You are on page 1of 3

2, CALVARY CLOSE, OPP. TAP, KM. 17 PH/ABA EXPRESSWAY, PORT-HARCOURT.

Email: thusbukeservices@gmail.com, Phone: +23 48053454867

PROPOSAL FOR DRILLING, WELL LOGGING, COMPLETION AND DEVELOPMENT OF 1


NO.5” 800FT BOREHOLE WITH 5.5HP PUMP AT UZUOKALI, URUALLA, IDEATO NORTH
L.G.A., IMO STATE.
S/N DESCRIPTION UNIT QTY RATE AMOUNT N

1 Mobilization of drilling BH 1 Lump


equipment, accessories,
and demobilization of
same upon job
completion 304,300.00

2 Preparation of drilling BH 1 Lump


site, construction of
mud circulation
complex, rig-up and
ready to drill 134,250.00

3 Drilling of 10’’ hole to FT 800 Lump


required depth and
collection of formation
samples at 10’’ intervals 2,327,000.00

4 Supply and Install 5’’ FT 800 Lump


PVC casing pipes
complete end fittings
(14 bar thickness) 1,790,000.00

5 Supply and Install 5’’ BH 4 Lump


PVC screen complete
end fittings (14 bar
thickness) 107,400.00

6 Provide and install BH 1 Lump


gravel park around
screen, consisting of
grated alluvial gravel of
appropriate mesh size 205,850.00
2, CALVARY CLOSE, OPP. TAP, KM. 17 PH/ABA EXPRESSWAY, PORT-HARCOURT.
Email: thusbukeservices@gmail.com, Phone: +23 48053454867

7 Provide cement and BH 1 Lump


grout well annulus of
appropriate depth in
borehole annulus 98,000.00

8 Develop borehole using BH 1 Lump


a submersible pump by
test running and surging
until water becomes
clean 277,250.00

9 Supply 5.5HP BH 1 Lump


submersible pump
complete with 2.5mm
Nigeria cable 1,074,000.00

10 Provide 11/4 PVC riser FT 1 Lump


mains for pump
installation including
other accessories 98,450.00

11 Allow for installation BH 1 Lump


charges, handling and
delivery 89,500.00

TOTAL 6,506,000.00

Based on our discussion with you on the above project, we hereby submit to you our proposal based on the
estimate and current market prices. As indicated, we intend to drill 800ft production borehole, which is
mainly sedimentary formation (clay, silt and sand) as well as install 5.5HP submersible Pump. The borehole
will be drilled with motorized water drilling rig and quality drilling chemicals in a professional manner.

The total contract sum is Six million, five hundred and six thousand naira (N6,506,000.00) only

TERMS OF PAYMENT AND QUOTE VALIDITY


2, CALVARY CLOSE, OPP. TAP, KM. 17 PH/ABA EXPRESSWAY, PORT-HARCOURT.
Email: thusbukeservices@gmail.com, Phone: +23 48053454867

1. 70% - Down payment


2. 20% - After drilling of the borehole but before Casing pipes installation
3. 10% - Immediately after completion of the entire project
Due to rising inflation and forex factors, this quotation is valid for only two weeks from the day of
submission.
Thank you, Sir, for your patronage as we promise to give you the best of our service professionally.
Yours faithfully,
For: THUSBUKE SERVICES

…………………………….
Prosper Oghalomeno
Principal Consultant