Professional Documents
Culture Documents
operators
Technical assistance was provided by John Karounos, Brian Jeffrey, Tad Plata and
Paul Pedretti from Geelong Wool Combing Ltd.
April 2003
Contents
Section 1: Introduction 1
1.1 The training program 1
1.2 The top-making process at GWC 2
1.3 Overview of the ETP process 3
1.4 Operator tasks 7
1.5 The Environmental Management System 8
1.6 Word list 9
Section 5: Documentation 39
Section 7: Assessment 46
7.1 The assessment procedure 46
7.2 Checklist of operator tasks 47
7.3 Oral questions – ETP operator 49
ETP Operator Manual
Section 1: Introduction
1.1 The training program
The purpose:
To train you to operate and monitor the Effluent Treatment Plant (ETP) efficiently and
safely, with little supervision in accordance with company enterprise agreements.
Training objectives:
Assessment methods:
April 2003 1
ETP Operator Manual
1.2 The top-making process at GWC
April 2003 2
ETP Operator Manual
suint 5-8%
Most of the dirt, suint (pronounced ‘swint’) and grease are removed during the scouring
process. The scouring line has seven bowls through which the wool passes.
Bowl 1 is the de-suint bowl where the heavy contaminants are removed from the wool, and
combined with the underflow liquors of wash bowl 4 and the rinse bowls 5, 6, & 7.
Bowls 2,3 & 4 are wash bowls which are heated to 650C, with detergent added to bowls 3
& 4. This provides ideal conditions for removal of the woolgrease, creating a grease
enriched emulsion.
April 2003 3
ETP Operator Manual
The two scour streams follow a separate path through the ETP and are subsequently treated
differently due to their makeup. First the liquor from each stream is run through a
noggerath. This is a rotating drum strainer/filter that removes wool fibres and some
vegetable matter. The greasy stream then goes into the South pit while the heavy stream
goes into the North pit.
WOOL
From the North pit the heavy stream passes through the primary and secondary sand traps,
causing the heavy particles to settle before being removed to the compost plant. The liquor,
with unrecoverable woolgrease and small particles that will not settle readily is then fed
into the aerated biological tanks for further treatment before being discharged to the sewer.
April 2003 4
ETP Operator Manual
The aeration tanks therefore contain the balance of the effluent from the rinse and grease
streams. This liquid contains detergent, fibres and plant matter that provide food for the
bacteria, called the biological load. These bacteria require oxygen, which is circulated into
the aeration tanks via the turbine blowers.
The treated liquor then passes to the settling tank or clarifier. Here the sludge, sand and
bacteria sink to the bottom while the clarified water is discharged into the sewer.
The sludge passes to the thickener where the material settles further. The upper liquid layer
is then redirected back to the aeration tanks. The settled sludge goes to the bio-decanter for
dewatering, where some of it is recycled back to the aeration tanks to replenish the
bacteria. The rest of the sludge is directed to the compost plant.
April 2003 5
ETP Operator Manual
Flow chart of the ETP process
April 2003 6
ETP Operator Manual
April 2003 7
ETP Operator Manual
• Legal Requirements
There are various agreements and regulations relating to the environment which
have to be followed so that GWC can lawfully carry on its activities at Lara.
• Marketing Demands
Certain clients require GWC to offer proof that our operations are carried out in a
manner that does not harm the environment.
• Cost Savings
Reduction in waste and recycling should deliver cash savings.
• Neighbourhood Relations
GWC can have an effect on neighbours from the emission of noise, dust or
odours. We have procedures in place to monitor each of these impacts.
Several environmental procedures and work instructions cover the ETP. Your trainer will
take you through the procedures and work instructions related to your job.
April 2003 8
ETP Operator Manual
Sediment The resulting sludge when scour liquors are allowed to stand
April 2003 9
ETP Operator Manual
Remember, once your ears are damaged they never get better.
In certain work areas such as the boiler room and when handling
chemicals, long trousers must be worn - not shorts.
