You are on page 1of 9

ARAB CENTER FOR ENGINEERING STUDIES

DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 1 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

METHOD STATEMENT
HOTEL SERVICED APARTMENT (G + 4P + 1HC+ 31+
PROJECT : MECH. FLOOR + ROOF) JVT07I0HR001 JVT, DUBAI,
U.A E
CLIENT : M/S. KRATI JAIN RAJESH JAIN

CONSULTANT : M/S. DYNAMIC ENGINEERING CONSULTANTS

MAIN M/S. SHAANXI CONSTRUCTION ENGINEERING


:
CONTRACTOR GROUP CORPORATION
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 2 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

1- SCOPE

This method statement presents the procedure to monitor the temperature changes which
occur in concrete structures in order to enable controlling of thermal cracking in different
types of structures. The measurement purposes are to finding the temperature development
within the concrete mass. The results will show peak temperature and the temperature
differential for such measuring points.

2- INTRODUCTION

Temperature monitoring of concrete components during handling and batching, and of the
fresh concrete before and after its discharge into the forms, can be adequately accomplished
with ordinary portable thermometers capable of 0.5C resolution.

Post-cooling systems require embedded temperature-sensing devices (thermocouples) to


provide information for the control of concrete cooling rates. Similar instruments will serve
to evaluate the degree of protection afforded by insulation. A set of thermocouples will be
installed and embedded to the concrete at the bottom, middle & top (top & bottom shall be
installed with minimum 10cm concrete cover).

3- EQUIPMENT

1) Temperature Logger

Temperature Logging system consists of a range of sensor cum logger which


measure and record physical properties of in-place concrete.

General Specification: -
Operating Temperature:-20° C to 99° C
Reading interval:-Every 30 Minutes
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 3 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

2) Reader

A specially designed reader will be used for communicating with the loggers
embedded in the concrete, in order to transporting the data from loggers to a PC.
The reader is used to instruct the loggers to begin logging, download information
from loggers and upload logger data to a PC for interpretation.

4- PROCEDURE

4.1 Installation of Concrete Temperature Loggers

The Temperature loggers shall be installed typically at minimum five levels at various
locations at approx. 60cm interval of the mass concrete, as shown in the below diagram. In
addition a separate logger shall be fixed near to test location in order to monitor the ambient
temperature. Temperature monitoring is normally required for mass concrete of depth above
800 mm.

The temperature loggers shall be fixed to a PVC pipe of 0.5” OD at required lengths and pipe
shall be tied to the reinforcement bars.
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 4 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

Typical Temperature Logger Installation & Monitoring

4.2 Temperature Monitoring

Measurement and recording of Temperature at fixed intervals (every half hour) will be done
automatically by the Temperature logger. Recorded data shall be collected by connecting the
reader to the loggers. Data recording shall be done minimum for 7-10 days to confirm the
heat of hydration process.

*Note: Curing Procedure and all the precautionary measurements to avoid exceeding
maximum concrete temperature and differential temperature shall be arranged by Contractor.
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 5 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

4.3 Reporting

Comprehensive report, including test locations identification and recorded data shall be
submitted after completion of the temperature monitoring of each zone.

ACI CRITERIA FOR TEMPERATURE:

REFERENCE:
Manual of Concrete Practice, 207.4 R – 93.
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 6 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

APPENDIX A

LOCATIONS OF SENSOR INSTALLATION


KEY PLAN N
1 2 3 4 5 6 7 8 9

BLOCK WORK
BLOCK WORK BLOCK WORK -1.500 (100mm TK.)
(100mm TK.) -1.500 -1.900 -1.500 -1.900
(100mm TK.) -1.500 -1.900 -1.500 -1.900 EBL EBL EBL
-1.500 -1.900 -1.500 -1.900 -1.500 -1.900 EBL EBL EBL NOTE:
EBL EBL EBL EBL EBL 1. ALL DIMENSIONS ARE IN MILLIMETER AND LEVELS ARE IN METER
EBL EBL EBL EBL UNLESS OTHERWISE NOTED
-1.900 2. GATE LEVEL -0.33 FFL = +7.95 DMD LEVEL
3. WATER PROOFING DETAILS TO BE SUBMITTED SEPARATELY

A EBL 4. MANHOLES, CHAMBERS & GREASE TRAP DETAILS ADDED AS PER MEP
REQUIREMENT.

