression about the concrete. In these cases spalled layer of concrete can be
removed then tests can be performed.
Effect of reinforcement
The propagation travelling time through the reinforcement bar is almost twice as
of concrete hence if the reinforcement bar is along the length of the testing points
then tests can’t be relied upon. This Puts a serious question marks on the
application and utility of test.
All these limitations of this testing technique doesn’t let this NDT technique to
qualify as a reliable testing technique for the evaluation of the fire damaged
concrete structure but still can give valuable input if properly conducted with care
to its sensitivities and results are properly adjusted for respective deviations.30
30 CPWD, India. 2002, Handbook of repair and rehabilitation of R.C.C buildings, page no III-20.
21
penetrates into the concrete is related to the strength of concrete by the help of
empirical relationship. The results are usually not much disturbed due to the
moisture content or concrete texture but care has to be taken in term of surface
preparation and minimum dimensions of the test subject. Limitations states that
minimum edge distance and member thickness should be 150 mm. Moreover the
presence of reinforcement direct under the probe or in the vicinity of 50 mm will
obviously be a problem and will give misleading reading hence have to be
avoided.31
The accuracy of the test depends upon the correlation used to relate probe
penetration with the compressive strength of concrete. The correlation is provided
by the manufacturer for specific type of aggregate and concrete mix used
because. It is sensitive to the aggregate hardness unlike crushing test of concrete
cubes. For concrete of same strength measured by crushing test of concrete
cubes, penetration resistance test can give different values of strength if one has
harder aggregate and the other one has softer. Hence the charts or correlation
provided is for a specific aggregate concrete because it is prepared by the tests
on concrete with specific aggregate in the laboratory.33
Windsor probe test can be employed for the evaluation of the fire damaged
concrete structure but again inherits the limitations associated to non-destructive
testing techniques. It is sensitive to the aggregate used in concrete hence
Core sampling and testing is one of the most trusted techniques used as non-
destructive testing technique. Actually it is partially destructive testing technique.
Core sampling and testing is pretty much reliable if properly conducted and
conditions fulfilled. In core sampling, the core is cut by rotary cutting tool with
industrial diamond bits at its tip. Concrete core is obtained and then taken to
laboratory for testing. Concrete cores size (diameter) is not specified but
minimum criteria is the diameter of the core must be 3.5 times the maximum size
34 CPWD, India. 2002, Handbook of repair and rehabilitation of R.C.C buildings, page no III-24.
23
of aggregate. The length to diameter ratio of the core that is used to measure
compressive strength must be between 1 to 2, most preferable between 1 to 1.2.
Before testing core can be trimmed to the length satisfying the above criteria of
length to diameter ratio with the help of diamond saw.35
Core obtained by drilling don’t have smooth ends moreover due to fire there may
be some spalling and rough texture so it is important to smooth these regularities
up and made end parallel and smooth. Usually it is done by capping. Material
used for capping is high aluminium cement or sulphur sand mix. During obtaining
core samples special care has to be taken into account so that there wouldn’t be
any damage to core (usually it happens). Then these cores are tested in
compressive strength measuring machine by loading them upto crushing hence
compressive strengths are measured.37
35 CPWD, India. 2002, Handbook of repair and rehabilitation of R.C.C buildings, page no III-28.
36 http://www.cctia.org/FAQ_Files/10.001_Concrete_Core_Tests.html accessed 21.07.2014.
37 CPWD, India. 2002, Handbook of repair and rehabilitation of R.C.C buildings, page no III-29.
24
sensitive to some factors majorly the geometry and dimensions of the core and
lack of standardization. But the results are fairly accurate for normal and standard
core sizes in normal practice. Core’s compressive strength obtained from good
concrete and from damaged concrete from same structure or even different ones
can be compared in order to evaluate the damage done by fire.
Investigation of the fire damaged structure started by the means of desk study,
where general knowledge about fire and structure was studied. After desk study,
visual inspection is carried out to witness the damage and to have some idea
about the nature, and extent of damage. Visual inspection and inspection of
debris is concluded to understand the fire behaviour and properties like if
aluminium frames of windows are melted then it means that the temperature of
fire would be around 500 Celsius. After visual inspection of the building’s
38Ivan Detchev, Ayman Habib, Mamdouh El-Badry. 2011. Case study of beam deformation
monitoring using conventional close range photogrammetry. Page no 1.
25
structural and non-structural parts condition assessment with field and laboratory
testing can be conducted as damage is located during visual inspection part. The
field test mainly consisting of NDTs and partially destructive testing like core
sampling. These NDTs mainly gives quantitative idea about the residual
strengths of the structural members. The results obtained from NDTs can exhibit
accuracy upto 80% with 20% margin of disturbance (which is still a lot). If that is
what is required then further delicate laboratory testing techniques like
Petrography, Differential thermal analysis and Thermo gravimetric analysis
(TGA) and Fire modelling Techniques are not required. But if exact nature, extent
and depth of damage is required to be evaluated then following laboratory
techniques will do the rest of job. In case of fire damaged buildings, Petrography
test is the ideal test and give what is needed. Other Techniques like DTA and
TGA wouldn’t be discussed, as they are not usually required or feasible to be
carried out.
2.4.3.1. Petrography
Petrographic test are conducted for understanding the cause of failure, condition
assessment of damaged structure due to known cause like fire or freeze thaw
cycles etc. Petrographic testing can define a range of parameters that can exactly
evaluate the fire damaged building. Some of the common parameters that can be
investigated by Petrography are as under40
Petrography is done on the samples that are obtained from the field by core
sampling at various depths. These samples are then treated with proper surface
treatments like polishing or thin sectioning to prepare them for testing. Thin
sections are prepared of the thickness one quarter of the hair to study it under
petrographic microscope. The sample must be extracted with care as it must
inhibit the characteristics of the damage that is needed to be studied. Moreover
information of the concrete mix is also helpful like water cement ratio, concrete
mix and minimum air content.
The samples are placed within the grips of the UTM and then they are loaded
under uniform tensile load until failure. The reinforcement bar piece will be
elongated in the centre. In case of ductile failure it will show necking and in case
of brittle failure it will not show any necking as shown in the next figure. The data
is obtained and inform us about the ultimate load, ultimate stress, maximum
elongation and reduction in area. Form these data other important information
like yield strength and Young’s modulus can be obtained. Hence Tensile Test
gives us virtually all necessary information we require about the reinforcements
of the fire damaged concrete structure. The effectiveness of tensile test is more
important in the sense that it doesn’t calculate the strength by any indirect
measure but actually gives the original residual strength of the damaged
reinforcement bars.
Summary
Fire damages the building and the extent of damage depends upon
temperature and duration of fire, Conditions of fire (e.g. air ventilation), building
materials, location of fire (basement, top floor, etc.), quality of design and
construction and load sustained by building. After the fire, building structure
must be secured first and building must be cleared by respective authorities
for further investigation.
Schmidt hammer doesn’t measure the compressive strength directly but infact
measures surface hardness, which is then used to estimate compressive
strength with the help of empirical correlations. Ultrasonic pulse velocity test
30
If field test, which usually are not very accurate, are not enough and higher
level of accuracy is required then laboratory tests like Petrography for
concrete and tensile test and Scanning electron microscopy for
reinforcements are done. Petrography is a complete test as it gives
approximately all kind of information that is required to access condition of
concrete in fire damaged concrete buildings. Techniques like DTA and TGA
are not required or even feasible sometimes after Petrography. So collectively
in authors opinion, core sampling and testing combined with Petrography are
sufficient to evaluate concrete in case of fire damaged concrete building. But
to jump for these testing techniques in every case of fire damage is not
advisable. For light to moderate damages simple visual inspection and NDT
testing may be sufficient enough.
31
For fire damaged building not many options are available for retrofitting of
structure. Most conventional ones are strengthening of structural members with
fibre reinforced plastic and replacement of damaged concrete either with
shotcrete or in-situ placement of concrete. These are quite commonly practiced
and may not be very suitable in every case. Some new methods for retrofitting of
fire damaged structures will also be discussed that are not common for such
cases like steel jacketing, concrete jacketing or provision of extra members.
These measures are usually used for other purposes like protection against earth
quakes but if chosen after careful analysis then may prove to be beneficial in
comparison to other more conventional measures.
3.1. Cleaning
Just after the fire building is in filthy condition, depending upon the size, nature
and duration of fire. It is better to clean the building and secure the residual stuff
32
In the beginning all water accumulated in the building must be removed by the
help of pumps and manual equipment. Fire extinguishing foam is removed as well
from the building. It is very important to dry the wet surface as it will otherwise
generates the problem of mold. High ventilation in the building is highly
recommended and if possible or required then dehumidifiers can be used.
Professional cleaners are required for cleaning job in case of heavy fires.46
Heavy soot47 will be deposited on the accessories and the building structure. It is
important to deal with it properly and remove it from the surface otherwise it will
deteriorate them and the smoke smell will become a permanent stay in the facility.
Inspection of building services like HVAC is important. All such building services
or property that has been damaged beyond repair should be identified in the
beginning and disposed properly. For the remaining belongings and building
structure can then be subjected to cleaning and repair works.
There are various techniques to deal with soot deposited on different surfaces.
For curtains and upholstery (furniture), it is preferred to use vacuum cleaners
before washing them. It is necessary to uplift soot with the nozzle of appropriates
vacuum cleaner before washing otherwise soot will penetrate into the fabric. Soot
have to be removed from the walls and ceiling as well with the help of chemical
45 Institute of Food and Agricultural Sciences, University of Florida. 1998. The Disaster Handbook
National Edition. Section (13.17). Page no 1.
46 Institute of Food and Agricultural Sciences, University of Florida. 1998. The Disaster Handbook
sponge and if required then some counter chemicals can be used. If soot is not
properly removed from the surface of walls and ceiling then the smell of fire
wouldn’t go away.48
Smoke penetrates the building in the event of fire. The smoke is very problematic
in case of fire. Smoke penetrates virtually through very other material present in
the building. It persists in the building if not properly removed. Records recovered
from 1906 San Francisco fire that are currently stored in National Achieves of
USA, still have very strong odour of smoke. It can give the idea that how critical
this problem is. To understand the gravity of the problem first it is necessary to
understand smoke and its composition. Smoke is the combination of gases, liquid
and solid fumes that emits from the fuel. They are considered as the unburnt part
of the fuel and they may contains toxic and carcinogenic particles. The size of
these particles is less than 10 microns in diameter, mostly they are less than 1
micron. Hence it is critical to get rid of smoke particles as they pose serious health
issue and sometimes acidic fumes that may contain corrodes and damages the
property and structure like wise.50
48 Department of Public health, Los Angeles County. 2013. How to clean up smoke and soot from
a fire. Page # 2.