April 2003 10
ETP Operator Manual
Heavy lifting
• Keep your back straight and let your legs do the lifting
Hot surfaces
• Beware of burns from hot equipment, pipes and liquids.
Slips, falls
• Take care when moving around the plant. Wet floors and
steps can be slippery.
Emergency stops
• Know where the on/off and emergency stop buttons are
located, in case of emergency.
Chemicals
• Know the hazards associated with the chemicals you use
in the ETP
• Refer to the MSDS for each chemical for safe handling
procedures
April 2003 11
ETP Operator Manual
Polyelectrolyte spill
Dry Powder: Collect the powder and reuse it. The residual must be hosed down to
the sand trap pit. Do not throw it in a bin.
April 2003 12
ETP Operator Manual
The following procedures outline what to do in the case of emergencies such as power
failure and fire. These procedures are only to be followed if it is safe to do so.
Do not put yourself at risk to carry out these procedures.
Power failure
• Stop the feed into the PX machines.
• Open the drain valve of emulsion phase to drain in SX and PX machines.
• Close steam valve to SX heat exchanger.
• Do not apply brakes on SX and PX machines. (Let the machine stop)
• Proceed to the assembly area.
Resumption of power
• Reset the plant.
• Inspect the condition of the sand trap.
• Start the boiler.
• Start the blower and circulation pumps for the aeration tanks.
• Start all of the pumps for the ETP and ensure their operation on the SCADA
monitor.
• Reset decanters and start as required.
• Start the scraper in the clarifier.
• Start the scraper in the thickener tank.
• Start the water treatment room.
• Start Monopump.
Fire
• In case of fire hazard hit the group emergency switch.
• If time permits follow the steps under power failure, do not put yourself at risk.
• Proceed to the assembly area.
April 2003 13
ETP Operator Manual
Noggerath Filters out fibres from scour liquor to prevent pipe blockages.
Fibres are disposed of as rubbish.
Wool wash decanter Removes heavy suspended material. (See following diagram)
Alfa Laval separators There are 3 stages to progressively separate the grease and
remove the water. (See diagrams on next pages)
In the primary separator the emulsion reaches 70%.
In the concentrator the emulsion reaches 90-95%.
The purifier produces >99.0% pure wool grease.
Blowers Blows air into aeration tank for bacteria (1-5 pp million)
Thickener Allows the sediment from the clarifier to settle further. The
top material is redirected to the aeration tank to replenish the
bacteria content.
Softener Treats the water for use in the scour and boiler.
April 2003 14
ETP Operator Manual
Operating principles
The separators use centrifugal force to separate the wool grease from the water, and
remove any solids at the same time. As the machine rotates rapidly, the liquor is fed into
the top of the machine and out towards the discs. The separation takes place in the space
between the discs.
The lighter liquid (grease) is directed to the centre of the bowl and up to the light phase
outlet. The heavier liquid (water) moves to the outside of the discs and up to the paring
chamber, where it is pumped out by the paring disc.
The separated solid particles are forced towards the edges of the bowl and out through the
nozzles together with some water.
April 2003 15
ETP Operator Manual
The purifier
April 2003 16
ETP Operator Manual
The sludge is pumped through the feed pipe (1) into the inlet chamber (2).
Under centrifugal force it leaves the chamber through ports (3) and flows into the
centrifugal bowl (4).
Sedimentation begins just outside the feed ports and continues for the length of the bowl.
The solids and the liquid travel in the same direction, with the heavy solids settling on the
inside wall of the bowl due to the centrifugal force.
The screw (5) transports the solids towards the discharge ports (7), where it is ejected into
the housing and then via a pipe to the compost plant.
The bowl and the screw turn in the same direction but at slightly different speeds,
controlled by the gearbox (6).
The centrate flows through the return channels (11) on the screw hub, in the opposite
direction to the solids, back to the feed end.
