Document no:
1CP01-MDS_KEL-CV-ITP-SS08_SL23_GF-000002
Work Package Ref: 1205S07
CP-DEL
N. ACTIVITY REQUIREMENT REFERENCE ACCEPTANCE CRITERIA RECORD FORM COMMENTS / NOTES
TfL/LU
CP-RE
INSPECTION FREQUENCY INSPECTION
HS2
NR
SC
Pre-Construction Activities
Lifting Operations and Lifting Equipment regulations (LOLER) SC: Appointed Person
Lift plans to be Authorised project Keltbray AP to plan and detail lift
BS 7121 Prior any lifting CP-DEL: Package Manager
5 Lift Plans H W A - - - planned by AP and plan. Lift Plan Brief to relevant site personnel involved in lifting operations prior start of lifting activity.
MDjv strategic Lifting Plan operation on site CP-RE: Temporary Works
approved by MDjv. MDJV review and accept.
MD-H&S-PR-2375 Coordinator
1CP01-MDS-CL-PLN-S003-000005
MDjv excavation & Breaking Ground Procedure MD-H&S-PR-
2325 V5
HS2-Service avoidance group- Expectations and guidance PH-
Permit to dig with appropriate services drawings,
HS-GDE-000-000003 Rev 4
Ensure a permit to surveys to be issued to Keltbray prior start of
MDjv Permit To Breaking Ground/service strike avoidance Prior to start of SC: Project Engineer
6 Permit to dig H A - - - - dig is in place, to excavation activity. All services are to be identified on Permit to dig Site personel to be briefed prior start of excavation works on all area services layout.
Procedure 1CP01-MDS-EN-PRO-SS08_SL20-000002 excavation works CP-DEL: Package manager
be issued by MDjv service drawing including specific to the area
MDjv Permit & Authorisation to Proceed Procedure MD-H&S-PR-
restrictions.
2677 V1
Thames Water Guidance on piling, heavy loads, excavations,
tunnelling and dewatering.
Title: Drainage Installation ITP Associated Method Statements ASSET CLASSIFICATION Key - Control Points
CP-DEL
N. ACTIVITY REQUIREMENT REFERENCE ACCEPTANCE CRITERIA RECORD FORM COMMENTS / NOTES
TfL/LU
CP-RE
INSPECTION FREQUENCY INSPECTION
HS2
NR
SC
Materials / Equipment Approvals
Material Approval Request/Material Compliance Report for
drainage:-
- Yard Gully With Light duty ( 1 tonne) Grid code RGP5 with
stainless steel gully fitted with Naylor Smart Sponge C/w
Filter/silt Bucket code IBP3.
- Precast concrete trapped gullies with Gully grating to BSEN
124 Class D400.
- Precast concrete concrete rings to comply with BS 5911 and
C30/20 cover slab with approved bituminous material of
CP-DEL provide RIBA 4 technical design. Supplier
toweling grade with Standard rungs @ 300mm c/c vertically
information/requirment. Drainage drawings:-
and galvanised to latest version of BS 729 or equivalent.
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000001-S4-C01 -
- Manhole depths >3.0 to use fixed ladders to BS 4211
Scheme Overview Drainage Plan
requirements or equivalent with ladders rungs handrails
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000001-S4-C01 -
safety chains etc to be hot dipped galvanised to BS 729 or
Standard Construction Details 1 of 2
equivalent.
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000004-S4-C01 -
- Insitu base C20/20 concrete and 150mm min for concrete Prepare document Supplier Compliance to BIS requirement. Confirmation All deliverables, Delivery SC:Project Engineer
Standard Construction Details 2 of 2 Any damaged good to be removed from site and re-ordered
7 surround. H R A - - - and submit for goods match the delivery documentation and condition prior to start of documentation CP-DEL: Package Manager
Civil engineering specification for the water industry (7th MAR to be updated as soon as materials certs are verified
- Min 75mm C7.5 or Gen 1 concrete for blinding/bedding. approval is acceptable works MAR CP-PE: Materials Engineer
edition).
- Engineering class B bricks to BS6073; Part1: 1981, make up
to gully frame.
- Benching 2:1 sand cement mortar or Granolithic concrete
- Covers, Gratings & Frames to be heavy duty iron cover to
BS EN124 ref. F900 Fitted with Standard Locking Bolts (S9,
grating).
- Vented manhole covers required at all Roof Storm runoff
manhole locations (RS1 to RS5).
- uPVC pipes to EN 1401 or equivalent. Solid and perforated
- Type A granular bedding
- Type B granular fill
- Type 3 open graded unbound granular material to clause
805 SHW
- Impermeable membrane category 2 HDPE heavy duty
material as per BS 7533-13 2009 clause 6.5
Construction Activities
Setting out/site engineering:-.
- Drainage runs, gullies, Manholes. Check equipment
CP-DEL to provide RIBA 4 technical design. Supplier Pre-pour Sheets
- Reinforced concrete ground slab. and latest Visual. Relationship to other structures and pre-pour SC: Site Engineer
10 I/R R - - - - information. Drawings 1CP01-MDS_WWH-DR-DGA- Each element or recorded on
- GSHP (ground source heat pipes). coordinates checks CP-DEL: Site engineer
SS08_SL23_GF-000001 ITR document
- Brickwork walls information
- Impermeable / permeable pavements.