49 http://www.ccwonline.com.au/prod437.htm accessed 11.08.2014.
50 http://chicora.org/fire.html accessed 11.08.2014.
34
Thermal insulation can significant capacity to store smoke particles and retain it
for long time. If there is any such insulation in contact with smoke then it’s better
to replace it otherwise dry cleaning and treatment with counter chemicals will take
care of the problem to some extent. Thermal insulations at attic are mostly
damaged in case of fire if there are any. It is better to replace the insulation with
new one. Smoke that has penetrated the ducts can be sealed on the walls of the
ducts with the help of chemical sealers as it is very difficult to access the inner
side of these ducts.51
For the rest of the building and its belongings thermal foggers, ozone machines
and air scrubbers are used. Aerosol sprays or deodorisers can’t cover the smoke
smell for long and sometimes they mix with the smoke and creates a new smell
that might be more irritating. Thermal foggers creates a fog from water based
masking agent. It super heats the masking agent that produces the fog. Fog then
travels through the building and its properties just like smoke and reaches where
smoke might have reached. Thermal foggers comprehensively deals with the
smoke but it has its disadvantages too. The material that has already been under
stress from fire and smoke is then again subjected to the high temperature fog to
ward off smell. It puts extra stress over the material of property.52
Ozone machines produces ozone in large quantities. Ozone roams through the
building and disinfect the building. The problem associated with ozone treatment
is serious though as ozone is a strong oxidizing agent and oxidize virtually all
organic matter. Due to ozone treatment, leather will be damaged. It embrittles
paper, inks and dyes will be faded, and if concrete spalling is extensive then it
will reacted to the exposed steel surface to make metallic oxide. Moreover ozone
causes irritation in eyes, lungs and skin. Hence its application is very limited and
should not be used everywhere as it virtually ages every material in household. 53
51 Institute of Food and Agricultural Sciences, University of Florida. 1998. The Disaster Handbook
National Edition. Section (13.17). Page no 4.
52 http://chicora.org/fire.html accessed 11.08.2014.
53 http://chicora.org/fire.html accessed 11.08.2014.
35
Air scrubbers are used to depollute the particles and fumes from the air. Smoke
particles that are suspended in the air or trapped in the corners will be removed
with the help of air scrubbers. Special air scrubbers are used for smoke damage
that cycles air 5 to 6 times in an hour. After repeated cycles the air is pollutant
free and smoke particles are arrested by it.56
During fire, non-structural members and utilities undergoes more damage than
structural members. Thanks to the inherent properties of concrete and steel that
54http://www.agi.my/index.php/our-solutions/disaster-restoration/a-restoration-services-
include/stubborn-unpleasant-odor/thermal-and-mist-treatment-to-remove-all-types-of-malodor/
accessed 11.08.2014.
55 http://www.cleanfax.com/articles/105969-effective-thermal-fogging accessed 11.08.2014.
56 http://www.wisegeek.com/what-is-an-air-scrubber.htm accessed 11.08.2014.
57 http://www.emssales.net/store/cart.php?m=product_detail&slug=predator-600-portable-air-
scrubber. (accessed 11.08.2014.)
36
makes them inert even on high temperature and provides necessary fire proof
properties up till sufficient temperature. Fire damage is quite serious in case of
materials made up of combustible material like plastics, fibre plastics, wood etc.
and these are the materials that are usually used for non-structural members and
utilities. Commonly, HVAC ducts are made from plastics and fibre plastics not
only get damaged but infact increases the fire load.
Utilities like HVAC, if decided to be repaired after feasibility studies then they
would be restored but usually that’s only the case of partial destruction. If they
have endured heavy damage then it is usually better to restore them. Special
attention can be provided towards the improvement of already existing systems.
Challenges sometimes are there from the provisions and code requirements.
Sometimes building design doesn’t support the changes and actual material for
replacement is not available in market or have to be exported from somewhere
else which cost too much time or money.
Non-structural members like façade, partition walls, suspended ceiling etc. bears
heavy damage as well and again their damage depends upon the material of their
composition. Glass façade usually gets heavy damage where it gets in contact
with the direct flames and usually glass is broken within 30 minutes. Glass façade
provides safety issues as they retains gases and smoke inside the building
because of lack of sufficient openings which markedly increases the causalities
in fire incident. Glass panels that are damaged has to be replaced with similar
ones and rest of the damaged glass tiles can be rehabilitated just by cleaning.
Other façade materials like metallic sheets, terracotta, marble tiles, brick tiles etc.
doesn’t suffer heavy damage and usually just few tiles that would be in direct
access of high temperatures are required to be replaced. Otherwise, cleaning job
will take care of the rest of the job. Sometimes it is required to use Soda-blasting
technique to remove the accumulated soot and smoke over the surface. Soda
blasting is a very handy technique in which Sodium bicarbonate particles that are
very fragile in nature are bombarded over the surface from an air pressured
nozzle just like paint job for vehicles. These small particles struck the surface and
explodes into smaller particles and takes the coating soot or rust or smoke with
37
them, leaving clear undamaged original surface beneath. Soda also spreads over
the surface and deodorize the surface from smoke smell.58
Walls, like façade also depends upon the material of construction. In case of brick
of concrete walls, damage is not significant as both have good resistibility. The
damaged part of plaster or concrete can be removed and repair is provided with
new concrete and plaster but usually it is not required. Surface treatment of
roughness and spalled concrete is provided. Afterwards soda-blasting is done to
remove smoke and soot deposited on the surface. Partition walls are sometimes
need removal of partitioning boards and repair of wooden frame. If wooden frame
is deeply damaged then it is better to replace it. For plaster boards once again
soda blasting will provide fitting solution to get rid from fire stains and odour.
Same goes for suspended ceilings. Those panels that are too much damaged
are replaced otherwise they are cleaned with soda blasting.
Structure is the skeleton of the building. It provides the integrity, strength and
stability to the building to perform its function. Structural safety is one of the
outmost important thing. During fire, building’s structure resists the fire and
counters it upto a certain point according to its fire rating. If structure is loaded
during fire as well then it reduces the material capacity of fire resistance. Under
fire structure shouldn’t fail, which would ultimately cause the demolition of the
whole building. Concrete structures have proven to be very stable in fire
especially when compared to wood and steel structures, all thanks to the superior
fire resistant properties of concrete. In the event of fire R.C.C members endured
damage due to high temperature but this is not the only worrying point when it
comes to retrofitting of structure. After fire , use of water to extinguish the fire or
fire retardant foam cause sudden cooling of structure that have been at very high
temperatures this causes permanent set of deformation, cracking and spalling.
Hence FRP sheets are wrapped in such a way that the direction of the fibres is
perpendicular to the longitudinal axis of the element or to the axis along which
element requires flexural stiffness.60
Another factor that plays very important role in the overall success of repair and
instalment of strength and stiffness is the method of application. For different
members the method of application of FRP sheets or straps is different which will
be described in detail later in the topic. Last but not least epoxy resins that are
used as glue for the application of FRP wraps over the damaged structural
member is of prime importance. Some researches even states that it is the telling
factor for the successful restoration of the strength. Surface of damaged member
should be prepared before the application of the FRP straps. Any irregularity that
may cause rupture in the FRP sheets must be taken care of by grouting or resin
injections. Sharp edges of non-circular members must be rounded by grinding
machine. All these measures are important because FRP material is prone to
rupture and it dramatically changes the behaviour and scenario of strength re-
instalment. After preparing the surface of concrete epoxy resins are applied to
the surface and on the wraps as per requirements and then applied to the
structural members immediately and some pressure is applied over it to squeeze
out the extra strength from bonding. Hence application of FRP over the damaged
structure should be properly monitored for above mentioned factors.61
Beams are repaired by two ways. One is by applying FRP plates on the tension
side of the beam which is on the downwards side in the middle of supports.
Alternatively beams are wrapped on three sides by FRP wrapping sheet making
a U and additional protective layers are provided along the axis of beam as shown
in the figure below. For application of FRP material usually epoxy resins are used
but sometimes steel bolts are also provided but it should be monitored that they
don’t provide a weaker plane in cross section.63
For column repairs, FRP wrapping sheet material is used. The surface is
prepared and FRP sheet are wrapped around the column with epoxy resins. The
FRP sheets are slightly overlapping with each other. Number of sheets used for
the repair is dependent upon the design and degree of damage member has
endured during the infortune event. The confinement provided by the FRP wraps
provides the stiffness and enhanced flexural strength along with better
compressive strength. There are two methods to apply the FRP wraps. Applying
wraps with pre tensioning and filling of grout between member and the FRP
wrapping sheet. Second method is to apply FRP wraps in passive mode in which
counter stress is produced for confinement when concrete column is subjected
to expansion under the action of loads. The direction of fibres in the FRP is kept
perpendicular to the longitudinal axis of column.66
For slab repairs, FRP sheets are pasted on the tension side of the slab so provide
extra flexural strength to the element. FRP wraps are also provided to increase
the shear capacity of the slabs where it has been damaged due to fire. FRP wraps
are applied to the slab elements just as for beams. Usually the FRP sheet are
wrapped with the help of epoxy resins, and mechanical fixings.
Figure 14: FRP sheet wrapped on the tension side of fire damaged slab 68
accessed 15.08.2014.
68 Fay Engineering. 2003. KBP Coil Coaters Fire Repair and Shear Strengthening. Ppt.
42
69 Burgozne, Balafas. 2007. Why is FRP not a financial success?. Page no 1-9.
70 Martin Alberto Masuelli. 2013. Introduction of Fibre-Reinforced Polymers – Polymers and
Composites: Concepts, Properties and Processes. Page no 1-5.
71 Martin Alberto Masuelli. 2013. Introduction of Fibre-Reinforced Polymers – Polymers and
Composites: Concepts, Properties and Processes. Page no 1-5.
72 Burgozne, Balafas. 2007. Why is FRP not a financial success?. Page no 1-9.
73 Martin Alberto Masuelli. 2013. Introduction of Fibre-Reinforced Polymers – Polymers and
Composites: Concepts, Properties and Processes. Page no 1-5.
74 Martin Alberto Masuelli. 2013. Introduction of Fibre-Reinforced Polymers – Polymers and
Composites: Concepts, Properties and Processes. Page no 1-5.
43
FRP material is light in weight that is one of its many qualities but this
is a double edge sword as it also not as good in stiffness as its
challenger steel. This lack of satisfactory stiffness is responsible for
heavy deflection which is not very appreciated. For example how many
of us would like to sit under a heavily deflected beam. So although FRP
proves to be a good repair material for fire damaged building but still it
doesn’t take cares of heavy deflection.