The centrate is discharged over weir plates (12) which can be adjusted to control the depth
of overflow and the volume inside the centrifuge.
The centrate passes into the housing and through the discharge pipe to the centrate sump.
April 2003 17
ETP Operator Manual
April 2003 18
ETP Operator Manual
April 2003 19
ETP Operator Manual
Noggerath pits: Check baskets at least once per shift, clean as required.
April 2003 20
ETP Operator Manual
GWC GWC
Drum number
Drum No. Gross…..kg
Nett…..kg
Gross
Nett
April 2003 21
ETP Operator Manual
April 2003 22
ETP Operator Manual
1. Allow wax to cool To prevent the drum from collapsing as the wax cools,
engage and turn the drum closure a maximum of one
turn, so that air can enter the drum as the wax
contracts.
3. Close cooled drum Only when the drums have cooled, tighten the drum
closures to prevent moisture contaminating the wax.
Initial the appropriate ‘SEALED BY’ cells in the
Wool Wax Log, GWC-263.
4. Move pallet to storage When the pallet is full, transfer it to the wool wax
storage area using a forklift.
5. Complete records At the end of the day, place the original Wool Wax
Log GWC-263 sheet in the tray to be collected.
1. Check shipping advice The ETP Operator will receive the Shipping Advice,
GWC-028, (1 original and 3 copies) at least three
working days before scheduled pickup.
2. Assemble drums The ETP Operator will assemble the drums indicated
in the Shipping Advice, GWC-028, with a forklift at
least 24 hours before due pickup, on pallets near the
truck loading bay north of the ETP.
3. Check drums The forklift driver will check each drum closure and
drum number prior to loading and sign all four
Shipping Advices, GWC-028, in the ‘Checked By’
column when satisfied that all drum closures are tight
and all drum numbers are correct.
4. Sign shipping advice The driver must sign the original Shipping Advice,
GWC-028 and the three copies.
5. File records After loading the wool wax drums onto the truck the
original Shipping Advice, GWC-028, and one copy
will be handed to the truck driver and two copies will
be placed in the office tray.
April 2003 23
ETP Operator Manual
1. Check the pressure Ensure a pressure of 0.9 bar in the saturation tank. The
same pressure should be indicated on the steam
pressure controller on the Control Panel
2. Open steam valves Open steam supply hand valves (AV-27 and AV-28)
to the heat exchanger. Open slowly to avoid
hammering in the piping
3. Open air supply The air supply hand valve, located on the left side of
SX 8.1, should be open.
4. Open sludge valve Open sludge valve (A-V6-1) from the machine to the
drain pipe.
5. Check water line open The hand valve (AV-13) in the start-up water line,
located behind SX machines, should be open.
8. Open the drain valve Open the drain valve (V-X-4) to divert the light phase
to the drain.
10. Press cleaning button When the machine reaches its full speed, indicated by
a green light ON, press the ‘Cleaning’ button to light
the ‘cleaning’ indicator on the Control Panel.
12. Transfer emulsion Open hand valves (A-CV-23-1 and A-CV-23-2) for
transferring emulsion from SX-8.1 to PX-3.1
overhead tank.
13. Check the nozzles Check the nozzles and the vibration monitor.
April 2003 24
ETP Operator Manual
To start production
1. Check sump level Check that the centrate sump level is above 30%.
4. Start production and Press the ‘Production’ button. Adjust the feed rate
adjust feed rate using the ‘feed adjust’ potentiometer on the Decanter
Control Panel.
6. Close drain valve, open Divert the emulsion to the emulsion pump by closing
pump valve the hand valve (V-X-4) to the drain and opening the
hand valve (V-X-3) to the pump.
7. Adjust the feed Adjust the feed to maintain a level of about 30% in the
centrate sump
April 2003 25
ETP Operator Manual
To stop production
1. Press standby button Press the ‘Stand By’ push button on control panel, the
‘Stand By’ light will flash and becomes steady.