-1.300 -1.300

EB 300
EBL -1.500 EBL -1.300

L
- 1.
EBL -1.500 -1.500 -1.300 -1.500 EBL
EBL EBL -1.500 EBL EBL
EBL -1.500
-1.500 EBL
-1.500 EBL
EBL BLOCK WORK
(150mm TK.) BLOCK WORK
B -1.900 (100mm TK.)
-1.900 -1.900 EBL
EBL -1.500 EBL -1.500 -1.500
EBL EBL EBL -1.900
-1.500 EBL
EBL BLOCK WORK
-1.300 (150mm TK.) -1.500
-1.500 EBL -1.500 EBL
VAR. VAR. VAR. EBL EBL
EBL EBL EBL -1.500
VAR. BLOCK WORK EBL
(150mm TK.)
EBL
-2.35 SHUTTER -2.35
Loc 19
EBL EBL
-1.500
EBL

Loc 1 Loc 18 -1.900


EBL
-1.300
-2.150 EBL
EBL
Loc 6 -1.900
C EBL
Loc 15 -1.900
EBL
-1.300
EBL
-1.500
-1.500 EBL
EBL
-1.500
EBL
BLOCK WORK Lower Raft Excavation works @ Level -5.710 m
(150mm TK.) SLOPE

-1.500 Loc 4 Loc 13 -1.500


EBL
EBL BLOCK WORK
(150mm TK.)

-1.500
EBL
Loc 17 BLOCK WORK
(150mm TK.)

Loc 2 Loc 7 -1.900


D EBL
Upper Raft Excavation works @ Level -3.100 m
SLOPE Loc 14 -1.500 -1.900 -1.500
EBL EBL EBL
-1.300
EBL Loc 11 Loc 16
-1.500 -1.500
EBL EBL
-1.500
EBL

SLOPE BLOCK WORK DRAWING SUBMITTAL STATUS


(150mm TK.)
Loc 9 -1.500
EBL A Approved B Approved as Noted

Loc 5 C Revise and Resubmit D Rejected


-1.300 -1.900
EBL -1.900
Loc 12 EBL
-1.900
EBL Reviewed By: Date:

EBL
E
-1.500
Loc 8
EBL Loc 10 -1.500
EBL
-1.500
EBL

BLOCK WORK
Loc 3 BLOCK WORK
(150mm TK.) 1 21.MAR.2021 FOR APPROVAL IM

0 28.FEB.2021 FOR APPROVAL IM

REV. DATE DESCRIPTION DRAWN

PROJECT:

SHUTTER HOTEL SERVICED APARTMENT


-1.500 -1.500 -1.500 -1.500 (G+4P+1HC+31+MECH.FLOOR + ROOF)
EBL EBL EBL EBL BLOCK WORK
-1.300 (100mm TK.) -1.500 -1.500 JVT07I0HR001

EBL -1.900 JVT, DUBAI,U A E.


EBL EBL EBL CLIENT:

KRATI JAIN RAJESH JAIN


Plot No./ Area:

-1.500 JVT07I0HR001 / AL BARSHA SOUTH FIFTH

EBL
CONSULTANT:
F OFFICE 2805 - 2810, CONCORD TOWER,
MEDIA CITY, DUBAI, UNITED ARAB EMIRATES,
P.O. BOX: 79593

-1.900 -1.900 -1.900 -1.900 TEL.: 04-2989220, FAX: 04-2989210

-1.900 EBL
www.decengineering.net

EBL -1.500 EBL -1.500 EBL -1.500 EBL MAIN CONTRACTOR:

EBL EBL EBL -1.500 -1.900 Shaanxi Construction Engineering Group Corporation
EBL -1.500 EBL Office 310, Emaar Business Park Building-4

EBL -1.500 Dubai, United Arab Emirates.


Tel.: 04-5776183

-1.900 EBL
EBL SUB CONTRACTOR:

Tie Beam
G DRAWING TITLE:

-1.300 -1.300
-1.300 -1.300 -1.300 EBL RAFT FOUNDATION
-1.300 EBL EBL 21 MAR 2021
EBL EBL EBL GENERAL ARRANGEMENT LAYOUT

SCALE: 1:100 DRAWING NO. REV.

DATE: 21.MAR.2021 FIV-SGC-CIV-GF-SHD-004-01 01

EXCAVATION LAYOUT PLAN DRAWN BY

IM
Sign. & Dt. ...............
CHECKED BY

Sign. & Dt. ...............


SUBMITTAL REF. NO:

SCALE : 1/100
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 7 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

APPENDIX B

LEVELS OF SENSOR INSTALLATION


ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 8 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi

You might also like