FRP sheets are prone to wear and tear76. It can be ruptured due to any
sharp object pointing force through it that’s why corners of non-circular
column are rounded prior to the application FRP over them.
During fire, both concrete and steel undergoes damage. Degree of damage is
assessed in condition assessment and survey. For retrofitting of the damaged
structure it is mandatory to have clear ideas about the structural condition and its
integrity because only then the methodology and requirement for this method can
be decided.
Basic idea behind this repair method is to remove the damaged concrete by some
suitable mean (hydro blasting, Jack hammer etc.) upto the depth of damage.
Then remove the part of reinforcement bar/bars that has/have been damaged (if
any). Then preparation of surface for repair application. Usually the surface is
prepared and good enough for repair application in case of concrete removal by
hydro blasting. After concrete removal and preparation of surface reinforcement
bars that have been removed are replaced by suitable means (overlapping or
welding etc.)80. Then concrete is replaced by in-situ casting with the help of form
work or by shotcrete such that it reinstate the original form and provides sufficient
strength for structural requirements. The whole process is explained in detail
below.
80 In case where reinforcement bars have been damaged and needs replacement.
81 http://frbiz789.blog.com/2009/12/01/hydrodemolition/ accessed 15.08.2014.
46
and chisel. Serious precautions are required to use this method because water
gun that has such huge pressure that it can cut through concrete can easily cut
skin and bones. Hence serious precautions are required for this process. Hydro
demolition is conducted by two ways. Manual hydro demolition and robotic hydro
demolition. Hydro demolition is shown in the figure on the below.82
It doesn’t damage the reinforcement bars but infact cleans the corrosive
chlorides from the surface.
It is faster than mechanical measures for concrete removal.84
If fire was intense and unluckily have damaged the steel bar/s of reinforcements
or if reinforcement bars were having previously lying shortcomings then they have
to be accessed by experts. If it is concluded that the cross section of the bar has
been seriously reduced and the steel bar can’t fulfil the intended purpose then it
has to be replaced. As the whole length of steel bar is not usually replaced in
repair jobs because it requires serious damage by fire to inflict any damage to
the reinforcement bars. If temperature of fire was high enough that it penetrated
the cover and temperature at high degrees sustained there for long enough then
reinforcement bars may endure damage. This doesn’t happen very often, and
even if it does then such damage is localized which demands partial removal or
replacement of steel/reinforcement bars before concrete repair is applied.
After reinforcement bars are covered with protective epoxy to protect from
corrosion and damaged reinforcement bars are replaced (if any), removed
damaged concrete is replaced with new one. In case reinforcement bars are
repaired, then new concrete should surround reinforcement bar from all around
to provide strong enough bong that can accommodate stress transfer between
concrete and steel. Thumb rule is to provide 1 inch new concrete around the bars.
Moreover to avoid premature corrosion of reinforcement bars, coat the new
concrete surface with same epoxy that has been used to coat reinforcement
bars.87
Shotcrete
In-situ Replacement with formwork
to ensure good bonding between old and new concrete and to avoid cold joint.
Following figure explains the phenomenon of shotcrete.88
In-situ replacement can also be used for the replacement of damaged concrete
but it cannot always be used as in case of top surface repair as in case of slabs.
For vertical members like columns in situ concrete can be used but still in-situ
replacement is not beneficial more than shotcrete as it requires more labour,
formwork and effort. Special concrete mix is required for preventing cold joint that
exists between new and old concrete. Bonding agent has to be applied to the
surface as surface preparation measure same as in shotcrete. Shotcrete may
require a costly mix than conventional concrete but labour and other requirements
like vibration are not required which makes it more financially feasible. Moreover
shotcrete can be used almost for all kind of concrete repairs (vertical, horizontal
or overhead repairs).
Partial removal and replacement technique reinstate the form and shape
of damaged element. It also revitalise its structural strength to reasonable
88 http://www.shotcrete.org/pages/products-services/technical-questions-archive.htm accessed
16.08.2014.
89 http://www.sustainableconcrete.org/?q=node/171 accessed 16.08.2014.
50
mean. Hence structure can continue its normal function and load pattern
of building doesn’t change significantly.
One striking benefit of this technique that others don’t is that it not only
takes care of shortcomings due to fire damage but also covers the inherent
shortcoming to somewhat. If there had been some carbonation of concrete
or corrosion of steel then it will automatically takes care of it as well.
Due to the removal of the concrete the section of the element reduces
and it can be dangerous as element may be barely stable and during
chipping damaged concrete it may lose its stability and fails.
Cold joint is always existing between old and new concrete. That would
automatically be the case on replacing new concrete hence for proper
bonding special surface preparing measures have to be used. Bonding
51
agent is usually required for surface treatment moreover epoxy resins are
required to add into concrete mix.
Use of epoxy resins, propping, and lot of activities involved makes this
measure costly and not very financially feasible when we compare it with
other possible options like FRP.
Concrete jacketing has its unique demands in terms of designing. The newly
added width and depth of the member changes the behaviour or structural
member. It automatically got stiffer and now will attracts more loads. After
concrete jacketing the load pattern of the structure changes hence design has to
sound enough.91
Concrete that is used for jacketing can be in-situ or shotcrete. Concrete jacket
must be atleast 100 mm thick and of higher compressive strength of the old
existing one. If it is not feasible then it should be atleast equal to the compressive
strength of the old concrete. If possible then all four sided jacket should be
provided to retain the symmetry, centre of gravity and neutral axis as before.
Reinforcement that are provided in the concrete jacketing process should be
carefully calculated and must pass all the checks of designing process.93
91 Teran, Ruiz. 1992. Reinforced concrete jacketing of existing structures. Page no 5107.
92 http://www.corecut-jo.com/index.php?module=services&id=6 accessed 16. 08.2014.
93 Teran, Ruiz. 1992. Reinforced concrete jacketing of existing structures. Page no 5107.
53
Addition of jacketing reduces the available space and hence reduces the
net rentable area which is pretty loathsome factor for architects.
The whole process takes too much time and projects where time is of
essence, this technique provides no help.
94 http://theconstructor.org/structural-engg/strengthening-of-r-c-columns/1935/ accessed
18.08.2014.
55
This method is used in structural repairs, where increasing size of element is not
permitted due to any reason. It could be rules and regulations or demand by the
owner to retain the net rentable floor area etc. As steel will be exposed to the
weathering agents hence it is mandatory to apply protective coating against rust.
In case of future fire, steel will be in direct contact with fire flames and as being
excellent conductor of heat it will not be only damaged by itself but can prove to
be a cause of fire spread. Figure below shows the concrete column repaired by
steel jacketing.
Steel is a green material as it doesn’t depletes fossil fuel and waste too
much energy in its manufacturing as it is in case of FRP. Hence it can be
credited as a sustainable repair technique.
It revitalise the structural element yet doesn’t changes its form and
appearance. It also reinstate its structural strength to reasonable mean.
Hence structure can continue its normal function and load pattern of
building doesn’t change significantly.
Cost of this retrofitting technique could be higher than other measures like
FRP especially because of handling costs.
For retrofitting of structure and providing more strength to the structure few other
methods are also practiced. It is not possible to discuss all in this text. So for the
sake of mentioning few common solutions to fire damaged structures are as
under.
If damage due to fire is not extensive and not concentrated on some defined
locations but infact equally damaged the structure. Resultantly strength has been
reduced but still structure seems to be sound enough. Above mentioned
techniques makes it too costly and unfeasible to retrofit. In such scenario overall
demand of the structure can be decreased. This measures may be not always
possible as it is not possible to shift some equipment installed or the purpose of
the facility can’t be altered. Still this is possible in some cases to go with this
57
Cracks are often case of fire damage in R.C.C buildings. Fire can also create
radial cracks around the reinforcement bars. These kinds of cracks cause de-
bonding of steel and concrete. Such scenario will cause loss of load transfer
between two materials. Structural cracks can cause dowel action and prove to be
a mile stone of ultimate failure. To take care of these cracks epoxy injections are
used. The epoxy injections can also alone take care of the problem but if problem
is extensive then these measure can complement other measure like FRP
reinforcing or partial removal and replacement of concrete and reinforcement.
Etc. The efficiency of the measure is dependent on the skill of the workers and
staff. This comprehensively conceals the cracks and nip the evil in the bud.
58
Summary
Rehabilitation and retrofitting starts with cleaning of the property. After fire,
building has to be cleaned as soon as it is cleared to be entered. It will stop
further damage due to the water sprinkled to extinguish fire and due to the
deposition of smoke & soot. It is necessary to remove smoke and soot from
the surface of belongings and building likewise. Otherwise it will damage them
because of acidic fumes it may contain. Moreover, smoke smell will be difficult
to remove. To remove smoke smell thermal foggers and ozone machines can
be used but comes with their respective shortcomings. Air scrubber provides
better solution than former two. Smoke and soot that are deposited on the
surface of building and can’t be removed by ordinary methods can be removed
by soda blasting. It is a green practice to remove smoke and soot deposits
with soda blasting rather than harsh chemicals. Combustible non- structural
members and utilities are often in poor condition after fire. If they can be
repaired economically then it is better to repair them otherwise replace them.
Non-combustible non-structural members are not often damaged much.
Usually only cleaning with soda blasting is required.
FRP reinforcing sheets and plates are commonly used for various kind of
rehabilitation techniques including fire damaged repairs. FRP has many
inherent characteristics that make it very good repair material like excellent
tensile strength, durability, light weight, nonmagnetic behaviour and ease of
handling but also has serious shortfalls specially sustainability and future fire
resistance. It also allows excessive deflections in structural members that is
not very desirable. It is weak in shear resistance and suspected to damage if
not handled properly.
for this purpose as it also prepares the surface and rinse out any rust that may
be present over the reinforcement bars. Then surface is prepared and
concrete is provided again either by shotcrete or in-situ casting. This method
is old and tested method. It doesn’t change the dimensions of the structural
element and also take care of any inherent shortcomings that may present in
the element. It provides good fire protection and a sustainable retrofitting
technique. It requires propping sometimes to support the member until it is
fully repaired.
Concrete and steel jacketing are mainly repair or strengthening techniques for
seismic design or repairs. But can be deployed for fire retrofitting. Concrete
jacketing is done by jacketing a member with extra layer of concrete preferably
all around after removal of cover that has been damaged. Reinforcements are
also provided in concrete jacket. Success of the method depends upon the
monolithic behaviour of jacket and original structure and design competency.
