OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 1 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi
METHOD STATEMENT
HOTEL SERVICED APARTMENT (G + 4P + 1HC+ 31+
PROJECT : MECH. FLOOR + ROOF) JVT07I0HR001 JVT, DUBAI,
U.A E
CLIENT : M/S. KRATI JAIN RAJESH JAIN
1- SCOPE
This method statement presents the procedure to monitor the temperature changes which
occur in concrete structures in order to enable controlling of thermal cracking in different
types of structures. The measurement purposes are to finding the temperature development
within the concrete mass. The results will show peak temperature and the temperature
differential for such measuring points.
2- INTRODUCTION
Temperature monitoring of concrete components during handling and batching, and of the
fresh concrete before and after its discharge into the forms, can be adequately accomplished
with ordinary portable thermometers capable of 0.5C resolution.
3- EQUIPMENT
1) Temperature Logger
General Specification: -
Operating Temperature:-20° C to 99° C
Reading interval:-Every 30 Minutes
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 3 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi
2) Reader
A specially designed reader will be used for communicating with the loggers
embedded in the concrete, in order to transporting the data from loggers to a PC.
The reader is used to instruct the loggers to begin logging, download information
from loggers and upload logger data to a PC for interpretation.
4- PROCEDURE
The Temperature loggers shall be installed typically at minimum five levels at various
locations at approx. 60cm interval of the mass concrete, as shown in the below diagram. In
addition a separate logger shall be fixed near to test location in order to monitor the ambient
temperature. Temperature monitoring is normally required for mass concrete of depth above
800 mm.
The temperature loggers shall be fixed to a PVC pipe of 0.5” OD at required lengths and pipe
shall be tied to the reinforcement bars.
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 4 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi
Measurement and recording of Temperature at fixed intervals (every half hour) will be done
automatically by the Temperature logger. Recorded data shall be collected by connecting the
reader to the loggers. Data recording shall be done minimum for 7-10 days to confirm the
heat of hydration process.
*Note: Curing Procedure and all the precautionary measurements to avoid exceeding
maximum concrete temperature and differential temperature shall be arranged by Contractor.
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 5 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi
4.3 Reporting
Comprehensive report, including test locations identification and recorded data shall be
submitted after completion of the temperature monitoring of each zone.
REFERENCE:
Manual of Concrete Practice, 207.4 R – 93.
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 6 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi
APPENDIX A
BLOCK WORK
BLOCK WORK BLOCK WORK -1.500 (100mm TK.)
(100mm TK.) -1.500 -1.900 -1.500 -1.900
(100mm TK.) -1.500 -1.900 -1.500 -1.900 EBL EBL EBL
-1.500 -1.900 -1.500 -1.900 -1.500 -1.900 EBL EBL EBL NOTE:
EBL EBL EBL EBL EBL 1. ALL DIMENSIONS ARE IN MILLIMETER AND LEVELS ARE IN METER
EBL EBL EBL EBL UNLESS OTHERWISE NOTED
-1.900 2. GATE LEVEL -0.33 FFL = +7.95 DMD LEVEL
3. WATER PROOFING DETAILS TO BE SUBMITTED SEPARATELY
A EBL 4. MANHOLES, CHAMBERS & GREASE TRAP DETAILS ADDED AS PER MEP
REQUIREMENT.
-1.300 -1.300
EB 300
EBL -1.500 EBL -1.300
L
- 1.
EBL -1.500 -1.500 -1.300 -1.500 EBL
EBL EBL -1.500 EBL EBL
EBL -1.500
-1.500 EBL
-1.500 EBL
EBL BLOCK WORK
(150mm TK.) BLOCK WORK
B -1.900 (100mm TK.)
-1.900 -1.900 EBL
EBL -1.500 EBL -1.500 -1.500
EBL EBL EBL -1.900
-1.500 EBL
EBL BLOCK WORK
-1.300 (150mm TK.) -1.500
-1.500 EBL -1.500 EBL
VAR. VAR. VAR. EBL EBL
EBL EBL EBL -1.500
VAR. BLOCK WORK EBL
(150mm TK.)
EBL
-2.35 SHUTTER -2.35
Loc 19
EBL EBL
-1.500
EBL
-1.500
EBL
Loc 17 BLOCK WORK
(150mm TK.)
EBL
E
-1.500
Loc 8
EBL Loc 10 -1.500
EBL
-1.500
EBL
BLOCK WORK
Loc 3 BLOCK WORK
(150mm TK.) 1 21.MAR.2021 FOR APPROVAL IM
PROJECT:
EBL
CONSULTANT:
F OFFICE 2805 - 2810, CONCORD TOWER,
MEDIA CITY, DUBAI, UNITED ARAB EMIRATES,
P.O. BOX: 79593
-1.900 EBL
www.decengineering.net
EBL EBL EBL -1.500 -1.900 Shaanxi Construction Engineering Group Corporation
EBL -1.500 EBL Office 310, Emaar Business Park Building-4
-1.900 EBL
EBL SUB CONTRACTOR:
Tie Beam
G DRAWING TITLE:
-1.300 -1.300
-1.300 -1.300 -1.300 EBL RAFT FOUNDATION
-1.300 EBL EBL 21 MAR 2021
EBL EBL EBL GENERAL ARRANGEMENT LAYOUT
IM
Sign. & Dt. ...............
CHECKED BY
SCALE : 1/100
ARAB CENTER FOR ENGINEERING STUDIES
DUBAI, U.A.E.
OPERATIONAL PROCEDURE Ref. No. : OP-021(P21/2021)
Issue No. : 1
Rev. No. : 0
TEMPERATURE MONITORING OF CONCRETE BY Rev. date : 28/03/2021
Page No. : 7 of 9
USING TEMPERATURE LOGGING SYSTEM
Approved by : Eng Mohammad
Shatnawi
APPENDIX B