2. Press cleaning button Press the ‘Cleaning’ button. The emulsion pump will
stop after a short delay.
3. Open hand valve Open the hand valve to divert the emulsion phase to
drain.
4. Press standby button Continue cleaning for at least 20 minutes, or until the
light phase going to funnel is clear. Press the ‘Stand
by’ button.
5. Complete records Record the date and any comments on the Alfa-Laval
Separator Cleaning form, GWC-245.
6. Close steam valves Close steam supply hand valves (AV-27 & AV-28)
8. Press stop button and Press the ‘Stop’ button. Check that the current in the
apply brake current meter drops to zero. Immediately go to the
machine and apply the brake.
April 2003 26
ETP Operator Manual
System start up
1. Check tank level and If the overhead emulsion storage tank is at least ¼ full, open the
temperature steam valves for the heating system for piping and overhead
If tank ¼ full - open tank (B-V5 and B-V6) (located under the tank at the north-east
steam valves corner).
The temperature of overhead tank should be between 88 - 92oC.
If tank empty do not If the overhead emulsion tank is empty, do not open the steam
open valves. valve at this stage.
3. Open sludge valve Open the sludge valve (B-V6-1) located at back of the machine.
4. Open heavy phase Open heavy phase valve (B-V5-1) located at back of machine.
valve
6. Open drain valve Open hand valve between the light phase funnel and the drain.
7. Open valves to Open the hand valves between the emulsion pump and the
purifier tank purifier overhead tank (B-V4-1 and C-V4-3).
8. Turn rotary switches Turn all rotary switches on the Alfa-Laval Control Panel to the
to Auto Auto position.
9. Press start button Press the ‘Start’ button on the Alfa-Laval Control Panel.
10. Open water valves Open bowl operating water valves (B-V16-1 and B-V15-1).
11. Open gravity disc When machine reaches full speed, the stirrer & emulsion pump
sealing water valve will start. Open gravity disc sealing water valve (B-V14). An
extension rod is used to control the opening of the valve.
12. Open heating valve When overhead tank is at least ¼ full of emulsion start heating
the tank by opening the valve located under the tank (middle).
13. Check heating Check all heating systems for normal operation. The
systems temperature of overhead tank should be between 88 - 92oC.
14. Open feed valve When there is enough emulsion in the overhead tank, open the
feed valve to the machine.
15. Close drain valve, When the light phase starts emerging into the funnel, close the
open pump valve valve between the funnel and the drain and open the valve
between the funnel and the emulsion pump. The emulsion will
then go to the purifier overhead tank
April 2003 27
ETP Operator Manual
2. Open sealing water Open the sealing water valve (B-V14) about ¾ full.
valve
3. Open light phase valve Open the hand valve from the light phase funnel to the
drain.
4. Close sealing water When clean water starts to come out of the heavy
valve phase outlet, close the sealing water valve (B-V14)
6. Complete records Record the date and any comments on the Alfa-Laval
Separator Cleaning form, GWC-245.
7. Apply brake When the current in the meter drops to zero, go to the
machine and apply the brake.
9. Drain overhead tank Drain the overhead tank completely and clean it if
machine is to stop for a long time. This should be
done during machine change over.
9.1 Open hand valve (B-V17) to flush tank with hot
water.
9.2 Open drain valve (B-V9).
9.3 Close hand valve (B-V17).
9.4 When tank is empty close drain valve (B-V9)
April 2003 28
ETP Operator Manual
System start up
1. Check tank level and If the overhead emulsion storage tank is at least ¼ full
temperature open the steam valves for the heating system for
If tank ¼ full - open steam piping and overhead tank (C-V5 and C-V6), located
valves under the tank at the north-east corner.
The tank temperature should be between 90-95oC
If tank empty do not open If the overhead emulsion tank is empty, do not open
the steam valve at this stage.
valves.
2. Open sludge valve Open the sludge valve (C-V6-1) located at the back of
the machine.