It provides better fire resistance and also a green practice. Steel jacketing, is
the same philosophy but here we jacket with steel instead of concrete. It
doesn’t alter the dimensions of the member but at the same time it is
suspected to fire and rusting hence protective coating is a must.
Along with these retrofitting methodologies some other techniques can also
be practiced like reducing the load over structure by change of usage,
construction of some new structural members, provision of extra prefabricated
member beneath an already existing one and epoxy injections etc. All these
methods are not common ones but can be used alone or in combination with
other measures.
60
4. Feasibility study
Evaluation of the fire damaged building, put us in the position where it is possible
to understand the condition of the building. Decision regarding building has to be
made, that either, it should be reconstructed after demolition or rehabilitated and
retrofitted. To make such decisions comprehensive, elaborated and structured
feasibility study is required.
The decision making process is quite complex. Every case has its own
uniqueness and demands that differs from case to case. Fire damage is not
consistent. Sometimes fire stays long but doesn’t damage much while contrary
to this sometimes fires of medium tenure inflicts serious damage. Design of the
facility has a serious role to play in it. If design is comprehensive and fire has not
been able to stay for long time, then it inflicts small damage which can be
repaired. Unfortunately if structure has endured serious damage then decision
making is not such an easy job. Evaluation of the building and testing must be
practiced over it, to determine its residual strength. If building can be restored to
code acceptance level, after fire, then it is possible to restore it, but many time
code requirements and local laws makes it difficult.96
Many factors are involved in the decision making process. Economy and code
requirements are not the only factors that are considered. Life span of the
proposed solution is also important from sustainability and life cycle analysis
perspective. Repairs are greener than demolition and reconstruction97. In case of
commercial buildings, time for which building will be under construction or repair
also cause loss of business. If decision is controlled by some supreme factor like
building is of historical importance e.g. Reichstag or building facilitates business
or activates that can’t be compromised like national security e.g. Pentagon. Then
economic factor doesn’t count. But if there is no such supreme limitation as it is
in normal cases then independent feasibility study is required to attest the
economic and technical viability of the proposed solution. It can be rehabilitation
accessed 10.08.2014.
61
4.1.1.1. Columns
Columns are the vertical load bearing members and lowest in the super structure
of the building. Columns usually bear heavy damage in case of fire as they would
be fully exposed to the fire. Under fire and sustained load it is extremely important
for columns to carry on their purpose otherwise structure will collapse. Columns
usually outperform their duties and don’t collapse until the reinforcement fails and
damage is usually limited to the damage upto the cover.
98 http://www.barberhoffman.com/portfolio/project-detail.aspx?PortfolioID=113 accessed
30.07.2014.
63
4.1.1.2. Beams
Beams are the horizontal members of the structure that bears shear and flexural
load to provide the clear space underneath. In the event of fire, beam has to
remain structurally sound and perform its functions. Beams are usually
significantly deflected, in case of serious fires under the sustained and fire loads.
Damaged beams can be repaired and it turns out to be first preference after
damage but they can be replaced as well. Replacement of concrete beam is
usually done by steel beam but sometimes concrete beams are also placed just
under the existing beam. Various tests are performed over beams as described
in 4.1.1.1 “Column”
undamaged if cover
is <26 mm
4 BM Concrete is buff 30 to 600 to < 42 <50%
coloured (whitish 20 900 exposed, not
(n,n)
grey), Serious more than
spalling reveals one bar
2.1 to
reinforcement bars, buckled
3.0
Deflections are
minor, wide
structural cracks
appeared.
5 BM Seriously damaged, < 20 > 900 Total >50%
Heavily deflected loss of exposed,
(n,n)
and fractured, More cover more than
or less total one bar
< 2.1
removal of concrete buckled
cover, Main
Reinforcement bars
buckled.
Table 7: Technical feasibility study of Beam Retrofitting
Slab panels provide the solid surface at an elevated ground. It is shallow in depth
while relative in length and width. It is a horizontal structural element which is
usually designed for flexural and shear loads. Sometimes point loads are also
considered. Same as column and beam, various tests are performed over it as
explained in 4.1.2. These floor or slab panels are mostly prefabricated and hollow
with pre-stressing. Due to these characteristics it is not as resilient to fire as
columns or beams usually are. Moreover the temperature in fire is maximum at
the top of the flames. Hence these members are directly in max temperature
zone. These panels can be effectively repaired and retrofitted unless pre stressed
steel has endured serious damage and the slab panel is completely un-functional.
Technical assessment of damage of slab element is as follow.
Enterprises and companies has only 3 goals in corporate world “Money, Money
and Money”. This phrase may be an exaggeration of reality but reflects the
importance of financial factor in any business decision making process. When
real estate business is under the lime light, importance of financial factor only
magnifies. Therefore, decision making regarding fire damaged building, either it
should be demolished and reconstructed or rehabilitated and retrofitted, very
much depends upon the financial factor. Though it is not the only important factor
but one of the most important factors.
update the financial feasibility analysis as more accurate and precise data is
obtained.114
There are certain factors that must be considered before financial analysis is
conducted. They are given below115
4.2.2. Structure
114 Matson. 2000. U.S. Department of Agriculture; Rural Business-Cooperative Service, Service.
Report 58: Vital Steps, A Cooperative Feasibility Study Guide. Page no 1-4.
115 Helfert. 2001. Financial analysis tools and techniques: a guide for managers 1st edition.
116 Zizzo. 2014. Life cycle costing: Financial costing. Page no 6.
69
In this step, all costs that may play their part in the appraisal of proposal must be
included. There will be many different kinds of cost associated to the financial
calculations. It depends upon the approach selected for the cost calculation and
the time span for calculations. In general costs are divided into four basic
categories for financial analysis namely; construction costs, maintenance costs,
operational costs and end of life costs. This is the costing model that is used in
Life cycle costing approach. Now it depends upon the scope of the financial
analysis and the analysis tool that is used for the calculation of costs. Life cycle
approach is not compatible with all analysis tools and independently it can’t
decide for the better proposal. It is better integrated with the NPV analysis
method. LCC can be regarded as NPV of costs as NPV takes cash flow in present
value similarly LCC takes only all costs in present value.117
For fire damaged buildings’ financial analysis, it is not very feasible to calculate
costs by LCC technique because there are certain conditions to be fulfilled for
using this technique for comparison purpose. Most important of them is function
equivalence. LCC costing for repair may or may not have function equivalence of
reconstructed building. So if this condition is unfulfilled then LCC methodology
can’t be used. For financial analysis of fire damage buildings detail investigation
must be conducted to calculate all the cost that are incurring over the reference
life span of the building with relative accuracy. Special focus must be planted over
financing, maintenance and operational costs.
Incomes that are going to be obtained from the proposed investment over the
duration of reference life should be identified and analysed. It would be good
practice to check assumption with market analysis. Assumptions made in income
calculation must be comprehensively described and justified. Special care is
required to deal with the assumed data. As it will decide for the course of
projected profit or loss.
There are different analysis tools present for use. They can help in calculating
financial feasibility of different proposals. There are lot of analysis tools that
differentiate from one another on the basis of their methodology short comings
and working principal. Financial feasibility can be calculated on the basis of
accounting profits/losses (from actual business financial statements) or by
projected cash flows. Projected cash flows is the better option as it accounts time
value of money and can be used for both new businesses which has no financial
statements yet. Moreover it has a standardised method for calculating values
whereas accounting profits can be calculated in several different ways e.g.
inventory listing, depreciation methods etc. Few methods of financial analysis will
be presented in this study.118
118 Björnsdóttir. 2010. Financial feasibility assessments: Building and Using Assessment Models
for Financial Feasibility Analysis of Investment Projects. Page no 1-18.
71
There are different financial ratios that can help in analysing the financial
feasibility of investment. They can’t be used independently for calculating
financial feasibility but can be really supportive in giving perspective analysis
about investments. Financial ratios can be used for the analysis on accounting
value bases. From financial statements, values are used to calculate these ratio.
Projected value can also be used to better understand the impact of decisions.
There are different kinds of financial ratios that are used as given below
Liquidity ratios
Asset management ratios
Profitability ratios
Market trend ratios
Debt management ratios.119
Net present value is the difference of present values of all project costs and
incomes. Costs of the project that are intended to be included happens at different
time. Similarly income or return from the investment also happen at different time.
NPV discounts the future cash flows to present value to include time value of
money which gives rational meanings to the analysis. In the end, sum is obtained
for the inputs and outputs to calculate NPV of investment. Critical factor in
determining NPV is discount rate. It is explained by Park (2002) as “MARR”
minimum attractive rate of return. It is the rate which is achievable by the investor
if he invests his money to an alternative investment i.e. rate of interest from bank
or other alternate investment120. Moreover, planning horizon or reference life of
the project is estimated. This has a telling effect over the calculation results. So
must be estimated with care. At the end of reference life, we get NPV of the
119 Park. 2002. Contemporary Engineering Economics. 3rd edition. Page no 288- 291.
120 Park. 2002. Contemporary Engineering Economics. 3rd edition. Page no 288- 291.
72
investment.121 Decisions are made upon its basis as shown along with the
formula used for the calculation of NPV.
Here i= MARR.
For comparing two investment proposals, the proposal with higher NPV should
be selected. But for the purpose, Zizzo (2014) said that same interest rate or “i”
and reference period/life should be selected for which sometimes small changes
have to be made. Formula for calculating NPV as described by Park (2002) is
given below122.
(Park, 2002)
This method is not really feasible for comparisons of two different proposals that
are not of equal life time (n) as it is a common case when dealing with fire
damaged buildings.
Internal rate of return is the interest rate at which Net present value is equal to
zero. This interest rate set a criteria for the investors to make decision that either
they should accept it or reject it, consistent with net present value analysis. For
121 Zizzo. 2014. Life cycle costing: Financial costing. Page no 24-28.
122 Park. 2002. Contemporary Engineering Economics. 3rd edition. Page no 289.
73
simple financial calculations where we have only 1 change in sign with respect to
cash flow. In those cases i* is same as IRR. In complex cases, story may be
different. IRR is equal to i* (rate of return) when following mathematical
expression gives zero value. The following formula is given by Park (2002).123
(Park. 2002)
Investor are usually more interested in getting profit rather than breaking even.