As per RIBA 4 drawings to be provided:
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000003
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000002
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000002
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000003
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000004
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000001
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000001
Drainage & Service Coordination:
1CP01-MDS_WWH-CV-DSE-SS08_SL23-000001
1CP01-MDS_WWH-CV-DSO-SS08_SL23_B1-000001 SC: Project Engineer and TWS/TWC
Permit to dig, Temporary works
1CP01-MDS_WWH-CV-DGA-SS08_SL23_GF-000001 As per method statement or design brief where when required
11 Excavating Pits for chambers H I - - - - Permit to Load Each element register where
Structural: required CP-DEL: Package manager, TWC &
where required required
1CP01-MDS-CL-PLN-S003-000005 TWS where applicable
MDjv excavation & Breaking Ground Procedure MD-H&S-PR-
2325 V5
HS2-Service avoidance group- Expectations and guidance PH-
HS-GDE-000-000003 Rev 4
MDjv Permit To Breaking Ground/service strike avoidance
Procedure 1CP01-MDS-EN-PRO-SS08_SL20-000002
MDjv Permit & Authorisation to Proceed Procedure MD-H&S-
PR-2677 V1
Thames Water Guidance on piling, heavy loads, excavations,
tunnelling and dewatering.
1CP01-MDS-CL-PLN-S003-000005
MDjv excavation & Breaking Ground Procedure MD-H&S-PR-
Temporary works
2325 V5
register where
MDjv Permit To Breaking Ground/service strike avoidance SC: Project Engineer and TWS/TWC
Permit to dig, required
Procedure 1CP01-MDS-EN-PRO-SS08_SL20-000002 As per method statement or design brief where when required
12 Formation of trenches H I - - - - Permit to Load Each element Recorded on ITR
MDjv Permit & Authorisation to Proceed Procedure MD-H&S- required CP-DEL: Package manager, TWC &
where required or Keltbray
PR-2677 V1 TWS where applicable
Quality Check
Thames Water Guidance on piling, heavy loads, excavations,
Sheets.
tunnelling and dewatering.
Temporary work register
Title: Drainage Installation ITP Associated Method Statements ASSET CLASSIFICATION Key - Control Points
CP-DEL
N. ACTIVITY REQUIREMENT REFERENCE ACCEPTANCE CRITERIA RECORD FORM COMMENTS / NOTES
TfL/LU
CP-RE
INSPECTION FREQUENCY INSPECTION
HS2
NR
SC
CP-DEL to provide RIBA 4 technical design. Supplier
information. Drawings 1CP01-MDS_WWH-DR-DGA- Recorded on ITR
Drainage
SS08_SL23_GF-000001 (including details assosiated with a Installed as per details on the drawings and pass the air or Keltbray SC: Project Engineer
13 Installation of drainage runs R/H I - - - - inspection Each element
MF drainage pack sheet 1-5) tests Quality Check CP-DEL: Package manager
approval
Civil engineering specification for the water industry (7th Sheets.
edition)
CP-DEL to provide RIBA 4 technical design. Supplier
information. Drawings 1CP01-MDS_WWH-DR-DGA-
SC: Project Engineer and TWS/TWC
SS08_SL23_GF-000001 (including details assosiated with a Temporary works
Installation of Manhole Chambers/Attenuation tanks:- Permit to Load As per method statement or design brief where when required
14 R/H I - - - - MF drainage pack sheet 1-5) Each element register where
Possibly Modular units. where required required CP-DEL: Package manager, TWC &
Civil engineering specification for the water industry (7th required
TWS where applicable
edition)
Temporary work register
Survey to reflect design spec and RIBA 5 as built drawing. All
Site engineer to constructed to:
survey and 1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000001-S4-C01 - Recorded on ITR
carryout As-built Scheme Overview Drainage Plan As per method statement or MDjv inspection or Keltbray SC: Project Engineer
15 Survey before backfilling I R - - - - Each element
survey and site 1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000001-S4-C01 - when required. Quality Check CP-DEL: Package manager
manager to take Standard Construction Details 1 of 2 Sheets.
photo 1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000004-S4-C01 -
Standard Construction Details 2 of 2.
CP-DEL to provide RIBA 4 technical design. Supplier
information. Drawings:
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000003
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000002
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000002
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000003
Recorded on ITR
1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000004
As per Method statement or design brief where or Keltbray SC: Project Engineer
16 Backfill of chambers and trenches I I - - - - Visual inspection 1CP01-MDS_WWH-DR-DDE-SS08_SL23_GF-000001 Each element Compaction will be under taken as per
required Quality Check CP-DEL: Package manager
1CP01-MDS_WWH-DR-DGA-SS08_SL23_GF-000001
Sheets.
Drainage & Service Coordination:
1CP01-MDS_WWH-CV-DSE-SS08_SL23-000001
1CP01-MDS_WWH-CV-DSO-SS08_SL23_B1-000001
1CP01-MDS_WWH-CV-DGA-SS08_SL23_GF-000001
(including details assosiated with a MF drainage pack sheet 1-
5)
Approved by:
Prepared by:
Checked by:
Key
SC = Subcontractor; CP-DEL = CP's Delivery Team; CP-RE = CP's Responsible Engineer; HS2 = HS2 Supervisor; TfL/LU = Transport for London/London Underground; NR=Network Rail
SIGNATURE
N° ACTIVITY RESPONSIBLE DATE NCR Ref. COMMENTS
SC CP-DEL CP-RE HS2 TfL/LU NR
Pre-Construction Activities
5 Lift Plans
6 Permit to dig
Construction Activities
Setting out/site engineering:-.
10 - Drainage runs, gullies, Manholes.
- Reinforced concrete ground slab.
11 Excavating Pits for chambers
12 Formation of trenches
17 Installation of Covers