3. Open heavy phase valve Open the heavy phase valve (C-V5-1) located at the
back of the machine.
5. Open light phase valve Open the hand valve between the light phase funnel
and the drain.
6. Turn rotary switches to Turn all rotary switches on the α-Laval Control Panel
Auto to the Auto position.
7. Press start button Press the ‘Start’ button on the α-Laval Control Panel.
8. Open water valves Open the two bowl operating water valves (CV-16-1
and CV-15-1).
9. Open sealing water Open the sealing water to the gravity disc after the
machine has attained full speed.
10. Start tank heating When the overhead tank is at least ¼ full, start the
system heating system for the tank. The temperature of the
tank should be between 90-95oC.
11. Check grease line Check the heating system for the grease transport line
heating to the drums.
12. Open feed valve When there is enough emulsion in the overhead tank,
open the feed valve to the machine and adjust as
required.
13. Close drain valve, open When grease starts to flow into the jacketed transfer
drum valve line, close the valve from the transfer line to the drain
and open from transfer line to drum for storing grease.
April 2003 29
ETP Operator Manual
Shut down
3. Open drain valve, close Open hand valve from the transport pipe to the drain
drum valve and close the valve from the transport line to the
drum.
4. Close cleaning water, When clean water starts to come out of the heavy
press stop phase outlet, close the cleaning water and press the
‘Stop’ button on the Control Panel.
5. Complete records Record the date and any comments on the Alfa-Laval
Separator Cleaning form, GWC-245.
6. Apply brake When the current in the meter drops to zero, go to the
machine and apply the brake
8. Drain overhead tank Drain the overhead tank completely and clean it if
machine is to stop for a long time. This should be
done during machine change over.
8.1 Open hand valve (C-V17) to flush tank with hot
water.
8.2 Open drain valve (C-V9).
8.3 Close hand valve (C-V17).
8.4 When tank is empty close drain valve (C-V9)
April 2003 30
ETP Operator Manual
Prestart checks
1. Check tank level Make sure that the 100m3 scour liquor storage tank
level is above 30%. (35-40% is a good starting range).
System startup
1. Open water valve Open the cooling water valve for the hydraulic
system, located near the hydraulic oil tank.
3. Start decanter After 5 minutes press the “decanter start 2B” button.
4. Open cleaning water if If decanter has been stopped for some time, open
required cleaning water located in front of decanter. Continue
flushing until clear water appears in the funnel.
6. Stop conveyor then When the decanter reaches full speed press the “stop”
select forward button 5B and start “forward”.
7. Open diverter gates if If the sludge is to be run into bins open the diverter
required gates for the conveyors:
8. Open feed valves Open the hand valves in the feed line.
9. Open motorised valve Press the motorised valve “MV2 open” button. A
green light will come on.
10. Turn feed pump on Press the feed pump drive “3C ON” button.
11. Open steam line Open hand valve in steam line to decanter.
12. Adjust feed rate Adjust the feed rate to synchronise with the
Alfa-Laval centrifuge feed and 100m3 tank level.
April 2003 31
ETP Operator Manual
System shutdown
3. Open cleaning water Keep running the system for 10 minutes and then open
the hand valve for cleaning water located in front of
the decanter.
6. Stop conveyor and select Run water for another 10 minutes, then press the
reverse Discharge “conveyor stop” button and the Discharge
“conveyer reverse” button.
10. Stop pump after 45 Keep the hydraulic pump running for 45 minutes and
minutes then stop it by pressing the “hydraulic pump stop”
button.
11. Close feed valves Close the hand valves in the feed line.
April 2003 32
ETP Operator Manual
1. Select tank Select the tank to be filled. (An alarm will sound as
one tank empties)
3. Start water and stirrer Press the start buttons for filling the tank with water
and starting the stirrer, these are located on the pillar
near the floc tank. (Ground level)
The stirrer will start when the level in the tank
exceeds 25%.
5. Stop water then air Turn the water hand valve off.
Turn the air valve off.