Their target is established by MARR. So MARR and IRR can be used to make
decision about investment based on following criteria
There are certain draw backs attached to the IRR method. First and foremost it
is not consistent. It may give more than one IRR if there is a complex scenario
i.e. if there is more than one sign change in the cash flow. NPV is generally
considered as better method than IRR but the importance of IRR can’t be ignored
as in some cases it may prove to be better than NPV.124
As the input data collected for the purpose of financial analysis is based upon
projections and many assumptions are involved in it as well. Therefore there is
always a risk of uncertainty, wrong estimation or change in assumed values
though they are taken with great care and responsibility. To deal with this issue
risk analysis is done by following techniques
123 Park. 2002. Contemporary Engineering Economics. 3rd edition. Page no 410.
124 Lee. 2009. Financial Analysis, Planning And Forecasting: Theory and Application, 2nd edition.
74
Sensitivity analysis gives the investor an insight about the risks that are
associated with the change in input values. It is conducted by changing the input
value one at a time to understand its effect on the output. In this way the most
sensitive input variable is identified. The most sensitive input variable is then
estimated with even more accuracy to mitigate the risks and to get better analysis.
It also tells the investor that which parameter can have a significant effect on the
project. Best practice for sensitivity analysis is to plot graph of different sensitivity
analysis for different parameters.125
Scenario analysis is used to define the best and worst case scenarios compared
to the base case. Base case is the analysis made by analysis methods explained
above. Then it includes the change in the values of key variables and the range
over which they can possibly fluctuate. Extreme cases are identified in case of
each variable or parameter. Worst scenario of each parameter is accumulated
and same goes for best scenario of each parameter to determine worst and best
case scenario. One drawback of this system is that it only gives information about
extreme case and doesn’t inform about the case that will lie in between them. 126
Summary
125 Zizzo. 2014. Life cycle costing: Financial costing. Page no 34-52.
126 Zizzo. 2014. Life cycle costing: Financial costing. Page no 34-52.
75
Technical feasibility plays half role to decide that either fire damaged concrete
building should be rehabilitated or demolished and reconstructed. For the
task, first the results obtained from condition assessment are assembled and
analysed to assign the degree of damage, building has endured. To
assemble, analyse and getting meaning full information from the data
obtained evaluation tables in 4.1.1 are developed. This meaning full
information will be then analysed to develop the technical aspect of feasibility
study.
Financial feasibility makes the second half of the feasibility analysis that
makes the basis of decision making. Financial feasibility calculation for
demolition and reconstruction or retrofitting and rehabilitation are similar to the
financial feasibility calculations of new development. Before conducting
financial feasibility analysis, preliminary assessments regarding the limitations
of respective proposal and understanding of its scope will definitely help a lot.
It will set the tone of the financial analysis. Financial feasibility starts with the
calculation of costs. LCC technique can’t be used for comparison as it doesn’t
fulfil the functional equivalence criteria of compared proposals. Various
analysis methods are available to choose for financial analysis like payback
period, NPV, IRR etc. Only the mentioned methods have been discussed
along with their respective pros and cons. After analysis, the risk analysis has
to be conducted to determine the most sensitive parameters in the cash flow.
So that they can be more accurately calculated and right amount of effort is
provided to all variables according to their significance. Best and worst case
scenarios are also identified to understand the positions in which investor can
possibly be. On the collective basis of technical and financial analysis decision
must be made.
76
Results of studies that have been done until now presents following results,
findings and problems.
5.1. Results
Concrete buildings are damaged under the event of fire. The damage is not only
caused by fire. Smoke, soot and water (fire extinguisher) contribute in overall
damage. Degree of damage depends upon many factors like temperature and
duration of fire, design of building etc. Nobody, should enter the building unless
structure is secured (if not) and building got clearance from respective authorities.
Water should be dried out at first which would otherwise cause further damage
and accelerates deterioration. Concrete buildings are naturally much tolerant to
fire, thanks to the fire proofing properties of concrete. In concrete buildings,
mostly fire damage is retained by concrete cover and steel is escaped from
damage. Desk study has to be done before evaluation of building, to understand
salient features of building and fire.
Condition survey is conducted on the building (for both structural and no structural
members) to have basic understanding about degree of damage. It is done by
means of visual inspection, hammer tapping and chiselling. Condition
Assessment is conducted on structural members to precisely access their
condition and to determine actual degree of damage endured. Mostly NDTs are
practiced to find out the residual strength and stability of structure. Non-
destructive test like Schmidt hammer, UPV test and penetration resistance test
gives good idea about the structure’s residual strength, if they are conducted
properly. They can’t be totally relied upon owing to their inherent shortcomings
as none of them directly calculates the strength of concrete or steel. Instead, all
NDTs uses indirect correlations to evaluate the certain criteria which is not
necessarily be strength. To sum it up, NDTs results have 65% to 85% accuracy.
They can serve up the purpose for some case (especially those buildings which
are not much damaged) but can’t be considered as authority. Cases, where better
77
accuracy is required, core sampling & testing and petrography test should be
conducted for evaluation of concrete. For steel, tensile test and SEM microscopy
can provide accurate evaluation. Combination of core sampling & testing,
petrography and tensile test is enough to thoroughly understand the condition of
conventional R.C.C buildings. If pre-stressing is involved then SEM microscopy
may be added. These tests are bit costly in market hence they should be used
as per requirement if necessary.
Literature study was quite helpful in context of building evaluation after fire
damage. It helped understanding the condition assessment and condition survey.
Comprehensive articles, journals, books and internet sources are available over
the context of condition assessment and condition survey. It comprehensively
covers evaluation techniques presented in the thesis.
the strength and physique of structure. So industry practice seems rational and
result oriented.
The biggest concern is over decision making process. Literature study doesn’t
provide with any suitable structure for feasibility study that is specialised for
decision making in case of fire rehabilitation. Financial feasibility studies has been
available in abundance but they are general purpose financial studies. Same
financial feasibility analysis method are used for nearly all investment cases but
as fire damage buildings are not ordinary case. Here we need comparison
between proposed solutions with certain conditions. Limitations of conventional
analysis methods like NPV, IRR, payback period is not always suitable especially
in complex cases because of these limits. Whereas literature for structured
technical feasibility have not been found. Probable reason for that is, there are
lot of factors and variables involved in any such studies as every case is a unique
case. Hence serious efforts are required to establish a structure and technique
for such feasibility study which can help in taking confident decisions. Whether
building should be rehabilitated and retrofitted or demolished and reconstructed?
How to determine overall feasibility involving both technical and financial
feasibilities? Can comparison between two rehab techniques be made? All these
questions are important questions while making decisions and need to be
properly answered.
Literature study provides fair knowledge over the process of dealing with fire
damaged concrete buildings but it has some issues. It lacks some knowledge that
is required for complete understanding of the decision making process.
To develop a feasibility analysis tool that can give guidance in decision making
process (described in section 4.). It should include both financial and technical
feasibility. So that the final recommendation it will give, must have weighted
contribution of all significant factors involved.
80
6. Solution development
Technical and financial feasibility tools would be separately developed and then
merged to give birth to overall feasibility analysis tool. This technique is adopted
to attain accuracy, which would be hammered otherwise, with the involvement of
too many variable at once. The tool that is developed here is a basically a
parametric mathematical model. At first, it account for technical analysis only.
Later, it got contribution from financial analysis and becomes overall feasibility
analysis tool. It is developed at first on its unique philosophy of accounting various
parameter that are most significant for feasibility study according to their
importance in respective case. Afterwards, they have been tested and here starts
the loop of testing and improvement, until it got its current shape.
Damage of structural and non-structural members are identified from the analysis
of data assembled in tables presented in 4.1.1 and 4.1.2. After damage is
identified, it’s time to conduct technical feasibility study. Technical feasibility
analysis is governed to decide that whether it is recommendable to rehab the
building instead of demolishing and reconstructing on technical ground.
Structure’s condition and its chances of getting its old strength back completely
or upto the extent where it can perform its intended function are studied. Upon
these facts and figures, it is decided on technical ground that whether it is
worthwhile to rehab the building or to demolition and reconstruction, is the better
answer to the problem. Factors that are important and considered in the technical
feasibility analysis are described below
As described earlier that every case is a unique case and holds its own demands
and requirements. It has its own structure, degree of damage etc. Similarly
complexity is very much oriented upon the nature of element and the structural
system. For example. Normally, it is easier to replace damaged column with a
81
new one than it is to replace beam. Reason behind this is that, in frame structure,
beams are sandwiched between slab (on upper side) and columns (on lower
side). So if beam is to be replaced then it will have an obvious effect on more
adjoining members. While in case of columns it is only in contact with beam or
slab directly and disturb less adjoining members. So effect on adjoining
member, plays its part and considered as one of the most important factor in
order to decide degree of complexity. Method of repair or replacement is
another important factor. The technique that is used to replace or repair the
element is vital. For example to repair a beam, it might not require the vertical
temporary support from beneath by formwork (propping) but for beam
replacement propping or may be hydraulic jack support or any other kind of strong
support is required that can replace the function of beam for time being. If another
beam is provided beneath the already existing beam then formwork requirements
will provide the complexity. For replacement of concrete beam with steel one may
require special measures to lift it. Hence method of repair or replacement add to
the complexity level. Design requirements also adds up in the complexity level.
As described every case is a unique case, so degree of complexity differs from
case to case. It also differs for repair and replacement in same case as well.
Degree of complexity is assigned in a numeral figure from 1 to 5. One being the
lowest and 5 being the highest degree of complexity. The assignment of degree
is based upon the opinion of technical staff, engineer and analyst. Moreover case
specific analytical approach can be used for assigning the degree of complexity.
For example, for replacement job of roof and non-structural members it can be
assigned as 1, for load bearing walls it can fluctuates between 1 to 2, for columns
2 to 3 and for beams and slabs from 3 to 5127.
127These figures are highly subjective and based upon the opinion of the author. These figures
are for normal cases excluding the effect of any special condition/situation that might be present.
82
considered. For technical feasibility analysis, the lesser figure in expected life of
the building and the expected life of the solution is taken as life expectancy “L”.
The reason behind that is to make sure that proposed solution will serve for its
expected life “L”. For example if the remaining expected life of building is 30 years
and expected life of reconstructed new beam is 50 years then we will consider 30
years in analysis because it will only be able to serve us for next 30 years after
which building will complete its expected life and will be demolished. In which
case, the new beam wouldn’t be able to serve upto its expected life (50 years).
Time is another important factor. T is the number of days required for the
proposed solution (repair or reconstruction) to be executed. Time is money. In
case of loans and investments made by investors it is more pressing issue.
Moreover the building services and the purpose of the building sometimes make
it more critical and important e.g. state department building, parliament house of
state or house of commerce etc. Time unit can be months if the proposal duration
is too long and undermines the other factors involved. This may happen in huge
projects where multi complex buildings have to be rehabilitated. Normally in
cases of elements repair or reconstruction, number of days are considered as
units. Anyways, for each case analyst can select suitable time unit as per his own
approach but same unit should be used for both repair and reconstruction
comparison analysis.
