Professional Documents
Culture Documents
Quantity Surveying
Quantity Surveying
Powerpoint T
Templates
emplates
Page 1
Introduction to Quantity
Surveying
Powerpoint Templates
QUANTITY SURVEY???
Introduction
Once a construction project is completed or depending on the form of
contract upon completion of certain parts of the work, the contractor must
be paid for appropriately completed works.
This would then require that the actual works done be somehow
estimated or measured for payment purposes.
On the other hand to estimate how much a civil engineering project may
cost, the actual quantities of materials, labor, equipment etc. that is needed
for the construction work must be calculated at the beginning of the
work.
Such work of calculating the amount of materials and other
incidentals necessary for the realization of the work is called quantity
surveying.
Page 2
Powerpoint Templates
QUANTITY SURVEY???
Introduction Cont.
Quantity surveying is a term or processes used in the construction
industry to take measurements of civil works, prepare
specifications, and estimate the cost of works either for each trade of
work or for the whole project.
The term “surveying” means to inspect, study, review, investigate,
asses, and hence “to measure” therefore the term “quantity
surveying” means “quantity measuring” as applied to civil
engineering projects.
Quantity surveying is the application of standard methods of
measurement to quantify the amount of various items in a
construction project, for the undertaking of valuation, and certifying
payments.
Page 3
Powerpoint Templates
QUANTITY SURVEY???
Introduction Cont.
The following tasks are covered in quantity surveying.
1. Preparation of Specification
2. Taking measurements of civil works (Taking off quantities and
preparing BOQ)
3. Preparation of approximate (preliminary) cost estimate at the
very early stage of the project
4. Preparation of detail cost estimate at different stages (taking as
built measurements and preparing payment certificates or
approval of payment certificates prepared by taking
measurements)
5. Valuation of property
Page 4
Powerpoint Templates
QUANTITY SURVEY???
Pur pose of Quantity Sur veying
The purpose of quantity surveying hence the preparation of Bill of
quantities is:
i. Assist the client to have an accurate estimate of the volume of
work as well as the required budget.
ii. To assist in the accurate preparation of tenders, by providing
uniform measurement of quantities.
iii. To give an accurate checklist of work accomplished
iv. To assist in the certification of payments
v. To give insight into the required variation work amounts.
Page 5
Powerpoint Templates
ESTIMATE???
a. to judge tentatively or approximately the value, worth,
or significance of
b. to determine roughly the size, extent, or nature of
c. to produce a statement of the approximate cost of
Merriam - Webster
Page 6
Powerpoint Templates
Page 7
Powerpoint Templates
Purpose of Estimating
1. Estimating Materials
2. Estimating Labor
3. Estimating Equipment
4. Estimating Time
Page 8
Powerpoint Templates
Types of Construction Estimates
1. Estimates for Conceptual Planning
Page 9
Powerpoint Templates
Types of Construction Estimates
2. Estimates for Feasibility
±15 – 20 % accurate
Page 10
Powerpoint Templates
Types of Construction Estimates
3. Estimate During Engineering and Design
Page 11
Powerpoint Templates
Types of Construction Estimates
4. Estimates for Construction
•Subcontractor quotations
•Quantity takeoffs
•Construction procedures.
5% accuracy
Page 12
Powerpoint Templates
Types of Construction Estimates
5.Control Estimates.
Page 13
Powerpoint Templates
Estimating Techniques
Approximate Estimates
An approximate estimate is an approximate or rough estimate prepared
to obtain an approximate cost in a short time. For certain purposes the
use of such methods is justified.
Detailed Estimate
A detailed estimate of the cost of a project is prepared by determining the
quantities and costs of every thing that a contractor is required to provide
and do for the satisfactory completion of the work. It is the best and most
reliable form of estimate. A detailed estimate may be prepared in the
following two ways
Page 10
Powerpoint Templates
Qualification of an Quantity Surveyor
Page 15
Powerpoint Templates
Data Required for Preparing an Estimate
2. Specifications indicating
the exact nature and class
of materials to be used.
Page 16
Powerpoint Templates
Steps in Preparing Estimates
2. Squaring out
- Working out volumes, areas, etc. and casting up their total in recognized units.
3. Abstracting
- In the third step all the items along with the net results obtained in the second
step are transferred from measurement sheets to specially ruled sheets having
rate column ready for pricing.
Page 17
Powerpoint Templates
Work Breakdown Structure
Work Breakdown Structure (WBS)– provide a common
hierarchical framework for summarizing information and for the
quantitative reporting to customers (client/owner) and management.
Page 18
Powerpoint Templates
Page 19
Powerpoint Templates
Basics for Preparation of Estimates
Review Contract Documents
Prebid Conference – a meeting held prior to bid opening for the purpose of
explaining the project and answering questions that bidders have with respect to
the contract documents and the work.
Page 20
Powerpoint Templates
Basics for Preparation of Estimates
Planning The Work
Quantities
Page 21
Powerpoint Templates
Basics for Preparation of Estimates
Types of Cost
Direct Cost – all cost elements that can be associated with a specific item of
project work e.g. cost of labor, cost of materials, cost of equipment
Page 22
Powerpoint Templates
Basics for Preparation of Estimates
Historical production and cost data from similar past work are excellent
resources of when adequate details have been saved and adjustments to
project specifics can be defined.
Page 23
Powerpoint Templates
Basics for Preparation of Estimates
Unit Cost
Labor Unit Cost – cost based on a defined crew that performs the task
at an assigned production rate.
Page 20
Powerpoint Templates
Basics for Preparation of Estimates
cost for each task is developed by summing up the direct cost elements
for labor, equipment, materials, supplies and subcontractors.
Indirect cost and other markups associated with each task or work item
should be identified and considered properly.
Page 25
Powerpoint Templates
Basics for Preparation of Estimates
Supporting Documents
Page 26
Powerpoint Templates
Reference:
Page 27