Professional Documents
Culture Documents
Project Office
th
4 Floor – 10 King William Street
Safely
London EC4N 7TW
Table of Contents
1. Purpose ......................................................................................................................... 4
2. Scope ............................................................................................................................ 4
3. Glossary of Terms.......................................................................................................... 4
4. Continual Improvement .................................................................................................. 5
4.1 Customer Satisfaction ............................................................................................. 5
4.2 Non-Conformities and Corrective Actions ............................................................... 5
4.3 Supplier Performance ............................................................................................. 6
4.4 Preventive Actions .................................................................................................. 6
4.5 Lessons Learned .................................................................................................... 7
5. Management Review ..................................................................................................... 9
6. Accountabilities and responsibilities ............................................................................. 11
7. References .................................................................................................................. 11
Appendix A. Guidance on Running Lessons Learned Workshops .................................. 12
1. Purpose
The purpose of this procedure is to define the monitoring, measurement, analysis and
improvement arrangements established to:
a) Demonstrate conformity to product requirements,
b) Ensure conformity of the Quality, Health & Safety, and Environmental Management
Systems, and
c) Continually improve the effectiveness of the Quality, Health & Safety, and
Environmental Management Systems,
on the Bank Station Capacity Upgrade (BSCU) project.
2. Scope
This procedure applies to the Dragados BSCU Quality, Health & Safety, and Environmental
Management Systems.
3. Glossary of Terms
3.1 Abbreviations
Abbreviation Meaning
3.2 Definitions
Term Definition
4. Continual Improvement
The BSCU project fosters a culture of quality and improvement, emphasised to project staff
through induction and training. To continually improve the performance of the BSCU
Management Systems, the following measurements will be established:
• Information relating to Customer satisfaction i.e. customer perception as to whether
the organisation has met customer requirements.
• Analysis of non-conformities;
• Analysis of corrective action requests; and,
• Analysis of lessons learned.
The methods for obtaining this information are described in the sections 4.1 to 4.5 below.
Additionally, the information gathered as part of the monitoring activities detailed in sections
4.1 to 4.5 and the Audit & Surveillance process shall then be analysed by the Quality &
Assurance Manager on a monthly basis. The results of this analysis will be reported as part
of the ‘Quality & Assurance’ section of the Period Reports.
The management of corrective action requests, from identification, root cause analysis, and
action implementation to effectiveness review is detailed in the Corrective Action Request
procedure, please refer to DRA-8798-PRO-G-001786.
Projects / Company
Lessons Learned
(DRA SA UK and LU)
Supply Chain
Performance Review
Review Relevance
Package Post- “Open”
to BSCU Project
Completion Review
Customer Satisfaction
(Complaints /
Compliments)
Not Relevant
Trend Analysis of CARs Relevant
and NCRs
Determine potential Determine
Interested Parties Action(s) to be Implemented
CDM Action
No Action. For
All other
Consideration at
Actions
relevant phase
Transfer
Communicate to “For Follow-up Action information to
Identified Parties Consideration” Implementation Construction Team
via CDM Risk
Register
Communicate to Project
Team For Consideration into
No “Under Action”
Method Statements and
Toolbox Talks
Action
Implemented?
Yes
“Closed”
END
4.5.1 Collate
The Lessons Learned Register (ref. DRA-8798-RGT-G-003656) is populated with
information feeding from the following (non-exhaustive) list:
• Lessons Learned from other projects within Dragados SA and LU;
• Safety / Quality / Environmental alerts and bulletins from Dragados SA, LU and other
relevant Clients and Contractors;
• BSCU work package post-completion reviews 1 (refer to Appendix A for guidance);
• Supply chain performance reviews;
• Trend analysis of Corrective Action Requests and Non-Conformity Reports;
• Stakeholders’ satisfaction (complaints / compliments) reviews; and
• Lessons Learned sessions1 as requested by the Project Director or Project Manager.
The information logged includes details of the Project / Site and Contractor, identifies
whether it is safety / environmental / quality / security-related, provides a description of the
problem or success and its impact as well as details the recommendations drawn, and
provides key words to facilitate the search.
The lessons are initially logged as “Open”; their status will change when the analysis by the
HSQE team has been carried out.
4.5.2 Analyse
All input shall be reviewed by the HSQE Team within 48hrs of receipt to identify whether or
not it is relevant to the BSCU Project:
• Should it not be, the HSQE Team determines whether this information could
potentially benefit other parties – e.g. Dragados SA Head Office – and communicates
it to them where relevant.