Enough debate had already been done on this factor especially in 4.1.1 and 4.1.2.
Degree of damage is the extent of damage that the element of the building has
endured. It is decided by the proper technique described before. It varies from 1
to 5. Five (5) being the worst case scenario. In case of whole building analysis,
degree of damage will be assigned to the overall building based upon the overall
damage its elements have endured. Such figure of degree of damage may be
allotted to the whole building after a systematic approach by team of experts.
83
I = I 1 + I2 + I 3 + I4 = 1
For comparison and decision making following mathematical model is used. For
both rehab and repair same mathematical model is used. Degree of damage will
remain same for rehab and repair. Other factors like Life expectancy, Complexity
and Time for proposed solution will differ depending upon respective solutions.
As the result, of the solution of this model, a figure will be obtained called
Feasibility Index (F.I). For both rehab and reconstruction, F.I will be obtained and
one with lower F.I will be the preferred option. One more thing to notice is C, D
and T are making positive contribution while L is making negative contribution in
the model given below. Reason for that is, higher value of D, C and T will have
opposite effect than higher value of L. higher value of C, D and T is a negative
thing while more life is a positive thing. As they are having opposite effects,
therefore they are making opposite contribution to the sum and this is also the
reason for selecting the measure with lesser accumulated/sum value. It will be
84
more clarified in 6.2, where this mathematical model will be tested on a case
study
Coal Coating Manufacturing Facility that has been built in 1956. Single floor
building has area of 59,032 sq. ft. Roof structure has been damaged. Details
about roof are128
128 Fay Engineering. 2003. KBP Coil Coaters Fire Repair and Shear Strengthening. Ppt.
(http://www.fayengineering.com/articles/repair-fire-damaged-building-case-study accessed
5.8.14).
129 Fay Engineering. 2003. KBP Coil Coaters Fire Repair and Shear Strengthening. Ppt.
(http://www.fayengineering.com/articles/repair-fire-damaged-building-case-study accessed
5.8.14).
85
Not whole roof structure was damage. Some valleys observed worst damage.
Three Valleys with total area of 66ft. × 85 ft. beard most severe damage. The
feature of damaged area are
For Concrete
Visual Inspection:
Colour is Buff to pink, Cracks along the reinforcement bars, Crazing is apparent
on surface, Concrete spalls are apparent as well.
Shows Depth of damage upto 1.25 ft. or approx. 32 in. with surface temperature
is concluded to be reached upto 1100 F or approx. 593 C. Radical cracks are
around reinforcing bars. Loss of bond between reinforcement and concrete is
around 30% to 50%
weightage to more accurate tests such as petrography and core sampling and
testing plus the healthy condition of steel, degree of damage is estimated to be
3. Only worrying point is the loss of bondage between concrete and steel ranging
from 30 % to 50%. But it is not detrimental as it can be cured with bonding agents.
Also considering the area of roof damaged in case of fire also has its impact in
the final decision of degree of damage.130
Figure 23: Top view of damaged Valley- Ridge concrete roof 131
130 Fay Engineering. 2003. KBP Coil Coaters Fire Repair and Shear Strengthening. Ppt.
(http://www.fayengineering.com/articles/repair-fire-damaged-building-case-study accessed
5.8.14).
131 Fay Engineering. 2003. KBP Coil Coaters Fire Repair and Shear Strengthening. Ppt.
(http://www.fayengineering.com/articles/repair-fire-damaged-building-case-study accessed
5.8.14).
87
Life expectancy for new slab would be at-least 50 years. Whereas for repaired
slab with Glass Fibre Epoxy Composite Reinforcing, epoxy injections for epoxy
inject cracks and Shot Crete would be around 20 years.
Time required for partial demolition and reconstruction depends upon no of daily
site hours, efficiency of labour and management. Considering normal
circumstances, it can be estimated to be around 100 to 150 days. In actual repair
project, it took almost 4 months but considering this time to be bit too much and
with proper management it could be done easily done within half of the period.
Hence
Importance factor will be considered as 0.25 for all four factors to obsolete its
effect, because data regarding the importance of factors is missing. Hence
considering all four factors as equally important. But in cases, the importance
factor can be divided according to the wishes of the decision makers depending
upon the circumstances and goals. Now calculating F.I
Now, let’s consider a phase where durability of the solution is the most important
factor and complexity, Time required for proposal to execute and degree of
damage are not that important and have equal weightage in sight of owners. Then
Debate over financial feasibility study has been much covered in literature theory.
But as a matter of fact none of the conventional analysis methods like payback
period, NPV and IRR actually sits well with the mathematical model presented
before in 6.1. There are obvious limitations of these analysis tools/methods that
makes it unfeasible for the financial feasibility analysis. Moreover, these
shortcomings will reflect heavily in the mathematical model results as well if they
will reside in financial analysis. There is a need for a financial analysis tool that
can accurately compare complex and inconsistent proposals. Reason for that is
89
After consulting the limitations of many financial analysis methods for investment
feasibility, it has been identified that Annual equivalent worth method can
somehow do the job if properly modified for including financial factor in parametric
mathematical model. It doesn’t have the limitation of same time period as required
by NPV. It is more easily understandable as it excludes the time factor from the
group of time, money and risk. This simplicity and accuracy is exactly what is
required to be consistent with the mathematical model. AEW method is also
consistent with NPV method. After all these advantages and suitability for
financial evaluation of proposals concerning fire damaged buildings, still
modifications are required. So the financial analysis tool used here has the same
philosophy as AEW but has its own structure for better compatibility with
parametric mathematical model and inclusion of risk factor in it. The financial
analysis tool is described in detail below.
There are many factors which have their say in technical feasibility. Similarly in
financial feasibility there are many factors which contributes their share and must
be included. Principal five factors on expense side that have their say in financial
feasibility are
All these expenses are accumulated over the years and not always linear as well.
But for ease, they are considered to be linear (constant average is used). An
additional principal factor for rehab is fixed cost which may be present in some
cases. It will be explained later. As finances will be provided as an investment
therefore return of investment is also expected. Income factor is then included in
90
the financial feasibility analysis to calculate the difference between income and
investment that will eventually establish the profit or loss. Each factor included
many perspectives of financial considerations and collectively decides for the
financial feasibility of the proposal. Both rehab and reconstruction proposal are
financially analysed on annual basis and the better option with greater financial
benefit is identified.
6.2.1. Depreciation
There are different lives of the building depending upon the definition. Life of the
building that is used in here is the useful life of the building. It is the life for which
building remain economical and physically sound to carry out its intended
function. The depreciation of assert is zero percent in the beginning means
building investment hold its full capacity without losing a penny due to
depreciation. In the end of useful life the depreciation is 100% which means
building investment is totally diminished. Useful life is also known as write-off life.
It is not the actual life of building but more like an analytical tool. It is an assumed
figure in the financial calculation. Realistic approach must be used to determine
this life. Following consideration must be considered while allotting useful life to
the building as well.
Maintenance and operation are the running costs of the facility. Every now and
then building has to undergo routine maintenance and minor repair to keep it
functionally astute and to safe guard its expected life. Maintenance costs are
important factors and can’t be ignored. Although maintenance and operation
costs are not uniform over the life span of the building. In some years it is less
and in others higher. But usually they are taken as uniform average over the life
span of building and vary from 1% to 3 % of total construction cost132&133. Some
unusual cases of big repairs are not part of this percentage figure.
6.2.3. Interest
Interests are applicable on every investment. If money is loaned from the bank
then interest has to be paid. If own investment is used still cost of interests are
incurred because investor is missing the money that he may earn by investing
the money in the bank and can have immediate return on investment without
132 Joel Levitt. Evaluating Real Costs for Building Maintenance Management. Page no 1-2.
133 http://realestate.msn.com/article.aspx?cp-documentid=25490855 accessed 20.08.2014.
92
moving a muscle. Interest cost are there and it is quite tricky to calculate interest
cost incurred in the total expenses. It vary from one scenario to another scenario.
A scenario is, where building is rehabilitated and the other is where building is
reconstructed after demolition. Plus what is going to happen with the building
afterwards. Will it be sold or used or rented out. Moreover what are the conditions
of mortgage if loan is issued form the bank. Should the investor pay fix amount
over a decided period of time or compounded interest will be returned back.
Therefore interest cost have to be independently calculated but should be
included in investment calculation to reflect the true picture of the investment.
Interest is applied over average capital cost134 or interest rate can be halved and
then applied over the full capital cost. Interest is applied for the duration of
useful/write-off life of the building.
6.2.4. Tax
Tax are applied in some cases. Specially the cases where demolition and
reconstruction is involved. Tax rules differs from area to area and need to be
accessed by fiscal experts to determine that how much taxes will apply on the
proposal (if any). Cases where taxes are not involved and doesn’t accumulate in
the expenses, there they are taken as zero.
6.2.5. Insurance
Buildings are insured against damages for example fire damage insurance or
flood insurance. In those cases where owner doesn’t go for any kind of insurance,
still these insurance cost have to be included in the annual costs as risks of future
hazards can’t be ruled out and this cost will act as risk management. Although, in
certain cases and in certain areas it is mandatory to have insurance against fire
and such hazards. So simply this factor can’t be ignored and should be counted
in financial analysis. Usually insurance costs vary depending upon the design
and material of construction and other such contributing factors. Usually, in
134Capital cost loaned from the bank is paid off gradually hence the interest-able amount is full in
the beginning and zero at the end.
93
Costs of all above described factors are the principal costs. Except these costs
sometimes there are some special costs. Although, it would be a rare incident but
if there is some special cost are involved then they have to be added on expense
side. If there are no such costs then it would be regarded as zero.
All the above mentioned costs collectively decides for the annual costs of the
proposal which comes out in shape of percentage of total cost incurred for the
specific proposal. For example if there is a building that has been damaged by
fire and total cost (capital cost) of demolition and reconstruction is 10000 Euros.
The useful/write-off life of building after reconstruction is considered as 25 years.
The rate of depreciation would be 100/25 = 4%. Interest rate applied over the
average capital cost or half interest rate applied over full capital cost gives same
results. Therefore to make it compatible with other cost factors that are applied
over capital cost, we will take half interest rate 5/2 = 2.5%. Considering there are
1% maintenance and repair charges, 0 % taxes and 1 % insurance cost.
Therefore annual cost would be as given on the next page.
135
http://thelawdictionary.org/article/what-is-the-average-annual-cost-of-homeowners-insurance-
and-property-taxes-for-florida-residents/ accessed 20.08.2014.
