Contract Number: C435 Location: Farringdon
Main Activity: GFRC Completion Pack Review Date of Surveillance: 28th Feb 2020
EXECUTIVE SUMMARY
At the request of Chief Engineers Group (CEG) Architectural Lead, a desktop Surveillance was undertaken at
C435 Farringdon to check on the compliance of Glass Fibre Reinforced Concrete (GFRC) and Stainless Steel
(S/S) support framework ‘Completion Packages’, mainly Installation. The GFRC Cladding and S/S support
framework has been installed on the Platforms and in the Tunnels.
The Contractors Architectural designer is Atkins. SORBA is completing the F2 detailed design and drawing
development. The steel is fabricated at JVB (Holland) and the GFRC panels are manufactured at Concrete
Valley (Holland); both are part of SORBA, the onsite installation is also being carried out by SORBA.
The surveillance focused mainly the provided scope mentioned in this report. All comments regarding
omissions and discrepancies are noted in detail within this report.
Prepared By: Asif Babar Approved by: Peter Andrews Date: 06th March 20
Distribution:
Neil Young, Colin Brown, Chris Binns, Chris Sexton, Lee John Allen, Chris Titterton, Stuart
Westgate, Piotr Swieboda, Julian Robinson, Soji Abass, Mike Twiddy, Chris Goatman.
REPORT
The scope of this desk top surveillance is to check as follows:
3. JH40.2200
4. JH40.2300
a. Test Reports
i. Impact
ii. Fire performance
iii. Fixings
iv. Materials testing (including witnessing by CRL Field Engineering in accordance
with the ITP)
v. Blast
8. O&M manual
Controlling Documentation
Glass Fibre Reinforced Concrete Panels at Platform Levels at Level -6 and in Escalator Shafts ES1
(Escalators 4, 5, 6) and ES2 (Escalators 10,11): C435-BFK-A-CER-M123-50017 Rev 1.0
ETH Architectural Works - Glass Fibre Reinforced Concrete Panels at Level 0, -3 and Escalators 7, 8,
9: C435-BFK-A-CER-M123-50072 Rev 1.0
Page 2 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
C1: Soft Body Impact Testing of GRC Panels C435-BFK-Y-CER-M123-50002 Rev 1.0 Code1.
Unable to find this technical report for Soft Body Impact Testing in the package listing C435-BFK-A-CER-
M123-50017 and C435-BFK-A-CER-M123-50072. Please note impact testing is a review point for CRL as
per the approved ITP C435-BFK-C-ITP-M-123-50263 Rev 2.0.
Testing and Fixing deliverable document C435-BFK-Y-RGN-M123-51002 Rev 1.0 Test report: pull out test
on cast-in brackets of GFRC panels. This document appears as obsolete on eB. The testing of fixing is a
witness point for CRL. As per the approved ITP.
C2: The check sheets are missing Smoke screen and protection of works with Corex checks as per ITP
deliverables.
C3: O&M manual: Wall Cladding System at Farringdon Station C435-BFK-K2-OMT03-M123-50004 Rev
2.0 is obsolete on eB.
Page 3 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
Check ITP for Fabrication is at The status of the following ITPs was checked on
1 Code1 eB to see if they are Code1:
2 Check ITP for Installation is at C435- ITP for Installation of GFRC Panels C435-
Code 1 BFK-A-ITP-M123-50002 Rev 3.0 Code1
(Ref: Glass Fibre Reinforced Concrete Panels at
Platform Levels at Level -6 and in Escalator
Shafts ES1 (Escalators 4, 5, 6) and ES2
(Escalators 10,11): C435-BFK-A-CER-M123-
50017 Rev 1.0)
3 JH40.2200 Ref: Glass Fibre Reinforced Concrete Panels
at Platform Levels at Level -6 and in Escalator
a. Samples acceptance by CRL Shafts ES1 (Escalators 4, 5, 6) and ES2
(Escalators 10,11): C435-BFK-A-CER-M123-
b. Prototype inspection and 50017 Rev 1.0
acceptance record with
acceptance by the CRL Materials Compliance Record - GFRC - Typical
Section C435-BFK-A-LRC-M123-50176 Rev 1.0
c. Bench Mark installation record Code1 by CRL FE
– signed Code 1 by the CRL
Materials Compliance Record - GFRC - Typical
Junction C435-BFK-C4-LRC-M123-50506 Rev
2.0 Code1 by CRL FE
Page 4 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
JH40.2300
Soft Body Impact Testing of GRC Panels C435- C1
a. Check Test records for BFK-Y-CER-M123-50002 Rev 1.0 Code1.
i. Impact Unable to find this technical report for Soft Body
ii. Fire performance Impact Testing in the package listing C435-BFK-
iii. Fixings A-CER-M123-50017 and C435-BFK-A-CER-
iv. Materials testing (including M123-50072. Please note impact testing is a
witnessing by CRL Field review point for CRL as per the approved ITP
Engineering in accordance with C435-BFK-C-ITP-M-123-50263 Rev 2.0.
4 the ITP)
Fire Test Report (Sorba) C435-BFK-Y-RGN-
M123-51001 Rev 2.0 Code1 C1
Fire test is a witness point for CRL as per the
approved ITP C435-BFK-C-ITP-M-123-50263
Rev 2.0.
5
Material Compliance Records a. C435-Materials Compliance Record - GFRC
Page 5 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
Page 6 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
Page 7 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
Page 8 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
Page 9 of 10
© Crossrail Limited CRL RESTRICTED
Template Number: CRL1-XRL-O4-ZTM-CR001-50011 Rev 3.0
Surveillance Report C435-XRL-O4-RGN-CR001-50054
Notes
Quality surveillance in the context of this report is defined as a check of compliance of selected aspects of the work in
accordance with package listings, ITP and specifications. It does not certify the work; this remains the responsibility of the
organisation as defined by contract.
Quality surveillance has taken place of a sample of activities completed or in progress. As this surveillance was carried out on
a sample basis, non-conformances may exist that were undetected as part of this process. The documents above have not
been reviewed in details surveillance has been carried out as per the provided scope only.
Page 10 of 10
© Crossrail Limited CRL RESTRICTED