The stirrer will continue for 25 minutes after the tank
is full and will then stop automatically.
April 2003 33
ETP Operator Manual
Machine start-up
1. Check poly mix Make sure that the poly mix is ready.
2. Check water is on Ensure that the cooling water valve for the hydraulic
system located near the oil tank is on.
4. Select forward, open poly When the decanter attains full speed:
feed valve then start floc Press the “forward” button.
pump
Open the poly feed motorised valve,MV3 or
MV4, depending on which tank is selected.
Press the “Floc pump drive start” button.
5. If required, direct sludge If the sludge is to be run into bins do the following:
to bins Start conveyors 9, 10 and 11 and open the
diverter gates.
Open the hand valves in the feed line.
Press the motorised valve MV1 “open” button. A
green light will come on.
6. Start decanter feed To start feeding the decanter press the “feed pump
drive 3A start” button.
8. Stop when silo full Stop Bio-sludge when sludge silo is 23T full. In
case of emergency use tippler bin and inform shift
manager of the situation.
April 2003 34
ETP Operator Manual
7. Switch off conveyor When the decanter stops completely, switch off
conveyor 5A.
8. Run pump for 45 minutes Keep the hydraulic pump running for 45 minutes
and then stop it by pressing the “hydraulic pump
stop” button.
9. Close feed line valve Close the hand valve in the feed line.
April 2003 35
ETP Operator Manual
1. Check valve position Open valve V-41, then close V-42. If this is not
done the biosludge will go to the centrate pump.
2. Start wool wash decanter Start wool wash decanter. Refer to Operating
Procedures for Scour Liquor Decanters ETP-WI-006
and proceed up to step 7
3. Open valves to divert Go to feed pumps area and open hand valves to
sludge divert sludge through spare feed pump 3B, and wool
wash flow meter FM2.
8. Adjust feed rates Adjust feed rates for sludge and polyelectrolyte.
April 2003 36
ETP Operator Manual
Scour recycle from Check oil and grease % Take sample from 5l bottle,
Autosampler (Sandtrap) then empty and clean it.
Reset auto sampler.
Send sample to lab before
0800 in labelled 2l bottle.
Aeration tank 1 & 2 Measure mixture liquid Fill sample bottle from
suspended solids. overflow at top of tank.
(MLSS g/l) Send to lab before 0800 in
Also measure pH labelled 2l bottle.
Clarifier underflow Total solids (TS g/l) Open tap, let run for 10 secs,
then take sample.
Send to lab before 0800 in
labelled 2l bottle.
Thickener underflow Total solids (TS %) Take sample from tap before
bio-decanter pump.
Send to lab before 0800 in
labelled 2l bottle.
April 2003 37
ETP Operator Manual
Refer to the Documentation section of this manual for other checks that the ETP operator
is expected to do.
April 2003 38
ETP Operator Manual
Section 5: Documentation
The ETP operator is required to keep accurate records of ETP production and equipment
operational performance. This requires the completion of a number of forms that record
daily and/or weekly measurements.
Document Purpose
Aeration tank check sheet Record data each morning to monitor bio-activity
(GWC-248) and tank conditions (temperature, oxygen probe,
settle-ability, etc).
Scour liquor decanter form Completed at end of each shift. (Day and night)
(GWC-241) Bottom section is completed weekly.
Measurements are taken from SCADA and main
control panel.
SX machine record sheet Record shift data at end of shift (bottom of sheet)
(GWC-246) Record weekly data at top of sheet.
Measurements are taken from SCADA and local
equipment controls.
PX machine record sheet Record shift data at end of shift (bottom of sheet)
(GWC-247) Record weekly data at top of sheet.
Measurements are taken from SCADA and local
equipment controls.
April 2003 39
ETP Operator Manual
Document Purpose
Wool wax log (GWC-263) Record data on number and weight of drums.