94
Depreciation Rate 4%
Tax Rate 0%
Insurance 1%
Total expenses are determined and have to be compared with the total income
of the proposal that is under observation. Annual Income represents the total
income generated from the facility after investment on yearly basis. In cases,
where building is rented out, calculating annual income is pretty much straight
forward business. In these cases simple total monthly rental income after taxes
is multiplied with 12 to get the final annual rental income but that’s not always that
simple and straight forward. In case, where owner has decided to sale out the
building after it is being rehabilitated and retrofitted from fire damage gives a twist
to the situation. In such cases, total annual income is calculated by dividing the
total selling price after taxes and commission by the useful or write-off life of the
facility (same as used for calculating depreciation). The total annual income
mechanism would be elaborated later.
After total annual cost in term of percentage of capital cost is determined and total
annual income is determined. Difference between them can be easily calculated
to determine annual profit or loss. But that’s not it. Debate over more sensible
investment or decision making should include risk factor as well. General rule of
thumb is more risk means more profit. A sensible investor doesn’t accept greater
risk if he can’t see greater profit. Now how much one can gamble? And the
95
Now, consider the second option of rehabilitation and reconstruction. The total
cost over rehabilitation and reconstruction is calculated to be 400000 €. Almost
one third of what has been proposed to spent on demolition and reconstruction.
But, the useful life or write off life for retrofitting is determined to be max 10 years.
So depreciation rate would be 100/10 = 10. Moreover, insurance rate will be more
for rehabilitated and retrofitted building than the insurance rate of new
construction with better fire design. Conclusively. Annual costs would be as follow
Tax Rate 0%
Insurance 2%
Hence in this case profit percentage indicates that retrofitting is a better option.
But it is not as simple as it seems. In real world we have risks that have their
telling factor in decision making. So risk factor should be considered in financial
feasibility analysis. Investments in which pay back periods are longer, risk is
usually higher than the investments where pay back periods are shorter. Many
risks are covered upto an extent by insurance but still there are many risks that
are not even covered by insurance. In above case, if retrofitting measure that was
possible is not very reliable and there is high risk attached to its seismic
performance then situation may differ. To normalise the profit percentage with
inclusion of risk degree of risk can be introduced in financial feasibility analysis.
Risk factor (R.F) may range from 1 to 5 with 5 being the case with minimum risk
and 1 being the maximum risk.
Risk factor (R.F) is multiplied with percentage profit (P.P) to obtain financial
feasibility Score (F.F.S). The proposed solution with more value of F.F.S will be
financially more feasible.
Now again consider the case showed in example. The retrofitting option that was
the only way to retrofit and rehabilitate the building, carry risks of again serious
damage to structure in case of any seismic activity. Unluckily the building is
located in high seismic zone. Therefore risk factor is fixed as 1. While in case of
demolition and reconstruction new design takes care of seismic issue and assure
good performance over any such event thus the risk factor is decided to be 4.
Now calculating financial feasibility score for both cases
Hence, final results shows that demolition and reconstruction seems to be more
viable option in F.F.S. but this is highly subjective. Some investors like risk and
are glad to take them while others don’t. So to include Risk factor in financial
feasibility factor in analysis is totally upto the choice of the decision makers or
analysts.
After technical and financial feasibility analysis, we are at the point where we can
determine the overall feasibility of each proposal presented on the desk. With the
addition of financial feasibility in the parametric mathematical model of technical
feasibility, we can determine total or overall or simple feasibility analysis.
Financial feasibility score (F.F.S) or Profit percentage (P.P) can be used in
mathematical model to include financial factor in analysis. The final shape of
mathematical model would be as follow
Or
Whereas;
C = Degree of Complexity
D = Degree of damage
I = Importance factor
I = I1 + I2 + I3 + I4 I5= 1
98
Summary
The case used here for elaborating the validity of mathematical model and its
understanding, is located in Islamabad, capital city of Pakistan. The building is a
commercial shopping mall with some office space as well. Building originally got
damaged by fire and then rehabilitated. We will test our mathematical model over
it. As this building has been retrofitted and rehabilitated instead of demolition and
reconstruction therefore we already know the right choice. If our model favours
the same solution and consider it a better option, then it can be interpreted that
model works fine and can be used for feasibility study or comparison studies. The
data about the case is as follow.
A fire broke out on Sunday, 16 January, 2011 at about 2030 hrs on the Eastern
side of 4th floor. The fire spread up to 5th floor when it was extinguished after
approximately 9 hrs at 0545 hours on 17 Jan 2011 as per the statements of the
136Courtesy of Syed Ameer ul Hassan. Sub Divisional Officer in Communication and Works
department. Govt. of Punjab. Pakistan.
100
eye witnesses interviewed and fire department report. As a result top two floor of
building has undergone heavy damage. Approximately most of the building
interior in top two floors was damaged and un-useable. HVAC had undergone
critical damage as well. Structure somehow has retained its integrity as luckily
building lies in high seismic zone so design was having extra capacity. Moreover
columns were jacketed with concrete to give it some extra strength and seismic
capacity as well. This concrete jacket worked as extra cove and protected the
structural member too.
The structure has been evaluated at first with different testing techniques and
found out to have its structural strength more or less intact while most of the
building equipment and HVAC got damaged.
The Beverly Centre did not undergo major structural damage due to the
fire, erupted on top two floors.
137 Courtesy of Syed Ameer ul Hassan. Sub Divisional Officer in Communication and Works
department. Govt. of Punjab. Pakistan.
138 Courtesy of Syed Ameer ul Hassan. Sub Divisional Officer in Communication and Works
Fire affects mainly consist of calcinations of concrete blocks used for floor
system construction between the ribs and the concrete cover for the ribs,
solid slabs, columns and shear walls.
The bottom steel reinforcement in the ribs does not have adequate bond
with concrete at a number of locations due to improper detailing and poor
concrete quality.
A few concrete blocks between the ribs fell down during the fire action.
However blocks neither fell nor cracked during the load test which
indicates adequate integrity of these blocks with the floor structure.139
To demolish top two floors and then to rebuild it takes time. According to current
practices the time estimates for reconstruction is about 5 months or 150 days.
Lack of the possibility to use heavy machinery in the highly commercial area
makes demolition and reconstruction slower. Whereas, retrofitting the structure
and rehabilitating of building has been scheduled for 70 days 140. One factor for
slow repair was also the working hours of the site. Hence
To demolition the whole upper two floors of the building and then provide with a
new one doesn’t impose any certain complexity. It would be pretty much straight
forward and standard process. Whereas retrofitting a fire damaged structure that
has been retrofitted for seismic activates is not as simple as it seems. But yet
there has not been any striking or challenging situation except in designing for
following measure that have been taken to rehab the top two floors of the building.
These remedial measures are given below.
139 Courtesy of Syed Ameer ul Hassan. Sub Divisional Officer in Communication and Works
department. Govt. of Punjab. Pakistan.
140 Courtesy of Syed Ameer ul Hassan. Sub Divisional Officer in Communication and Works
Remove the concrete blocks, provided in between the ribs of the floor
system
Loose concrete around the rib bottom reinforcement should be removed
The ribs should be properly concreted with shotcrete, using dry or wet
procedure
The seismic retrofitting, as already designed, should be redone making
sure that appropriate quality assurance procedures are followed
The upper two stories are considered softer as compared with the other
floors. Solid partition walls may be provided between the columns to
enhance the lateral stiffness of the structure
The foundation structure is relatively flexible and needs to be stiffened for
the seismic performance requirements.
Expected life of new floors that has been built after demolition must have
considerable more life than reconstructed or patched one, especially, in the area
which is active in terms of seismic activities. Moreover it is a commercial building
so expected life for both proposals are as under.
141 Because actual measure to bring building back to its functional state was Rehabilitation and
retrofitting.
103
Tax Rate 2%
Insurance 2%
Total annual income = 6 €/year/sq. ft. × 0.55 × 121968 sq. ft. = 402494 €
Here 6 € is the yearly rental rate for one square foot. 121968 is the total floor area
of top two floors. 0.55 is the percentage of total rentable space on 3 rd and 4th
floor144. It is calculated as explained on next page
Average monthly rent of the space on 4th and 5th floor fluctuates between 50 to
82 PKR per square feet per month depending on market and location factors 145.
So taking the mean value of 66 PKR per square feet per month.
lobbies etc.
145 Current market Rates 22.08.2014.
104
Annual per square feet rate of rent= 66 × 12 PKR =792.6 PKR =6.001146 € or 6 €
Difference between total annual cost and income = 402494 145142 =257352 €
(R.F)R&R = 2
(F.F.S)R&R = 2 × 177.3
(F.F.S)R&R = 354.6
Depreciation Rate 4%
Tax Rate 2%
Insurance 1%
146 Conversion rate is Forex exchange rate 08.09.2014 (17:32 GMT1). 1 Euro = 132.1 PKR
147 It is not actual profit percentage (see 2nd paragraph of Summary (financial feasibility)).
105
Total cost of Demolition and Reconstruction = 121968 sq. ft. × 4000 sq. ft.
= 487872000 PKR148
Here 121968 is the total floor space of 2 floors and 4000 is the construction cost
of 1 sq. ft.
Total annual income = 7.5 €/year/sq. ft. × 0.6 × 121968 sq. ft. = 548856 €
Here 7.5 € is the yearly rental rate for one square foot. 121968 is the total floor
area of top two floors. 0.6 is the percentage of total rentable space on 3 rd and 4th
floor150. Efficiency of design can improve from 0.55 to 0.6 in new design with use
of slender structural members and eliminating the need of jacketing.
As new design can improve the risks attached to the building as explained earlier
hence maximum protection can be insured. But still building lies in active seismic
zone therefore
(R.F)D&R = 4
148 Market price ranges from 2500 to 5000 PKR per sq. ft. in the area for commercial construction.
149 Conversion rate is Forex exchange rate 08.09.2014 (17:32 GMT1). 1 Euro = 132.1 PKR.
150 Actual space that can be rented.Total space on 2 floor excluding
construction,stair,cases,lobbies etc.
151 It is not actual profit percentage.
106
(F.F.S)D&R = 4 × 23.84
(F.F.S)D&R = 95.38
Now,
Now putting all these values in mathematical model will give F.I values.
