You are on page 1of 1

DAILY PROGRESS REPORT

Client : Site : Total No of People :


Contact : Date : Number of House keeping Time
Tag No : Shift : REMARK Number for time Sheet Time Coments
Number of people for Dismantle
% Completed : Supervisor
Number of people For Erection
& Signature
Number of people on Guard

Hours Activity Dimension Total


Total Detials: Type of work & Location Elevation start height
E D M Daywork L W H Qty B/L Sus Level m3/m2
Sl.no ID no Name Grade Hours E D M

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

Progress Summary M3/hr Manpower Summary Day work Summary


3
Erection (m ) Type Nos Hrs Total Hours Grade Cost / Hr Nos Hr Amount

Dismantle(m 3) Erection : Supervisor

Modification (m 3) Dismnatle : Forman

Prepared by Modification : Stager

Daywork :