(Kept at drums) One page is completed for each 24 hours
Decanter centrifuge return tube Completed at weekly cleaning when tank levels
cleaning form (GWC-244) are low.
April 2003 40
ETP Operator Manual
April 2003 41
ETP Operator Manual
April 2003 42
ETP Operator Manual
The Mimic screens display the current operating values and settings for the selected
process. Below is the mimic screen for the wool grease process.
The trend screens give a graphical display of how various functions are running, using
different coloured lines. The screen below displays the trends for the noggerath and sandpit
levels. Notice the peak in the pink line, indicating a problem in the heat exchanger.
April 2003 43
ETP Operator Manual
Grease from purifier Bowl clogged with sludge. Actuate sludge discharge,
contains water Liquid seal broken. and reduce interval between
discharges.
Stop and clean bowl.
April 2003 44
ETP Operator Manual
April 2003 45
ETP Operator Manual
Section 7: Assessment
7.1 The assessment procedure
There are two parts to the assessment of a trainee:
• a checklist to monitor the progress of the trainee and assess their competence
in all areas of operation.
The checklist
The checklist sets out all major areas of ETP operation and the related sub-tasks.
• as the trainee demonstrates the task while observed by the assessor for
assessment.
• when the trainee has mastered all the sub-tasks and is therefore competent in
the major area of operation.
• when the trainee answers the oral questions to the satisfaction of the assessor.
Note: The checklist does not set out the tasks in order of teaching.
The training program will determine in what order to teach the tasks, and trainers should
also take advantage of situations that occur in normal daily operations
(e.g. occurrence of problems and faults).
Oral test
This will take place in the training room and in the workplace during the training period.
April 2003 46
ETP Operator Manual
Trainee observed by
Trainee assessed
Task explained by
Effluent Treatment Plant
as competent
conditions
Major tasks/areas of operation
trainer
Individual skills/sub-tasks
• Effluent to drain
• Aeration tanks
• Clarifier underflow
• Thickener underflow
• Wool grease
April 2003 47
ETP Operator Manual
Trainee observed by
Trainee assessed
Task explained by
Effluent Treatment Plant
as competent
conditions
Major tasks/areas of operation
trainer
Individual skills/sub-tasks
Respond to alarms
• Bio-sludge decanter
• SX machine record
• PX machine record
• Shipping advice
April 2003 48
ETP Operator Manual
Explain the major duties of the E.T.P. operator by answering questions 4 – 14.
4. Materials handling is an important aspect of E.T.P. operation. What materials
handling does the operator have to perform? What are some of the potential
problems the operator has to avoid?
5. List each item of documentation the operator has to complete and its purpose.
6. List the position titles of the people with whom the E.T.P. operator has to
communicate, and the nature of the information communicated.
7. Operating the E.T.P. means that a lot of work has to be performed without much
contact with other people. What are some of the issues that can arise for the E.T.P.
operator because of this factor?
8. Describe the main operator duties involved in:
8.1 Monitoring and controlling E.T.P. tank functions
8.2 Monitoring and controlling overhead tank temperatures
8.3 Monitoring and controlling separator hot water supply
8.4 Operating air pressure supply
8.5 Operating and adjusting turbo blowers
8.6 Operating and adjusting SX and PX machines
8.7 Labelling and preparing empty drums for filling
8.8 Adjusting decanter parameters
8.9 Adjusting polymer addition rates to biosludge decanters
9. Why does and E.T.P. operator require….
9.1 A Basic Boiler Operation Certificate
9.2 A Dogman’s Licence
10. Describe at least sic basic maintenance functions carried out by the E.T.P. Operator.
11. Name at least ten regular checks and samples carried out by the E.T.P. operator and
briefly describe their purpose.
12. Name the hazardous chemicals used in E.T.P. and the type of hazard each can cause.
13. List at least five safety issues (other than hazardous chemicals) in the E.T.P. area.
14. Name the five common reasons why the E.T.P. operator may need assistance from
another tradesperson.
April 2003 49