• Should the information be relevant, the HSQE team decides on the best course:
1) No Action Required but To Be Considered – The HSQE team determines that
although no action is required at this stage, the information will apply at
specific phases of the project. The HSQE team shall then identify the lesson
as “For Consideration” and detail the phase(s) at which the lesson best
applies. These will then be taken into account when producing or reviewing
safe systems of work.
2) Action To Be Implemented – The HSQE team determines how the proposed
recommendations are to be implemented on the Project, also identifying
actionee(s) and target date(s). The lesson status is then changed to “Under
Action”.
A review of all safety-related lessons is also held periodically with the Health
& Safety Manager and Engineering Safety Manager to identify which lessons
should be translated as risks into the CDM Risk Register, and therefore be
mitigated as such.
1
These sessions are identified on the Schedule contained within the Lessons Learned Register.
4.5.3 Implement
The HSQE team ensures that all identified actions are satisfactorily implemented, at which
point the status of the associated lesson is changed to “Closed”.
The BSCU Method Statement Procedure (ref. DRA-8798-PRO-G-000126) requires that all
Method Statements produced for the Project, whether by Dragados or its supply chain,
incorporate any relevant control measures detailed in the Lessons Learned Register (i.e.
those lessons identified as “For Consideration”), as well as any relevant control measures
detailed in the CDM Risk Register.
The implementation of Lessons Learned within Method Statements is also controlled by the
BSCU Submission Sheet, as the Construction Manager / delegated Package Manager’s
endorsement signifies that he/she has confirmed that, where relevant, the above has been
satisfactorily considered.
4.5.4 Record
All lessons identified throughout the project are recorded in the Lessons Learned Register
held in ASITE, ref. DRA-8798-RGT-G-003656. Additionally, all relevant supporting
information is stored in ASITE, with the associated hyperlink included in the Register.
The outputs from Lessons Learned workshops will be communicated to the LU Project
Manager for consideration and inclusion in LU’s Project Lessons Learned database in
accordance with WI 880 Lessons Learnt.
5. Management Review
5.1 Data Collation & Analysis
The project Quality, Environmental and Health & Safety Managers shall collate information
to enable an effective review of the project Quality, Environmental and Health & Safety
Management Systems to be carried out, and report this information using the BSCU
Management Review template ref. DRA-8798-TEM-G-004739.
The information reported shall comprise as appropriate, but not necessarily be limited to:-
• Status of previous Management Review actions.
• Project Quality, Environmental and Health & Safety policies and objectives.
• Results of audit reports.
• Evaluations of compliance with legal and other requirements (HSE-specific).
• Conformity of the works.
• Process performance.
• Key Performance Indicators relating to all QHSE processes.
• Status of corrective and preventive actions.
• Status of incident and accident investigations.
• Lessons learnt and actions taken.
• Results from Customer satisfaction surveys (Quality-specific), and communications
from external interested parties including complaints (HSE-specific).
• Progress on Management Systems development.
• Changes (including organisational and legal) which could affect the Management
Systems.
• Recommendations for improvement.
• Any other data that the BSCU Project Director considers appropriate.
6.2 Responsibilities
Responsibilities for monitoring compliance to the specific Quality, Environmental and Health
& Safety requirements reside respectively with the Quality, Environmental and Health &
Safety Managers.
The Dragados BSCU Project Quality and Assurance / Health & Safety / Environment
Managers are responsible for collecting and analysing the Quality / Health & Safety /
Environment Management Systems performance data respectively, and managing their
respective inputs and outputs to and from the Management Review.
7. References
The following documents should be referred to in the interpretation and application of this
document:-
• Dragados BSCU Audit & Surveillance Procedure, ref. DRA-8798-PRO-G-001076.
• Dragados BSCU Control of Non-Conforming Product Procedure, ref. DRA-8798-
PRO-G-001393.
• Dragados BSCU Corrective Action Request Procedure, ref. DRA-8798-PRO-G-
001786.
• Dragados BSCU Project Controls Management Plan and Procedures, ref. DRA-
8798-PLN-G-000154.
• Dragados BSCU Method Statement Procedure, ref. DRA-8798-PRO-G-000126.
• Dragados BSCU Environmental Management Plan, ref. DRA-8798-PLN-G-001855.
• Dragados BSCU Code of Construction Practice, ref. DRA-8798-PLN-G-001856.
• BSCU Risk Management Plan, ref. LUSTN-0008798-PLN-002908.
• Dragados S.A. Quality Management Procedure, GP-1.01 System Analysis and
Review.
• Dragados S.A. Quality Management Procedure, GP-4.02 Corrective and Preventive
Actions.
• Dragados S.A. Quality Management Procedure, GP-4.04 Client Satisfaction.