(F.I)D&R = 18.9
8.1. Conclusion
Risk of fire is always there for all kind of buildings. Concrete buildings are no
exception to it. Though concrete buildings are more resilient to fire than others
but a serious fire can inflict damage which depends upon salient features of fire
and building. After fire is extinguished and structure is secured, condition survey
and condition assessment is done over it. Condition survey is done by a team of
experts. Visual inspection, hammering and chiselling techniques are used for
condition survey. It gives basic idea about the building condition. Afterwards
condition assessment is done, if it is felt to be required. In condition assessment,
different tests are conducted and their values are recorded, to access the true
condition of building. Different non-destructive testing and destructive testing
techniques are used like Schmidt hammer test, UPV test, penetration resistance
test, core sampling and testing, petrography, deflection test, tensile test and SEM
microscopy. There are lot of other testing techniques available to serve the cause
but these techniques are selected after careful selection on the bases of purpose,
economy, availability, accuracy, efficiency and damage to the building and
environment. Use of NDTs for evaluation of concrete strength is beneficial but
comes with accuracy of 65% to 85% (if properly conducted). More accurate and
detailed techniques like core sampling, tensile test and petrography are bit costly.
So only to be used when necessary.
152C: degree of complexity, L: life expectancy, T: time required, F.F.S: financial feasibility score,
P.P: profit percentage
110
of damaged concrete and steel, concrete or steel jacketing and epoxy injections.
FRP reinforcing technique is a good measure with many excellent advantages
like performance, light weight etc. but falls short on the criteria of future fire
proofing and sustainability. Partial removal and replacement is a sound technique
for retrofitting and most popular one. It is a sustainable method with good fire
proofing qualities but it might prove to be bit more costly than FRP. Partial
removal can put extra stress on adjoining members hence needs propping.
Concrete jacketing is used basically for earthquake retrofitting but can be used
for fire damaged concrete buildings in certain cases. It is a fire proof and
sustainable technique but may alter the structural behaviour of structure and
dimension of members. Steel jacketing is more suitable than concrete jacketing
for the purpose and it also doesn’t change the dimensions of members
significantly. It is sustainable but needs protection from fire and rusting with a
protective coating. Epoxy injections are used to fill cracks and to make up for the
loss of bonding between steel and concrete.
8.2. Recommendations
8.3. Scope
The study provides with a system to take care of fire damaged concrete buildings.
It encompasses evaluation, decision making (feasibility study) and rehabilitation
of fire damaged concrete buildings. Findings of the thesis can be helpful for
insurance companies, professionals of construction industry, banks/investors and
especially fire rehabilitation companies. The study can contribute to the research
that may be done in future on the topic.
8.4. Critique
The study covers the whole process of dealing with fire damaged concrete
building and able to equip its readers with good understanding. It develops a new
tool for feasibility analysis that includes both technical and financial aspects.
Hence, it will help its users in decision making, especially in those border line
case which are complex. Study introduces a total new analysis tool for feasibility
assessment of proposed solution for fire damaged concrete buildings but it is
without any proven record as it is the case of all new tools. Hence can’t be readily
used as independent decision making tool. Further improvement in structure and
philosophy will improve its capacity and efficiency.
involved then SEM microscopy may be added. The prices of these tests are
higher in market than other conventional tests. Therefore should be conducted in
case of necessity.
Chapter no 3, describes the measures that are required for retrofitting and
rehabilitation of fire damaged buildings including both structural and non-
structural parts. This chapter answers research question number 6 and 7, which
are given below.
Partial removal can put extra stress on adjoining members hence needs
propping. Concrete jacketing is used basically for earthquake retrofitting but can
be used for fire damaged concrete buildings in certain cases. It is fire proof and
sustainable technique but may alter the structural behaviour of structure. It
changes the dimension of members. Steel jacketing is more suitable than
concrete jacketing for the fire retrofitting and it also doesn’t change the
dimensions of members significantly. It is sustainable but needs protection from
fire and rusting with a protective coating. Epoxy injections are used to fill cracks
and to make up for the loss of bonding between steel and concrete.
Chapter 5 describes the results and findings of the literature study done in chapter
2, 3 and 4. Literature study have been evaluated in this chapter. Problems that
were associated with literature study and the area of knowledge that has been
lacking in literature have been identified. Once problem is identified, its solution
has been proposed. There are no research question that have been answered in
this chapter.
Chapter 4, 6 and 7 deals with feasibility study of different solutions that can be
realised for the damaged concrete building to bring it back to its functional
capacity. In feasibility study, both financial and technical aspects have been
considered. This part of thesis answers research questions number 3, 4 and 5 as
given below.
What can be done with buildings that are damaged because of fire
(Demolitions, Re-use etc.)?
Is it possible and feasible to retrofit the structural components and
rehabilitate the building, concerning the damage they have endured
(Technical feasibility)?
Is it financially feasible to retrofit and rehab the fire-damaged building?
Chapter 6 explains that feasibility analysis tool that is developed as the part of
solution development addresses the issue concerning feasibility study. As it
brings lot of ease and inherent characteristic to cover almost all factors that must
be considered in decision making. But it can’t be granted with final authority as it
has been very much in development phase. Its Alpha version is ready to be tested
as Beta version. Repeated and rigorous testing with improvements is required to
make it better and more efficient in a cyclic manner. Yet, this model is good
enough to give a clear enough idea about the feasibility of proposals presented
on the desk. As it has a philosophy to quantify parameters that usually can’t be
quantified and then it uses those figures to draw a comparison. The philosophy
integrated in the feasibility analysis tool for comparison between rehab or
reconstruction cover almost all corners. It is because it dictates a system that
starts with proper condition survey and condition assessment (deciding “D”), then
it progresses towards technical and financial assessment of proposed solutions
(deciding “C, T, L” & “F.F.S, P.P”) for the case on hand. Then it includes the
116
impact of factors that has its say in the decision, by the help of importance factors
and allots them their respective share in decision making which is often quite
vague and unclear.
Financial part of feasibility analysis tool has the same conceptual methodology
as AEW (annual equivalent worth). AEW method doesn’t have the limitation of
same time period as required by NPV. It is more easily understandable as it
excludes the time factor from the group of time, money and risk. This simplicity
and accuracy is exactly what is required to be consistent with the mathematical
model. Although, AEW method is suitable for financial evaluation of proposals
concerning fire damaged buildings, but can’t be used as it is. Modifications has
been required to tailor fit it for financial analysis (of fire damaged building’s)
needs. Therefore, financial part of feasibility analysis tool has been developed in
such a way that it works on the principals of AEW but it has its own structure for
the sake of better consistency with the feasibility analysis tool. It also included
the risk factor to provide a combined assessment of investment including both
profit and risks involved. The feasibility analysis tool (parametric mathematical
model) is given below
Chapter 7, introduces a real life case study to test and to understand, the working
method of feasibility analysis tool (parametric mathematical model). The case
used here is commercial building known as “Beverly centre Islamabad” located
in Islamabad, capital city of Pakistan. The building is a commercial shopping mall
with some office space as well. It got damaged by fire and then rehabilitated.
Mathematical model have been tested over it. As this building has been retrofitted
117
9. List of Literature
AGI:
http://www.agi.my/index.php/our-solutions/disaster-restoration/a-
restoration-services-include/stubborn-unpleasant-odor/thermal-and-mist-
treatment-to-remove-all-types-of-malodor/ (accessed 11.08.2014.)
Barber hoffman:
http://www.barberhoffman.com/portfolio/project-
detail.aspx?PortfolioID=113 (accessed 30.07.2014.)
Björnsdóttir:
Building green:
http://www2.buildinggreen.com/article/retrofits-usually-greener-new-
construction-study-says (accessed 10.08.2014.)
Burgozne, Balafas:
http://caltransd7info.blogspot.de/2011_12_01_archive.html (accessed
31.07.2014)
CCTIA:
http://www.cctia.org/FAQ_Files/10.001_Concrete_Core_Tests.html
(accessed 21.07.2014.)
Ccw Online:
Chicora:
Clean Fax:
http://www.cleanfax.com/articles/105969-effective-thermal-fogging
(accessed 11.08.2014.)
119
Cleaners Coach:
http://compositesmanufacturingmagazine.com/2010/08/pursuit-newfrp-
protection-heats/ (accessed 15.08.2014.)
Concrete UK:
http://www.concrete.org.uk/fingertips_nuggets.asp?cmd=display&id=893
(accessed 11.07.14.)
Corecut-jo:
http://www.corecut-jo.com/index.php?module=services&id=6 (accessed
16. 08.2014.)
CPWD, India:
Concrete Society:
EMS Sales:
http://www.emssales.net/store/cart.php?m=product_detail&slug=predator
-600-portable-air-scrubber. (accessed 11.08.2014.)
Engineering Civil:
http://www.engineeringcivil.com/visual-inspection-of-concrete-
structure.html (accessed 10.07.2014.)
Engingeering Arhives:
http://www.engineeringarchives.com/les_mom_tensiletest.html (accessed
26.07.2014)
ESCA Blast:
Fay Engineering:
Frbiz789:
http://frbiz789.blog.com/2009/12/01/hydrodemolition/(accessed
15.08.2014.)
Gbg. UK:
Haseeb Uz Zaman, Tahir Saleem, Azhar Shehzad, Mohsin Ashfaq & Muhammad
Bilal:
Helfert:
Financial analysis tools and techniques: a guide for managers 1st edition.
2001.
IstructE:
Jeremy P Ingham:
Joel Levitt:
JPCL:
Laura J. Powers:
Lee:
Matson:
Metrocorp:
http://www.metrocorp.com.au/services-item.php?id=4(accessed
15.08.2014.)
Michael Hayes:
Park:
Ponmalar:
Ramsetmbtmedan:
http://ramsetmbtmedan.blogspot.de/2012/09/jacketing-struktur.html
(accessed 18.08.2014.)
http://realestate.msn.com/article.aspx?cp-documentid=25490855
(accessed 20.08.2014)
122
Shotcrete:
http://www.shotcrete.org/pages/products-services/technical-questions-
archive.htm (accessed 16.08.2014.)
Structure Mag:
Sustainable Concrete:
Teran, Ruiz:
The Constructor:
http://theconstructor.org/structural-engg/strengthening-of-r-c-
columns/1935/ (accessed 18.08.2014.)
http://thelawdictionary.org/article/what-is-the-average-annual-cost-of-
homeowners-insurance-and-property-taxes-for-florida-residents/
(accessed 20.08.2014.)
Wise Geek:
http://www.wisegeek.com/what-is-an-air-scrubber.htm (accessed
11.08.2014.)
123
Youtube:
Zizzo:
Statutory Declaration
I herewith formally declare that I have written the submitted master thesis
independently. I did not use any outside support except for the quoted literature
and other sources mentioned in the paper.
I clearly marked and separately listed all of the literature and all of the other
sources which I employed when producing this academic work, either literally or
in content.
I am aware that the violation of this regulation will lead to failure of the thesis.
541108_________________ Berlin,15.09.2014_________